ANALYSIS OF RATE

FINISHING WALL WITH WATER PROOFING CEMENT PAINT OF APPROVED BRAND & MANUFACTURE & OF REQUIRED SHADE ON UNDECORATED WALL
SURFACES ( TWO COATS) TO GIVE AN EVEN SHADE AFTER THOROUGHLY BRUSHING THE SURFACE TO REMOVE ALL DIRT & REMAINS OF LOOSE
POWDERED MATERIALS. (DETAILS FOR 10 ^2 MTS.)
S.No. Description of item Qty. Rate Unit Amount
(A) MATERIAL:-
CEMENT PAINT 3.00 30.00 KG 90.00
BRUSHES & SAND PAPER ETC. LS 6.74
TOTAL 96.74 1)
(B) CARRIAGE:-(LIKE HEAVY MATERIAL ETC.)
BY MECH.TPT. 42.00 KM 0.003 673.05 MT 2.02
BY H.LOAD. 0.50 KM 0.003 365.72 MT 1.10
TOTAL 3.12 2)
(B ) LABOUR:-
Painter (G-I) 0.40 374.50 /DAY 149.80
Beldar 0.40 320.83 /DAY 128.33
Bhisti 0.40 320.83 /DAY 128.33
SUNDRIES (SCAFOLDING ETC.) LS 6.74
TOTAL 416.32 3)
TOTAL (1To3) 508.34
ADD 1.5 %FOR WATER CHARGES 508.34 7.63
TOTAL 515.97
ADD 10% C.P. & 5% O.H.C. 515.97 77.40
G.TOTAL 593.37
593.37
59.34
SAY Rs. 59.35
Add GST @ 12.00 % 0n Rs.= 59.35 (+ ) Rs. 7.12
Add Labour Cess @ 1.00 % 0n Rs.= 66.47 (+ ) Rs. 0.66
G.Total Rs.= 67.13
Say Rs. 67.15