Академический Документы
Профессиональный Документы
Культура Документы
Notice
This document and its contents have been prepared and are intended solely for OPW’s information and use in relation to
the construction of Ireland’s Pavilion for the Dubai Expo 2020.
Atkins assumes no responsibility to any other party in respect of or arising out of or in connection with this document
and/or its contents.
Document history
Client signoff
1
Expo 2020: Ireland Pavilion
The following outlines a general description of the additional information added and revisions to
specification in line with overall design development. The contractor should review all information to
ensure to include for all to complete the works as intended in the design and to meet compliance with
the current building regulations.
2
Expo 2020: Ireland Pavilion
CONTENTS LIST
Note: If any specification clauses are duplicated between the respective consultants
specifications, the contractor should agree the over-riding clause with the Contract
Administrator (CA). For definitions of 'similar ' / 'equal' refer to Architect's specification.
3
Expo 2020: Ireland Pavilion
CLEARANCE/EXCAVATION
161 SITE FEATURES: Before starting work verify with CA which existing fences, gates, walls,
roads, paved areas and other site features are to be removed. Materials arising are to be removed
from site.
210 MATERIALS ARISING: Remove from site materials arising from the works.
BENCHING: Surfaces of excavations with a gradient greater than 1 in 5 which are to receive
filling must have horizontal benches cut to match the depths of compacted layers of filling.
240 ADJACENT EXCAVATIONS: Where an excavation encroaches below a line drawn
at an angle of 45 degrees from the horizontal from the nearest formation level of another
higher excavation, the lower excavation, all work within it and backfilling thereto must be
completed before the higher excavation is made.
310 UNSTABLE GROUND: Inform CA without delay if any newly excavated face will not remain
unsupported sufficiently long to allow the necessary earthwork support to be inserted. If the instability
is likely to affect adjacent structures or roadways, take appropriate emergency action until instructions
are obtained.
320 OBSTRUCTIONS: All obstructions and existing services encountered during the phase 1
Demolition and archaeological works have been removed/sealed off. Should further obstructions be
encountered ie: old foundations, beds, basements, filling, tanks, service pipes, drains, etc. not shown
on the drawings, do not enter and obtain instructions before proceeding.
4
Expo 2020: Ireland Pavilion
DISPOSAL OF MATERIALS
All excavated material, debris and obsticles on site to be disposed in accordance with the Expo
Requirements. Contractors to make themselves aware of the Expo requirements.
450 WATER: Keep all excavations free from water until formations are covered and
below ground constructions are completed.
454 GROUND WATER LEVEL: The existing ground water level is to be confirmed on site by the
Main Contractor. Ground water is not forseen as a problem.
457 PUMPING:
Do not disturb excavated faces or the stability of adjacent ground or structures.
Avoid flooding of the site, or adjoining property, by disposal of pumped water.
Construct sumps, and/or settlement tanks, which may be required, clear of the excavations
and fill as specified on completion.
Method statement of any proposed pumping regime/procedure is to be submitted to the CA
prior to any of the works commencing on site for review and comments.
650 HARDCORE:
- Granular material, free from harmful matter and excessive dust or clay, well graded,
passing a 75 mm BS sieve and one of the following:
- Crushed hard rock or quarry waste (other than chalk).
- Crushed concrete, brick or tile, free from plaster.
- Gravel or hoggin.
- Spread and level both backfilling and general filling in layers not exceeding 150 mm.
Thoroughly compact each layer with a vibratory roller, vibrating plate compactor, vibro- tamper, power
rammer or other suitable means.
5
Expo 2020: Ireland Pavilion
700 HARDCORE UNDER CONCRETE SLABS: As clause 650 and not less than 225 mm thick.
Excavate extra material as necessary. Increase thickness as necessary to make up levels from
stripped site levels to underside of slabs.
- There shall not be used or specified for use in the construction of the works any
substances or materials which are not in accordance with Local Standards or Codes of
Practice in so far as they may be applicable or relevant (and if there are no Irish Standards
or Codes of Practice then the appropriate British Standards and Codes which shall be
applicable or relevant) or any materials or substances known to the building trade or
profession at the time of specification to be deleterious to health or safety or the durability or
suitability of the Works in the particular circumstances in which the same is used.
- Hardcore materials used in backfill, excavations, floors, road bases etc should be
certified by a competent laboratory that they are of a suitable nature and quality in relation to
the purpose and conditions of their use. They should be chemically analysed to check is
such materials contain any chemicals, which should also include the petrographic indicator
or swelling potential.
Frequency of testing should be 1 petrographic and 1 chemical suite (ie acid soluble sulphate
and (S) total sulphur test only) per building.
6
Expo 2020: Ireland Pavilion
acceptable or unacceptable for incorporation into the works. This is generally the category
of material used in Dublin.
The following hardcore is acceptable in each area which meet the requirements set out in
I.S. EN 13242:2002 +A1 :2016 – Aggregates for unbound and hydraulically bound materials
for use in civil engineering work and road construction or similar approved.
Clauses dealing with particular aspects of certain types of construction may thus be
dispersed over several sections.
The ambient temperature should not be above 40°C, or is expected to reach such a level
during concreting.
Temperature of concrete should not be more than 30°C
7
Expo 2020: Ireland Pavilion
Sudden irregularities not permitted. When measured with a slip gauge to BS 8204: Part 1 or
2, Figure 3 or equivalent, the variation in gap under a straightedge (with feet) placed
anywhere on the surface to be not more than the following:
- Floors which are to be self-finished, and floors to receive sheet or tile finishes directly
bedded in adhesive:
5 mm under a 3 m straightedge
2 mm under a 1 m straightedge
- Floors to receive screeds/toppings/beds up to 50 mm thick:
10 mm under a 3 m straightedge.
- Floors to receive mastic asphalt flooring or underlay laid over mastic asphalt levelling
coat(s):
10 mm under a 3 m straightedge.
- Floors to receive mastic asphalt flooring or underlay laid direct:
SR1 from BS 8204-1
8
Expo 2020: Ireland Pavilion
For substructure (below ground level) 36%-65% GGBS or 26%-35% fly ash as required to
satisfy the durability requirements and concrete workability.
Micro silica: condensed silica fume to BS 6699, maximum weight 8% of the total cementitious
materials
• Chloride class: As per soil report for substructure and concrete against soil.
• Admixtures: To BS EN 934-2, BS 3892 1-3, BS 5075-1 and BS 5075-3 as appropriate.
• The maximum total percentage of chloride ion by mass of cement: 0.15% including
cementitious additive.
• The total content of acid soluble sulphates shall not exceed 3% by weight of cement including
cementitious additive.
• Rate of sampling for compressive strength testing: one sample ( 6 cubes ) per 20 m³ or 20
batches whichever represents the lesser volume, but not less than one for each day of use.
• The alkali content (Na2O and K2O) of the concrete shall not exceed 3 kg/m³
• Information to be provided by the producer: As BS 5328-3, clause 3.
• Maximum Slump = 200 mm ± 25mm for concrete with admixture.
CONCRETE MIXES
9
Expo 2020: Ireland Pavilion
215 READY-MIXED CONCRETE must be used for all concrete and must be obtained from a plant
which holds current certification meeting the requirements of the NACCB, Category 2 for product
conformity. Each mix must be obtained from only one source unless otherwise approved. Confirm name
and address of depot(s) to Engineer before any concrete is delivered. Retain all delivery notes for
inspection.
255 CEMENTS:
- The following abbreviations apply:
Class 42.5N CEM 1, CEM 11/A, CEM 11/B, CEM 111/A, CEM 111/B
ggbs Ground granulated blastfurnace slag
pfa Pulverized fuel ash
- Cements, ggbs and pfa must comply with the relevant British Standards. Portland
cements must have cement certification meeting the requirements of the NACCB, Category 2 for product
conformity.
305 NATURAL AGGREGATES FOR DESIGNED/PRESCRIBED MIXES: To give a drying shrinkage
of concrete not exceeding 0.075% when tested to BS 812:Part 120.
10
Expo 2020: Ireland Pavilion
315 AGGREGATES FOR EXPOSED WORK: To BS 882, of consistent colour, free from absorbent
particles which may cause 'popouts', and other particles such as coal and iron sulphide which may be
unsightly or cause unacceptable staining. Obtain from one source, and ensure that adequate supplies can
be maintained throughout the contract. Provide samples of proposed aggregates on request.
325 EXPOSED CONCRETE: Obtain approval before altering constituent materials or proportions of
concrete, which will be exposed in the finished work.
355 RISK OF ALKALI SILICA REACTION IN DESIGNED/PRESCRIBED MIXES: Take one of the
precautions specified for Designated mixes in clause 5.5.7 of BS 5328: Part 2. Inform CA/Structural
Engineer if this necessitates a change in specification. Submit evidence of compliance to CA/Structural
Engineer before making concrete for use in the Works.
415 ADMIXTURES FOR DESIGNED/PRESCRIBED MIXES:
To BS 5075.
Use only if specified or approved, and then in accordance with their manufacturer's
recommendations.
Do not use admixtures containing calcium chloride.
Ensure that admixtures are compatible with all other materials, including other admixtures.
418f Reinforcement:
All reinforcement shall be high tensile rib deformed bar to the Consulting Structural Engineer’s
detail drawings.
Proper curing shall be carried out in accordance with BS8110 or equivalent. For slabs, curing
should start immediately after finishing and as soon as the concrete can withstand a man’s
weight without marking. For larger slabs, curing should be done in sections and this is
especially the case with powerfloat finishes where commencement of curing must not be
delayed. For walls, the top surface must be appropriately covered as soon as finishing is
complete. Curing of the walls must commence immediately the formwork is removed. All
concrete surfaces are to be protected from direct sunlight and frost by appropriate covering
during the curing period. The curing time should be for a minimum of 72 hours after placement
or longer as specified. Spray-on curing membranes are not recommended unless the
immediate use of plastic sheeting over wet hessian will mark the concrete. Where a resin-
based curing membrane is used under such circumstances, it should have a minimum 90%
efficiency rating. Covering with wet hessian and plastic sheeting should commence as soon as
practicable thereafter.
18k Loading:
11
Expo 2020: Ireland Pavilion
Loading of the structure, including back-filling, is not permitted until the concrete has reached
the strength specified by the Consulting Structural Engineer and approval has been given.
TESTING/CERTIFICATION
500 SAMPLES OF FRESH CONCRETE should be sampled at a rate of one sample per 20 cubic m, or
one sample per days use of that particular mix if less than 12 cubic m is used. From each sample a
minimum of four standard 150 cubes shall be made. A minimum of one cube shall be tested at 7 days and
two after 28 days. The remaining cube shall be kept in a suitable environment for the duration of the
contract and only tested when/if instructed by the engineer.
510 COMPLETE CORRELATED RECORDS must be maintained for each Designed and Prescribed
mix including:
Information in accordance with BS 5328:Part 3, clauses 3.1 and 3.2.
All sampling, site tests and identification numbers of all specimens tested in the laboratory.
The location of the part(s) of the structure represented by each sample.
The location in the structure of the batch from which each sample is taken.
520 TEST LABORATORY: All specified testing of concrete other than slump testing of cubes, to be
carried out by an approved laboratory. Submit the name of the selected laboratory to CA/Structural
Engineer as soon as possible and in any case before making trial mixes or concrete for use in the works.
- A digital copy of the test reports in pdf to be issued to the Engineer within one day
of completion of each test.
- 2 hard copies of reports to be issued to CA for information purposes
A schedule of cube results summarising: the cube reference; location of each the mix; date of the pour;
the slump; the date of the tests and the cube test results (7 and 28 day) to be issued to the Engineer
weekly in a suitable digital format
A complete set of reports to be kept on site.
550 BROKEN CUBES: Keep separately the pieces of each cube which fails to meet the compliance
requirements for individual results. Obtain agreement of CA/Structural before discarding.
570 EARLY AGE STRENGTH TESTING: A regime of accelerated or normal curing and early testing
which is capable of predicting the 28 day strength of Designed mixes may be used for determining
compliance, subject to prior approval. If such a regime is adopted, two additional cubes must be made
from each sample and cured normally so that, in the event of non-compliance, they can be tested at 28
days to provide information, which will help in deciding the action to be taken.
580 FAILURES:
If a concrete sample fails to achieve specified criteria or to pass specified tests, inform the
Engineer without delay and submit:
Confirmation of the validity of the test results, and/or
Proposals for further tests to assess the strength of the concrete in the structure, as set out in
BS 6089, and/or
Proposals for rectification. At the expense of the Contractor.
Obtain approval of all such evidence and proposals before proceeding. The Engineer may issue
instructions for the work to be stopped or delayed until reasons for the failure have been
established, possible consequences assessed, and appropriate preventative and remedial
measures taken.
581 FAILURES: Wherever the specified sampling, testing and compliance procedures show that a
concrete mix is not in accordance with the specification (even if the work is eventually accepted), and
measures are taken to help in establishing whether or not the work is acceptable, such measures:
12
Expo 2020: Ireland Pavilion
Entrained air: Anticipate effects of transport and placing methods in order to achieve specified
air content.
Use suitable walkways and barrow runs for traffic over reinforcement and freshly placed
concrete.
680 PLACING:
Record time, date and location of all pours.
Place as soon as practicable after mixing and while sufficiently plastic for full compaction. After
discharge from the mixer do not add water or retemper mixes.
Ensure that temperature of concrete is not more than 30°C in hot weather and not less than
5°C in cold weather. Do not place against frozen or frost covered surfaces.
Place in final position in one continuous operation up to construction joints. Avoid formation of
cold joints.
Do not discharge from an excessive height or through reinforcement or other obstructions in a
way which may cause uneven dispersal, segregation or loss of ingredients or adversely affect
the formwork or formed finishes. Use suitable chutes or trunking where necessary.
Place in layers no thicker than can be effectively compacted with the equipment being used,
without delay between layers. Merge together by compaction.
Do not use vibrators to make concrete flow horizontally into position, except where necessary to
achieve full compaction under void formers and cast in accessories and at vertical joints.
690 COMPACTING: Fully compact concrete to full depth (until air bubbles cease to appear on the top
surface), especially around reinforcement, cast-in accessories, into corners of formwork and at joints.
Ensure amalgamation with previous batches, but do not damage adjacent partly hardened concrete. Use
appropriate type(s) of mechanical vibration for all concrete except blinding.
730 PLASTIC SETTLEMENT: At the top of deep sections and at significant changes in the depth of
concrete sections, closely and continuously inspect the fresh concrete for signs of settlement during the
first few hours after placing. While the concrete is still capable of being fluidised by the vibrator, revibrate
as necessary to remove settlement cracking, which may be forming either on the top surface or against
the upper part of the vertical formwork.
13
Expo 2020: Ireland Pavilion
820 CURING PERIODS, in days (t = the average number of degrees centigrade air
temperature during the curing period):
Concrete surfaces which in the finished building will be exposed to the elements; concrete
wearing surface floors and pavements; watertight concrete:
Concrete made Concrete made
using PC42.5, using PPFAC,
PC52.5, SRPC PBFC, HSBC
pfa, ggbs
Damp weather,
protected from 100 100
sun and wind t+10 t+10
Intermediate 60 80
conditions t+10 t+10
Damp weather,
protected from No special No special
sun and wind requirements requirements
Obtain prior approval for curing periods for mixes using admixtures or other types of cement.
822 CURING PERIODS, not less than:
Surfaces which in the finished building will be exposed to the elements, and wearing surfaces of
floors and pavements, regardless of weather conditions: 10 days
Other structural concrete surfaces: 5 days
14
Expo 2020: Ireland Pavilion
15
Expo 2020: Ireland Pavilion
GENERALLY/PREPARATION
110 LOADINGS: Design and construct formwork to withstand the worst combination of:
Total weight of formwork, reinforcement and concrete.
Construction loads including dynamic effects of placing, compacting and construction traffic.
Wind and Snow loads.
130 PROPPING: Provide adequate propping to prevent deflection and damage to the structure. Carry
down such props to bearings strong enough to provide adequate support. Areas requiring additional back
propping for design purposes, ie to reduce the long-term deflections, are noted on the Structural
Engineers Drawings.
170 WORK BELOW GROUND:
Vertical faces of strip footings, bases and slabs may be cast against faces of excavation,
provided:
Prior approval is obtained.
The faces are sufficiently accurate and stable.
Supports to faces are withdrawn progressively as concrete is placed.
Adequate measures are taken to prevent contamination of concrete.
Faces of walls must be cast against formwork.
210 STEELWORK: Remove all loose millscale and loose rust before encasing in concrete.
CONSTRUCTION
310 ACCURACY: Construct formwork accurately and robustly with adequate supports to produce
finished concrete to the required dimensions. Formed surfaces must be free from twist and bow (other
than any required cambers), all intersections, lines and angles being square, plumb and true.
320 JOINTS IN FORMS: Construct formwork, including joints in form linings and between forms and
completed work, to prevent loss of grout, using seals when necessary. Secure formwork tight against
adjacent concrete to prevent formation of steps.
STRIKING
510 RESPONSIBILITY: Strike formwork without disturbing, damaging or overloading structure, and
without disturbing props. Notwithstanding other clauses in this specification and any checking or approvals
by the Engineer, the responsibility for safe removal of any part of the formwork and any supports without
damaging the structure rests with the Contractor.
520 MINIMUM PERIODS:
The following periods (in days) for retaining formwork in position before striking apply to class
42.5 or sulphate- resisting Portland cement concrete with no cement replacement materials or
admixtures:
Type of Average mean of daily minimum
formwork and maximum air temperatures
during the period
16xºC 7xºC 3xºC
Vertical formwork to
columns, walls and
beams 0.5 0.75 1
Props to beams 14 21 28
Submit details of proposed periods for mixes using admixtures or other types of cement.
521 MINIMUM PERIODS: Alternative methods of determining minimum periods for retaining
formwork in position may be submitted for approval. The contractor is to accept responsibility
for cost of checking of proposals by Engineer and for any testing.
17
Expo 2020: Ireland Pavilion
REINFORCEMENT
110 QUALITY ASSURANCE: All steel reinforcement specified to comply with BS 4449 or BS
4483 and cut and bent to BS 8666 is to be obtained from firm(s) holding a valid certificate of
approval issued under a product certification scheme operated by a third party certification body
with appropriate Category 2 accreditation from the United Kingdom Accreditation Service
(UKAS).
WORKMANSHIP
310 CUT AND BEND reinforcement to schedules and to BS 8666. Do not bend when below
5°C without approval. Steel may be warmed to not more than 100°C. Do not rebend bars
without approval. Tag bundles of reinforcement with labels to BS 8666
311 CUT AND BEND stainless steel bars to BS 8666 as for high yield bars.
317 MECHANICAL DAMAGE: Reinforcement must not be roughly handled, dropped from a
height, or subjected to shock loading or mechanical damage.
330 ADJUSTMENTS: Provide on site facilities for hand bending to deal with approved minor
adjustments.
360 PROJECTING REINFORCEMENT: Grade 250 bars may be bent to radii not less than
BS 8666, Table 3. Grade 500 bars must not be bent or straightened without approval
410 LAPS OR SPLICES: Obtain instructions if details are not shown on drawings.
420 LAPS in nominal bar reinforcement to be not less than 300 mm.
421 LAPS in fabric reinforcement, where not detailed, to be not less than 250 mm. Where
necessary seek instructions to avoid a four layer build-up at corners.
444 MECHANICAL JOINTS will not be permitted, without prior agreement with the Structural
Engineer.
18
Expo 2020: Ireland Pavilion
481 GROUND BEARING SLABS: Where these are reinforced with a single layer of fabric in
the upper part of the slab, either:
Lay fabric on top of the first compacted layer of concrete, followed by the top layer of concrete,
placed within two hours of the first layer, or
Fully support the fabric on suitable proprietary supports/chairs.
491 SPACERS to formed concrete finishes, if permitted (see section E20) to be approved
type(s).
500 DAMAGE: Prevent damage to and disfigurement of forms, form linings and adjacent
work.
510 RUST STAINING: Prevent rust staining of surfaces of concrete which will be exposed to
view in the finished work, caused by, e.g. rust stained formwork or unprotected projecting
reinforcement.
520G CHECKING COVER: Check the position of the reinforcement in the hardened concrete
as soon as practicable after casting using a magnetic induction digital display type cover meter
in accordance with manufacturer's recommendations and BS 1881-204. Pay particular attention
to columns, beams, cantilevers, soffits of slabs and all faces which will be exposed to the
weather in the finished building. Inform CA when such checking is to be carried out, confirm
that it has been carried out and that the results were satisfactory.
19
Expo 2020: Ireland Pavilion
110 ACCURACY: All joints to be accurately located, straight and well-aligned, and truly vertical or
horizontal or parallel with the setting out lines of the building.
210 FORMED JOINTS: Construct using rigid, grout-tight side forms or stop ends designed to
accommodate projecting bars or fabric without temporary bending or displacement.
230 ROUGHENING OF CONSTRUCTION JOINT FACES: Brush and spray surface of construction
joints while concrete is still green to leave a thoroughly roughened exposed aggregate finish.
21
Expo 2020: Ireland Pavilion
510 SURFACE HARDENER: Not less than three weeks after casting, clean surface of concrete by
wetting with soap suds and scrubbing with wire brush and fine steel wool. Mop up and scrub with fibre
brush and clean water. Allow to dry thoroughly for several days then apply an approved proprietary
chemical surface hardener to manufacturer's recommendations.
520 SURFACE SEALER: Apply an approved resin sealer to concrete wearing surface floors in
accordance with manufacturer's recommendations.
22
Expo 2020: Ireland Pavilion
23
Expo 2020: Ireland Pavilion
Architectural board mark finish to be achieved with panels of timber boards to finish Class F8,
with panels as large as is practicable and arranged in an approved regular pattern as a feature
of the surface. Do not replace parts of formwork panels where this may cause a change of
colour in the concrete.
24
Expo 2020: Ireland Pavilion
25
Expo 2020: Ireland Pavilion
250 DESIGN: Complete the design of the floor deck in accordance with BS 8110 and to meet the
requirements of this specification. The floor deck must withstand the worst combination of dead and
imposed loads, both in the finished building and during construction.
280 BASIC FIRE RESISTANCE, as specified in the fire certificate, and must be determined without
regard to applied finishes and in accordance with BS 8110:Part 2, section 4 or by testing to BS 476:Part 8
(if assessed prior to 1 January 1988) or BS 476:Part 21.
F MASONRY
F10 BRICK/BLOCK WALLING
51 BASIC WORKMANSHIP:
- Store bricks/blocks in stable stacks clear of the ground. Protect from inclement weather
and keep clean and dry.
- Build walls in stretching half lap bond when not specified otherwise.
- Lay bricks/blocks on a full bed of mortar; do not furrow. Fill all cross joints and collar
joints; do not tip and tail.
- Rack back when raising quoins and other advance work. Do not use toothing.
- Bring both leaves of cavity walls to the same level at
- Every course containing rigid ties.
- Every third tie course for double triangle/butterfly ties.
- Courses in which lintels are to be bedded.
- Do not carry up any one leaf more than 1.5 m in one day unless permitted by the CA.
60 ALTERATIONS/EXTENSIONS:
- Arrange brick courses to line up with existing work.
- Unless otherwise specified or agreed block bond new walls to existing by cutting pockets
not less than 100 mm deep, the full thickness of the new wall, and:
Brick to brick: 4 courses high at 8 course centres.
Brick to block, block to brick or block to block: Every alternate block course.
Bond new walling into pockets with all voids filled solid.
26
Expo 2020: Ireland Pavilion
- Except where a straight vertical joint is specified, new and existing facework in the same
plane to be tooth bonded together at every course to give a continuous appearance.
- Where new lintels or walling are to support existing structure, completely fill top joint with
semidry mortar, hard packed and well rammed to ensure full load transfer after removal of temporary
supports.
65 FIRE STOPPING: Fill joints around joist ends built into cavity walls with mortar to seal cavities
from interior of building.
66 FIRE STOPPING: Ensure a tight fit between brickwork and cavity barriers to prevent fire and
smoke penetration.
70 HOLES, RECESSES AND CHASES IN MASONRY: Comply with the relevant clause in section
P31.
27
Expo 2020: Ireland Pavilion
280 FIXING TIES IN MASONRY CAVITY WALLS WITH FULL FILL CAVITY INSULATION:
- Bed not less than 50 mm into bed joint of each leaf.
- Slope downwards towards outer leaf with drip centred in the cavity and pointing
downwards. Do not bend ties to suit coursing.
- At 750 mm centres horizontally, and 450 mm centres vertically, unless specified
otherwise.
- Space top (eaves) row of ties at 450 mm centres.
- Provide additional ties within 225 mm of reveals of unbonded openings at every course of
blockwork or vertically at 300 mm maximum centres.
62 JUNCTIONS/STOP ENDS FORMED IN SITU: Where preformed cloaks/stop ends are not
specified form three dimensional changes of shape in dpcs and/or cavity trays carefully and neatly to
ensure a fully watertight installation. Preformed cloaks/stop ends may be used in lieu, subject to approval.
28
Expo 2020: Ireland Pavilion
76 MOVEMENT JOINTS WITH SEALANT: Maximum 6m centres, exact locations to be agreed with
the CA.
- Filler: Polyethylene ‘Flexcell Board’
Build in as the work proceeds ensuring no projections into cavities and correct depth of
joint to receive sealant system.
- Sealant: Mastic Sealant
Colour: To be agreed with the Architect
Prepare joints and apply sealant as section Z22.
29
Expo 2020: Ireland Pavilion
GENERAL REQUIREMENTS
240 CHLORIDES: The total chloride ion content of the constituents of each mix, expressed as a
percentage by weight of cement (including GGBS or PFA if used) in the mix, must not exceed 0.4. Do not
use admixtures containing calcium chloride.
250 REINFORCEMENT:
- Type of reinforcement, unless otherwise specified: To BS 4449 and/or BS 4483, cut and
bent to BS 8666.
- Galvanized reinforcement: Galvanized to BS 729 after cutting, chromate treated.
- Stainless steel reinforcement: To BS 6744, type 304 or 316.
30
Expo 2020: Ireland Pavilion
320 DETAILS OF SAMPLES: After approval of appearance of samples and before making production
components:
- Confirm details of proposed aggregates, including type, maximum nominal size, grading
and source.
- Submit evidence to demonstrate compliance in respect of compressive strength and free-
water/cement ratio.
330 AGGREGATES FOR EXPOSED WORK: To BS 882, of consistent colour, free from absorbent
particles which may cause popping, and other particles such as coal and iron sulfide which may be
unsightly or cause unacceptable staining. Obtain from one source, and ensure that adequate supplies can
be maintained throughout the contract.
350 QUALITY OF FINISHES must match the approved samples and be consistent throughout the
contract. Components having arrises or faces which are broken, chipped, cracked, crazed, honeycombed,
irregular, inconsistent, stained or otherwise marred such that their appearance or performance is
significantly impaired will not be accepted.
Maximum free
water/cement ratio 0.55 0.50 0.45
Single mix 50 40 30
370 COVER SPACERS must not be used to concrete faces which will be exposed in the finished
work. Where such faces are to be cast against a mould submit details of proposed method of ensuring the
specified cover.
380 UNIFORMITY OF METHOD: All exposed faces which are specified to be of the same finish must
be identical in appearance. If different methods of producing such faces are proposed, submit evidence
that there will be no difference in appearance and obtain approval; otherwise all such faces must be
produced in the same way.
390 INSPECTION: All completed components must be carefully inspected and checked by the
manufacturer for match with approved sample(s) and compliance with specification before despatch to
site. Make arrangements for the CA to inspect completed components in the factory.
400 DAMAGED COMPONENTS: Do not repair without approval. Such approval will not be given
where the components are badly damaged or where the proposed repair would impair appearance or
performance.
INSTALLATION
32
Expo 2020: Ireland Pavilion
410 PROTECTION:
- Prevent overstressing of components during transit, handling, storage and fixing. Lift units
at designed lifting points where provided.
- Store components on level bearers clear of the ground and separate with resilient
spacers.
- Prevent damage to components and any chipping, staining, marking or dirtying of
surfaces which will be visible in the completed work.
420 LAYING:
- Unless specified otherwise, lay components on a full bed of mortar used for adjacent
work. If packing is required use slate.
- Position components accurately, true to line and level.
- Faces which will be exposed to view in the finished work to be kept clean with no mortar
encroachment. Rubbing to remove marks or stains will not be permitted.
430 SUPPORT OF EXISTING WORK: Where new lintels are to support existing structure, completely
fill top joint with semidry mortar, hard packed and well rammed to ensure full load transfer after removal of
temporary supports.
440 ONE PIECE SILLS/THRESHOLDS: Leave bed joints open except under end bearings. On
completion point with mortar to match adjacent work.
33
Expo 2020: Ireland Pavilion
GENERAL REQUIREMENTS/INFORMATION
110 DESIGN:
The structural steelwork shown on the drawings and described in this specification has been
designed to BS 5950 where applicable, unless stated otherwise.
Steel grade(s): S355 unless noted otherwise (hereinafter noted as uno) in accordance with
tables 4-7 in BS5950-1:2000 (BS EN 10025, grade S275). Stainless Steel grade 316 noted on
relevant structural drawings in accordance with BS5950-1:2000 (BS EN 10088-2, grade 316).
Complete the design and detailing of connections to BS 5950 to satisfy loading requirements
specified or otherwise calculable from the information given.
115 DESIGN CONSTRAINTS: Unless required or permitted otherwise, comply with the following when
completing the design and detailing of the work:
Position members forming bracing systems or girders of lattice construction so that their lines of
action intersect at a point.
Bolts to be grade 8.8 high tensile and not less than 16 mm diameter.
Not less than four bolts to be used in any connection.
Welds to be 6mm continuous fillet weld (cfw) unless noted otherwise on the drawings.
120 DRAWINGS, ETC: Before preparing detailed fabrication drawings, submit:
Calculations for all major connections.
General arrangement drawings with individual steel members clearly identified.
125 SPECIFICATION:
Comply with the latest edition of the National Structural Steelwork Specification (hereinafter
called the NSSS) unless specified otherwise in this section.
Ensure that a copy of the NSSS is available at all times during the course of the Works at the
fabrication shop and on site.
FABRICATION GENERALLY
180 GENERAL REQUIREMENTS:
Inform CA when fabrication is due to start. Do not fabricate steelwork for which the drawings
have not been checked by CA.
The steelwork fabricator is to allow the structural engineer 5 working days to comment on the
fabrication drawings.
Before fabricating, ensure that surface condition of steel which is to be coated complies with
requirements for cleaning given elsewhere in this specification.
Ensure that fabrication processes do not cause changes in properties of materials resulting in
non-compliance with specified requirements.
34
Expo 2020: Ireland Pavilion
190 MARKING:
Submit details of proposed methods of identifying and recording materials and components to
ensure correct use and location in the structure.
Marks to be placed in positions such that they will be visible for checking after erection.
191 MARKING of weathering steel to be on surfaces that will not be exposed to open view in the
completed work.
192 MARKING of steel that is to be blast cleaned, pickled, metal sprayed or galvanised to be done in
such a way that subsequent treatment cannot obliterate the marking.
195 HARD STAMPING: Notwithstanding NSSS clause 4.1.3(ii), hard stamping must not be used
except where specified on the drawings by the engineer.
210 END CONNECTIONS: Ensure that angle cleats, if used, project beyond ends of simply supported
members.
215 HOLLOW SECTIONS: Ensure that insides of sections are dry and clear of debris before sealing
ends and openings.
220 BASE PLATES: Make 25 mm diameter holes in all base plates more than 1 sq m in area to allow
the escape of air when grouting after erection of columns.
230 SHOP ASSEMBLY: Check fit, profile and camber before making connections in lattice girders and
trusses that are to be assembled before delivery to site.
235 SHOP INSPECTION: Give 5 working days notice before starting fabrication of structural steel
frame.
WELDING
255 WELDING ON SITE: Notwithstanding NSSS clause 8.7, site welding is not permitted unless
shown on drawings or otherwise approved. When permitted, ensure suitable, safe working conditions. Do
not weld when surfaces are wet or when the ambient temperature is below 0°C.
270 ADDITIONAL WELDS: Do not, without approval, make any welds (including tack welds) that are
not shown on the drawings, even for temporary attachment or repair of faulty plates.
290 FINISHING WELDS: Carefully dress welds to remove slag by light hammering, wire brushing or
other methods that do not deform the surface of the weld.
BOLT ASSEMBLIES
305 All BOLTS AND NUTS: To be galvanised and Design by Structural Steelwork Fabricator.
308 SPACING and distance to edge of concrete or masonry to comply with fixing manufacturer's
recommendations for maximum safe static load.
325 LOAD INDICATING WASHERS:
Manufacturer and reference: To be agreed with the Engineer.
When placed under bolt head, prevent bolt turning when tightening.
When placed under nut, protect nibs with a hardened washer and prevent both washers from
turning when tightening.
335 SPRING WASHERS: To BS 4464.
345 BOLT BOXES:
To be supplied by the steelwork fabricator for fixing by the main contractor.
Manufacturer and reference: To be agreed with the Engineer.
ERECTION
35
Expo 2020: Ireland Pavilion
Not less than 7 days before proposed start date, check foundations and other structures to
which steelwork will be attached for accuracy of setting out, and holding down bolts for position,
protruding length, condition and slackness.
Report any inaccuracies and defects to Main Contractor and CA without delay.
Obtain permission of CA to commence erection.
425 MODIFICATIONS:
Inform CA of any defects due to detailing or fabrication errors.
Obtain approval of methods of rectification before starting modification or remedial work.
441 MORTAR FILLING/BEDDING OF COLUMN BASES: Completely fill bolt pockets with a neat
cement slurry and the space beneath column base plates with grout or mortar as follows:
Proprietary non-shrink grout. Fosroc or similar approved.
444 FINE CONCRETE FILLING/BEDDING OF COLUMN BASES: Completely fill bolt pockets with a
neat cement slurry and the space beneath column base plates with a 1:1:2 cement:sand:fine aggregate
mix, well tamped against properly fixed supports as filling proceeds. Maximum size of aggregate 10 mm.
445 MOVEMENT JOINTS
Coat sliding surfaces with molybdenum disulphide grease before connecting.
Ensure that bolts are in centre of slotted holes after erection of structure and that the joint is
free to move.
INSPECTION/TESTING OF STEELWORK
460 INSPECTION: Permit the CA, and/or an independent inspection authority appointed by him/her, to
inspect the work at all reasonable times and at all places where it is being carried out. Provide all facilities,
hand tools, lighting, etc. as necessary to ensure adequate inspection.
465 TESTING:
Arrange for the following testing to be carried out in accordance with the National Structural
Steelwork Specification. Prepare any necessary test pieces. Submit 1 copy of all test and
examination results to CA immediately they are available.
Test: non-destructive testing of welded joints
Frequency/Number: all full structural butt welds (fsbw)
10% of all welds other than fsbw
Level of acceptability: To CA’s approval
470 TESTING AUTHORITY: All tests to be carried out by competent & approved authority
475 PRODUCTS: When requested by CA submit a copy of test certificates for steel.
480 DEFECTIVE WORK: As soon as possible after any part of the work or any materials are known or
suspected to be defective, submit proposals to CA for further testing, inspection or replacement and
obtain instructions.
36
Expo 2020: Ireland Pavilion
515 OPERATIVES must be appropriately skilled and experienced in the use of specified materials and
methods of application.
520 COATING MATERIALS:
Wherever possible, to be from one manufacturing batch. Where more than one batch is to be
used, keep separate, allocate to distinct parts or areas of the work, and inform the CA
accordingly.
Check that all coating materials to be used are recommended by their manufacturers for the
particular surface and conditions of exposure, and that they are compatible with each other.
521 ALTERNATIVE MANUFACTURERS: Coating materials to be obtained from one only of the
following manufacturers unless specified otherwise. Inform CA of selected manufacturer at an early date.
525 PREPARATION MATERIALS AND ANCILLARIES: Types recommended by their manufacturers
and the protective coating manufacturer for the surfaces being prepared.
530 GALVANIZING: All cutting, welding and drilling must be completed beforehand. Provide all
necessary vent and drain holes in approved locations and seal to approval after galvanising.
535 INSPECTION:
Permit coating manufacturers to inspect the work in progress, including surface preparation,
and to take samples of their products if required. Do not comply with any directions or requests
given by the coating manufacturer's representative unless and until confirmed by CA.
Notify CA of projected dates for start of surface preparation and coating.
Give CA at least 7 days notice before coated members or components leave the works.
540 HANDLING AND STORING COATED STEELWORK:
Use methods and equipment which will minimise chafing, chipping and other damage to coated
components.
Ensure an adequate drying/curing period for each coat before handling.
Use suitable packings, lashings, lifting harnesses, nylon slings, rubber protected chains and
chocks, etc.
Stack coated components clear of the ground, separated by timber chocks, and so that ponding
does not occur.
545 PROTECTION:
Protect freshly applied surface coatings from damage.
Exhibit ‘Wet paint' signs and provide protective barriers where necessary.
Protect surfaces adjacent to those being covered.
550 REMEDIAL WORK:
Early degradation of coatings by blistering, peeling, flaking, cracking, lack of adhesion, etc.
must be made good by complete removal, preparation and reapplication of all coats, as
instructed.
Inadequate dry film thickness or surface defects due to adverse weather may, depending on
the type of paint, be remedied by rubbing down and applying further coat(s), as instructed.
Mechanical damage to coatings must be made good by local cutting back of coatings,
preparation and reapplication of all coats to leave a neat, continuous and flat finish.
Where damage to coatings or subsequent surface preparation has exposed bare metal, it must
be thoroughly cleaned and primed within two hours.
37
Expo 2020: Ireland Pavilion
710 OFF-SITE PREPARATION AND PAINTING to be carried out under cover in properly lit, heated
and ventilated conditions. Select sequence of working from one of the following and inform CA before
starting work:
Fabricate - blast clean - prime as specified
Blast clean - fabricate - prime as specified (Immediately before priming remove flash rust with a
light overall sweep blast), or
Blast clean - prime with a weldable prefabrication primer recommended by the manufacturer of
the specified primer - fabricate - prime as specified (Thickness of post-fabrication priming coat
may be reduced if and as recommended by manufacturer).
715 INACCESSIBLE SURFACES: The sequence of working must be such as to ensure that surfaces
inaccessible after assembly receive the full specified treatment and coating system including, if necessary,
local shop application of site coatings.
725 MANUAL CLEANING OF NEW STEELWORK:
Chip, scrape, disc sand and grind surfaces to remove all fins, burrs, sharp edges, weld spatter,
loose rust and loose scale to leave a clean but unpolished surface to BS 7079: Part A1, grade
St2.
Thoroughly degrease and clean down. If using water based cleaners, remove subsequent
rusting back to grade St2.
Apply primer without delay.
730 PREPARATION FOR SITE WELDING OF SHOP PAINTED STEELWORK:
Blast clean and mask weld areas before coating surrounding areas. If more than one coat is
applied to surrounding areas, step each coat 30 mm back from edge of preceding coat.
Remove masking immediately before welding.
Alternatively prepare and shop paint weld areas as specified, then grind off to bare steel
immediately before welding.
735 TREATMENT OF SITE WELDED JOINTS IN PAINTED STEELWORK:
After welding, and without delay, remove all scale and weld spatter from the weld areas by
grinding or chipping, abrade to remove all traces of rust, wash with clean water and allow to dry.
Prime without delay and apply further coatings to the weld areas to match the surrounding
painted areas.
740 BOLTED JOINTS (NONFRICTION GRIP):
Where steelwork is to be shop painted, ensure that the full shop specification is applied to joint
faces.
Where steelwork is to be erected with a mill finish then site painted, prepare and prime joint
faces before erection and allow to dry.
Immediately before assembling bolted joints in externally exposed steelwork, apply a further
coat of primer and bring the surfaces together while still wet.
Before applying site coatings to externally exposed steelwork, seal all crevices to bolts and joint
perimeters with a compatible mastic.
745 FAYING SURFACES OF FRICTION GRIP JOINTS:
38
Expo 2020: Ireland Pavilion
Blast clean and mask before coating surrounding areas. The masking must adequately protect
the faying surface from deterioration and contamination.
If more than one coat is applied to surrounding areas, step each coat 30 mm back from edge of
preceding coat.
Remove masking immediately before bolting, check faying surfaces are free from adhesive,
and clean with solvent if necessary.
750 FRICTION GRIP JOINTS IN SHOP PAINTED STEELWORK:
After final tightening of bolts, and without delay, thoroughly degrease and clean bare steel at
joint edges and prime as specified.
Seal all crevices to bolts and joint perimeters with a compatible mastic.
Apply further coatings to surrounding areas to match adjacent shop painted areas before
applying specified site coatings.
755 UNCOATED FASTENINGS: After erection, thoroughly degrease and clean and, without delay,
apply coating(s) to match surrounding shop painted areas before applying specified site coating(s).
760 GALVANIZED FASTENINGS: After erection, thoroughly degrease and clean and apply a suitable
etch primer before applying specified site coating(s).
765 SITE PREPARATION OF SHOP PAINTED STEELWORK: Carry out all necessary remedial work
as specified. Prepare all surfaces by abrading and/or washing down as recommended by manufacturer
before applying coats.
770 SITE PREPARATION OF GALVANIZED SURFACES FOR PAINTING: Thoroughly degrease. If
metal coating is defective obtain instructions before proceeding. Remove any white corrosion products
with a stiff brush, wash off and allow to dry before applying specified etching wash or primer.
PAINTING
39
Expo 2020: Ireland Pavilion
Over any square metre of coating the average accumulated dry film thickness must equal or
exceed the specified thickness, with no reading less than 75% of the specified thickness.
825 STRIPE COATS: Where specified, brush apply an additional stripe coat to all external angles,
nuts and bolt heads, rough weld seams, and areas that are difficult to coat.
830 COLOUR OF TOP COAT to be selected by the Architect (unless already specified). Colour of
preceding coat to be as recommended by the paint manufacturer to suit the top coat colour.
40
Expo 2020: Ireland Pavilion
M FINISHES
250 CONDUITS UNDER FLOATING SCREEDS: Haunch up in 1:4 cement:sand on both sides of
conduits before laying insulation for floating screeds.
255 PIPE DUCTS/TRUNKING: Before laying screed, ensure that preformed access ducts are
securely fixed to the base and accurately levelled in relation to the finished floor surface.
BATCHING/MIXING/LAYING
310 BATCHING: Proportions of mixes made with dense aggregates are specified by weight and,
where practicable, should be batched by weight. Volume batching will be permitted on the basis of the
previously established weight:volume relationship(s) of the particular materials and using accurate gauge
boxes. Allow for bulking of damp sand.
311 BATCHING: Proportions of mixes made with lightweight aggregates are specified by volume and
should be batched using accurate gauge boxes.
330 MIXING:
- Do not use admixtures containing calcium chloride.
- Water content of mixes to be the minimum necessary to achieve full compaction, low
enough to prevent excessive water being brought to the surface during compaction.
41
Expo 2020: Ireland Pavilion
- Mix materials thoroughly to a uniform consistence. Mixes other than no-fines must be
mixed in a suitable forced action mechanical mixer. Do not use a free fall type (drum) mixer.
- Use while sufficiently plastic for full compaction.
- Use ready-mixed retarded screed mortar within the working time and site temperatures
recommended by the manufacturer. Do not retemper.
380 FLATNESS/REGULARITY OF FLOOR SCREEDS: Sudden irregularities are not permitted. When
measured with a slip gauge to BS 8204:Part 1, Figure 3 or equivalent, the variation in gap under a
straightedge (with feet) placed anywhere on the surface to be not more than the following:
- Screeds to receive toppings or beds 15-30 mm thick: 10 mm under a 3 m straightedge
- Screeds to receive mastic asphalt flooring/underlays:
5 mm under a 3 m straightedge
- Screeds to receive sheet or tile finishes bedded in adhesive:
5 mm under a 3 m straightedge
2 mm under a 1 m straightedge
FINISHING/CURING
510 TIMING: Carry out all finishing operations at optimum times in relation to the setting and
hardening of the material. Do not wet surfaces to assist surface working. Do not sprinkle cement onto
surface.
520 WOOD FLOATED FINISH: Use a wood float to give an even slightly coarse texture with no ridges
or steps.
530 SMOOTH FLOATED FINISH: Use a hand float, skip float or power float to give an even surface
with no ridges or steps.
- Immediately after laying, protect surface from wind, draughts and strong sunlight.
- As soon as screed/topping has set, closely cover with polyethylene sheeting and keep in
position for not less than 7 days.
- Do not heat screeds/toppings or the building artificially during first 4 to 6 weeks after
laying, thereafter raise temperature slowly.
44
Expo 2020: Ireland Pavilion
45
Expo 2020: Ireland Pavilion
GENERAL REQUIREMENTS
220 APPLICATOR'S PERSONNEL must have appropriate skill in applying and general knowledge of
anticorrosive and intumescent coatings. Provide evidence of competence and experience to the CA on
request.
240 DIFFICULT ACCESS AREAS: Consider, well in advance, any problems of access to areas to be
coated, bearing in mind the need to achieve complete integrity of the fire protection. Seek advice from the
intumescent coating manufacturer and, if required, obtain instructions from the CA.
250 SPRAY DRIFT: Wherever practicable arrange the sequence of trades so that spray drift is
avoided or covered by subsequent work, and in general ensure that it is kept to an absolute minimum.
Adjacent self-finished surfaces to be masked out.
260 CONTROL SAMPLE(S): Prepare sample area(s) of the finished work in advance of the remainder
as set out below. Obtain approval of appearance before proceeding:
270 INSPECTION:
- Permit intumescent coating manufacturer to inspect the work in progress and all quality
control records, take dry film thickness and other measurements, and take samples of coating products if
required. Do not comply with any directions or requests which vary the specification unless and until
confirmed by the CA. Submit a copy of intumescent coating manufacturer's inspection reports to the CA
without delay.
- Notify the CA of projected date(s) for start of surface preparation and coating.
PREPARATION OF SURFACES
46
Expo 2020: Ireland Pavilion
- Ensure that all necessary cleaning down and repair of damage to priming system is
carried out.
APPLICATION OF COATINGS
47
Expo 2020: Ireland Pavilion
- The average measured intumescent DFT to be not less than the specified
thickness (exclusive of primer and top sealer).
- If any reading is less than 80% of target DFT, the extent of the thin area must be
established. Any areas less than 80% of target over an area greater than 100 mm equivalent diameter
must be brought up to thickness.
440 BASIC FINISH: Reasonably smooth and even; orange peel, other texture, minor runs and similar
minor defects are acceptable.
450 NORMAL DECORATIVE FINISH: A good standard of cosmetic finish generally when viewed from
a distance of 5 m or more. Minor orange peel or other texture is usually acceptable.
460 HIGH DECORATIVE FINISH: A high standard of evenness, smoothness and gloss when viewed
from a distance of 2 m or more.
500 MARKING OF COATED STEEL: Apply self adhesive labels in approved locations giving:
- Manufacturer and reference of coating system.
- Warnings regarding damage to or removal of coatings.
- Requirements regarding maintenance and overcoating.
510 REPAIR DAMAGE TO INTUMESCENT COATINGS by locally abrading and cutting out, followed
by reapplication of primer, intumescent coat and top sealer coat to the original specification. Do not
overlap existing intumescent with new primer, or existing top sealer with new intumescent.
48
Expo 2020: Ireland Pavilion
Q PAVING
Q10 STONE/CONCRETE/BRICK KERBS/EDGINGS/CHANNELS
LAYING
220 ADVERSE WEATHER: Do not cast foundations, lay units or place haunching if the temperature is
below 3°C on a falling thermometer or 1°C on a rising thermometer. Adequately protect foundations,
bedding and haunching against frost and rapid drying by sun and wind.
230 CONCRETE FOR FOUNDATIONS AND HAUNCHING: To BS 5328, Designated mix not less
than GEN0 or Standard mix not less than ST1, very low workability.
270 CHANNELS: Set out to an even gradient to ensure no ponding or backfall. Lowest points of
channels to be 6 mm above drainage outlets.
49
Expo 2020: Ireland Pavilion
300 ANGLE KERBS to be used for both internal and external 90 deg changes of direction; cutting of
mitres will not be permitted.
320 NARROW MORTAR JOINTS: Butter ends of units with bedding mortar as laying proceeds to
completely fill joints. Tightly butt to a thickness of 3 mm and clean off surplus mortar immediately.
330 TOOLED MORTAR JOINTS: Butter ends of units with bedding mortar as laying proceeds to
completely fill joints to a thickness of 6 mm. Tool to a neat flush profile.
331 TOOLED COLOURED MORTAR JOINTS: Butter ends of units with bedding mortar as laying
proceeds to completely fill joints to a thickness of 6 mm. Rake out to a depth of 10 mm and point with 1:3
cement:sand mortar with pigment, colour to approval.
50
Expo 2020: Ireland Pavilion
120 CHECKING CBR OF SUBGRADE: The specified thicknesses of sub-bases are based on an
assumed subgrade of 350mm with an assumed CBR of 2.5 %.
If the subgrade material appears to be different from this, or if there are extensive soft
spots, test CBR of subgrade, report results to CA, and if different from the assumed CBR obtain
instructions before proceeding with laying sub-base.
151 SUBGRADE FOR VEHICULAR AREAS: Immediately before placing sub-base compact subgrade
with not less than four passes of a roller weighing 8-10 tonnes or by equivalent other means.
160 SUBGRADE FOR PEDESTRIAN AREAS: Immediately before placing sub-base thoroughly
compact subgrade with a roller weighing not less than 2.5 tonnes or equivalent other plant.
250 LAYING GRANULAR SUB-BASES FOR PEDESTRIAN AREAS: Spread and level and, as soon
as possible thereafter, compact with a roller weighing not less than 2.5 tonnes or other equivalent plant.
310 ACCURACY: Maximum permissible deviation from the required levels, falls and cambers to be as
follows:
Roads Footways
Parking areas Recreation areas
Subgrade +/- 25 mm +/- 20 mm
Sub-base +/- 20 mm +/- 12 mm
52
Expo 2020: Ireland Pavilion
320 BLINDING: Surfaces to receive interlocking brick or block paving to section Q24 to have sufficient
sand, fine gravel, PFA or other approved fine material applied and surface vibrated to provide a close and
smooth surface.
340 PROTECTION:
- Cover sub-bases as soon as practicable with subsequent layers, specified elsewhere.
- Prevent damage to subgrades and sub-bases from construction traffic, construction
operations and inclement weather.
53
Expo 2020: Ireland Pavilion
TYPES OF PAVING
GENERAL/PREPARATION
210 COMPLETE CORRELATED RECORDS must be maintained for each prescribed mix including:
- Information in accordance with BS 5328:Part 3, clauses 3.1 and 3.2.
- All sampling, site tests and identification numbers of all specimens tested in the
laboratory.
- The location from which each sample is taken.
220 TESTING:
- Test prescribed mixes in accordance with BS 5328: Part 4.
- Rate of sampling: As E10/500
- Tests to be carried out by one NAMAS accredited laboratory. Submit name of selected
laboratory as soon as possible and in any case before making trial mixes or concrete for use in the works.
- Submit 2 copies of test reports within one day of completion of each test. Keep a
complete set of reports on site.
- Use steel side forms, drilled as required for dowel bars, free from warping and kinks.
- Fix securely to required line, ±10 mm, and level, ±3 mm. Use locking plates where
necessary to ensure rigidity and prevent movement during laying and compaction of concrete.
- Remove forms not less than six hours after completing compaction and treat exposed
edges with approved waterproof compound.
LAYING CONCRETE
330 COMPACTING:
- Fully compact concrete to full depth (until air bubbles cease to appear on the surface)
especially around reinforcement, cast-in accessories, into corners and at joints.
- Poker vibrators must not be used to make concrete flow into position and must not come
into contact with fabric reinforcement.
- Rectify any irregularities at wet formed joint grooves by means of a vibrating float.
- Finish with an approved scraping straightedge immediately after completing compaction
to produce a dense, even textured surface free from laitance or excessive water.
- Remove any excess concrete from top of groove formers.
350 LEVELS:
55
Expo 2020: Ireland Pavilion
- Lines and levels of finished surface to be smooth and even, with regular falls to prevent
ponding.
- Finished surfaces to be within ±6 mm of required levels (+6 -0 mm adjacent to gullies and
manholes).
JOINTS
56
Expo 2020: Ireland Pavilion
- Round upper edges of slabs at joints to 5 mm radius using bullnose arris trowel without
overworking concrete.
- Remove fillet when concrete on both sides of joint is fully cured.
460 CONTRACTION JOINTS WITH WET FORMED GROOVE: To Concrete Society technical report
28.
- Prior to concreting, set formwork and dowel bars rigidly in position and support to prevent
displacement. Maintain support until concrete has set.
- Bottom crack inducer: Contractor’s proposal to be agreed with the CA.
Locate vertically below the top groove within a horizontal tolerance of ±10 mm and fix
securely to sub-base to retain in position during construction.
- Form deep groove in the surface of the plastic concrete and insert a 20 mm thick
temporary fillet.
- Recompact the displaced concrete without overworking it and round the edges of the
groove to 5 mm radius, using bullnose arris trowel.
- Keep temporary fillet in position until concrete on both sides of joint is fully cured.
SURFACE FINISH
510 SAMPLE AREA: Complete a sample area of the pavement, size 2 m², in advance of the
remainder and in an approved location. Obtain approval of CA before proceeding.
520 TAMPED FINISH: Tamp surface with edge of a board or beam to give an even texture of parallel
ribs.
540 SMOOTH FLOATED FINISH: After compaction allow the concrete to stiffen sufficiently to be
properly worked. Finish with a skip float, hand float or power float to produce an even smooth surface with
no ridges or steps.
57
Expo 2020: Ireland Pavilion
- Successively power trowel at intervals, applying sufficient pressure to close the surface,
to give a uniform smooth finish free from trowel marks and other blemishes.
- Resume specified curing without delay.
CURING/PROTECTION/FINISHING
610 CURING:
- Immediately after completion of surface treatment prevent evaporation from the surface
and exposed edges of the slab for a minimum period of seven days.
- Coverings for curing to be a suitable impervious sheet material, a resin based aluminised
curing compound containing a fugitive dye and with an efficiency index of 90% when tested to BS 7542 or
an approved sprayed plastics film.
- Curing compounds applied to surfaces that are to be decorated/stained must be removed
by light grit blasting.
- Until the surface of fresh concrete is in a state suitable to receive sheets which are in
direct contact or a sprayed curing compound as applicable, cover with waterproof sheeting held clear of
the surface and well sealed against draughts at edges and junctions.
58
Expo 2020: Ireland Pavilion
670 OPENING TO TRAFFIC: Light vehicles will be permitted on the pavement after 7 days and heavy
vehicles after 28 days.
59
Expo 2020: Ireland Pavilion
R GROUNDWORKS
EXCAVATING/BACKFILLING
205 EXCAVATED MATERIAL: Unless otherwise specified, set aside turf, topsoil, hardcore, etc. for
use in reinstatement.
210 LOWER PART OF TRENCH: From bottom up to 300 mm above crown of pipe the trench must
have vertical sides and be of a width as small as practicable but not less than external diameter of pipe
plus 300 mm or larger dimension if specified.
220 LOWER PART OF TRENCH: Where the depth of cover exceeds the transition depth for the size
of pipe, trench width up to 300 mm above crown of pipe to be not more than:
Nominal pipe size DN 100 150 225 300
Transition depth (m) 6.0 5.4 4.0 2.9
Maximum trench width (mm) 600 700 800 900
221 LOWER PART OF TRENCH: Where bedding class S is specified (see clause 370) trench width to
be not more than the following, regardless of depth of cover:
Nominal pipe size (DN) 100 150 225 300
Maximum trench width (mm) 600 700 800 900
230 ASSUMED TYPE OF SUBSOIL: Where the type of subsoil at the level of the crown of the pipe
differs from that stated for the type of pipeline, obtain instructions before proceeding.
250 COMBINED TRENCHES: Where one pipe is at a lower level than another adjacent pipe in a
common trench:
- A subtrench is permissible provided the soil of the step is stable and unlikely to break
away.
- If a subtrench is not permissible, the whole trench must have a depth related to the lower
pipe, with increased thickness of bedding to the upper pipe as necessary.
- The lower pipe must be backfilled with compacted granular material to not less than half
way up the higher pipe.
260 TRENCH SUPPORTS: Remove trench supports and other obstacles sufficiently to permit
compacted filling of all spaces.
270 BACKFILLING TO PIPELINES GENERALLY: Unless specified otherwise, backfill from top of
specified surround or protective cushion with material excavated from the trench, compacted in layers not
exceeding 300 mm thick. Do not use heavy compactors before there is 600 mm of material over pipes.
60
Expo 2020: Ireland Pavilion
280 BACKFILLING UNDER ROADS AND PAVINGS: Backfill from top of specified surround or
protective cushion up to formation level with Granular Subbase Material Type 1 to DOT Specification for
Highway Works, Clause 803, laid and compacted in 150 mm layers.
281 BACKFILLING OVER CONCRETE: Do not start backfilling within 24 hours of placing concrete.
Do not use heavy compactors and prevent imposition of traffic loads within 72 hours of placing concrete.
290 TEMPORARY BRIDGES: Provide temporary bridges over trenches as necessary to prevent
construction traffic damaging pipes after backfilling.
BEDDING/JOINTING
61
Expo 2020: Ireland Pavilion
- Cut holes in trench bottom for couplings/sockets and lay pipes resting uniformly on their
barrels, adjusting to line and gradient. Do not use hard packings under pipes.
- After initial testing, backfill to 150 mm (250 mm for adoptable sewers) above crown of
pipe with a protective cushion of selected fill, free from vegetable matter, rubbish, frozen soil and material
retained on a 40 mm sieve. Compact by hand in 100 mm layers.
63
Expo 2020: Ireland Pavilion
- Lay 75 mm deep bed, at least 100 mm wider than pipe, with 10 mm single size material to
BS 882.
- Lay pipes and adjust to line and gradient.
- Complete surround with 20 mm single size material compacted to 150 mm above crown
of pipe.
470 TRENCHES LESS THAN ONE METRE FROM FOUNDATIONS: Where bottom of trench is lower
than bottom of foundation, use Class Z concrete surround as clause 461. Top of concrete to be not lower
than bottom of foundation.
490 CROSSOVERS: Where two pipelines (other than plastics pipes) cross with less than 300 mm
separation, surround each with Class Z concrete surround as clause 461 for not less than 1 m centred on
the crossing point. Extend length of concrete surrounds as necessary to within 150 mm of next nearest
flexible joints.
64
Expo 2020: Ireland Pavilion
- Invert of horizontal drain at base of stack to be not less than 450 mm below centreline of
lowest branch pipe.
- Stabilize bend(s) by bedding in concrete without impairing the flexibility of couplings.
530 RIGID BACKDROP PIPES outside the manhole wall: Encase with not less than 150 mm of
concrete as specified under Generally. All excavation beneath the backdrop pipe and its surround must be
replaced with concrete.
TERMINAL/ACCESS FITTINGS
680 MANUFACTURE: Obtain each complete assembly of fittings, traps, etc., including appropriate
couplings, from the same manufacturer, and check compatibility of components with each other and with
the pipe system.
MANHOLES/CHAMBERS/SOAKAWAYS/TANKS
- Steps: to BS 1247.
Bed in joints to all chambers over 900 mm deep at 300 mm vertical centres staggered
300 mm horizontally, with lowest step not more than 300 mm above benching and top step not more than
450 mm below top of cover.
Cover slabs: precast or in situ concrete at Contractors discretion. If precast, bed solid in 1:3 cement:sand
mortar to brickwork.
Openings to suit required access covers.
Concrete mix as specified under Generally.
Reinforcement: Steel fabric to BS 4483, reference E30
Access covers and seating: Class C25 Cover and Frame To IS/EN 124
835 LIFTING KEYS: Provide suitable lifting keys for each type of access cover and hand over to the
Employer at Practical Completion.
851 OUTFALL(S)
- Drawing reference(s): Refer to the Civil and Structural Engineers drawings.
- In situ concrete base: 500mm thick plain concrete, mix as specified under Generally.
- Brickwork/Blockwork: Type F10
- Ensure that pipe outflow invert is no lower than seasonal peak level or 150 mm above
normal water level, whichever is the higher.
- Pipe surround and backfill to the last 2 m run of drain to be excavated subsoil, rammed
home.
- Vermin grating: Mild steel frame to extend 75 mm beyond pipe opening on all sides, with
25 mm maximum opening steel mesh grille. Top hinged on built-in fish-tail straps and with bottom pin
lock. All galvanized to BS 729 after fabrication.
861 CONNECTIONS TO SEWERS: Connect new pipework to existing adopted sewer(s) to the
requirements of the Statutory Authority or its agent.
CLEANING/TESTING/INSPECTION
66
Expo 2020: Ireland Pavilion
900 CLEANING:
- Flush out the whole of the installation with water to remove all silt and debris before final
testing, before CCTV inspection if specified and immediately before handover.
- Safely dispose of washings and any detritus without discharging them into sewers or
watercourses.
67
Expo 2020: Ireland Pavilion
Z BUILDING FABRIC
20 FIXINGS/ADHESIVES
10 FIXING GENERALLY: Use fixing and jointing methods and types, sizes, quantities and spacings
of fasteners which are suitable having regard to:
- Nature of and compatibility with product/material being fixed and fixed to,
- Recommendations of manufacturers of fasteners and manufacturers of components,
products or materials being fixed and fixed to,
- Materials and loads to be supported,
- Conditions expected in use,
- Appearance, this being subject to approval.
30 FIXING THROUGH FINISHES: Ensure that fasteners and plugs (if used) have ample penetration
into the backing.
35 PACKINGS
- Provide noncompressible, rot proof packings at fixing points to take up tolerances and
prevent distortion.
- Ensure that packings do not intrude into zones that are to be filled with sealant.
40 CRAMP FIXING:
- When not specified otherwise, position cramps not more than 150 mm from each end of
frame sections and at 600 mm maximum centres.
- Secure cramps to frames with matching screws as masonry work proceeds, and fully bed
in mortar.
50 PELLETING: Countersink screw heads 6 mm below timber surface and glue in grain-matched
pellets cut from matching timber. Finish off flush with face.
60 ADHESIVES:
- Types: As specified in the relevant section.
- Surfaces to receive adhesive to be sound, unfrozen and free from contamination likely to
affect bond. Where necessary, clean as recommended by manufacturer.
- Adjust surface regularity and texture as necessary to suit bonding and gap filling
characteristics of adhesive.
- Observe manufacturer's and statutory requirements for storage and safe usage of
adhesives.
- Do not use in unsuitable environments or beyond the storage period recommended by the
manufacturer.
- Apply using recommended spreaders/applicators to ensure correct coverage. Bring
surfaces together within recommended time period and apply pressure to ensure full bonding.
- Remove surplus using methods recommended by manufacturer, without damaging
surfaces.
68
Expo 2020: Ireland Pavilion
Z21 MORTARS
10 MORTAR MIX PROPORTIONS and other particular requirements are specified elsewhere.
40 CEMENT FOR MORTAR: When not specified otherwise, to be Portland cement or Portland
blastfurnace cement, to class 42.5 or 52.5, manufactured and supplied under the BSI Kitemark scheme
for cement. All cements must comply with the appropriate British Standard.
50 ADMIXTURES: To BS 4887. Do not use in mortar unless specified or approved. Do not use
calcium chloride or any admixtures containing calcium chloride.
60 MAKING MORTAR:
- Keep plant and banker boards clean at all times.
- Measure materials accurately by volume using clean gauge boxes or clean, undamaged
buckets. Proportions of mixes are for dry sand; allow for bulking if sand is damp.
- Mix ingredients thoroughly to a consistence suitable for the work and free from lumps. Do
not overmix mortars containing air entraining admixtures.
- Do not mix mortar when the air temperature is at or below 3°C and falling or below 1°C
and rising.
- Use mortar within about two hours of mixing at normal temperatures. Do not use after the
initial set has taken place and do not retemper.
69
Expo 2020: Ireland Pavilion
Z22 SEALANTS
10 SEALANT TYPES: As specified in the relevant section.
30 PREPARING JOINTS:
- Remove all temporary coatings, tapes, loosely adhering material, dust, oil, grease and
other contaminants which may affect bond.
- Backing strip, bond breaker, primer: Types recommended for the purpose by sealant
manufacturer.
- Insert backing strips and/or bond breaker tape into joint leaving no gaps.
- Cover adjacent surfaces with masking tape to prevent staining and protect surfaces which
would be difficult to clean if smeared with primer or sealant.
40 APPLYING SEALANTS:
- Do not apply to damp surfaces (unless recommended otherwise), to surfaces affected by
ice or snow or during inclement weather. Do not heat joints to dry them or raise the temperature.
- Fill joints completely, leaving no gaps, excluding all air and ensuring firm adhesion of
sealant to required joint surfaces. Tool the sealant to a neat, slightly concave profile unless specified
otherwise.
70