Академический Документы
Профессиональный Документы
Культура Документы
GOVERNMENT OF PUNJAB
PRE-QUALIFICATION DOCUMENTS
FOR THE WORK
Description Page
1. Brief of Project 4
A. General 6
B. Content of PQD 8
C. Preparation of Application 9
D. Submission of Application 10
E. Evaluation of Application 11
F. Prequalification of Application 11
1. General 14
4. Conflict of Interest 20
2
2.5 Updating Prequalification Information---------------------------------------- 20
Letter of Application - 22
A. General
5.7 An Applicant shall submit only one application for one work in the
prequalification process. In case of applying for both projects, the
applicant must submit a separate request for each project. The
applicant must have technically, financially and managerially
capable of executing / handling the works in case of applying
for both projects. An Applicant who submits more than one
application for single a work thereby liable for disqualification of all
the applications.
6. Eligible 6.1 The materials, equipment and services must meet the eligible
Materials, criteria as defined in this document.
Equipment and
Services
9. Amendment of 9.1 Not later than Seven (07) days prior to the deadline for submission
Prequalification of Applications, the Employer may amend the Prequalification
Documents Documents by issuing addenda.
C. PREPARATION OF APPLICATIONS
10. Cost of 10.1 The Applicant shall bear all costs associated with the preparation
Applications and submission of its application, and the Employer shall in no
case be responsible or liable for those costs, regardless of the
conduct or outcome of the prequalification process.
11. Languages of 11.1 The application, as well as all correspondence and documents
Application relating to the prequalification exchanged by the Applicant and the
Employer, shall be written in the English language. Supporting
documents and printed literature that are part of the application
may be in another language, provided they are accompanied by
an accurate translation, duly authenticated by Embassy or
counsel, of the relevant passages into the English language, in
which case, for purposes of interpretation of the application, the
translation in English shall govern.
14. Documents 14.1 To establish its eligibility in accordance with ITA Clause 5, the
Establishing Applicant shall complete the eligibility declarations in the
Application Submission Sheet and Forms included in, Application
the Eligibility of Forms.
the Applicant
15. Signing of the 15.1 The Applicant shall prepare one original of the documents
Application comprising the application as described in ITA Clause 12 and
clearly mark it “ORIGINAL”. The original of the application shall be
and Number of
typed or written in indelible ink and shall be signed by a person
Copies duly authorized to sign on behalf of the Applicant.
15.2 The Applicant shall submit one original along three (03) hard and
soft copies individually clearly marked as “ORIGINAL” and
“COPY” on the title page for one project or in case of applying in
more than one projects. In the event of any discrepancy between
the original and the copies, the original shall prevail.
D. SUBMISSION OF APPLICATIONS
16. Sealing and 16.1 The Applicant shall enclose one original along with three (03) hard
Marking of and soft copies for every project. The application shall be
submitted in a sealed envelope; which shall
Applications
(a) Bear the name and address of the Applicant;
(b) Be addressed to the Employer’s Representative, in accordance
with Sub-Clause ITA 8.2; and;
(c) Bear the specific identification of this prequalification document
indicated in the ITA Sub-Clause 2.1.
16.2 If the envelope is not sealed and marked as required, the
Employer will assume no responsibility for the misplacement of
the application.
16.3 The applicant should attach the detail of contents with page
numbers at the start and should properly flag / append the
relevant pages in the application.
17. Deadline for 17.1 Applications shall be submitted by the Applicant through courier /
Submission of express mail or by hand at the address indicated in the ITA Sub-
Applications Clause 8.2. However, applicant must ensure that the application
must reach not later than the following deadline:
17.2 The Employer may, at its discretion, extend the deadline for the
submission of Applications by amending the Prequalification
Documents in accordance with ITA Clause 9, in which case all
rights and obligations of the Employer and the Applicants subject
to the previous deadline shall thereafter be subject to the deadline
as extended.
18. Late 18.1 The application received after the deadline will not be entertained
Applications and shall be considered as rejected.
19. Opening of 19.1 The Employer shall prepare a record of the opening of
Applications Applications that shall include, as a minimum, the name of the
Applicants.
E. EVALUATION OF APPLICATIONS
22.Responsiveness 22.1 The Employer may reject any Application which is not responsive
of Applications to the requirements of the Prequalification Documents.
F. PREQUALIFICATION OF APPLICANTS
23. Evaluation of 23.1 The Employer shall use the criteria and methods define in Section
Applications II, Prequalification Criteria to evaluate the qualifications of the
Applicants for every project.
24. Employer’s 24.1 The Employer may reject all Bids or Proposals at any time prior to
Right to Accept the acceptance of the Bid or Proposal as provided in Rule 35 of
or Reject Punjab Procurement Rules, 2014.
Applications
25. Prequalification 25.1 All Applicants, whose applications have been determined to be
of Applicants responsive to the requirements of the Prequalification Documents
and who have met or exceeded the specified criteria (Passed)
shall be prequalified by the Employer.
26. Notification of 26.1 Once the Employer’s Representative has completed the
Prequalification evaluation of the Applications, it shall notify all Qualified &
disqualified Applicants in writing.
27. Invitation to Bid 27.1 Promptly after the notification of the results of the prequalification,
the Employer shall invite bids from all the Applicants that have
been prequalified.
27.2 Bidders may be required to provide bid security in the form of a
Call Deposit Receipt (CDR) for an amount as specified in the
bidding document.
28. Changes in 28.1 Any change in the prequalification status of an Applicant after
Qualification of being prequalified in accordance with ITA Clause 25 shall be
subject to the written approval of the Employer. Any such change
Applicants
shall be submitted to the Employer not later than fourteen (14)
days after the date of the Invitation to Bid. Such approval shall be
denied if as a consequence of any change;
2. Weightage /Marks
The weight age / distribution of the marks is as given below:
1. Work Experience 45
3. Personnel Capabilities 15
4. Financial Soundness 30
Note:-Prequalification status shall be determined on the Pass/Fail basis. The applicant
must score total 65 marks and at least 50% marks in each category, to qualify. If
applicant fails to score 50% marks in any of above mentioned categories, will be
considered disqualified.
The firms fulfilling the following basic requirements shall only be considered for further
evaluation (relevant documents to be attached):
OR
OR
Full marks in case of water
Completed at least 01-Project of
Civil work for worth not less than supply component ≥ 30 Million.
120 Million in last ten years
30-Marks in case of water
involving water supply supply component ranging
component. from 25-29.99 Million. 25-
marks in case of water supply
component ranging from 20-
24.99 Million. 20-marks in case
of water supply component
ranging from 15-19.99 Million.
Sr. MAX
DESCRIPTION / CRITERIA REMARKS
# MARKS
Finance /Business Management Staff
(1 No. MBA / M.com (Finance /
Accounts / HR) with at least 3 years of Add CV's, experience
experience. certificates, affidavit of
OR employee on judicial
i) 2.5
1 No. BBA / B.com with at least 5 years stamp paper. No marks if
of experience. required documents are
No marks for less than minimum not attached.
experience.
i) The joint venture must collectively satisfy the criteria illustrated at points 2.2.1 to
2.2.4 for which purpose the relevant figures for each of the partners shall be added
together to arrive at the JV’s total capacity. Individual members must satisfy each of
the requirements of point 2.1.1, 5 and 6 heretofore.
b) Any change in a pre-qualified JV after prequalification, shall be subject to written
approval of employer prior to deadline for submission of bids. Such approval may be
denied if:-
(i) Partner (s) withdraw from a JV and remaining partners do not meet the qualifying
requirements.
(ii) The new partners to a JV are not qualified individually or as another JV.
(iii) In the opinion of employer, a substantial reduction in competition would result.
c) Bid shall be signed by all members in the JV so as to legally bind all partners, jointly
and severally, and bid shall be submitted with a copy of the JV agreement providing the
joint and several liabilities with respect to the contract.
d) The JV must submit the copy JV agreement clearly showing the percentage shares
of each member of JV along with the application.
3.2 The prequalification of a JV does not pre-qualify any of its partners individually or as
a partner in any other JV or association. In case of dissolution of JV or association,
each one of the constituent firms may pre-qualify if they meet all the prequalification
requirements and any partner of J.V has requested / shall request for the same and
then his prequalification shall be subject to the written approval of the Employer.
4. Conflict of Interest
4.1 The Applicant (including all members of a JV) must not be associated, nor have
been associated in the past, with the consultant or any other entity that has prepared
the design, specifications, and other prequalification and bidding documents for the
project, or was proposed as Engineer for the contract, over the last five years. Any such
association may result in disqualification of the applicant.
5.1 Bidders shall be required to update the financial, personnel and equipment
information used for prequalification at the time of submitting their bids, to confirm their
continued compliance with the qualification criteria and verification of the information
provided at the time of prequalification. A bid shall be rejected if the Applicant’s
qualification thresholds are no longer met at the time of bidding.
6 Other Factors
6.1 Only firms and JVs that have been pre-qualified under this procedure shall be
invited to bid. A qualified firm or a member of a qualified JV may participate only in one
bid for the contract. If a firm submits more than one bid, singly or as a JV, all bids
including that bidder will be rejected. This rule will not apply in respect of bids which
include specialist sub-contractors who are used by more than one bidder.
Letter of Application
Date:................................
To: ............................................................
.............................................................
Sir,
{Note: The Applicant is to delete, any contract for which he does not wish to pre-qualify,
and sign and date the deletion. If the prequalification refers to only one contract, delete
this note and spaces for additional contract references}.
(c) The place of incorporation (for applicants who are corporations); or the place of
registration and the nationality of the owners (for applicants who are partnerships or
individually-owned firms).
3. Your Agency and its authorized representatives are hereby authorized to conduct any
inquiries or investigations to verify the statements, documents, and information
submitted in connection with this application, and to seek clarification from our bankers
and clients regarding any financial and technical aspects. This Letter of Application will
also serve as authorization to any individual or authorized representative of any
institution referred to in the supporting information, to provide such information deemed
necessary and requested by yourselves or the authorized representative to verify
statements and information provided in this application, or with regard to the resources,
experience, and competence of the Applicant.
4. Your Agency and its authorized representatives may contact the following persons for
further information, if needed.
Applicants who are not joint ventures should delete para 6&7 and initial the
deletions.
Name Name
Where the Applicant proposes to use named subcontractors for critical components of
the works or for work contents in excess of 10 percent of the value of the whole works,
the following information should also be supplied for the specialist subcontractor(s).
1 Name of Firm
2 Head Office Address
3 Telephone Contact Person:
Name:
Title:
4 Fax Telex
The applicant must attach the following basic eligibility documents with basic
information form duly illustrated in detail of the Section II.
Application Form A-2
All individual firms and all partners of a joint venture are requested to complete the
information in this form. The information supplied should be the annual turnover of the
Applicant (or each member of a joint venture), in terms of the amounts billed to clients
for each year for work in progress or completed over the past ten years.
Year
Turnover Rs. in
(in actual currency) Millions.
1.
2.
3.
Application Form A-3
1. Lead Partner
2. Partner
3. Partner
4. Partner
5.Partner
6.Partner
3.Partner
4.Partner
5.Partner
6.Partner
Total
Application Form A-4
1 Name of Contract
Country
2 Name of Employer
3 Employer Address
4 Nature of works and special features relevant to the contract for which the Applicant wishes
to prequalify
8 Date of Award………………………………………………………………
9 Date of Completion………………………………………………………..
Personnel Capabilities
Name of Applicant
Title of Position
1
Name of Prime Candidate
Title of Position
2
Name of Prime Candidate
Title of Position
3
Name of Prime Candidate
Title of Position
4
Name of Prime Candidate
Title of Position
5
Name of Prime Candidate
Title of Position
6
Name of Prime Candidate
Application Form A-5(ii)
Engineers Details
Name of Firm/Contractor:
Net
Sr. Engineer's PEC Monthly Total Paid Salaries of Tax
NTN Salary
No. Name No. Salary Last Three Years Deposited
Paid
1
10
Name of Applicant
The Applicant shall provide adequate information to demonstrate clearly that he has the
capability to meet the requirements for each and all items of equipment listed in the
Instructions to Applicants. A separate Form shall be prepared for each item of
equipment listed in para 2.2.5of the Instructions to Applicants, or for alternative
equipment proposed by the Applicant.
Item of Equipment
Name of manufacturer Model and power rating
Equipment
information
Capacity Year of manufacture
Current location
Current
Details of current commitments ------------------------------------------------------
status
Fax Telex
Agreement Details of rental/lease specific to the Project.
Financial Capability
Name of Applicant or Partner of a Joint Venture
Applicants, including each partner of a joint venture, should provide financial information
to demonstrate that they meet the requirements stated in the Instructions to Applicants.
Each applicant or partner of a joint venture must fill-in this form. If necessary, use
separate sheets to provide complete banker information. A copy of the audited balance
sheets should be attached.
Address of banker
Fax Telex
Summarize actual assets and liabilities in Pak Rupees for the previous five years, based
upon known commitments, projected assets and liabilities in Pak Rupees.
Specific proposed sources of financing to meet the cash flow of the Project, net of
current commitments.
Source of financing Amount (Pak Rs.)
1.
2.
3.
4.
Annual Audit Report for the last five years duly certified by Chartered Accountant Firm
and Bank statement for the last ten years showing the transactions of completed works
of last ten years.
Firms owned by individuals, and partnerships, may submit their balance sheets certified
by registered accountant, and supported by copies of tax returns, if audits are not
required by the laws of their countries of origin in case of foreign firms.
Application Form A-8
Litigation History
Applicants, including each of the partners of a joint venture, should provide information
on any history of litigation or arbitration resulting from contracts executed in the last five
years or currently under execution. A separate sheet should be used for each partner of
joint venture.
Disputed
Award for or
Name of client, cause of Amount(current
Against
Year litigation, and matter in dispute value
Applicant
Pak Rs.)
Application Form A-9
Past Performance
Organization Name:
Remarks
Sr. No Description
A B C
1 Managerial capabilities
2 Planning capabilities
3 Execution capabilities
4 Equipment capabilities
5 Quality of the executed works
6 Handling of urgency of works
7 Execution of mega projects
8 Litigation History
9 Safety measures
10 Fulfillment of Project time period
Note: Certificate should be signed by an officer not below the rank of SE/Director
Works showing name, designation, department and official contact number.
Performance should be evaluated/ranked as:
A= 1 Mark
B= 0.5 Mark
C= 0 Mark