Академический Документы
Профессиональный Документы
Культура Документы
To get optimum good result more realistic approach has been adopted taking in account the
various consequences that may arise during the real practice. The detail estimate was made
based on DoLIDAR norms and Nepal Rural Road Standard (NRRS 1st Revision) and the
designed surface is blacktop.
Total 32 IPs stations along with Bench Marks were fixed and were carried from “Dovan” to
“Nuwakot”. The total length of road surveyed was 2.00 Km. Total project cost for the
construction of this road is NRs 1,99,20,281.61
i
ACKNOWLEDMENT
The satisfaction that accompanies the successful completion of any task would be
incomplete without mentioning the people who made it possible. So, we acknowledge all
those whose guidance and encouragement helped us and crowned our efforts with success.
We express our heartiest gratitude with great pleasure to School of Engineering, Pokhara
University which provided us an opportunity in fulfilling our cherished desire of attaining
our goal and for the encouragement rendered by them.
We find no word to express our sincere gratitude and we are extremely thankful to our
supervisor Er. Buddhi Raj Joshi, who has been a constant source of inspiration and
encouragement. His valuable advice and expert suggestions have been the primary source for
the successful completion of this project.
We would also like express our deepest gratitude and special thanks to Er. Arjun Guatam
Director of School of Engineering and Er. Rajendra Aryal Co-ordinator of School of
Engineering for kind suggestion in surveying and design work of this project. We are also
thankful to all local participants and friends for kind co-operation, guidance and help during
execution of field survey work and required information.
ACKNOWLEDMENT..............................................................................................................v
CHAPTER-1.............................................................................................................................x
INTRODUCTION....................................................................................................................1
1.1 General............................................................................................................................1
CHAPTER: 2............................................................................................................................3
LITERATURE REVIEW.........................................................................................................3
2.4.2 Reconnaissance........................................................................................................7
2.4.4 Leveling...................................................................................................................9
2.4.7 Economy..................................................................................................................9
2.5.2 Cross-section..........................................................................................................11
2.11Highway Drainage.......................................................................................................31
2.13.1 Introduction..........................................................................................................38
CHAPTER 3...........................................................................................................................42
METHODOLOGY..................................................................................................................42
CHAPTER 4...........................................................................................................................49
CHAPTER 5...........................................................................................................................60
COST ESTIMATE..................................................................................................................60
4.2.1 Earthwork...............................................................................................................60
4.5 Report............................................................................................................................61
CHAPTER 6...........................................................................................................................62
BIBLIOGRAPHY 63
ANNEXES
INTRODUCTION
1.1 General
Road development in Nepal started only after the advent of democracy in 1950. The national
road network comprises of national highways, feeder roads, urban roads, district roads and
village roads. The national highways together with feeder roads constitute the strategic road
network (SRN) of country. The SRN is the backbone of the national road network. The
construction and maintenance of the SRN falls on the responsibility of the DOR. The district
roads together with village roads constitute the district road networks. At present the national
road networks has altogether 11,635.58Km (64% blacktop, 25% gravel and 11% earthen
road) according to last update of 2012 by DOR.
Gravel
25%
Black top
64%
The proposed road is situated in Lumbini zone, connecting Dovan V.D.C. to Nuwakot
V.D.C. of Palpa district. At present, the roadway is a 3.0m wide earthen road which
excessively degrades during rainy season making it nearly impossible for use due to absence
of proper drainage system. The road is also found to be narrow for efficient use. Road is
used by local residents for commute. Farmers use it to transport produced goods and
emergency use like ambulance, fire brigade and the police.
The road is not subjected to extreme landslides and soil erosion but ruts and potholes of mud
during monsoon hinder effective use of the road.
1
The site is so located that it has a great importance in connecting the places from point of
agricultural production. Although it is very near from the Butwal city, most of the peoples
are uneducated and it lacks proper schooling for the children. Thus it may provide an
opportunity for the children to be in touch with butwal city to have better communication
with national and international world.
The existing surface is covered almost with broken stones and earth thus making difficulty in
the movement of vehicle in the opened track. The road excessively degrades during rainy
season making impossible for use due to proper drainage system. Furthermore the existing
earthen road is washed out by rain water during rainy season deteriorating the condition of
the road more and more. The upgrade of the proposed alignment would help in the overall
development of the Dovan and other connected VDCs.
LITERATURE REVIEW
The previous project thesis, detail reports of road design, Nepal Road Standards, training
manual for engineers were thoroughly taken in consideration and discussed among the
project team during the development of project work. The study of different road related
publications, documents, etc gave the good idea of the project scenario and guided
significantly for the completion of the final year project.
It is highly uneconomical to change the road alignment once it is aligned and constructed
due to increase in cost of adjoining land and construction of costly structures by the road
side. Thus careful consideration should be taken while finalizing the alignment.
Easy: The selected alignment should be easy in construction and it should have minimum
complications while it is in maintenance phase. In addition, the alignment should be easy for
the operation of vehicles with easy gradients and curves.
Safe: The alignment should be safe enough for construction and maintenance from the
viewpoint of stability of natural hill slopes, embankment and cut slopes and foundation of
embankments. In addition, it should be safe for the traffic operation with safe geometric
features.
Economical: The road alignment can be considered economical only if the total cost
including initial cost, maintenance cost and vehicle operation cost is lowest along with the
consideration that it is short, easy and safe. All these factors should be given due
consideration before working out the economics each alignment.
b) Traffic
c) Geometric design
d) Economics
e) Other considerations
a) Obligatory points
These are the control points governing the alignment of highway .These are of two
categories.
Points through which a highway is to pass such as:
An industrial area or mine zone to which a highway is to serve additionally
Tourist spots
Bridge site (suitable)
Hill pass
Link with intermediate towns
b) Traffic
Traffic requirements need to be fulfilled while selecting the alignment. The desire lines
should be drawn showing the trend of traffic flow and the detail study of their origin and
destination points need to be carried out. The desired lines, traffic flow patterns and future
trends need to be carefully considered while aligning the highway.
c) Geometric design
Factors such as gradient, radius of curve and sight distance also would govern the final
alignment of the highway. The gradient should be flat and less than ruling or design gradient
as far as possible. Adjustments considering the horizontal alignment along with the view of
design speed, maximum allowable superelevation and lateral friction need to be considered.
d) Economy
In working out the economics, the initial cost of maintenance and vehicle operation should
be taken into account. There should be balance in cutting and filling with the decrement of
high embankment and deep cutting.
e) Other considerations
Factors like drainage considerations, hydrological factors, political considerations and
monotony may govern the alignment. The vertical alignment is guided by drainage
considerations. The subsurface water level, seepage flow and high flood level are the factors
to be kept in view.
For hill roads, special considerations have to be given, for the followings:
a) Stability
b) Drainage
d) Resisting length
2.4.2 Reconnaissance
The second stage of surveys for highway location is the reconnaissance to examine the
general character of the area for deciding the most feasible routes for detailed studies. A
field survey party may inspect a fairly broad stretch of land along the proposed alternative
routes of map in the field using simple instruments like Abney level. All relevant details not
available in the map are collected and noted down. Some of the details to be collected during
reconnaissance are mentioned as follows:
1. Valleys, ponds, lakes, marshy land, ridge, hills, permanent structures and other
obstruction along the route, which are not available in the map study.
2. Approximate value of gradient, length of gradient and radius of curves of alternative
alignments
3. Number and types of cross drainage structures, maximum flood level and natural
ground water level along the probable routes.
4. Soil type along the routes from the field identification tests and observation of
geological features
5. Sources of construction materials, water and location of stone quarries.
6. When the road passes through hilly or mountainous terrain, additional data regarding
the geological formation, type of rocks, dip of strata, seepage flow etc may be
observed so as to decide the stable and unstable sides of the hill for highway
alignment.
Aerial survey is the best method of reconnaissance especially when the area is vast and the
terrain is difficult. From the details collected during the reconnaissance, the alignment
proposed after map study may be altered or even changed completely for better design of
road.
Plan:
It is the top view of project in a map. It consists of
a) North line.
b) Location of IPs and BMs with references.
c) Location of road centerline, formation width and right of way.
2.4.4 Leveling
Leveling is the branch of surveying which deals with the measurements of relative heights of
different points on the surface of earth. The objective of leveling is to find the elevations of
given points with respect to a given elevations or at a different elevations with respect to a
given or assumed datum. Leveling deals with measurements in a vertical plane. For the
purpose of road construction, the profile leveling is carried out to determine the R.L. of the
centerline located with driven pegs. The leveling determines the alignment of the road. The
leveling is taken at the suitable interval according to the site.
2.4.7 Economy
On the basis of above requirements the alignment should be finalized and should also be
economical. The initial construction cost might be the governing factor due to budget
constraints and alignment is selected accordingly even if the road yields highest maintenance
cost and vehicle cost. The initial cost of construction can be decreased if high embankments
and deep cuttings are avoided and the alignment is chosen in a manner to balance the cutting
and filling.
2.5 Geometric design of highway
The dimension and layout of visible features of highway such as alignment, sight distance
and intersections are dealt in the geometric design of road. To provide optimum efficiency in
traffic operations with maximum safety at reasonable cost, the geometry of the road should
be designed carefully. The safe, efficient and economic operation of a highway is governed
to a large extent by the care with which the geometric design has been worked out. Efficient
and comfortable operation of traffic is possible only if the design elements have been
meticulously considered .A well designed highway has to be consistent with economy .Too
liberal standards may not fit with the available resources, whereas if the standards are too
lows, the cost of operation may mount up.
2.5.1.3 Chainage
The total length of the road alignment can be defined as the chainage. The proposed road
alignment consists of hilly terrain in almost all chainage. The cross sections were taken at
20m intervals in all places. The total chainage of the highway alignment we have surveyed is
approximately 2km.
2.5.2 Cross-section
Cross-sections run at right angles to the longitudinal profile and on either side of it for the
purpose of lateral outline of the ground surface. Cross-sections provide the data for
estimating quantities of earthwork and for other purposes. The scale selected for plotting is
equal in both the axes. Cross-sections are plotted for each elements of curve. The cross-
section consists of the following:
Existing ground level
Right of way
Formation width
Carriageway
Retaining wall
Pavement Width
Shoulder width
Side Drains
Building line
Control lines
2.5.2.3 Carriageway
Deduction of the width of shoulders from the formation width gives the width of the
carriageway. It depends on the width of traffic lane and number of lanes. The designed
Dovan - Nuwakot road is single lane road. So according to the NRS 2070 Standards the
width of carriageway is 3.75m.
Slide
Overturn
Overstress the materials of which the wall are constructed
Overstress the soils in which the wall rest
As per the Dolidar, the design speed based on above classification is taken 15 km per hour.
The standards for sight distance should satisfy the following three conditions:
Driver traveling at the design speed has sufficient sight distance or length of road
visible ahead to stop the vehicle, in case of any obstruction on the road ahead,
without collision.
Driver traveling at the design speed should be able to safely overtake, at the
reasonable intervals, the slower vehicles without causing obstruction or hazard to
traffic of opposite direction.
Driver entering an uncontrolled intersection has sufficient visibility to enable him to
take control of his vehicle and to avoid collision with another vehicle.
We = Wm + Wps
Where,
We = extra widening
Wm = Mechanical widening
Wps = Psychological widening
𝑊e = + √
Where,
n = no. of traffic lane
l = length of wheel base
R = Radius of curve
V = design speed, kmph
Extra widening has been provided in the inner side of the circular curve. Introduction of
extra widening commences gradually from the point which is ahead by length of curve from
beginning point of curve. The gradual introduction reaches to 2/3 We at the beginning of the
curve. The remaining 1/3 widening is provided on the circular curve.
1. Tangent Length (T): The length between the beginning of the curve or end of the
curve and the point of intersection is called the tangent length. It depends on the
deflection angle, and radius of the curve.
2. Length of curve (L): The length of curve from the point of commencement to the
point of tangency is called length of the curve. If the curve is designated by its degree
of curvature, the length of the curve will depend upon the criteria used for the
definition of the degree of curve.
3. Length of chord (l): It is the chord joining the point of curve with the point of
tangent.
4. Deflection angle: The angle between which a survey line makes with the
prolongation of the proceeding line is called deflection angle. It is measured to the
clockwise or anticlockwise from the prolongation of the previous line.It's value
ranges from 0-180.
5. Radius of curve(R): For the certain speed of vehicle, the centrifugal force is
dependent on the radius of the horizontal curve. To keep the centrifugal ratio within
low limit the radius of the curve should be kept corresponding high.
6. Apex distance (E): It is the distance between the points if intersection to the middle
of curve length. It also depends in the deflection angle and radius of the curve.
7. Bearing of line: The bearing of line is the angle made by that line with respect to the
magnetic north direction. It is also known as whole circle bearing (WCB).
2.8.3.2 Camber
The traverse slope provided on the either side from the centre line of the road is known as
camber. The main purpose of providing the camber is to drain out the surface water from the
road surface. Usually, camber is provided, by raising the centre portion of the road with
respect to the edge, but during the design of road, we use the following camber.
i. The super elevation for 75% of design speed (V kmph) is calculated neglecting the
friction.
e=
or
e=
ii. If the calculated value of e is less than 1/15 or 0.07, then the value so obtained is
provided.
If the value of e exceeds 1/15 or 0.07 then provide the maximum super elevation
equal to 1/15 and proceed with steps given below.
iii. Check the coefficient of the friction developed for the maximum value of e = 0.07 at
the full value of the design speed.
OR
f=
– 0.07 „V‟ in kmph.
If the value of thus calculated is less than 0.15, the super elevation is safe for the design
speed. If not, calculate the restricted speed from the above step.
iv. As an alternative to step iii, the allowable speed ( , kmph) at the curve is calculated
by considering the design coefficient of lateral friction and the maximum super
elevation
=√ , m/sec.
=√ , kmph.
If the allowable speed as calculate above higher than the design speed, then the designs is
adequate and then provides a super elevation of 'e' equal to 0.07. If the allowable speed is
less than the design speed then the speed is limited to the allowable speed V a kmph
calculated above.
C=
(m/sec3)
Ls =
Where,
Ls = V = Velocity in Kmph
Ls =
V = Velocity in Kmph
Due to the turning angle of vehicles, the curves resistance is developed at the horizontal
curves. When there are horizontal curves in addition to the gradient, there will be increased
resistance to traction due to both gradient and curves; it is necessary that in such cases, the
total resistance due to grade and curve should not exceed the resistance due to the maximum
value of gradient specified. For design purpose, this maximum value may be taken as the
ruling gradient and in some special cases as limiting gradient for the terrain. When the sharp
horizontal curve is to be introduced on a road, which has already the maximum permissible
gradient, the gradient should be decreased to compensate for the loss of tractive effort due to
the curves.
This reduction in gradient at the horizontal curve is called grade compensation. This is
calculated from the relation:
a. Summit curve
b. Valley curve
a. Summit curve
The summit curve is introduced when an ascending gradient meets with descending gradient
in the alignment. The maximum permissible gradient is taken as 12% and maximum average
gradient is 8 % (NRS2070). During the design, the minimum value of stopping sight
distance is considered as 50m for the design speed 40 Km/hr. according to NRS 2070.
Figure No. 2: Summit Curve
L= √√
√ √
L = 2S -
b. Valley curve
In the alignment, the valley curve is introduced when descending gradient meets with an
ascending gradient. The length of valley transition curve is designed based on the two
criteria: (i) the allowable rate of change of centrifugal acceleration (ii) the head light sight
distance, and the higher of the two values is adopted. Usually the second criterion of head
light sight distance is higher and therefore governs the design. During design, sight distance
is considered and according to NRS2070, which consist that the headlight sight distance will
be the stopping sight distance, minimum value of stopping sight distance is 50mand that the
centrifugal acceleration will be of 0.6m/sec2.
The valley curve is made fully transitional by providing two similar transition curves of
equal length. Refer figure 3 where ABC is the valley curve of total length L and AB and BC
are two equal transition curves each of length Ls=L/2, having minimum radius R at the
common point B.
N = deviation angle
L = Total length of valley curve
𝑣 = speed in m/s
𝐶 = allowable rate of change of centrifugal acceleration
V kmph = * + m/s
L=2*+
L = 0.38 [𝑁 3]12
Minimum radius of valley curve for cubic parabola is given by R = 𝐿𝑠 𝑁 = L 2𝑁
i. L > SSD
L=
L = 2S -
Substituting h=0.75 m and =1⁰ when L<S
L = 2S -
iii. Gradient
Gradient is the rate of rise or fall along the length of the road with respect to the horizontal.
It is expressed as a ratio of 1 in x.Sometimes it is also expressed as a percentage, n i.e. n
in100.
Gradients are divided into following categories:
a) Ruling gradient
b) Limiting gradient
c) Exceptional gradient
d) Minimum gradient
Topography
The topography or the terrain conditions also influence the geometric design of highway.
The terrain is classified based on general slope of the country across the alignment i.e.; level,
rolling, mountainous and steep.
As per NRS,
Level : < 10%
Rolling : 10%-25%
Mountainous : 25%-60%
Steep : > 60%
The adopted topography under consideration is mountainous road.
Subgrade course
Sub base course
Base course
Surface course or wearing course
2.11Highway Drainage:
The process of removing and controlling excess surface and sub-surface water within the
right of way can be termed as highway drainages. This includes interception and diversion of
water from the road surface and sub-grade. Highway drainage is achieved by two methods as
given below.
a) Surface drainage.
b) Sub surface drainage.
Lowering of water table.
Control of seepage flow.
Control of capillary rise.
Drainage of infiltration water.
Culvert
A culvert is a closed conduit placed under the embankment to carry water across the
roadway. Culvert is preferred than a minor bridge because it is more hydraulically efficient
according to Nepal Road Standard 2070; bridge structure of span less than 6 m are preferred
as culverts.
Slab culverts: A slab is placed over abutments made of masonry, sometimes called box
culverts if the span is below two meter.
Pipe culverts: Pipe of minimum diameter 60 cm and made of steel or pre-cast RCC is used
when the discharge is low. But, pipe culverts of diameter 75 cm, 90 cm, 120 cm are available
in the market.
A. Hydrologic Analysis
B. Hydraulic Analysis
Once the design discharge is determined the hydraulic analysis is done. The side drains are
designed based on principle of open channel flow. Longitudinal slope of channels, which is
parallel to the road profile, is selected. The type of lining from which value of „n‟
and permissible „V „is obtained is selected.
Then,
Q=A x V
Where,
Active earth pressure: it occupies when the soil mass yields in such a way that it tends to
stretch horizontally. It is a state of plastic equilibrium as the entire soil mass is on the verse
of failure. A retaining wall when moves away from the backfill ,there is a stretching of the
soil mass and the active state of earth pressure exists.
Passive earth pressure: it occupies when movement of the wall is such that tends to
compress horizontally. It is another extreme limiting equilibrium condition. Angle of repose:
it the natural slope taken up by any soil and it is given in term of the angle to the horizontal
base line. Angle of repose varies from 45˚to …….for wet clays but most of the soil angle of
repose is near about 30˚.
Surcharge load: The part of the material or load supported by a retaining wall at level of the
wall.
Let
Considering per meter length of the wall, by Rankin‟s formulae the lateral earth pressure
which is denoted by P is given which acts at H/3 above the base.
P = ˠsH2(1- )/2(1+ )
The weight of the wall per meter length denoted by W is given by:
W= ((a+b)*H*ˠ m )/2
2
X=
For the structure to be in equilibrium, the following condition must be satisfied:
i. The algebraic sum of all vertical forces must be zero i.e. ƩV=0.
ii. The algebraic sum of all horizontal forces must be zero i.e. ƩH=0.
iii. The moment of all forces acting on the wall about any point must be zero to check its
overturning i.e. ƩM=0.
Let R, and RH be the vertical and horizontal reactions at the point of application of the
resultant force R on the base of the wall.
From statement a. W = Rv
P× + W×x = RV (x+z)
Since, Rv = W
P× + W×x = RV (x+z)
z=
e = OF = BF-BO
e=x+z–
it is called eccentricity.
For safe design, the retaining wall has to be checked for following:
µ is the coefficient of friction between the base of the wall and the soil, the maximum
frictional resistance set up is equal to t.
FOS =
i. Horizontal pressure, P of the earth pressure acting at H/3 from the base.
ii. The weight W of the section acting at x from the face BD.
iii. The vertical component, Rv = W at F and
iv. The horizontal component RH = p, due to the frictional resistance.
The horizontal earth pressure, p and the frictional resistance µ, W at the base forms the
couple of magnitude and it tends to overturn the retaining wall. For the stability of the
section against overturning, the balancing moment must be equal to the overturning moment.
Therefore,
W×Z = PH/3
Z = PH/3W
As the resultant. R hits the base, the section cannot over turn. If R hits the base at A, The
section is on the point of overturning and if it falls outside the base, the section will overturn.
Hence, the limiting value equal to W×EA.
FOS = =
The pressure cause by Rv at the toe must not exceed the allowable bearing capacity of the
soil. The maximum compressive stress for the masonry for avoiding crushing of masonry at
the base.
The pressure distribution at the base is assumed to be linear. The maximum compressive
stress at the base of the wall denoted by fmax is given by;
fmax = V(1+ )
FOS =
A factor of safety of 3.00 is recommended for safe against no bearing capacity failure.
No tension:
There should be no tension at the base of the wall. When the eccentricity (e) is greater than
b/6 tension develops at the heel. Tension is not desirable. To avoid the tension within the
structure, the eccentricity. E should not be more than b/6 on either side of middle of the base
i.e. point o. in such a condition, the resultant; R will have to be with in middle third. The
extreme limit for F will then be:
BF =
Or, BE+EF =
Or, x + z =
In designing the gravity type retaining wall, a trial section is chosen and it is checked with
all the condition of the stability stated above. If the stability checks yield unsatisfactory
results, the section is changed and rechecked.
2.13.1 Introduction
The use of live plants either alone or in conjugation with small scale civil engineering
structures or non-living plant materials for reducing the shallow seated instability and
controlling erosion on slopes of any watershed can be named as bioengineering.
Afforestation along the roadside or the arboriculture is one of the very important aspects in
roadside development. Trees are proposed to plant on both sides of the road to enhance road
in the following ways.
It helps to improve road landscape from aesthetic point of view. Greenery along the
road apparently makes the road beautiful and attractive.
It provides shade and a highly cool feeling
It intercepts the annoying sound of vehicles.
Both forests resources and land for agriculture become economically important with access.
Under such conditions threat of vegetation becomes imminent. Roadside land provides an
excellent habitat for the conservation of such species. The management or the conservation
of plantations on the roadside is relatively easy and more effective to control. Representative
of all the endangered or threatened life forms such as trees shrubs and herbs can be
conserved in this fashion. In this process priority should be given to those plants that are
most need. Roadside plantation can also enhance the scope of bee keeping and increasing the
possibility of farmers to earn additional income from honey. This also increases the crop
production through pollination. List of species to be used are proposed as follows.
a) Trees
Uttis
Chilaune
Bamboo
Khannue
b) Shrubs
Nigalo
Assuro
c) Grass
Amliso
Khar
Narkat
Babiyo
For prevention on the environmental impact following measures will be adopted during
construction.
1. While selecting road alignment selection in such a way that uncultivated land was used by
road.
2. Cut/Fill volume should be minimum to reduce erosion soil dump area requirement and
change in landscape protection the susceptible surface affected by erosion at construction
site.
5. In the entire cut slope major, minor, good water management is required, which is the
main cause of land unsuitability of the region.
The alignment mostly following the existing track is within the manageable limit.
CHAPTER 3
METHODOLOGY
The list of equipment‟s that were used in surveying work can be mentioned as follows:
Total station
Measuring tape
Plumb bob
Level
Staff
Ranging rods and arrows
Abney level
Hammer
Wooden pegs
Paint and brush
3.2 General
After selecting the proposed project area, necessary secondary data on planning aspects and
costs was gathered. Socio-economic status, geological and demographic data of the area was
collected. The temperature, rainfall, vegetation, climate, of the area were studied which are
important for analysis of hydrological data. After the complete analysis of secondary data
and decision of alignment made, engineering survey was done along the proposed alignment
considering several geometrical parameters according to NRS2070. Collection of several
primary data such as type of the soil at different chainage, buildings, type of crop
production, deflection angle, and reduced level was done during engineering survey. Cost
estimate of the proposed road alignment was made considering various types of works to be
carried out during road construction with the help of Road Design Software, AutoCAD and
Excel program.
Reconnaissance is the first step in surveying. Reconnaissance work is done for selected
alignment. Detail survey was started from the first point of the starting chainage with taking
the bearing of the first line. At the beginning of the road, Benchmark was fixed having RL as
………..m as a reference point.
k
a=
43
Above figure-Gravity retaining wall
Where
b = bottom width
R = resultant force
H = height of wall
Ws = surcharge load
44
Above figure retaining wall
RV = Vertical reaction
M = M ass of wall
Ws = Surcharge load
∑
= ∑
i. The algebraic sum of all the vertical force must be zero i.e. ƩV=0.
ii. The algebraic sum of all the horizontal force must be zero i.e. ƩH=0.
iii. The moment of all forces acting on the wall about any point must be zero to
check its overturning i.e. ƩM=0.
FOS = >1.5
FOS= >1.5
iii. No tension case
e>
Where,
e>-
e = eccentricity (m)
FOS=factor of safety
CBR test is performed for the soil samples collected at the field. Load Vs penetration curve
is plotted for different load and penetration combinations. Thus the load for 2.5 mm and 5
mm penetration of the soil sample is found out.CBR value is obtained as,
CBR2.5 = × 100%
CBR5= × 100%
Normally CBR value of 2.5 penetrations which is higher than of 5 mm is reported as the
CBR value of the sample. The higher value obtain is adopted as CBR value of the sample.
The thickness of the pavement is given by any of the seven curves from the graph. The
future traffic is estimated on the basis of existing traffic and probable growth rate and it is
given by:
P = N (1+r)n+10
Where,
n = Construction period
i. The super elevation for 75% of design speed(V Kmph) is calculated neglecting the
friction.
e=
i.e. e=
ii. If the calculated value of e is less than 7% then the value so obtained is provided.
If the value of „e‟ exceed 0.07 then provide the maximum super elevation equal
to 7% and proceed with steps given bellow.
iii. Check the coefficient of friction developed foe the maximum value of e=7% at
the full value of design speed.
f=
If the value thus calculated is less than 0.15, the super elevation of 0.07 is safe for the design
speed. If not, calculated the restricted speed is given in step(iv).
ii. As an alternative to step (iii) the following allowable speed at the curve is
calculated by super elevation.
e + f = 0.07+0.015=0.22=
Va = √
Or if the allowable speed, as calculated above higher than the design speed, then the design
speed is adequate and provides a super elevation of „e‟ equal to 0.07. if the allowable speed
is less than the design speed the speed is limited to the allowable speed Va kmph calculated
above.
CHAPTER 4
i. Plan
The longitudinal profile is plotted for each IPs in 1:1000 horizontal and 1:100 vertical scales.
While designing the L-profile 7% of minimum longitudinal gradient is provided.
Cross-section for each IPs and pegs has been plotted in 1:200 scales.
Q=AV
V= average velocity
S= Longitudinal slope = 4%
Q=
Taking B=0.40m
0.6 =
We get D = 0.54
V = 4.48m/sec
Manning‟s coefficient=0.012
Q=A*V
Q= ( ) ( )
R = 0.29D
D = 0.438m
Adopt D=0.6m
V=
= 45.24°
R tan
a) Tangent length = 2
45.24
= 29 tan
2
= 12.083m
R
b) Length of curve =
180
29 45.24
= 180
= 22.898m
c) A R sec 1
pex distance 2
=
45.24
= 41 sec 1
2
= 2.41m
D) Chainage of BC = Ch of IP-TL
= 267.917 m
= 279.336 m
= 267.917 + 22.898
= 290.815 m
Where,
R = radius of curve
= deflection angle in degree
BC= Beginning of curve
EC=End of Curve
Here,
( ) ( )
and,
√ √
We know,
Here, at IP1
𝑊
√
= 0.278 V T
V2
254 ( f G)
Where
= 0.4
S = 12.64 m
S = 12.95 m
(Adopted S = 11 m )
4.3 Retaining Structure
Retaining walls are relatively rigid walls for supporting the soil mass laterally so that the soil
can be retained at different levels on two sides and sometimes the pressure of subsoil, water
and in many cases the wall may also be required to support vertical loads from above the
wall called surcharge.
R = Resultant force
Ẍ = Distance of Cg from the face BC
Ws = Surcharge load
H = 3m
A = 0.6
B = 1.5m
ɸ = 38
= 19.82 KN/m³
KN/m³
Ws = 5 KN/m³
W = *V =75.6 KN
K = 1- sinɸ/1+sinɸ
= 1- ( ) = 0.361
P = P1 + P2
= 24.6875 KN/m
Ẍ = a/b
FOS = >1.5
RF = W tan
= 75.6tan28
= 59.065 KN/m
SF = P
= 24.685 KN/m
= 78.280 KN/m
= 21.323 KN/m
e<
e = –z
Z* RV = RM
z = RM/RV
= 0.942m
e = 0.088
b/ 6 = 0.25
Here,
e < hence OK
Fmax = W (1+6e/b)
= W (1+6e/b)
For the soil the safe bearing capacity, SBC = 102.219 KN/m²
Fmax< SBC
Where,
Therefore, Design Curve „D‟ is used for design as the design traffic volume is in the range
150 to 450 cv/day.
58
Figure 4.1: Design Charts for Flexible Pavements - CBR Method
A 0-15
B 15-45
C 45-150
D 150-450
E 450-1500
F 1500-4500
G Over 4500
Using the design chart, the total thickness over subgrade having CBR of 7% is obtained as
30 cm from curve D.
Thus, 30 cm of pavement material is required to cover the natural soil subgrade having 7%
CBR value. Now to compute the thickness of compacted soil, the design curve D is again
used for CBR value of 15%. So, pavement thickness of 23 cm is required above the
compacted soil subgrade having CBR value of 15%, hence providing sub-base course layer
of thickness 18cm and thickness of the remaining layer is Similarly, the
thickness of pavement required over well graded gravel of CBR 40% is 10 cm. providing the
minimum thickness of bituminous concrete surface is 2 cm. The final pavement section is
shown in figure below:
59
CHAPTER 5
COST ESTIMATE
Net project cost includes the contractor‟s overhead and contractor tax whereas the gross
project cost is inclusive of provisional sum @ 4%, contingencies @5% and VAT @ 13%.
Basic unit rates of labor, material and equipment are adopted as per district rates of Palpa
district.
4.2.1 Earthwork
The earthwork in cutting and feeling is derived in cubic meters from average area method.
This is given by the combine computation of design line, summit curve and valley curve.
This is maintained in appendix.
4.5 Report
Final report and drawings including salient features and all outputs from detailed design and
survey was prepared.
CHAPTER 6
6.1General Conclusion
The alignment selected for this road, in general is successful as it considers topographic
conditions, engineering and geological features and road design parameters passes through
stable terrain. The environmental protection measures are also considered. The selected road
alignment does not possess major hydrological problems; designed drainage can resist
scouring and erosion problems. There are no other problems and this road alignment seems
as one of the most economical and stable route. The construction of road provides easy
accessibility to the people in turns of the following:
1. Agor, R., 1996- Eight Edition, A Textbook of Survey And Leveling. New Delhi:
Khanna Publishers.
3. Arora,Dr. K.R., 2003 -Sixth Edition, Soil Mechanics and Foundation Engineering.
Publication.
6. Manual for Survey, Investigation and Preparation of Road Project, 2001. New Delhi:
IRC Publication.