Вы находитесь на странице: 1из 13

Queensland University of Technology

EGH479 Advances in Civil


Engineering Practice
Woolloongabba Fiveways Mobility
Improvement Feasibility Design Study: Project
Proposal
Muhammad Fauzan, Group 81

18
Muhammad Fauzan - Team 81

Article I. Figures...................................................................................................................ii
Article II. Tables...................................................................................................................iii
1. Introduction......................................................................................................................1
2. Study Area........................................................................................................................1
2.1. Main Components....................................................................................................1
2.2. Qualitative Analysis...................................................................................................2
2.3. Quantitative Analysis................................................................................................2
2.4. Interests to be taken into consideration...................................................................2
2.5. Analysis Tools to be used..........................................................................................3
2.6. Measures of Effectiveness to be used.......................................................................4
2.7. Time Periods to be considered.................................................................................4
2.8. Planning and Design Horizons to be considered.......................................................4
3. Methodology....................................................................................................................4
3.1 Activities to undertake Study....................................................................................4
3.2 Key Considerations and Needs by Activity................................................................5
3.3 Generation of Package for Further Testing in Study.................................................6
3.4 Gantt Chart of Activities to Undertake Study............................................................7
4. Personnel..........................................................................................................................8
4.1 Professional capabilities of team members..............................................................8
4.2 Assignment of team members to activities...............................................................8
4.3 Team working plan....................................................................................................9
5. Conclusion......................................................................................................................10

Article I. FiguresY
Figure 1 Gantt Chart.................................................................................................................7

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page ii
Muhammad Fauzan - Team 81

Article II. Tables


YTable 1 Main Components
Table 2 Qualitative Assessment................................................................................................2
Table 3 Quantitative Assessment.............................................................................................2
Table 4 Stakeholders and Interest............................................................................................3
Table 5 Effectiveness Indicator.................................................................................................4
Table 6 List of Activities Regarding The Project........................................................................5
Table 7 Key Considerations on Each Activities..........................................................................6
Table 8 Capabilities of Members..............................................................................................8
Table 9 Task for Each Member.................................................................................................8

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page iii
Muhammad Fauzan - Team 81

1. Introduction
The ‘Woolloongabba Fiveways Mobility Improvement Feasibility Design Study’ project is
conducted to improve the Woolloongabba Fiveways existing condition. This project is
divided into two parts, Grade Separation and Mobility System. The Grade Separation will be
applied in the form of revitalization of the existing bus station such that it is moved
underground including the entrance and exit ways. However, the mobility system is
improving the mobility within and through the area.

Team 81 is assessed to evaluate and analyze the Grade Separation part of the project from
structural engineer point of view. The team will act as a consultant that will assess the
project whether it is feasible to execute or not.

2. Study Area
2.1. Main Components

Component Briefs Items Included


Should be considered in order to - The Gabba
minimalize the construction cost and - The Park
Existing Building
predicting the user behavior on the site - Heritage sites
- Historical building
Security and safety including for the - Speed limit
Safety and
workers, user, and the site should be - Casual surveillance
security
provided - CCTV
Ease of maintenance and the development - Ease of repair or maintenance
Adaptability and
in the future should be consider while the - Design provides for future
Maintenance
construction is designed. development/changes of use
Accessibility should be considered both in - Vehicle/labor access during
designing process and construction construction
process. On Design process, the designer - Future population growth
Accessibility should consider the accessibility of the - Disability access
facilities user while on construction - Pedestrian/cyclist space
process, accessibility of worker and - Car parking
equipment is considered.
A broad definition of sustainability is
adopted in this project. It refers to - Design
Sustainability “continuity”. This including sustainable - Material
design, sustainable material, and - Economically sustainable
economically sustainable.
The consultant requires to take into - Minimizing production cost
consideration of transporting materials, - Minimize transport of
Logistics and
minimalize the amount of materials materials
Finance
needed in order to reduce the production - Number of components
cost
Table 1 Main Components

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page iv
Muhammad Fauzan - Team 81

2.2.Qualitative Analysis
Qualitative Assessments Explanation
Safety Ensuring the safety of all the parties that involved and
affected by the project, such as the workers, road users,
pedestrians, visitors, etc. during project execution.
Aesthetics The analyses of the appearance of the construction should be
conducted to ensure it comply with the surrounding area.
Accessibility Ease of access is one of the important aspect that should be
considered since it is one of the goals for this project
Environmental Impact This project will affect the surrounded environment directly
and indirectly. Hence the damaging impact should be
minimalized
Choice of Materials The choice of materials should be considering the cost-
effectiveness and the sustainability
Efficiency Assess the level of efficiency of the methods used in the
project
Table 2 Qualitative Assessment

2.3.Quantitative Analysis
Quantitative Assessment Explanation
Budgeting A quantitative analysis to predict how much money will be
spent during the project execution. This included the
operational cost, set up cost, etc.
Quantities of Material The calculation of material quantities should be conducted.
This will anticipate the excess amount of the material that
being used in this project. Quantities of material will also
affect the budgeting assessment
Time and Scheduling Gantt chart is included to ensure the progress stick to the
timeline and the project finished on time.
Loads To calculate the structural component capability of handling
the load caused by pedestrians, transportation, and other
facilities
Capacity To predict the number of users that can be accommodated in
peak hour in order to gain the user satisfaction.
Design Life To anticipate the development in the future, the facilities
should be designed for a certain life span. This design life will
predict how long these facilities will survive before a
refurbishment should be conducted.
Table 3 Quantitative Assessment

2.4.Interests to be taken into consideration


The parties whose interests needs to be taken into consideration in this project are:

Stakeholders Explaniation
Brisbane City Council The Client of this project. This party have a
broad concern on the project but key
consideration for them is the cost and

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page v
Muhammad Fauzan - Team 81

efficiency
Public This is the main consumer of the project,
public will concern more about the
functionality, safety, and accessibility.
Local Business The construction will affect the local
business in such affecting the number of
customer, etc.
Contractor Consider as ‘executor’ of this project.
Interested in profit, efficiency, and safety of
the workers
Heritage Council This party will concern about how the
construction process affecting the heritage
site nearby.
Environmental Council Concern on the impact of the construction
to the environment surrounding.
Worker Union The main concern of the worker union is
the safety and the rights of workers
Local Resident The local resident concert more about the
effect of the construction for their daily
activities. They concern more in certain
things such as noise level, security,
Table 4 Stakeholders and Interest

Section II.1

2.5.Analysis Tools to be used


Analysis Tools:

1. AutoCAD 5. Email
2. 12d Model 6. Google Earth
3. Microsoft Project 7. SpaceGass
4. Microsoft Office

Guidelines:

1. AS 1726:2017—Geotechnical Site Investigation


2. AS 2159-2009—Piling Design and Installation
3. AS 4678-2002/Amdt 2-2008—Earth retaining structures
4. SS EN 1691 Ed. 1 (2014)—Tunnelling Machinery - Safety Requirements
5. PAS 8810:2016—Tunnel Design - Design of concrete Segmental Tunnel Linings –
Code of Practice
6. BS 6164:2001—Code of practice for safety in tunnelling in the construction industry
7. AS 1742 SET-2014—Manual of uniform control traffic devices set
8. AS/NZS 1158 SET-2010—Lighting for roads and public spaces
9. AS/NZS 3000:2018—Electrical Installations
10. The Australian Community Workers Code of Ethics

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page vi
Muhammad Fauzan - Team 81

2.6.Measures of Effectiveness to be used

Components Measures of Effectiveness


Project Functionality Degree of conformance to all technical
specification
Value for Money The project life costs and quality to meet
client’s need and expectation
Profitability Total net revenue exceeding total costs
Client and User Satisfactions The project meets client and user’s
requirements regarding the functionality
and quality of service
Achievement of Outcomes The project’s objectives are attained
Table 5 Effectiveness Indicator

2.7.Time Periods to be considered


The time periods that may affect the construction process are:

a) Peak Hours : the maximum traffic flow occur during peak hours. Hence the
designed capacity is based on this. Otherwise, reduced congestion could not be
achieved
b) Weekends : there might be a significant change in the number of pedestrian
and cyclist during the weekend. Hence the pedestrian walkway must be planned
properly to anticipate it.
c) Major Events : Events occurring at the Gabba could produce a heavier traffic than
the normal traffic flow.

2.8.Planning and Design Horizons to be considered


To maintain the user satisfaction and the effectiveness, several factors such as population
growth, major change in the transportation system, and other major trend. This facility will
be expected last for 10-15 years.

The main reason for this decision is, in few years there are several transportation modes
expected to be operated such as Brisbane Metro in 2022, Cross River Rail (CRR) in 2024,
Woolloongabba Bikeway Project in late 2018.

3. Methodology

3.1 Activities to undertake Study


No. Steps Study Area Activity
1 Research Construction area (Woolloongabba Investigate the current condition of
Place Park) the site based on the data given
Woolloongabba Fiveways
Tunnel Dive Structure construction site
(Jurgen St)

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page vii
Muhammad Fauzan - Team 81

Link from construction area to South


East Busway site (Main St. and South
East Busway)
Pedestrian walkway (Along Main st. and
Stanley rd.)
Local business and Heritage Buildings
Analyze the soil properties, current
Construction area (Woolloongabba
activity level, public utilities,
Place Park)
surroundings situation
Analyze traffic properties such flow
Woolloongabba Fiveways rate, degree of saturation, etc.;
Identify the peak hours periods
Tunnel Dive Structure construction site
Analyze the soil, traffic flow
(Jurgen St)
2 Data Analysis
Link from construction area to South
Analyze the soil, current public
East Busway site (Main St. and South
utilities (electrical, water, drainage)
East Busway)
Analyze the volume of pedestrian,
Pedestrian walkway (Along Main st. and
current public utilities (electrical,
Stanley rd.)
water, drainage)
Analyze the current condition
Local business and Heritage Buildings
(customer level)
3 Construction area (Woolloongabba
Place Park)
Woolloongabba Fiveways
Tunnel Dive Structure construction site
Preliminary (Jurgen St) Rough design and preferable
Design Link from construction area to South method of construction
East Busway site (Main St. and South
East Busway)
Pedestrian walkway (Along Main st. and
Stanley rd.)
4 Feasibility
Draft the report for the feasibility study
Study Report
Table 6 List of Activities Regarding The Project

3.2 Key Considerations and Needs by Activity


No. Steps Key Considerations and Needs
- Collecting the required data regarding the existing condition
- Validating the data that being used
1 Research
- Conduct the investigation in critical period
- Define the tools and methods that being used
- Use the suited method of analysis
- Highlight the significant findings
2 Data Analysis - Suitable software
- Define the key variables for each analysis
- Compare the findings with similar existing projects
3 Preliminary Design - Simulation of the design using appropriate software
- Assess the level of effectiveness of the project

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page viii
Muhammad Fauzan - Team 81

- Adjusting the design with the standards and guidelines


- Considering the project’s impacts towards the local
residents/business and environment
- Provide a rough cost estimation of the project
- Minimalize the existing infrastructures demolition.
- Present the data effectively and concisely
4 Feasibility Study Report
- Highlight the key findings of each analysis
Table 7 Key Considerations on Each Activities

3.3 Generation of Package for Further Testing in Study


There are 3 packages that can be applied on this Woolloongabba Fiveways. A further
explanation is listed below.

1. Underpass along the Stanley St. and pedestrian bridge from bus station to The
Gabba Stadium
An underpass will allow busses and cars that go through the Stanley St. move
without any interruption from the traffic light. Hence, it also reduces the cycle time
of the traffic light there that will reduce the bulking effect. Come up with this
underpass, a pedestrian and cyclist bride that connect between the bus station and
the Gabba Stadium. This bridge will minimalize the pedestrian interference on the
traffic light. However, congestion might be occurred during the construction process
due to lane closing on the Stanley St.
2. Overpass from Main St. to Ipswich Road.
The concept of this overpass is exactly the same as the underpass. However, a
heavier congestion might be occurred since it needs a lot of space to construct the
overpass. Furthermore, a heritage site that lies near the intersection make this
option not feasible. The site might be damaged due to the construction.
3. Relocate the Woolloongabba Bus Station to the Underground
Relocation of the bus station to underneath the park will be the most suitable and
efficient solution to reduce the congestion. It includes the relocation of the entrance
and exit ways of the bus station such that it will not interrupt the traffic light on the
cross intersection. The relocation of the entrance and exit of bus station will also
reduce the traffic flow of the bus on the corresponding road. The construction
process will interrupt the traffic less since the construction will be started on the
park using a top down method. For the tunnel construction, a bottom up tunnel
construction will be used to reduce the impact to the existing surroundings.

3.4 Gantt Chart of Activities to Undertake Study

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page ix
Muhammad Fauzan - Team 81

Figure 1 Gantt Chart

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page x
Muhammad Fauzan - Team 81

4. Personnel

4.1 Professional capabilities of team members


Name Expertise
Muhammad Fauzan - Principal of Construction
- Design of Concrete
- Structural Mechanics
Muhammad Gebri Adhya Putra - Structural Mechanics
- Research in Engineering Practice
- Civil Engineering Materials
Rahmat Tegara Hadinata - Geotechnical Engineering
- Associate Field Engineer experience
- Research in Engineering Practice
Vito Arista Pratama - Traffic and Transport Engineering
- Design of Concrete
- Structural Mechanics
Table 8 Capabilities of Members

4.2 Assignment of team members to activities


Name Task Assignment
Muhammad Fauzan - Conduct a research
- Provide gantt chart.
- Identify the key issues that will influence the structural
design.
- Prepare engineering design basic annotated drawing.
- Prepare a functional alignment design
Muhammad Gebri Adhya Putra - Conduct a research
- Review and evaluate foundation types
- Conduct a load evaluation.
- Prepare engineering design basic annotated drawing
Rahmat Tegara Hadinata - Conduct a research
- Provide a geotechnical interpretation.
- Identify the key issues that will influence the structural
design
- Prepare a functional alignment design
- Final drafter for report collection
Vito Arista Pratama - Conduct a research
- Evaluate the bearing and settlements limit of the soil for
foundation
- Review and evaluate existing structural forms
- Analyze the traffic condition in the location.
- Conduct a load evaluation
Table 9 Task for Each Member

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page xi
Muhammad Fauzan - Team 81

4.3 Team working plan

Data
Data Gathering
Gathering
Each member conducts a research based on their own expertise to gather data that is necessary to be analyzed individually and collectively.

Individual Data Analysis


Analyze data gathered individually with efficient team interaction and with the intention that the analysis will be necessary for other field of expertise as well.

Collective
Collective Analysis
Analysis
Analyze and discuss the individual analysis results together with the intention to review each other.

Data Sufficiency
If after review data is insufficient to continue analysis and providing options, gather any more data needed. If data is sufficient, continue the analysis.

2nd
2nd Individual
Individual Data
Data Analysis
Analysis
Resulting options to provide for the project according to each expertise.

Collective Decision-Making
Deciding which option is the best regarding to fulfilling the interests of each party.

a) Team meeting is compulsory for each team member and will be held every Wednesday
after class.
b) In the meeting, each member must report the progress of their expertise and any
technical conflict they have. Each member will have the opportunity to question after
the progress report and technical conflict has been delivered.
c) Any technical conflict must be resolved with full presence and participation of each team
member. The final resolution will follow a majority decision.
d) Minutes of Meeting will be assigned to one member each meeting, taking turns each
meeting.
e) Progress report will be assigned to one member each meeting, taking turns each
meeting.

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page xii
Muhammad Fauzan - Team 81

5. Conclusion
The main aim of this Feasibility Design Study is to evaluate and analyze the most feasible and
effective solution for ‘Woolloongabba Fiveways’. This includes the most efficient
construction method that will be applied. By having a feasibility study completed, the client
will have a general understanding of the project and aware of the risk that might be
occurred in this project.

We strongly recommend the feasibility study should be conducted to minimalize the losses
and problems. Our professional capabilities in working plan, scheduling and managing
people will ensure the project objective meets the efficiency and the requirements.

EGH479 Advances in Civil Engineering Practice: Semester 2, 2018 Project Proposal Page xiii

Вам также может понравиться