METHOD STATEMENT

Title:

METHOD OF STATEMENT FOR GLASS WINDOW WORKS

REVISION STATUS
Prepared by

Revision Revision
Date
No Description

24.0
Glass
3.07
00 Works. SW
CAMLOCK GENERAL MAINT. &CONTRACTING SERVICES EST |
P.O Box – 8596 | M-09 – ABU DHABI, UAE | Web:
www.camlockservices.com |

 The Glass Works carried out in strict accordance with the manufacturers’ recommendations and in
the sequence specified by the manufacturer. All work will also be carried out in strict accordance
with manufacturers’ recommendations.

 Before starting work ensure that the correct window sizes have been supplied, together with the
necessary fixtures and fittings.

 Where applicable the existing windows should first be removed by


removing the hinges from the window frame. The existing widow frame can
then be removed from the wall; this will be done by cutting through the
frame and levering the frame work from the wall with a wrecking bar.

 The old windows and frames will be removed from site and deliver the client.
 All work will generally be carried out from the inside of the property, however, where work is being
carried out on floors other than the ground floor, or where work is carried out on the ground floor
and level of the ground outside of the window is more than 1.5m below the sill height AND where
the internal sill height is less than 910mm above the internal floor level, then additional measures
must be implemented to safeguard against falls through the open window aperture. In such
instances where the sill height is below 910mm either a temporary hand rail at 950mm will be
erected; or those carrying out the works, will wear a full body harness with a lanyard attached to a
suitable anchor point.

 Prior to the fitting of the new glass window, the walls must be checked to ensure that they are
sound and that any old fixings have been removed and disposed of. Where sections of the wall have
been damaged or are not suitable, the area should be made good or alternative fixings used.

 Clean the area and prepare the recess for the installation of the new windows. Fit the new glass
window into position, ensuring a tight fit and ensuring that the frame is plumb and square.

 Once the windows and frames have been checked, the glazing units can be inserted. Each unit
should be installed and secured into position with the appropriate beading/seals. The glazed
panels can then be carefully lifted into position, grip gloves will be worn at all times when lifting
glazed units and for large panels a minimum of 2 persons should be used to lift and secure the
panels in place. The use of suction lifters should also be used to provide a safe and secure grip
when lifting large and heavy glass panels/units.

 The windows will then be tested to ensure that they open and close smoothly without rubbing or
catching, if necessary the hinges should be adjusted to ensure a suitable fit.

 The window frame should then be trimmed and sealed both internally and externally and the area
made good.
 Upon completion of the works, CAMLOCK will remove all rubbish, scrap and waste materials/packaging
from the premises and dispose of appropriately. Thoroughly vacuum and clean through the area and
all transit routes leaving the property in a clean and tidy state.

 Care will be taken to ensure that the glass is not broken and that when handling glass and windows,
CAMLOCK GENERAL MAINT. &CONTRACTING SERVICES EST |
P.O Box – 8596 | M-09 – ABU DHABI, UAE | Web:
www.camlockservices.com |
that appropriate gloves are worn.

8. MANPOWER

The sufficient number of workers will be employed as per site/planning requirement to perform their duties and
they will have sufficient tools to tackles the work assigned to them.

1. Glass Technicians
2. Helper/Laborers
3. Foreman

9. TOOLS AND EQUIPMENT


 Hand Tools
 Drill Machine
 Glass Suckers
 Sealant applicator
 Cutting Saw
 Lifting Belt
 Cradle/Scaffolds
 Tower/Mobile Crane

Responsibilities:

 Project Manager

Project manager is responsible for maintaining the safety and progress of the work. He shall ensure that he has
the latest drawings of the project and have updated information from the Engineer regarding project.

 Construction Manager

The Construction Manager is responsible for the arrangement of the work.

 HSE Manager

The HSE Manager is responsible for reviewing this procedure method statement, ensuring that the method
statement, JSA and STA are carried out at the required time by the Safety Officer. Ensuring that all operations
are briefed on the method statement and signed to confirm receipt of briefing

 Safety Officer (reports directly to the HSE Manager)


CAMLOCK GENERAL MAINT. &CONTRACTING SERVICES EST |
P.O Box – 8596 | M-09 – ABU DHABI, UAE | Web:
www.camlockservices.com |

The Safety Officer is responsible for the following:

 Insure that all safety requirements to start the activity are provided by the construction group as per
project HSE manual and specification.
 To conduct daily inspection to ensure that safety requirements are being maintained up to the
completion of this activity.
 Ensure operatives understand the method statement and are briefed on the method statement.
 Advise operatives on their responsibilities and safety requirements.

 Site Engineer

Site Engineer has to insure that all the glass window works are carried out as per required specifications and
Method of Statement. To insure that all parties required any kind of inspection or test are suitably informed as
to the delivery program. Insure that the notification time to QC is sufficient to meet notification time to
Engineer.

 Site Surveyor

Site Surveyor is responsible to allocate all glass window works levels as indicated in all arch. Drawings under
instruction of SE, IR has to be issued and approved.

 Site Foreman

Site Foreman team must work together to ensure that all activities regarding glass window works shall be
carried out properly. Preparation of area and necessary requirements for this method of statement must be
carried out carefully to ensure safety and on-time delivery of work.

 Quality Control Inspector (QCI)

 The QC Inspector is responsible for checking and verifying the documentation for the Inspection Request
(IR) submitted by the Site Engineer prior to submit the same to the client for inspection.
 QC Inspector is responsible for rejecting the work or prepare observation report if the work is found not
in-compliance or unsatisfactory.
 The Observation Note will specify the commented work by the QC Inspector and submit for rectification
prior to carry out the Inspection Request.
 Coordinate with the Site Engineer and Client representative during inspection.

HSE:

 Before any work commences, the Engineer shall ensure that all relevant permits are obtained and work
shall commence following the specific measures itemized in the permit.
 The work area will be clean and leveled prior to the work commencing, a walkway route will be
demarcated to and from the work area, and storage area,
 The Surveyor/Engineer in coordination with the Safety Officer shall check that all works are being done
in accordance with the project HSE manual. All operatives will receive a (STA) Safety Task Assignment
prior to commencing the works. This Method Statement will be briefed to all operatives carrying out the
works.
CAMLOCK GENERAL MAINT. &CONTRACTING SERVICES EST |
P.O Box – 8596 | M-09 – ABU DHABI, UAE | Web:
www.camlockservices.com |
 All staffs/workers shall use Personal Protective Equipment (PPE) as appropriate according to the nature
of the different jobs involved.

The foregoing procedure for the glass window works will serve as a guide or reference to the SE and QCI along
the course of their work to achieve an acceptable quality of workmanship, and at the same time to control
materials utilization and attaining the optimum results with less time and effort as:

Quality Assurance:

The QA/QC Manager will monitor and ensure that this Method Statement shall be observed so that smooth
Work Flow will be attained. Furthermore, the QA/QC Team shall ensure that each individual elements of the
work shall be completed substantially in compliance with the approved plans and project specifications to meet
client’s expectation. The following activities shall be observed: Single Source Responsibility: Provide materials
same manufacturers Coordination of Work: Review other Sections of these Specifications in which materials are
to be provided to ensure compatibility of complete stone mechanical cladding system for various sequences.
Upon request from other trades, furnish information or characteristics of materials provided for use, to ensure
compatible components are used. Material Quality: Provide manufacturer’s best quality trade sale granite/
Marble material of various stone types specified. Accessories material containers not displaying manufacturer’s
product identification will not be acceptable.

METHOD STATEMENT BRIEFING RECORD

(Glass Works)
Briefing delivered by:

Position: QA/QC Manager


Date: 03.05.2020

We (the undersigned) have read and understood the attached method statement and will comply with the
specified requirements and control measures. If the work activity changes or deviates from that originally
envisaged, we will seek further advice and request an amended method statement.

END OF METHOD OF STATEMENT

*********************************************************