Вы находитесь на странице: 1из 2

Detailed Estimate for construction of wing walls for Protection of Approach Road in

Turkwangam Lassipora Bridge by way of wire crates on Both side


Sno. ITEMS AMOUNT

1 Earthwork in excavation by manual/mechanically means for foundation,


trenches or drains (not exceeding 1.5mtr width as well as 10 sqm plain)
incl. dressing of sides all kinds of soil

a) upstream side:- 1x30x1.30x1.30=50.70 cum


b) Downstream side:- 1x30.0x1.30x1.30=50.70 cum Rs 18827
Total qty=101.40cum@ RS 168.80/cum

Supply and filling of nallha stones in wire crates of approved mesh


2 including laying of crates in position and binding tipping of crates after
filling including all carriages of stones and wire crates with loading
unloading and stacking but cost of crates complete job
A)upstream side:-
Tire Ist:- 1x30.0x1.22x1.22=43.92cum
Tire IInd:- 1x30.0x1.22x1.22=43.92cum
Downstream side:- Rs 225436
Tire Ist:- 1x30.0x1.22x1.22=43.92cum
Tire IInd:- 1x30.0x1.22x1.22=43.92cum
Total qty = 178.64 cum @ Rs1150/cum

3 Supply and filling of nallha bolders behind wing walls back filling duly Rs 58560
hand packed incl. all leads and lifts complete job

upstream side & downstream side Rs 157440


2x30.0x2.0x1.22=146cum@ Rs 450/cum
Rs 460806

Add cost of Crates


4 24x16’x16’=6298 sft @ Rs 25/sft 4.60 Lacs
Say Rs
Detailed Estimate for construction of washed away diversion due to heavy rain’s /cloud burst
on 24,25 July 2018 by way of Laying of RCC spun Pipes
S.no Items Amount

1 Supply spreading ‘watering of GSB/RBM including compacting with PRR


of 08-10ton capacity to required grade and level incl all carriages complete
job Rs 65450

1x250x2.50x0.30=187.0cum@350/cum

2 Providing and laying of RCC pipes by mechanically incl. trench


excavation and refilling of trench as cushion incl. all carriages involved

Qty=36 dia 6nos

6 x 8= 48rft @ Rs550/rft
Rs 26400

Add cost of pipes =6nos @13000/no


Rs 78000

Rs 169850

1.69 Lacs