Академический Документы
Профессиональный Документы
Культура Документы
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
1. PURPOSE ................................................................................................................................................ 4
2. SCOPE ..................................................................................................................................................... 5
3. DEFINITIONS .......................................................................................................................................... 5
4. RESPONSIBILITY ..................................................................................................................................... 8
4.1. The Offshore Installation Manager (OIM) / Person in Charge (PIC) .......................................... 8
4.2. The Lifting Responsible Person .................................................................................................. 9
4.3. The Maintenance Responsible Person ...................................................................................... 9
4.4. The Onshore Technical Person .................................................................................................. 9
4.5. The Lifting Appliance Operator ................................................................................................10
4.6. The Crane Operator .................................................................................................................10
4.7. The Signaller.............................................................................................................................10
4.8. The Slinger ...............................................................................................................................11
4.9. The Rigger ................................................................................................................................11
4.10. The Rigging Store Controller ....................................................................................................12
5. POLICY ..................................................................................................................................................12
5.1. Inspection ................................................................................................................................12
5.2. Control of Lifted Loads.............................................................................................................12
5.3. Safe Use of Lifting Appliances ..................................................................................................13
5.4. Platinum Rules for Cranes........................................................................................................13
6. SUMMARIZED PROCESS OF CONDUCTING A LIFT ...............................................................................14
6.1. Planning the lift ........................................................................................................................14
6.2. Preparing the lift ......................................................................................................................14
6.3. Conducting the lift ...................................................................................................................14
7. PROCEDURES (Expanded Process for Conducting a Lift) .....................................................................15
7.1. Planning the Lift .......................................................................................................................15
Step 1: Categorize the lift ....................................................................................................15
Step 2: Plan the Lift ..............................................................................................................15
Page RMS-DOP-904
Lifting Policy / Procedure
1
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
2
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
3
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
11.12. Shackles....................................................................................................................................35
11.13. Eye Bolts and Eye Nuts (Lifting Eyes) .......................................................................................35
11.14. Wire Rope Clamps ...................................................................................................................36
11.15. Beam Clamps and Trolleys .......................................................................................................36
11.16. Lifting Nipples, Caps, and Subs ................................................................................................36
11.17. Sheave Blocks...........................................................................................................................36
11.18. Load Carriers (Cargo Carrying Units - CCU's) ...........................................................................37
11.19. Plate Clamps ............................................................................................................................38
11.20. Barrel Lifters.............................................................................................................................39
11.21. Load Carriers for Gas Bottles ...................................................................................................39
11.22. Turnbuckles ..............................................................................................................................39
12. REFERENCES .........................................................................................................................................39
13. APPENDICES .........................................................................................................................................40
13.1. Appendix A – Platinum Rules for Cranes .................................................................................41
13.2. Appendix B - Lift Categorization Matrix...................................................................................42
13.3. Appendix C - Hand Signals and Verbal Commands..................................................................43
13.4. Appendix D – Sheave Block Angle Factors ...............................................................................44
13.5. Appendix E - Container Checklist .............................................................................................45
13.6. Appendix F – Color Coding .......................................................................................................46
Page RMS-DOP-904
Lifting Policy / Procedure
4
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
1. PURPOSE
Establishes requirements for offshore and onshore lifting and hoisting operations.
2. SCOPE
Lifting Operations conducted by all employees of the Company, all third-party personnel, and any
contractors performing work on a Company rig or facility, excluding Personnel Lifting (RMS-DOP-903) and
Forklift Operations (RMS-DOP-910).
3. DEFINITIONS
Adverse Weather: An environmental condition requiring precautionary measures
Barrier: Anything that prevents unauthorized personnel from entering an area. Barriers may be caution-
tape, chain, or a person physically warning personnel to keep out of the area
Blind Lifts: Lifts where the operator of the crane does not have a direct view of the load and lifting/landing
area
Boom: A member hinged to the revolving upper-structure of a lifting appliance and used for supporting
the hoist tackle
Cargo Carrying Unit (CCU): A load carrier (container / basket / half height / tank / rack)
Control of Work: Procedures used to plan and control work and risk at the task, facility and operational
level – JRA, RSOP, Lift Plan Card, RSOP-L, PTW, ORA, ORA-M
Deck Operator: Offshore personnel (Roustabout etc.) involved in general deck duties
Dynamic Lift: A lifting appliance lifting a load from or to anywhere not on the platform/vessel that the
lifting appliance crane is mounted on (e.g. from/to supply boats).
Dynamo Eye Bolt: An eyebolt designed for axial loading only, typically with a small diameter collar
between the eye and the screw thread which is not sufficient to support the eye if it is loaded at an angle
to the thread axis.
Enterprise of Competence: certified entity in the companies' organization, or institutions that have
sufficient theoretical knowledge and practical experience to understand calculations for lifting equipment,
its design and function, and to carry out necessary examinations and tests in order to issue certificates
Page RMS-DOP-904
Lifting Policy / Procedure
5
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Examination: function test of all safety devices, i.e. limiting and indicating equipment, brakes, clutches
etc. in order to verify that they operate within the tolerance requirements
Fixed Attachment Point: Pad eyes, winch and mobile crane foundations, lifting beams and beams for
attachment of beam clamps.
Functional Checks: Verifying the lifting appliance functions as designed by operating without a load.
Functional checks could include boom movements in all directions, verifying that all control handles are
producing accurate response, testing the brakes, and verifying load monitoring system is functioning.
Heavy Lift: Lifts that are > 90% of whip line or > 80% of main block rating.
High Critical Lift: critical lifting operations - lifting operations that may lead to major consequences in the
event of failure, e.g. lifting above pressurized hydrocarbon systems, lifting above critical equipment, lifting
outside limits in the load chart, personnel transport where there are no other approval arrangements,
tandem lifts where the load's weight exceeds the maximum lifting capacity of one of the lifting appliances
Inspection: visual control of lifting equipment for defects, and check of control devices, limiters and
indicators
Lifting Accessories: components or equipment used between the lifting appliance and the load or on the
load to grip it, but which is not an integrated part of the lifting appliance
Lifting Equipment: common term for lifting accessories, lifting appliances and lifting components, used
together or individually.
Lift Plan: The Lift Plan Card, RSOP-L, JRA, RSOP, and/or lift plan developed by the Technical Responsible
Person with the Permit to Work (if required). Used to safely plan, document, provide instruction to the
lift team, and authorize a lift.
Lift Categorization: The selection of appropriate control-of-work measures for a lift.
Lift Categorization Matrix: The matrix that contains risk-based criteria that the lift team will review for a
proposed lift to determine the appropriate control-of-work measures (type of lift plan and required
authorizations). The matrix ensures:
• The lift plan process is appropriate to manage the complexity and risk for the lift
• A competent person plans and authorizes the lift appropriate to the complexity and risk for the
lift
Page RMS-DOP-904
Lifting Policy / Procedure
6
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
• An operationally responsible person authorizes the lift appropriate to the complexity and risk for
the lift
Live Plant: Equipment and/or pipework, containing hydrocarbons, used for hydrocarbon production or
transportation
Lifting Operation: all administrative and operational activities before, during and after a load is moved
vertically, with or without horizontal movement, and until the lifting equipment is ready for a new load
Load Carrier - all types of containers, baskets, tanks, skids and frames that are used to transport loads.
The term "load carrier" includes the attached lifting sets
Material Handling Crane: A knuckle or lattice boom crane being used to move materials and is being
operated without a grabbing assembly
Pennant: A single part-line of wire rope suspended from the crane hook, permitting safe connection of
the hook to the load.
Pipe Handling Crane: A knuckle boom crane with a grabbing assembly that is being used to move tubulars
without the need of slings or other loose lifting accessories
Pre-use and Post-use checks: visual and functional assessment (not test) of the lifting equipment's
technical condition before and after use (without disassembly)
Rigging Loft: Store for loose lifting equipment that is, secure and weather protected
Safe Working Load: The maximum load a sling or lifting component is certified to withstand under normal
use in a given configuration
Signaller: A person responsible for directing movement of the crane and load. In some areas of operations
this person may be called a Banksman.
Significant Wave Height: The average height of the highest third of prevailing waves, typically measured
over a period of three hours. In general, the Significant Wave Height is about half the maximum wave
height.
Simple Lifting Appliance: lifting appliances [bridge cranes, winches, hoists, monorail cranes, etc.) where
use is not considered to involve a hazard to life, health and/ or material assets
Sling: An assembly connecting a load to a lifting device
Slinger: The individual responsible for ensuring a load is prepared to travel
Page RMS-DOP-904
Lifting Policy / Procedure
7
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Sheave Block: A device consisting of at least one sheave in a frame with an attachment point for rope,
wire sling, or chain that can be attached to a load. Sheave Blocks are used in heavy lifts to help give
mechanical advantage and to change the direction of lift.
Static Lift: A lifting appliance lifting a load from and to the deck of the platform/vessel that the lifting
appliance is mounted on.
Suspended Load: load hanging in a lifting appliance
Taglines: Lines attached to a load to safely guide the load to a landing point.
Tandem Lift: A lift using two or more cranes, lifting appliances, or hoists
Temporarily Assembled Lifting Appliances: Lifting Appliances that are not permanently installed and
used for rigging; for example, a chain hoist suspended from a beam clamp that will be removed as soon
as the lift is complete. * Note: If a chain hoist is part of a designed and permanent lifting arrangement it
would not be considered temporary; for example, a certified and inspected lifting appliance that consists
of a chain hoist attached to a trolley and trolley beam designed specifically to assist in mud pump
maintenance.
Temporary Attachment Point: An attachment point created for a lift that occurs infrequently. Beam
clamps designed for lifting or a sling around a beam are examples of temporary attachment points that a
mechanical lifting device, such as a chain hoist, can be attached.
Test: specific operation of lifting equipment, with or without a defined load, in order to determine
whether defined requirements for the equipment are fulfilled
Transferred Load: the load transferred from a lifting appliance to a structure
Tugger: An air-operated lifting appliance
Wind Speed – Sustained: Average (mean) wind speed measured over a 1-minute period
Wind Speed – Gust: Wind peaks of at least 3 seconds measured during a 1-minute period
Working Load Limit: Maximum load the lifting equipment is certified to withstand under normal use
Page RMS-DOP-904
Lifting Policy / Procedure
8
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
4. RESPONSIBILITY
4.1. The Offshore Installation Manager (OIM) / Person in Charge (PIC)
OIM/PIC will designates a Lifting Responsible Person and Maintenance Responsible Person using
forms RMS-DOP-FORM905 and post the form on a notice board.
For installations working on the Norwegian Continental Shelf, the roles and responsibilities are
defined in RMS-DOP-912).
Authorizes all high-category lifts using RMS-QHSE-0111 Permit to Work
Page RMS-DOP-904
Lifting Policy / Procedure
9
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
10
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
with the titles Crane Operator (RMS-JOB-117 and 222 Crane Operator Job Description) or
Assistant Crane Operator (RMS-JOB-118 and 223 Assistant Crane Operator Job Description).
The Crane Operator performs the role of Lifting Appliance Operator for Material and Pipe
Handling cranes
4.7. The Signaller
The Signaller is the individual responsible for directing movement of the crane and load. In
some areas of operations this individual may be called a Banksman.
The Signaller:
• Contributes to pre-job review of the lift plan
• Clears the lift path, and ensures necessary barriers are in place to keep unauthorized
personnel outside the lift path and verifies the load is slung according to the plan
• Before a lift, ensures the load is secure, the load is unrestrained, the load is free of any
potential dropped objects and the hoist line is directly above the load’s center of gravity
• Signals the Lifting Appliance Operator
• Monitors each lift, maintaining line of sight with the Lifting Appliance Operator and
Slingers
• Ensures Slingers are in a safe area before lifting or landing a load and the landing area is
clear
• Wears a highly visible vest or hard hat cover which is clearly marked indicating they are
the authorized Signaller
4.8. The Slinger
The Slinger is a person responsible for ensuring a load is prepared to travel. More than one
Slinger may be part of a lift team and the responsibilities equally apply to each Slinger.
The Slinger will:
• Contributes to pre-job review of the lift plan
• Conducts pre-use inspection of lifting accessories to ensure good condition, proper color
code, and suitability
• Ensures that, on rigs with significant motions, loads are secured against unintentional
movement or overturning
• Confirms to the Signaller when the load is ready for lifting and when the hook is free at
the end of a lift
• Attaches and detaches rigging to and from the load and lifting appliance
• Maintains constant communication with the Signaller
• Completes the CCI checklist for backloading of cargo, see Appendix E
Page RMS-DOP-904
Lifting Policy / Procedure
11
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Note: The Rigger has distinct qualification requirements as per the training matrix which are not
met by a person who only has Slinger qualifications.
• Performs the Lifting Appliance Operator Role for Temporarily Assembled Lifting
Appliances
• Ensures the Temporary Assembled Lifting Appliance is safe and fit for purpose
• Approves Temporary Attachment Points for loads under 4400 lbs (1995kg)
4.10. The Rigging Store Controller
The Rigging Store Controller is the person assigned by the Lifting Responsible Person to control
the storage and inventory of loose lifting equipment.
The Rigging Store Controller will:
• Issue loose lifting equipment and keeps a register of lifting accessories/appliances issued
5. Inspects loose lifting equipment before issuing and on return, ensures defective, damaged, or out-
of-certification lifting accessories are tagged and quarantinedPOLICY
5.1. Inspection
• Thoroughly inspect lifting appliances and accessories before use.
5.2. Control of Lifted Loads
• Plan and conduct the lift to reduce personnel interaction with the load to as low as
reasonably practicable.
• Control loads primarily with the lifting appliance. If required, assist with taglines or push
poles.
• Never touch a suspended crane load or sling under tension with the hands or other body
parts unless all three of the following conditions are met:
1. The exception has been specifically risk assessed, has been determined to have
low risk potential, and has been detailed on the plan (JRA, RSOP, RSOP-L);
2. There is no other way to guide the load safely; and
3. The load is within 4 feet (1.3 meters) of the deck or ground level.
• Crane lifts that meet the conditions and require the use of hands to guide the load are
categorized as medium in the Lift Categorization Matrix.
Page RMS-DOP-904
Lifting Policy / Procedure
12
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
• Only touch a crane’s wire rope when the weight of the block is not supported by the wire
rope (e.g., the rope is slack), and only with the approval of the Crane Operator.
• Do not position yourself in the swing path of a load.
• Never pass under a suspended load.
• Never swing a load over personnel.
• Always maintain a safe distance from loads and have an escape route.
• Immediately STOP any lifting operation if the operation deviates from the lift plan, there is
a breakdown in communication, or any other complication arises.
Page RMS-DOP-904
Lifting Policy / Procedure
13
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
14
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
15
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
If the technical information required to complete a lift plan is not available or the
lift plan requires engineering, the Lifting Responsible Person will complete an
Engineering Request (PR-CO-ENG-005) to obtain the assistance of an Onshore
Technical Person. For example, an Engineering Request would be raised for a
lifting a large load without dedicated lifting points from the Original Equipment
Manufacturer (OEM) and calculations are required to determine correct loose
lifting equipment and lift points to allow a safe and even lift. The Onshore
Technical Person may use a format other than the JRA, RSOP, or RSOP-L to
document the plan. The Onshore Technical Person also determines whether
additional risk assessment tools are to be used to support the lift planning, e.g.
HAZID/HAZOP
The safety measures required must be evaluated and will vary depending on the
lifting operation to be performed.
Page RMS-DOP-904
Lifting Policy / Procedure
16
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
• the lifting operation to be performed using a lifting appliance made for the
purpose (high-risk applications).
• the lifting equipment shall not have any known faults or defects of
significance for the safety level;
• the lifting height and speed of the lifting operation to be reduced and
restricted;
• strict requirements to be agreed for visibility, communication and weather
restrictions for performance of the lifting operation;
• personnel involved in the operation shall have experience from equivalent
operations.
The following consequence-reducing measures shall be considered for
implementation:
• pressurised hydrocarbon-carrying systems to be de-pressurised or critical
equipment to be moved out of the hazard zone for the lifting operation;
• protection to be fitted or installed against loads falling/swinging against
pressurised hydrocarbon-carrying systems/critical equipment/adjacent
systems;
• restrict simultaneous activities;
• powered lifting appliances to be used shall have an emergency operation
system;
• the establishment of contingency plans for the lifting operation if
unforeseen incidents occur on the facility or in the lifting operations,
including a shutdown plan for exposed parts of the facility if unforeseen
incidents were to occur.
Equipment Planning
Communication Planning
Page RMS-DOP-904
Lifting Policy / Procedure
17
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
18
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
19
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
whichever is less. Do not exceed the maximum operating wind limits for
the specific lifting appliance.
Page RMS-DOP-904
Lifting Policy / Procedure
20
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
• One Slinger
The Signaller will NOT guide, position, maintain control of the load with tag lines
or any other means or perform any duties, other than those of the Signaler, while
the lift is being conducted (Steps 9-13 of the lifting process).
Tagline Planning
Consideration should be given to controlling the load without tag lines to limit
exposing personnel to hazards. For example, lowering a load low enough to be
easily positioned with signaling, if needed, gaining control of the load by placing
it in a clear lay down area, and positioning with a push pull pole while placing the
load with the crane.
The use of tag lines for lifts to and from vessels should be avoided.
If tag lines are required:
• There will be one continuous length and knot free
• There will be 15 foot (4.5 meter) or longer for Cargo-Carrying Units and
tubulars.
• The Vessel Operator and Lifting Appliance Operator will agree on their use.
• Attach at least two taglines to tubulars and any Cargo-Carrying Unit longer
than 10 feet (3 meters).
Authorize the lift according to the requirements of the Lift Categorization Matrix, see
appendix B
Hold a pre-job safety meeting using the lift plan (Lift Plan Card, JRA, RSOP, or RSOP-L)
Clear and barrier the lifting route and prepare the landing area. Notify and remove
personnel who are not part of the lifting team from the route and landing area
Page RMS-DOP-904
Lifting Policy / Procedure
21
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Conduct pre-lift checks on loose lifting equipment. The Lifting Appliance Operator will
conduct pre-use checks on the Lifting Appliance immediately before conducting the first
lift in the lifting operation or ensure the pre-use checks have been performed according
to the frequency required for the type of Lifting Appliance
The Slingers and Signallers will verify the load is slung according to plan, the load is secure
and free of potential dropped objects, and any risk of an uncontrolled release to the
environment has been removed or controlled.
The Signaller and Lifting Appliance Operator will confirm and test the method of
communication. Radios will be tested to send and receive messages. Ensure that radios
have enough battery life to complete the lift.
• Verify the load is secure, slung according to the plan, and the load is unobstructed.
• Position the hoist line directly above the center of gravity (Consider a test lift to
confirm this).
• Ensure the policy requirements of the Control of Lifted Loads Policy (Section 5.2) are
applied
The Signaller will signal the Lifting Appliance Operator. The Lifting Appliance Operator
will only respond to signals and/or verbal commands from the Signaler but will obey an
emergency stop signal given by any person at any time.
Hand signals will always be clearly visible to the Lifting Appliance Operator.
Page RMS-DOP-904
Lifting Policy / Procedure
22
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
If using verbal communication with radios, the Signaller will state their role first and then
give the command. The Crane Operator will state their role and repeat the command to
confirm understanding. For example, the Signaller states “Signaller, boom up”, then the
Crane Operator states “Crane Operator boom up”.
Page RMS-DOP-904
Lifting Policy / Procedure
23
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Once the load is unhooked, confirm all members of the Lifting Team are at least 4 feet
(1.2 meters) from the hook or lifting accessories connected to the lifting appliance before
giving the signal to hoist the hook out of the landing area. If required, a push pole or tag
line will be used to guide the lifting accessories free of the load and landing area.
• Provide verbal signals to the Lifting Appliance Operator even if hand signals are used
• Be in a position to view the load and Slinger, control the load, and maintain continuous
line of site with the Lifting Appliance Operator to give the stop signal manually in the
event radio communication fails
Exception: If continuous line of sight is not possible, verbal commands will be the primary
means of communication and an additional person will be positioned between the
Signaller and Lifting Appliance Operator to relay the stop signal with hand signals in
the event radio communication fails.
Note: Cameras (including boom tip cameras) are not a substitute for personnel with
direct view of the load or landing area. This does not apply to remotely operated
pipe handling where a camera is used to monitor the operation, the equipment and
area is adapted to camera monitoring, the area is cordoned off and there are no
personnel in the lifting area.
Page RMS-DOP-904
Lifting Policy / Procedure
24
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Do not use flexible intermediate bulk containers (Big Bag / Super Sack).
In regions with mild sea conditions and where the crane is not provided with dynamic load
charts, divide the static Safe Working Load by 2.
For Norway, in order to address additional dynamic loads, a higher safety factor for lifting gear
used for lifts between the vessel and the installation should be applied. Safety factor should be
selected in accordance with requirements in NORSOK R-002 Annex F
The Supply Vessel Captain will position the supply vessel with input from the Crane Operator.
The rig may loan radios that are set to the crane channel, to the vessel.
Page RMS-DOP-904
Lifting Policy / Procedure
25
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Before loading, unloading, or bulk exchange, the Crane Operator and Vessel’s Duty Navigator
will discuss:
Page RMS-DOP-904
Lifting Policy / Procedure
26
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
27
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
28
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Do not stack tubulars higher than 10ft (3m) high from the deck level unless the installation is
designed for this with special stanchions and access platforms; for example, drillship casing
storage bays. Pipe racks or other supports will be included in the total height.
8.9. Unbalanced / Asymmetrical Lifts
Categorize as Medium.
Use dedicated lifting equipment.
Exception: if dedicated lifting equipment is not available onboard, contact Onshore Technical
Person for guidance.
Equipment delivered from onshore will have dedicated lifting equipment which will remain
onboard until the equipment is returned to shore.
8.10. Lifting in Connection with Assembly and Disassembly Work
Categorize as Medium
Follow equipment supplier’s instructions for assembly and disassembly.
Ensure the load is completely free before lifting.
Prevent lifting equipment overload by monitoring the weight indicator (if this is fitted to the
lifting appliance or assessed as necessary in the planning) to ensure the stated or assumed
weight of the load is not exceeded.
8.11. Lifts with Temporarily Assembled Lifting Appliances
Lifting equipment, such as chain hoists, may be temporarily assembled on fixed or temporary
attachment points and used as Temporarily Assembled Lifting Appliances. Lifts with a
Temporarily Assembled Lifting Appliance will be categorized, at minimum, as Medium category
Lifts.
A lifting appliance with overload protection should be used and components included in the
assembly, such as shackles, should have a capacity greater than or equal to the lifting appliance.
If either cannot be provided for, a load cell or load indicator will be used.
Only transfer the load between two (2) lifting appliances when the load is at rest with the load
bearing lifting appliance. The Red Zone for the lift must be sufficient to account for how the load
will move if one of the rigging arrangements fail.
For lifts less than 4400 lbs, the Rigger will assess whether a temporary attachment point is strong
enough. The Rigger will tag the Temporary Lifting Appliance confirming the equipment is ready
for use (Appendix E). If the Rigger is present throughout the lifting operation, (e.g. rigging up, use
and rigging down) and the lifting operation is continuous, there is no tag requirement. Except in
Norway where a tag is always required. If the Rigger leaves the work space, the equipment will
be tagged “Not approved for use”.
Page RMS-DOP-904
Lifting Policy / Procedure
29
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
If the rigger does not have the required information to determine if the attachment point is
strong enough, the Onshore Technical Person must approve the attachment point and the lift
will be categorized as High category. The Onshore Technical Person will issue a certificate or
authorize the lift plan to confirm the Temporary Lifting Appliance can be used.
The Onshore Technical Person must approve all lifts over 4400 lbs using temporarily assembled
lifting devices and temporary attachment points. For rigs working on the Norwegian Continental
Shelf the Enterprise of Competence approves all temporary attachment points over 2 tonnes (see
RMS-DOP-912).
These lifts are categorized as High category.
Do not use live plant pipework as a temporary attachment point.
8.12. Cargo Winch (Tugger) Lifts
Before use, the winch operator will ensure:
• The hook is attached to the load
• The hook and swivel are in order
• The wire rope is undamaged and spooled correctly.
• Function test has been carried as per OEM
Use the wire rope guide, not your hands, to spool onto the drum while it is in motion.
Drill floor winches working simultaneously will use a color match system where the working end
of the winch wire is color matched to the same color as the winch
Page RMS-DOP-904
Lifting Policy / Procedure
30
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
31
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Machinery Directive. All lifting equipment shall also be accompanied by a certificate from
an enterprise of competence
11.3. Certification for Third Party Lifting Appliances and Accessories
Third Party lifting accessories and appliances must have all certification. The crane operator will
confirm that certification is available for accessories used to lift a load onboard.
The Lifting Responsible Person will inspect lifting appliances and certification before they are
used.
Lifting appliances that have one or more of the below characteristics must also be managed
according to RMS-DOP-FORM14 Third Party and Temporary Equipment.
• Connected to Installation utilities (Power, Air, Water etc.),
• Self-powered (Diesel etc.),
• Integrated with containers that are ordinarily manned
• Connected to any Rig Safety or Environmentally critical elements
11.4. Marking
All lifting appliances and accessories for lifting loads will be clearly marked with the SWL.
Depending on type of equipment, the SWL may be replaced with the working load limit (WLL), if
it is more relevant than the SWL. All equipment will clearly identify the characteristics of the
equipment, including:
• SWL/WLL
• Unique identification number
• Manufacture identification
• Date of inspection / test.
• Load rating (Depending on the equipment’s configuration the SWL / WLL may vary)
• In the case of lever hoists and chain blocks, the height of lift.
• Color code
Note: The Independent Certified Inspection Company color codes equipment after periodic
inspection. Use the color codes in Annex F. Use the Americas Deepwater color code when a
regional color code chart is not available. Color coding is not a standard in all operating regions
and the Lifting Responsible Person will determine if color coding is required for Third Party Lifting
Appliances and Accessories.
Page RMS-DOP-904
Lifting Policy / Procedure
32
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
11.5. Additional Requirements for Marking Equipment Used for Personnel Lifting
All equipment for lifting persons will be marked in the following way:
Position the boom to avoid interference with other crane or helicopter operations.
Page RMS-DOP-904
Lifting Policy / Procedure
33
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Exception: In rare occasions when a fiber sling must be used for a dynamic lift, specify on the
RSOP that slings will have a Safe Working Load double the weight of the load.
Do not use fiber slings if you cannot read the data label or they may be exposed to
o Sharp edges or rough surfaces
o Temperatures exceeding 176° F (80° C)
o Chemicals (refer to the manufacturer’s instructions for use).
Page RMS-DOP-904
Lifting Policy / Procedure
34
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
11.11. Chain
Only use for lifting if part of certified accessories.
Chains may be used for securing loads on the rig when large movement is expected. Do not use
loose chain to secure moving equipment or to secure equipment for breaking or torqueing.
Check for corrosion and flexibility between each link.
Due to challenges with corrosion in the joint, articulated joint loops shall not be used
11.12. Shackles
Only use if approved and certified.
Use only four-part shackles for rigging or lifting.
Use cotter pins for permanent rigging (see figure 1).
Use reusable safety locking pins (e.g., Surelock, Aussie Clip, see figure 2) for lifting.
Reusable safety locking pins like Aussie clips are not allowed
Figure 1 Figure 2
Note: Do not use tractor or hitch pins, hairpins, welding rods, or home-made pins.
Page RMS-DOP-904
Lifting Policy / Procedure
35
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Exception: Lifting eyes may be used for inboard or outboard lifts when:
• This use is clearly stated on the lifting equipment certificate AND
• The eyebolts are included with the equipment for this purpose
Page RMS-DOP-904
Lifting Policy / Procedure
36
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
• Split pins, locking, and safety pins are in place and in good condition.
• The load bearing structure is strong enough to withstand the forces at the head fitting
(line pulls and any friction forces).
• The sheave block is positioned to prevent the wire rope’s rubbing against the side plates.
• Provide secondary retention for sheave blocks.
For complex arrangements, verify correct set-up and calculations. See Appendix D for
calculation.
Note: Do not use sheaves blocks with threaded connections at the head fitting if these
connections might be backed out by contact with moving equipment (e.g., do not use such
equipment in the derrick or other areas with a high potential for snagging against moving
equipment). The hub of the sheave should be encased within a retainer on the side plates.
11.18. Load Carriers (Cargo Carrying Units - CCU's)
Before use, the Slinger will
• Inspect the load carrier and attached lifting set.
• Complete the CCU checklist (see Appendix E).
Ensure:
• “Load Picking” does not take place. "Load picking" means taking load carriers that are
positioned in between other loads and requires crew to climb on other load carriers or
expose themselves to other hazards to hook the load.
• The load does not extend beyond the sides of the load carrier.
• Multi-leg slings are secured against snagging. When necessary, secure the legs with cable
ties or cover with net or canvas.
• The load is positioned for safe and easy unloading.
• Equipment is placed on pallets.
• Pallets or timber are used on the floor of a basket.
• If installed, a safety net is used to prevent load’s falling through doors.
• Heavy or unstable items are secured with a tensioning arrangement.
• Forklift pockets are clear.
• Slings are not crossed
• Dangerous goods are identified with hazard stickers on all four (4) sides according to local
regulatory requirements.
• CCUs are sealed and secured to local requirements.
The Lifting Appliance Operator will ensure the hazards and controls are identified prior to
entering a carrier that contains loose or unsecured items.
Page RMS-DOP-904
Lifting Policy / Procedure
37
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
38
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
If plate screw clamps are used, a minimum of 2 clips should be used where they can individually
take the full weight of the load
11.20. Barrel Lifters
Only use:
• To handle barrels in and out of a load carrier
• To move barrels the minimum possible distance to or from a location where no other load
carrier is viable
In both cases, only transport barrels in good condition with securely attached lids and transport
barrels as far as possible in a load carrier.
Page RMS-DOP-904
Lifting Policy / Procedure
39
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
13. APPENDICES
Appendix A, Platinum Rules for Cranes
Appendix B, Lift Categorization Matrix
Appendix C, Hand Signals and Verbal Commands
Appendix D, Sheave Block Angle Factors
Appendix E, Container Checklist
Appendix F, Color Coding
Appendix G, Tag for Temporary Attachment Point
Page RMS-DOP-904
Lifting Policy / Procedure
40
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Follow the 8 ‘Rowan Platinum Rules’ at all times. No deviation, exemption, or variance is
permitted.
Rule 1: NEVER operate a crane outside of its applicable and approved Load Chart.
Rule 2: Only trained and certified employees may operate a crane on a Rowan rig or facility.
Rule 3: Check boom-up/boom-down on lattice boom cranes and hoist upper stop limits on
cranes fitted with hoist limits prior to the first use each tour. NEVER use any limit to routinely
stop motion of the crane.
Rule 4: Investigate EVERY ALARM to understand its cause and properly address it.
Rule 5: NEVER lift a load when a crane safety system has been bypassed, disabled, or inhibited.
Rule 6: Prior to any lifting operation, establish a communication plan for all personnel involved.
STOP operations if the plan is disrupted.
Rule 8: NEVER use hands to control a load except as permitted by the control of lifted loads
policy.
Page RMS-DOP-904
Lifting Policy / Procedure
41
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
42
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
43
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
The total load is equal to the Line Pull X Angle Factor X Friction Factor.
Example 1: With a 7,500 line pull and a 30° Angle Factor and a Friction
Factor of 1.08, the total load on the sheave block head fitting will be
(7500 X 1.93 X 1.08) = 15633 lbs.
ANGLE LINE PULL EXAMPLE RESULTING EXAMPLE RESULTING K5UL Multiply by RESULTING
MULTIPLIER EXPECTED ACTUAL EXPECTED ACTUAL WINCH factor of ACTUAL
(FACTOR) LINE PULL LOAD ON LINE PULL LOAD ON RATED 1.08 for LOAD ON
SHEAVE SHEAVE PULL FULL bronze SHEAVE
BLOCK BLOCK DRUM bearings BLOCK
0° 2.00 2,000 4,000 8,000 16,000 10,000 21,600 20,000
10° 1.99 2,000 3,980 8,000 15,920 10,000 21,492 19,900
20° 1.97 2,000 3,940 8,000 15,760 10,000 21,276 19,700
30° 1.93 2,000 3,860 8,000 15,440 10,000 20,844 19,300
40° 1.87 2,000 3,740 8,000 14,960 10,000 20,196 18,700
50° 1.81 2,000 3,620 8,000 14,480 10,000 19,548 18,100
60° 1.73 2,000 3,460 8,000 13,840 10,000 18,684 17,300
70° 1.64 2,000 3,280 8,000 13,120 10,000 17,712 16,400
80° 1.53 2,000 3,060 8,000 12,240 10,000 16,524 15,300
90° 1.41 2,000 2,820 8,000 11,280 10,000 15,228 14,100
100° 1.29 2,000 2,580 8,000 10,320 10,000 13,932 12,900
110° 1.15 2,000 2,300 8,000 9,200 10,000 12,420 11,500
120° 1.00 2,000 2,000 8,000 8,000 10,000 10,800 10,000
130° 0.84 2,000 1,680 8,000 6,720 10,000 9,072 8,400
135° 0.76 2,000 1,520 8,000 6,080 10,000 8,208 7,600
140° 0.68 2,000 1,360 8,000 5,440 10,000 7,344 6,800
150° 0.52 2,000 1,040 8,000 4,160 10,000 5,616 5,200
160° 0.35 2,000 700 8,000 2,800 10,000 3,780 3,500
170° 0.17 2,000 340 8,000 1,360 10,000 1,836 1,700
180° 0.00 2,000 0 8,000 0 10,000 0 0
Page RMS-DOP-904
Lifting Policy / Procedure
44
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Page RMS-DOP-904
Lifting Policy / Procedure
45
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Mexico
Page RMS-DOP-904
Lifting Policy / Procedure
46
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Norway
Trinidad
*set by the STOW implementation board
Page RMS-DOP-904
Lifting Policy / Procedure
47
Uncontrolled When Printed
Uncontrolled When Printed
RMS Policy RMS-DOP-904
DOP
Issue Date 3 December 2019
Revision # 19
Lifting Policy / Procedure Originator Vincent Rivera
Approved Peter Wilson
Area
Weight of Load
Description of
Attachment Point
Total Lifting
Capacity
Describe any
limitations of use
Rigger Name
Rigger Signature
Date
Page RMS-DOP-904
Lifting Policy / Procedure
48
Uncontrolled When Printed