Академический Документы
Профессиональный Документы
Культура Документы
Raja Javed Akhtar (1), Saleh Ahmad Rabba (1), Markus W. Meier (2)
Abstract
U Lower raw material cost:
• Coke / pitch
Dubai Aluminium Company (DUBAL) is one of the largest • Lower pitch content
single site aluminium smelters in the world producing
761,000 MT/year of high quality premium product. It has Potroom related optimization goals focus on superior
its own carbon manufacturing plant with a production anodes to produce metal at lower cost:
capacity of 370,000 anodes/year of different sizes and
configurations. • Higher consistency of anode properties
• No anode cracking or slabbing
As part of a management drive to optimise the current • No spikes or mushrooms
assets, an exercise of Dynamic Process Optimization (DPO) • Good anode current distribution
was carried out in the greenmill. R&D Carbon was chosen
• Low anode voltage drop
as the technical partner and worked along with DUBAL
• High metal purity
operational personnel during the three phases of the DPO.
The process parameters were optimised systematically to • Low consumption figures
reduce pitch content, increase paste throughput and increase • High current efficiency
anode density. A mobile pilot press was utilised to prepare
samples for evaluation during the optimisation process. In order to identify in a systematic manner the area(s) with
the greatest potential for optimization, DUBAL contracted
The optimised parameter settings were implemented on both R&D Carbon to carry out an audit of the anode plant.
anode production lines in the greenmill following a Therefore a technical assessment was carried out by
successful 15 cell trial in the potrooms. following the material stream from the raw material intake
all the way to the potrooms and the butts recycling station.
This paper describes the DPO methodology, highlights the Every relevant processing step was investigated by
results achieved in the greenmill together with the sampling the product, analysing its properties and
subsequent improvement in anode quality and performance. comparing them with the worldwide typical level and
benchmark.
Introduction
The audit conducted by R&D Carbon concluded that
U
Prebaked anodes contribute as the biggest variable impact to DUBAL produces anodes of high quality with limited
the aluminium production cost [1]. Reducing the production options for further improvements of their performance in
cost is an ongoing process in every smelter. Optimization the pots. The high current efficiency of 95.1 % and low
goals may focus on the anode plant to produce cheaper anode net consumption of 406 kg/tAl in the CD-20 pots
anodes with the same performance in the pots or on the underline this conclusion.
potrooms to use anodes of superior quality to produce metal
at reduced cost [2]. On the other hand the results of the audit showed that there
is a potential to reduce the pitch content without negatively
There are numerous optimization goals in the anode plant affecting baked anode quality, in particular apparent density
that can lead to a reduction of the aluminium production and air permeability. Prior to the DPO the pitch content in
cost provided that the anode performance is not negatively green anode was 15.0 +/- 0.7 % depending on the coke type
affected: used. The baked anodes exhibited an apparent density of
1.580 g/cc and an air permeability of 0.6 nPm.
Lower conversion cost:
• Higher throughput Reduction of the pitch content without adversely affecting
the anode properties requires adjustments in the recipe and
• Less scrap
also to the preheating, mixing and forming processes. A trial
• Fewer breakdowns and error approach on a full production scale was not
• Lower energy consumption feasible due to a high risk of scrap generation and
• Lower maintenance cost potentially poor anode behaviour in the pots over an
extensive trial period. Instead, an approach on a pilot scale
was chosen which is described hereafter. hydraulic press, which took less than one hour. This allowed
the testing of many parameter combinations with the
The methodology of the Dynamic Process Optimization generation of a minimum amount of anode scrap. The short
(DPO) enabled the determination of the optimum production time reduced the effect of quality variations in
combination of processing parameters with negligible scrap the raw materials.
generation in a very short period of time. The
implementation of the optimization findings was made
within a few weeks. The optimization process was carried
out in 3 steps:
DPO Approach
U U
The actual procedure of the DPO [3] involved the The resulting anode properties were determined according
production of pilot electrodes with anode paste collected to standardized test methods [4]. The evaluation of the
directly after the cooler, (see figure 1). Only one parameter anode properties from each trial enabled the determination
was changed at a time while all others were kept constant. of the optimum combinations of process parameters.
For one set of parameters twelve pilot electrodes of
approximately 5 kg each were produced utilising a mobile
DPO Program Table II: Base line vs. optimized settings towards reduced
pitch and over-nominal throughput
Prior to the commencement of the DPO, a consistency test Optimization towards
was performed with standard conditions to verify stable Parameter / Property Unit Base Line
operation of the paste plant. This test was essential, as the Settings Reduced Over-
negative effect of process variations on the anode quality is Pitch level Nominal
Throughput
often underestimated.
Fines fineness Blaine No 2700 4000 4000
The best results were achieved when a combination of Fines content % 42 31 31
Pitch content % 15.6 14.4 14.4
parameters was optimised. However, several limitations Mixing temperature °C 177 187 187
were respected. The prime limitations were the capacity of Mixing power kW 260 280 280
the installed equipment, and their inherent operational Forming temperature °C 140 150 150
variations. These limitations were identified during the Throughput t/h 33 33 35
preliminary plant and capability check.
Green anode weight kg 1200 1204 1200
The sequence of optimization trials is summarized in table I. Green anode density g/cc 1.620 1.625 1.620
Due to the fast production procedure for the pilot electrodes, Baked anode weight kg 1145 1158 1155
the entire optimization program could be carried out in three Baked anode density g/cc 1.566 1.592 1.586
days. Air permeability nPm 0.50 0.49 0.54
Specific electrical m 57 58 59
resistance
Table I: DPO program principles Flexural strength MPa 10.5 9.5 8.6
Static elasticity modulus GPa 4.7 4.0 4.1
Seq. Focus Parameters Variations Thermal conductivity W/mK 3.89 3.48 3.38
Following positive laboratory results as illustrated in table The confidence gained as a result of the selected pots trial
11, the decision was taken to carry out a selected pots trial helped in making the decision to implement the revised
in the potrooms before implementation of the recommended DPO setting for plant wide production in March/2005.
revised settings for plant wide production. A batch of 2000
anodes each with the original parameters (control) and the The actual supply of anodes to the potrooms commenced in
revised DPO settings (test) were produced utilising the same May/2005. At the time of writing this article, these anodes
raw materials in the Greenmill. have completed four clear cycles of operation without any
adverse impact on pot operation.
Table 111- Green Anodes Quality Data
Apparent density (g/cc)
1. 5 8 0
Test 1 1987 Avg SD Avg SD Blaine SD
No.
Anode Group
Criteria Test Control 0 .7 5