Академический Документы
Профессиональный Документы
Культура Документы
cross the intersection several times during a day and it would be better to build a pedestrian sky-
bridge over this street to eliminate any risk of accidents in that crowded intersection (especially
at rush hour periods). Your job is to design a pedestrian sky-bridge over the Lincoln Way. In this
1. Design of your sky-bridge (a sketch that shows what the final structure looks like)
2. What type of material you would want to use to build it (e.g., concrete over steel, etc.)
Introduction:
At the beginning of the project, our group first came to the crossroads of what kind of
bridge we wanted to build. The two we decided between was either an indoor bridge or an
outdoor bridge. The reasoning for the indoor bridge is that it would be heated in the winter, and
air-conditioned in the summer to give students a break from the weather in Ames. It could also
have some tables or a few benches inside for students to study, or just take in the view of Lincoln
way. The ultimate reason we didn’t go with this solution was the huge cost and plus how small
the sky bridge is. We then decided that our sky bridge would have to be an outdoor one. It is
cars cross Lincoln Way a day in the area we are expecting to build the sky bridge. Buchanan Hall
was the first dorm to be built across the street in 1964 holding 409 students. At this time there
wasn’t as much traffic as the university because in 1962 they broke the 10,000 student milestone,
and compare that to fall 2018 enrollment of 35,000 students, it’s not even close. Then in 2016,
Geoffrey Hall was opened to 770 new students that would inhabit it each semester. Over a
thousand students now live across the street and need to cross every day in order to get to their
classes, and these numbers don’t even include fraternities and sororities. The high traffic in the
area, the amount of students and the safety liability the university now has are all reasons for
why a sky bridge is needed. Our group was also considering attaching the sky bridge to Geoffrey
hall, but we later scrapped this idea again due to costs and the distance from the road.
Land Surveying:
Our group estimated using Google Earth’s measuring tool
that our bridge should be around 60-65 meters (~200 ft) in length.
Map Server also tells us in the area we are looking to build, the land
is relatively level when crossing the street. Also on the map, we can
see there are two bus stops that are relatively near each other. We
decided to put the sky bridge because of this to the left of the intersection because we didn’t want
to disturb the bus routes and cause negative externalities. Our group tried to find soil samples
using the Iowa Geographic Map server but we had no clue as to what the data from the NRCS
meant. We tried to research what each data point was, but was unsuccessful and our lack of
Design:
We decided to keep the design of the project simple to reduce the price of the sky bridge
and the time needed to construct it. Designing a bridge with an enclosure doesn’t make much
sense because students will be exposed to the elements getting to and from the bridge. We
decided to use a ramp system on both sides of the bridge to ensure that it is accessible to people
who can’t travel up stairs. Originally we planned to use a straight ramp but found that it would
not be reasonable because, in order to comply with ADA, the ramp would have to have a
horizontal length of 204 feet. This is why we altered our plan and decided to use a spiral ramp
instead. We decided against an elevator system because it would be too expensive and also be
the cause for much more maintenance. Since concrete doesn’t have a good tensile strength we
created a design that had a vertical support in the middle of the bridge to shorten the span and
alleviate some of the tensile force. We made sure that this support would be narrow enough to fit
in the median of the road so it wouldn’t disrupt traffic flow. Our design materials are concrete
and steel. We will use cast in place concrete for the foundation and the main structure of our sky
bridge. The steel will be used in the form of rebar and hand railings.
Contractor:
For our contractor, we decided to use Story Construction Company. They are a local
company and they have a tremendous amount of experience working on campus. Some of the
Since they are a local business they will be more affordable because they won’t have to travel far
no way of knowing.
Challenges:
There are many challenges associated with the design and construction of the sky bridge.
One of the main challenges is that this project is located on campus and campus is a really busy
place when students are here. We are adjusting for this challenge by attempting to keep as much
construction as possible scheduled for the summer months when students are gone. Another
challenge with this project is that Lincoln way is a very busy street and construction can interfere
with car traffic. We will have to plan a route to redirect cars in the possibility of a road closure.
An additional challenge we face is approval from the City of Ames. They will have to approve
the project before we can start building. This means we will have to be flexible to meet their
Accessibility to the sky bridge is important and we will have to plan to comply with the
Americans with Disabilities Act, which means that we will have to have a ramp slope no greater
than 1:12. This caused us to have to alter our design because having a height of 17 feet would
require a ramp with a horizontal distance of 204 feet. This seemed too unreasonable to us, so we
Another challenge for us is trying to figure out what is beneath where we want to build
our skybridge. Since our group is not a contracting company, nor meets the standards and
qualifications in order to get utility information, we cannot factor in the difficulty or get the
information of what’s underneath the site in the project. An ongoing challenge is that the sky
The last challenge for our group is that we have to work with the city of Ames in order to
work around their ongoing project, using 70,000 dollars to add trees to the median of Lincoln
Way as part of their initiative to make Ames look nicer to visitors. We would either have to
modify our skybridge plans or they would have to modify their median project, in order to work
about the prices, but we can look at sky bridges that have already been built to get an idea of the
cost. The U.S. Bank Stadium Skybridge has an uncovered design, like ours, and cost $5.1 million
to build. It is also much bigger than ours, which means ours would be much cheaper. The U.S
Bank Stadium Skybridge is 25 feet tall and 345 feet long and has 4 elevators. Our design is 17
feet tall and 65 feet long and doesn’t have any elevators. The Pedestrian and Bike Center
estimates the cost of a steel bridge to be between $150-$250 per square foot. Covered sky
bridges tend to be much more expensive. The Davenport Skybridge is 50 feet tall and 600 feet
Our group tried to use the data from the skybridge from Hoover Hall to Howe Hall, and
Beyer Hall to State Gym, but were unable to find the numbers for these skybridges as when they
were built the money cost was lumped together with the building itself, which would be hard to
Projected Timeline:
For this project we estimated that the design of the project would take about three
months. We decided that it would be best to start the design of the bridge in December, so our
construction crew could start in early March. Starting in March and finishing in November, our
goal would be to have the construction of this bridge take nine months. The our reasoning for
this scheduling is to have the construction take place when temperatures are more adequate, and
there are less students students on campus in the summer, which would help with traffic re-
routing.
Disciplines of CE Involved:
The disciplines of Civil Engineering involved in this project are geotechnical,
transportation, construction, and structural. The Geotechnical Engineer will take soil samples and
determine if the bearing capacity of the soil is suitable to support the skywalk that will be built
there. The discipline of transportation for this project will need to be considered as well. This
skywalk is going to be built over a very busy roadway, and traffic may need to be rerouted at
some point in the construction. Another discipline of Civil Engineering involved in this project is
construction. Because of the tricky location of this project, the construction of this bridge will
need to be done in a timely and strategic manner. The design engineer will work on calculating
the maximum possible load that this skywalk may endure, and then they will aim for a design
Benefits:
Despite the many challenges in building a skywalk over Lincoln Way, there are many
rewarding benefits. It will be much safer for Iowa State students and Ames residents to cross
over this busy intersection. The flow of traffic will be improved, as cars will need to stop for less
pedestrians. Also, the architectural design of this skywalk will be attractive to the eye for people
entering campus, and it will show off the great Civil Engineering program we have here at Iowa
State!
Impacts:
Constructing this beautiful skywalk may come at the cost of removing some trees that
would be in the way at the construction site. The traffic may be interrupted at times due to the
construction, which is an inconvenience for the people who drive down Lincoln Way daily. This
skywalk will also require more maintenance and upkeep than a traditional crosswalk would.
Sources:
https://www.teachengineering.org/lessons/view/cub_brid_lesson02
http://iowadot.maps.arcgis.com/apps/MapSeries/index.html?appid=0cce99afb78e4d3b9b24f8263
717f910
http://iowadot.maps.arcgis.com/apps/Viewer/index.html?appid=a29e44be6e314799b612335342a
13f62
Google Maps & Earth
http://www.cityofames.org/home/showdocument?id=41594
https://www.teachengineering.org/lessons/view/cub_brid_lesson05
http://www.pedbikeinfo.org/cms/downloads/Countermeasure%20Costs_Report_Nov2013.pdf
https://www.minnpost.com/minnesota-blog-cabin/2015/04/unnecessary-pedestrian-bridge-going-
cost-6-million-public-money/
https://www.discountramps.com/wheelchair-ramp-length/a/B20/