Corporate Office II, 95 Institutional Area, Sector 32, Gurgaon 122001, India
T+91 124 262 0769 F+91 124 262 0777
info@punjlloyd.com
www.punjlloyd.com
Ref: 1) Kick Off Meeting (KOM) dated 27th September 2016 at Chief Engineer’s Office,
MbPT Building, Mumbai
Dear Sir,
It was indeed a pleasure to express Contractor’s understanding of the Project and present a
brief overview of the execution strategy including HSE, QA/QC, Project Control and Execution
Methodology to the Employer & Engineer and Contractor is thankful for the valuable guidance
provided during the meeting.
Thanking You,
For Punj Lloyd Limited
SAURABH JOLLY
Project Manager
Page 1 of 6
MINUTES OF
MEETING
Agenda:
The Kick-off Meeting was organized on request of MbPT (Employer) and EIL (Engineer) wherein Punj Lloyd
(Contractor) presented a detailed overview of its execution strategy including HSE, QA/QC, Project Control
and Execution Methodology.
S. NO. DESCRIPTION ACTION BY Target Date
Shri R.Murugadoss, Chief Engineer, MbPT welcomed the
1 Engineer and Contractor and wished the team success and Info
timely execution of the Project.
Contractor Senior Management, Shri V. P. Sharma, Project
Sponsor, stated that they have carried out projects in the
vicinity of the current Project routing and are well aware of the
2 Info
Project Location and assured MbPT that a capable team has
been put to execute the Project and Safety and Quality shall be
a prime objective.
Contractor introduced the Project Team and stated that most
of the Key Personnel for the Project are identified and awaits
3 Info
LOA for processing the documentation with the bank for
issuance of the guarantees.
Contractor Project Manager (Contractor’s Representative)
welcomed the gathering and gave a comprehensive
4 Info
presentation. Salient Points discussed during the presentation
are as under:
As there is no separate line item for Engineering in the SOR
which shall be the only work during the coming few months,
accordingly Contractor proposed that 5% weightage to be
assigned for Engineering Works. 28th October
4.1 Contractor
Employer stated that this should be closed with the Engineer 2016
during finalisation of the Baseline Schedule.
It was agreed that the Schedule should be based on the SOR
weightages so that Progress and Billing are aligned.
Page 2 of 6
MINUTES OF
MEETING
Page 3 of 6
MINUTES OF
MEETING
Page 4 of 6
MINUTES OF
MEETING
Page 5 of 6
MINUTES OF
MEETING
The Contractor stated that the water depth is just 4.5 metres
above CD that to based on survey carried out in the year 1999.
Based on Contractor’s experience within the vicinity and
current conditions, the water depth is insufficient for handling
and manoeuvring of bigger vessels, AHTs and associated
anchor movements.
Accordingly, the Pipeline Installation has been planned as
detailed in the presentation and summarized hereunder:
4.8 OPTION I Info
In this option, the offshore section of the pipeline is planned to
be installed by use of Lucker Winch and Barge. The Pipeline will
be installed in two section and a mid point tie-in will be carried
out.
OPTION II
In this option the offshore section of the pipeline is planned to
be installed in single section by use of Lucker Winch only.
5 The KOM Presentation is attached as ANNEXURE – I.
Contractor requested Employer/Engineer that the first co-
6 Info & Request
ordination meeting to be held at Contractor office in Gurgaon.
The Contractor proposed that it will carry out a detailed site
15th - 20th
visit with its Engineering Subcontractor, Trenching, Backfilling
7 Contractor October
& Cable Lay Subcontractor along with its pipelay team in mid
2016
October’2016.
The Meeting was duly concluded and the teams exchanged contact details among each other.
Page 6 of 6