METHOD STATEMENT
Textile Ducts
SIZE
A4
DEGREMONT REFERENCE REVISION WORKING STATUS
SUBJE PROCE
PROJECT NUMBER ISSUER TYPE NUM
CT SS NB
B-001032 STS EL 000 PR 001 A RFR
This document is confidential and shall be used only for the purpose on the BARKA IWP Project
B-001032-STS-EL-000-PR-001
BARKA IWP
Textile Ducts and Rev: A Working status :RFR
Accessories Page 2 / 15 Date : 28/05/2017
CONTENTS
1 PURPOSE....................................................................................................................................................... 3
2 SCOPE............................................................................................................................................................ 3
3 ENVIRONMENTAL.......................................................................................................................................... 3
3.1 ENVIRONMENTAL ISSUES.................................................................................................................................... 3
3.2 MITIGATION MEASURES...................................................................................................................................... 3
4 REFERENCES................................................................................................................................................... 3
5 FORMS........................................................................................................................................................... 3
6 ABBREVIATIONS & DEFINITIONS..................................................................................................................... 4
7 RESPONSIBILITY............................................................................................................................................. 4
8 GENERAL PROCEDURE.................................................................................................................................... 5
9 TEXTILE DUCTS AND ACCESSORIES INSTALLATION PROCEDURE (EXECUTION-WORK SEQUENCE).....................6
10 TOOLS & EQUIPMENTS................................................................................................................................. 10
11 SITE INSPECTION.......................................................................................................................................... 11
11.1 Textile Ducts inspection........................................................................................................................... 11
12 ACCEPTANCE.............................................................................................................................................. 12
13 HEALTH & SAFETY........................................................................................................................................ 13
14 TRAINING FOR EMPLOYEES & SUPERVISORS................................................................................................. 13
15 RISK ASSESSEMENT & CONTROL................................................................................................................... 13
16 JHA.............................................................................................................................................................. 14
17 FIRST AID / MEDICAL FACILITY / EMERGENCY RESPONSE..............................................................................14
18 ATTACHMENTS............................................................................................................................................ 14
19 APPENDIX-1 USER FEEDBACK SHEET............................................................................................................. 15
1 PURPOSE
To establish a procedure and provide minimum requirements for Ducts and accessories Installation and
conduits works.
2 SCOPE
This procedure is applicable to Ducts and accessories installation for BARKA IWP project and
operations.
This procedure is to be used in conjunction with relevant project specifications, installation drawings,
termination drawings, manufacturer’s instructions and the approved ITP. It is not intended to replace
or conflict with project specifications or the equipment manufacturer’s instructions.
3 ENVIRONMENTAL
Noise
4 REFERENCES
5 FORMS
Abbreviations:
AFC Approved for construction
RFC Ready for Construction
LV Low Voltage (>48 VAC or >110 VDC and <1kV)
ELV Extra Low voltage (<48 VAC or <110 VDC)
MV Medium voltage (>1 kV)
MR Material Request
MRIR Material receiving Inspection request
ITP Inspection & Test plan
ITR Inspection Test Record
JHA Job Hazard Analysis
PTW Permit to Work
SOP Safe operating procedure
RFI Request for Inspection
WMS Work Method Statement
Definitions:
Cable Tray Cable ladder/tray
7 RESPONSIBILITY
Material Controller Responsible for receiving the items & associated materials and
checks for any visible mechanical damages and cross checks the
received quantity against the purchase order. He should store the
items accordingly.
QC Inspector Responsible for inspection of all the received material for any
physical damages and reviews material / test certificates received
from the manufacturer for its conformance to the project
specifications. Co-ordinate with all subsequent inspection & testing
works and accepts/rejects based on inspection results.
Electrical Engineer Responsible for the overall coordination and control of items
complying with requirements of this procedure and successfully
completing the job.
HSE Adviser Responsible for all safety related aspects on site. Works in close co-
ordination with the Site Supervisor to identify all risks and
8 GENERAL PROCEDURE
9.1 Upon receiving the accessories from qualified and approved supplier.
DSIO site engineer will examine accessories for physical damages, dents
& scratches as per contract specification. Segregate, identify and
separate all damaged items/pieces for rework and / or replacement.
9.2 Apply approved anti-corrosion paint on all dents, scratches and welding
spots uniformly and fill all gaps with approved sealant to avoid any
leakage, especially near to the linear joint. Remove excess sealant from
the joints, make them clean and tidy
9.3 These inspected accessories will then be offered to Client/Consultant
representative for inspection prior to site delivery.
9.5.1 Determine the position of the damper to be fixed on the duct from the
construction drawing, mark and cut the duct as per the marked size.(The
cutting is necessary only when the opening for the installation is not available
in the duct)
9.5.2 Examine the location for requirement of installation tolerances and clearances
as specified in the drawings.
9.5.3 Manually move the volume control damper (VCD) to the desired position in a
way that damper channel frame matches the duct flange
9.5.4 Apply gasket to make the joint air tight and fastening the clamp on the duct
flange.
9.5.5 To install the insert type of volume control damper, insert the VCD inside the
duct into position through opening provided by cutting slot which has to be
closed and sealed later.
9.5.6 By using rivets or nuts and bolts of required size fix the VCD with duct work
9.6 Installation of Grilles & Diffusers :
9.6.1 Determine the position of the grills/diffuser to be fixed on the duct from the
construction drawing, mark it and cut the duct as per the marked size
9.6.2 Examine the location for requirement of installation tolerances and clearances
as specified in the drawings.
9.6.3 Place the grill/diffuser at notched position in plenum in such a way that
extruded edges or border of the grilles/diffuser, seats at plenum bottom edge.
9.6.4 To fix the grill/diffuser with clips, position the joining clips over notching of
plenum and lower on border of the diffuser and push it over.
9.6.5 If diffuser is fitted with riveting, drill holes in to grill/diffuser border, align
these holes with plenum notches and finally fix the reverts at notched locations
9.6.6 For slot diffusers assemblies, slip the slot diffuser assemblies in to the plenum
slot, alight the suspension point with the hole and screw them properly
9.6.7 After installation of diffuser adjust the blades of volume control damper as per
the requirement
9.9 Apply fire stopping sealant at all penetrations, where ever applicable
9.10 Make sure the proper safe covering of accessories until to proceed with final
system commissioning and handing over to consultant/client.
9.11 After completing the accessories installation, clean interiors from foreign
materials and leave the site clean and tidy.
10 Work Completion
12.1 Mark-up Drawings to be Updated if Any Changes. Changes to be transferred to the
Master File
12.2 Complete and Sign Worklot ITRs STS Sup/QCI
STS Sup/QCI
Use of appropriate following tools (but not limited) and equipment shall be used,
11 SITE INSPECTION
When Site Works defined in the Work lot are completed, then the Site Inspection is performed at site.
12 ACCEPTANCE
On completion of the work, All Worklot ITRs to be duly filled up, Reviewed and signed by:
STS Supervisor
STS QA/QC
If required, signature of acceptance of the activity is obtained from the Client’s representative
All persons involved in the activity shall undergo site HSE induction prior to deployment to the work site.
Site activities shall be carried out in a safe manner according to the approved “Project Health, safety and
environment plan”.
The following trainings shall be delivered to the crew but not limited to:
Manual Handling.
Working at height.
Lifting Equipment, tools and materials shall have to be inspected properly before using, power tools &
equipment must be colour coded.
Following control measures generally apply to all hazards that shall be adopted as a proactive
measure in addition to the specific controls identified in the JHA
Good Housekeeping.
16 JHA
HSE Hazards involved in the activity has been assessed through attached JHA.
The contents in JHA shall be disseminated within the crew by the supervisor / foreman through
Toolbox talk.
Any new Hazards identified other than in the JHA with reference to the site condition shall be
assessed and control measures shall be taken by the Site Engineer/Supervisor prior to
commencement of any activity.
Availability of First Aiders, with ready access to first aid boxes kept at site shall be ensured at
worksite.
Site contractor clinic will be manned with Male Nurse during working hours
18 ATTACHMENTS
The user is requested to return this page fully completed indicating precisely the amendment recommended or
comments on the document.
By : Date :
Note : Attach marked-up draft of the document showing the proposed changes/ additions.
CC to : File
Route to : Management Rep. > Operations Manager – E & I > Management Rep. > File