Вы находитесь на странице: 1из 15

MEGHANA AAC BLOCKS INDU

BILL OF MATERIALS (BOM


PILE FOUNDATION

TMT BAR TOTAL


USAGE FOR ST. LENGTH LAP/ BEND NOS
(Ø IN MM) LENGTH
STEEL FOR PILES (15''Ø)
12 MAIN 3485.2 120 3605.2 4
10 MAIN 3485.2 100 3585.2 4
8 STIRRUP 958 80 1038 24

STEEL FOR PILE CAP (4'X3'X1')


12 TOP MAT 1420 0 1420 6
12 1045 0 1045 9
10 BOTTOM MAT 1420 0 1420 6
10 1045 0 1045 9

PLINTH BEAM (300X230)


12 MAIN 106060 4000 110060 2
10 MAIN 106060 4000 110060 2
8 STIRRUP 904 80 984 531

COMPOUND WALL PILES (9''Ø)


10 MAIN 1510 100 1610 2
8 MAIN 1510 80 1590 4
6 STIRRUP 718 60 778 9

MATERIAL PROCUREMEN

NO. OF FULL WEIGHT WEIGHT COST PER TRANSP


TMT BARS (Ø)
LENGTHS (IN KG) (IN MT) MT (RS.) ORT

12 90 927 0.93
10 90 643 0.64
8 102 467 0.47
6 32 82 0.08
TOTAL 282 2037 2.04
18439
921.95 3
1843.9 6
AC BLOCKS INDUSTRY
MATERIALS (BOM)
E FOUNDATION
FOR F
NO. OF TOTAL LENGTH IN REQ. FULL WEIGHT WEIGHT
FOOTINGS LENGTH FEET LENGTHS (KG) (MT)

24 346099.2 1135.50 33.00 308 0.31


24 344179.2 1129.20 33.00 212 0.21
24 603701 1980.65 57.00 238 0.24
TOTAL 123 759 0.76

24 204480 670.87 18.00 182 0.18


24 225720 740.55 20.00 201 0.20
24 204480 670.87 18.00 126 0.13
24 225720 740.55 20.00 139 0.14
TOTAL 56 509 0.51

1 220120 722.18 19.00 196 0.20


1 220120 722.18 19.00 136 0.14
1 522587 1714.52 45.00 206 0.21
TOTAL 83 538 0.54

56 180320 591.60 16.00 111 0.11


56 356160 1168.50 31.00 141 0.14
56 372725 1222.85 32.00 83 0.08
TOTAL 79 335 0.33

MATERIAL PROCUREMENT

LOADING & TOTAL COST TOTAL COST


DETAILS OF SUPPLIER PAID AMT.
UN LOADING (IN RS.) (IN LACS)
1600 1
1450 1
689 0.43 2.83 1
1252 0.86 0.43 0.15216431
11.43438

72

DUE AMT.
ESTIMATE
MEGHANA AAC BLOCKS INDUSTRY
S.NO. DESCRIPTION OF THE WORK NOs. L(M) B(M) D/H(M) QUANTIY
1 Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 10m including all
operational,
For Piles incidental, labour charges such as shoring24 ,sheeting,
3.14 planking,
0.04strutting, etc.3.35
complete for9.13
finished item of
Alround 1 106.06 0.60 0.75 47.73
Deductions -24 3.14 0.04 0.75 -2.04
54.81 Cum
2 Sand filling in trenches, sides of foundations and basement with initial lead in layers not exceeding 15 cm thick,
consolidating
For Piles each deposited layer by watering and24 ramming including cost1.50
1.50 and conveyance of water to8.10
0.15 work site and all
Building 1 106.06 0.60 0.15 9.55
Basement 1 34.29 18.14 0.15 93.30
110.95 Cum
3 Plain Cement Concrete M 7.5 Grade (1:4:8:) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
For Piles 24 3.14 0.04 0.15 0.41
All round building 1 106.06 0.46 0.15 7.27
7.68 Cum
4 Random Rubble stone Masonry in CM (1:6) Cement: Sand) using hard granite stones from approved quarry including cost
and
Belowconveyance of all materials and labour charges1 etc., complete.
Ground level 106.06 0.45 0.75 35.80
Above Ground level 1 106.06 0.45 0.45 21.48
Deductions -24 3.14 0.04 1.20 -3.27
54.00 Cum
5 Filling with useful available excavated earth (excluding rocks) in trenches, sides of foundations and basement with initial
lead
InsideinBasement
layers not exceeding 15 cm thick, consolidating
1 each 34.29
deposited layer
18.14by watering and
0.55ramming342.11
includingCum
cost and

6 Supply and placing of the RCC M20 Nominal mix Concrete corresponding to Table 9 of IS 456 using with 20mm size
graded machine crushed hard granite metal (coarse
a) Pile Reams 24 aggregate)
3.14from approved
0.04quarry including
2.35cost and 6.41
conveyance of all
b) Above Ground level 24 3.14 0.04 0.75 2.04
c) Pile Cap 24 1.10 0.72 0.30 5.70
d) Plinth Beam
Alround (Main shed) 1 106.06 0.23 0.30 7.32
Cross Wall 0 17.98 0.23 0.30 0.00
7.32
Alround (Boiler shed) 1 35.00 0.23 0.30 2.42
Alround (Lime & Cement shed) 1 24.00 0.23 0.30 1.66
4.07
e) Lintels
Doors (Boiler, Lime & Cement shed) 3 1.40 0.23 0.15 0.14
Widows (Main & Boiler Shed) 38 1.72 0.23 0.15 2.25
Widows (Lime & Cement Shed) 6 1.40 0.23 0.15 0.29
2.40
f) Sunshades
Above Doors 1 1.40 1.40
Above Windows (Main & Boiler shed) 38 1.72 65.36
Above Windows (Lime & Cement shed) 6 1.40 8.40
66.76 Rmt.
Total RCC 27.94 Cum
7 Brick masonry 230 mm thick for panel walls in superstructure and 100 mm bricks for partition walls with CM (1:8)
proportion
Allround of using II Class
building (Main bricks
Shed) having crushing strength
1 not less than 35 0.23
106.06 kg/Sqcm including
2.74cost and 66.92
conveyance of all
Deduct Open access (Main Shed) -1 20.70 0.23 1.00 -4.76
Deduct Windows -31 1.52 0.23 1.22 -13.22
Allround of building (Boiler Shed) 1 35.00 0.23 2.74 22.08
Deduct Door (Boiler shed) -1 1.20 0.23 2.10 -0.58
Deduct Windows -7 1.52 0.23 1.22 -2.99
Allround of building (Lime & Cement Shed) 1 24.00 0.23 2.74 15.14
Deduct Doors (Lime & Cement shed) -2 1.20 0.23 2.10 -1.16
Deduct Windows -6 1.52 0.23 1.22 -2.56
48.93 Cum
DATE: 13-08-2020
MEGHANA AAC BLOCKS INDUSTRY
MATERIALS, CONSUMABLES, TOOLS & TACKLES REQUIREMENT
UPTO FIXED FLOOR LEVEL(FFL)/PLINTH LEVEL
DESCRIPTION UNIT QUANTITY
I MARKING PILLARS
1 Level posts (Bamboo or Survee)-4' Long Nr 32
2 Line Door LS LS
3 Clay Bricks Tractor Load 1
4 Cement Bags 3
5 Sand LS LS
II REINFORCEMENT (TMT BARS)
1 12 mm Ø Bar Full Legths 90
2 10 mm Ø Bar Full Legths 90
3 8 mm Ø bar Full Legths 102
4 Binding Wire Kg 10
III PCC (1:4:8)
1 40 mm Stone Aggregate Units 2.57
2 Cement Bags 26.21
3 Sand Units 1.29
IV RCC (1:2:4) FOR PILES
1 20 mm Stone Aggregate Units 8.69
2 Cement Bags 177.03
3 Sand Units 4.34
V RUBBLE STONE (6''-9'') FOR RR FOUNDATION
1 Rubble Stone Units 20.00
2 Cement Bags 77.00
3 Sand Units 5.00
VI OTHER CONSUMABLES
1 Wooden Posts (Survee)-10' Long Nr 50.00
2 Paint (White or Yellow) Small Box 2.00
3 Small Brush Nr 4.00
4 Cover Blocks (2'' & 1.5'')-60mmX60mm Nr 300.00

TO BE PROCURED
1 Clay Bricks Tractor Load 1
2 12 mm Ø Bar Full Legths 90
3 10 mm Ø Bar Full Legths 90
4 8 mm Ø bar Full Legths 102
5 Binding Wire Kg 10
6 40 mm Stone Aggregate Units 2.57
7 20 mm Stone Aggregate Units 8.69
8 Sand Units 10.63
9 Cement Bags 283.24
10 Rubble Stone Units 20
TRY
REQUIREMENT
LEVEL
WEIGHT(KG)

927
643
467

ROUNDED OFF TO
1
92
92
104
10
3
9
11
300
20
Calculation of material and labour requirement for rubble masonry incement mortar 1:5
in foundation
Random Rubble Masonry in Cement mortar 1:5 in foundation (1Cub=1Unit=100CFT)
Description Unit Qty.
6''-9'' Rubble Cu=Unit 1.3
Cement (50 Kg Bags) Nr 5
Sand Cu=Unit 0.3
Water Gal 100
Mason Day 1
Unskilled Labourer Day 3

in MM in Mtr
Width of Rubble foundation 460 0.46
Depth of Rubble foundation
Below NGL 457 0.46
Upto Plinth bottom above NGL 457 0.46
Total 0.91
Alround Length of Rubble foundation 101.5
Length-2 sides 69.18
Bredth-2 Sides 36.88
Column Size along length 0.19
Column Size along breadth 0.19
No. of columns along length 18
No. of columns along bredth 6
Effective Length 65.76
Effective Breadth 35.74
Total 101.5
VOLUME OF RUBBLE WORK (CUM) 42.69 43
VOLUME OF RUBBLE WORK (UNITS) 15.19

MATERIAL REQUIREMENT ROUNDED OFF TO


1. Rubble Stone (Units) 19.75 20
2. Cement (Bags) 75.97 77
3. Sand 4.56
Add wastage 5% 0.23
Total Sand requirement (Units) 4.79 5
LABOUR FOR THE WORK
Mason (Man Days) 15.19 16
Unskilled labourer (Man Days) 45.58 46

Вам также может понравиться