Академический Документы
Профессиональный Документы
Культура Документы
Project:
4 laning of KM 92+000 to KM 138+000 of Lucknow – Ayodhya Section
of NH-28 in Uttar Pradesh, India
Client:
NATIONAL HIGHWAYS AUTHORITY OF INDIA
HCC N 39 17 03
Revision No.: 0
Date of Revision: 24 April 2006
____________________________________________________________________________________________
I. History of Revisions
Chapter/clause
Revision
Revision date no. & text Reason for revision
No.
affected
0 24 April 2006 First Issue
1.0 PURPOSE:
The purpose of this Segment Quality Plan for Construction of Cross Drainage Works is
to provide details of the Construction Methodology, Quality Assurance & Control
System/Procedures adopted by H.C.C. and its Sub-contractor’s/Supplier’s in
execution of Cross Drainage Works i.e., Pipe Culverts at various locations/stretches as
shown in the Construction Drawings.
2.0 SCOPE:
The Scope of this Segmental Quality Plan covers the following activities:
(i) Cutting, removing and disposing of all materials such as trees, bushes,
shrubs, stumps, roots, grass, weeds, top organic soil etc., which in opinion of
the Engineer are unsuitable for incorporation in the works, from the area
within Toe line containing road embankment drains, cross drainage
structures and such other areas as may be specified on the drawing or by the
Engineer.
3.0 DEFINITIONS :
The words like Contract, Contractor, Engineer (Synonymous to Engineer’s
representative), Drawing, Employer, Government, Works, Worksite used in this
Quality Plan shall be considered to have the meaning as understood from the
definitions of these terms given in the General conditions of the contract. For other
general definitions pertaining to HCC Quality Management System, refer Project
Quality Plan, HCC P 39 17 01.
The following abbreviations shall have the meaning as set forth below:
5.0 RESPONSIBILITIES:
Responsible personnel for execution of the Segment of Cross Drainage Works are as per
the following Responsibilities Matrix and also as per the Project Organization Chart:
6.0 PROCEDURE :
The Hume pipes shall be laid, as per drawing, where two or more pipes shall be
laid adjacent to each other; they shall be separated by distance as mentioned in the
drawing. The laying of pipe shall be carried out as per specification laid in
M.O.R.T.H clause 2904. The newly laid pipe shall be placed in such a way that these
will be joining gap of 13mm to 18mm.The our side and inside jointing gap shall be
filled with cement mortar in 1:2 ratio. Care shall be taken to fill all voids of the joints
from inside and outside and surplus mortar shall be removed. After jointing of pipe
as per M.O.R.T.H Clause 2906, the pipe shall be in a cradle constructed of concrete in
M 15 conforming to section 1700. The shape and dimensions of the cradle shall be as
per the drawing.
All the Inspection and Testing requirements for various activities in the present
segment shall be carried out as per relevant M.O.R.T.H Specifications & Contract
Technical Specifications, other Codes/Standards as mentioned in References Chapter
are identified in the form of Inspection and Test Plans.
These Inspection and Test Plans shall consists of type of Inspection and name of the
Test to be conducted for Product Realization, frequency of testing, acceptance criteria
and category of Inspection as mentioned in the legend of ITP.
Inspection and Test Plans shall be revised whenever there is any change in
methodology and specifications etc. Various Field and Laboratory Test Formats referred
in Inspection and Test Plans shall be maintained as per the frequency mentioned in
respective ITP’s for various activities.
Any Non-Conformity observed during Field Inspection and also during Testing of
Materials the same Non-Conformity shall be recorded in the specified Format and
necessary Corrective/Preventive actions shall be initiated to prevent such things in
future.
The following Inspection and Test Plans for Flexible Pavements have been prepared in
line with the requirement specified in M.O.R.T.H Specifications and relevant Contract
Technical Specifications:
General Document/Records:
The following general documents/records shall be kept maintained as per relevant
applicable HCC Quality Management Procedures:
Refer the following Documents for details about the Site Safety Management system:
Environmental Aspects and Impacts associated with various activities and sub-activities
involved in the present segment and their mitigation/control measures shall be
identified and necessary measures shall be initiated.
Refer the following Documents for details about the Site Environmental Management
Plan: