Академический Документы
Профессиональный Документы
Культура Документы
TENDER NO.
TITLE of TENDER:
The following terms indicated hereunder that shall be frequently used in this tender.
Definitions
TILTCL - which has called for the tender and will employ the Contractor
The firm, company, or successful tenderer who’s tender proposals
Contractor
have been accepted
Land, buildings, plant rooms and other places on, into or through where
Job Site
works would be executed under the contract
Shall include working Project Manager, Engineers, Shifts In-Charges,
Operators, Technicians, Electricians, Helpers, Safety Officers and
Workmen
personnel from sub-contractors as well as out-sourced specialists and
vendors
Shall mean activities that shall be conducted at site, including but not
Works limited to all plant, equipment, facilities, installations or parts thereof
covered under the Contract according to the intent of the project.
Planned Preventive, Corrective, Predictive Maintenance, routine
Maintenance activities on fixed periods and hours of operation basis, material
Routine replacement prepared and based on the manufacturers
recommendations and as directed by TILTCL.
Tenderer/Bidder Interested firm/company/group who purchased the tender
1.0 Foreword
Gujarat International Finance Tec-City Company Limited” (“TILTCL”) is developing a Global
Financial Services Hub, being a Central Finance and Business District, known as TILT City,
on around 886 Acres of land situated and lying at Taluka and District Gandhinagar, Gujarat.
TILT City area comprises of Special Economic Zone (SEZ), and Domestic Tariff Area (DTA).
The DTA area of TILT City is being developed by TILTCL and SEZ area of TILT City is being
developed by TILT SEZ Limited (a wholly owned subsidiary of TILTCL Limited).
Gujarat International Finance Tec-City Company Limited (TILT CL) invites EOI from reputed
Agency for Design, Supply, Construction, Erection, Testing, Commissioning for
Augmentation of existing DCS Plant SCADA from GE SIMPLICITY to Siemens PCS 7
SCADA In TILT CITY.
The air conditioning of City buildings is being catered by State-of-the-Art District cooling
system (DCS). District cooling is a system in which chilled water is generated at a centrally
located plant by means of Chillers and distributed to various buildings and taken back to the
District cooling plant via pipelines. This system consists of 3 major parts as under:
“Distribution” - Supply and return Piping network from DCS plant up to individual
Buildings.
“Energy Transfer Station (ETS)” - Interface between DCS Chilled water network and
Developer’s Chilled water system located inside the Building.
2.0 Objective
TILTCL ( DCS ) is desirous of accomplishing its mission of reliably, responsively and cost
effectively Operate and Maintain the DCS system by employing outsourced service
contractor complete with work trades and other special service personnel to handle the
operation, troubleshooting, repair and maintenance services of all electrical, mechanical, air
conditioning, fire system and safety at DCS plant system along with associated network
referred to as (DCS System) including all equipment, PLC & controls and SCADA etc.,
installed in DCS and respective building terminals.
At present, DCP-1 has 10000 TR capacity chillers (5000 TR x 2) and 10000 TR-Hr.
TES Tank. The plant has 4 Nos of 2500 TR electrically driven solidstate starter
centrifugal water-cooled chillers arranged in two sets of series counter flow
configuration and working on R-134a eco-friendly refrigerant. The chillers work on 11
kV power.
Chilled water secondary and primary pumps, condenser pumps, cooling towers and
associated equipment all controlled by SCADA system.
Make up water is sourced from STP treated plant to the makeup water tanks.
Fire Pump house consisting of jockey pump, Electrical driven pump & Diesel operated
pump.
The state-of-the-art PLC based SCADA system has been provided for operation &
control and metering.
Main header & branch chilled water piping network is installed in underground utility
tunnel up to individual building’s Energy Transfer stations with Control system.
DCS system consist of DCS Plant machines and equipment located at DCS plant
room and associated Chilled Water supply network & Controls and equipment located
at the developer’s building where the Chilled Water circuit terminates and shall be the
boundary limit for the DCS system.
Generally, the Plate Heat Exchanger (PHE) at the buildings are supplied, installed &
maintained by the developers except for TILT CL buildings. Point of Supply (POS)
and Point of Return (POR) for DCS Chilled water for developer’s PHEs is 1 meter
after / before main tunnel at building level.
4.0 General Scope of Work and Area covered under the scope
SCADA SPECIFICATIONS
CONTENTS
Sr. Description
No.
4.1 SCOPE
Scope of work also includes supply, installation testing and commissioning of required
hardware and accessories for integration of new and existing electrical equipment’s as per
system architecture diagram. Contractor has to prepare and submit bill of material and
installation schedule for approval. All required hardware and accessories must be
incorporated in bill of material of SCADA schedule for fully commissioning of SCADA
system as per specification and requirements. Any cost implication will not be accepted for
fully commissioning of SCADA system as per requirement specified in specification,
drawings and bill of quantities. Scope of work also includes preparation of SCADA screens,
Operator control screen and engineering screen as per PCS-7.1 for existing equipment’s,
IEDs, function blocks and new proposed equipment’s. Scope of work majorly includes but
not limited to following items:
5. Supply, Installation, Testing & Commissioning of SICLOCK GPS 1000 along with
SICLOCK GPS 1000 PS including with integration with all IEDs, relays, servers,
CPUs, I&C equipment’s clients, etc.
10. Scope of work also includes supply, installation, testing and commissioning of
required single mode 6 Core armored FO (Fiber Optic), cat6 Ethernet, shielded
Modbus cables, etc. along with their joints and terminations with required accessories
for fully commissioning of system as per TILT approved system architecture.
11. Supply, Installation, testing & Commissioning of Fiber optic to Ethernet convertor with
required accessories required as per TILT approved system architecture including all
complete works.
12. It shall enable local station control via a PC by means of human machine interface
(HMI) and control software package, which shall contain an extensive range of
supervisory control and data acquisition (SCADA) functions.
13. It shall include communication gateway, intelligent electronic devices (IED) for bay
control and inter IED communication infrastructure. An architecture drawing for SAS
is enclosed.
4.3.1 Select-before-execute
For security reasons the command is always to be given in two stages: selection of the
object and command for operation under all mode of operation except emergency
operation. Final execution shall take place only when selection and command are
actuated.
4.3.4 Self-supervision
Continuous self-supervision function with self-diagnostic feature shall be included.
4.3.5 User configuration
The monitoring, controlling and configuration of all input and output logical signals and
binary inputs and relay outputs for all built-in functions and signals shall be possible
both locally and remotely. It shall also be possible to interconnect and derive input and
output signals, logic functions, using built-In functions, complex voltage and currents,
additional logics (AND-gates, OR gates and timers). (Multi activation of these
additional functions should be possible).
4.3.6.2 Measurements
The analogue values acquired/calculated in bay control/protection unit shall be
displayed locally on the station HMI and in the control center. The abnormal values
must be discarded. The analogue values shall be updated every 1 seconds. Threshold
limit values shall be selectable for alarm indications.
4.3.9 Reports
The reports shall provide time-related follow-ups of measured and calculated values.
The data displayed shall comprise:
Trend reports:
Day (mean, peak)
Month (mean, peak)
Semi-annual (mean, peak)
Year (mean, peak)
4.3.13 Gateway
4.3.13.1 Communication Protocol
The communication protocol for gateway to control centre must be open protocol and
shall have IEC 61850 for all levels of communication for sub-station automation such
as Bay to station HMI, gateway to remote station etc.
For all requirements listed above, the necessary cables, connectors, external
software media, manuals or any other hardware and software must be bundled and
included in the Supply.
Vendors should submit technical document showing the compliance to all the
technical specifications mentioned above.
4.3.14.3 Ethernet Cable
Category 6 Unshielded Twisted Pair 100 cable shall be compliant with EIA/TIA 568-
C.2
Transmission performance specifications:
Provide Stringent Crosstalk/Noise Suppression
Supporting Data Rates to 1 Gb/second
Conductors: Ultra flexible, finely stranded, tinned copper
Shielding: Ultra flexible, braided shields, with 90% nominal coverage
Minimum Bend Radius:
- 6x cable height for intermediate flex
- 10x cable height for continuous flex
Flex Life: 10,000,000 cycles nominal
Outer Jacket Durometer Rating: 65 (Shore A)
Environmental
Temperature Rating: -65°C to +165°C
Moisture Rating: Submersible, Salt Water Resistant
Clean Room Rating: Class 1, Zero Particulates
Extreme Environments: Sunlight, UV Light, Alcohol, Chemical and Oil Resistant
Outer Jacket Dielectric Strength: 450 volts/mil (17.7 kv/mm)
4.3.21 Spares
4.3.21.1 Availability Spares:
The bidder is required to list the spares, which may be required for ensuring the
guaranteed availability during the guaranteed availability period. Spares like Fuse, TB,
MCB, Ethernet connector, Patch cord, SC/ST connector etc. shall be maintained at
site.