Академический Документы
Профессиональный Документы
Культура Документы
-ooOoo-
This technical specification is applicable to stainless steel piping that forms part of the “RO Plant”.
Stainless steel piping includes austenitic, duplex and super duplex grades of material as shown in the
following table:
This specification covers the basis of fabrication, non-destructive examination, installation, flushing, pressure
testing, chemical cleaning and coding of stainless steel piping for the “RO Plant”.
This Specification does not cover:
∙ Building services piping
∙ Thermoplastic or GRP piping
∙ Carbon steel or ductile iron piping
∙ Instrument piping or tubing downstream of the first piping block (root) valve
The philosophy is such that specialist organisations will provide Quality Plan, ITP (Inspection Test Plan) and
work method statements based upon the requirements of the EPC contract, this technical specification and the
referenced documents.
2. DEFINITIONS
4. DESIGN
The subcontractor shall be responsible to execute the shop and spool drawings, based on the isometric provided
by OTV and the site investigations done by the Subcontractor.
Any modification on OTV isometrics shall be submitted to OTV for approval.
The Subcontractor shall ensure that the welding of stainless steel, and particularly the welding on super
duplex and duplex shall withstand for a minimum life of 30 (250,000 hours) years, taking account of industry
standards for operation and maintenance.
The purpose of this specification is also to set the minimum requirement for welding in order to ensure “the
welding durability”.
During operation, the main problematic on welding of superduplex and duplex are:
Pitting corrosion
Crevice corrosion
Pictures showing corrosion welding’s problem for superduplex welding during plant operation:
The area most susceptible to corrosion pitting is the welded joints. The welded joints are susceptible to pitting
attacks. However if these welds are subject to pickling and passivation the resistance to pitting increases All
piping and welds will be subject to internal acid pickling and passivation which is carried out to clean and remove
any chromium depleted surfaces (due to welding) allowing a strong chromium rich oxide bond to be formed
which is highly resistance to corrosion attack providing oxygen is maintained to the surfaces. External protection
of the welds will be done by applying a pickling and passivation paste or similar.
Provided the welds are pickled and passivated they will have a pitting resistance for a continuous exposure of
seawater. As mentioned all shop and field welds will be subject to an acid pickling and passivation procedure on
site. Once this procedure is complete examination of typical (accessible) welds will be done to ensure protection
of the welds has been achieved. It is essential the system is properly protected before going into the
commissioning and operation phases.
It is in the area of pipe and connection welds, including the heat affected zones, that is considered the most
susceptible to crevice corrosion (due to undercutting of the weld, inclusions, etc.) during the welding process
which is the starting point for corrosion. Small crevices present a bigger risk to corrosion than large crevices due
to the lack of movement of seawater in the small crevice. It is essential that correct welding and qualification
procedures are adopted and strict quality control of welders and welds are in place for both shop and site welds.
Site welds are more difficult to control due to welding in situ and these are being kept to a minimum. Provided
proper precautions are in place “in situ” site welding will achieve good results to the same standard as shop
welds. The Subcontractor has to produce a tight stainless steel fabrication, installation and welding specification
which will provide a solid base for producing quality work which is one of the keys in minimizing corrosion risk.
The welding procedures are applied to both in situ and off site welding.
It is clear that without due diligence in the welding process corrosion will occur irrespective of the selection of
material. This is amply demonstrated in a major desalination plant overseas where super duplex piping material
has been attacked by crevice corrosion of the welds and is a major ongoing problem. Whilst no definitive reason
has been provided for this corrosion it does appear that quality control of the welds may have been a major
issue. Welding defects appear to have been the most significant issue in the poor performance of the HP super
duplex system. Pitting of the pipe barrels is also a problem in this overseas plant which would tend to indicate
problematic quality control during fabrication and/or erection. Whether acid pickling and passivation has been
done (or to the correct standard) is unknown as this question remains unanswered.
The risk of systemic corrosion pitting of the welds resulting in systemic failures requiring repair or replacement of
piping is considered a low risk subject to the precautions being undertaken as outlined above.
6. ENVIRONMENTAL, HEALTH AND SAFETY PLAN (EHS)
All Subcontractors shall comply with the EHS plan. The Subcontractors shall comply with all statutory and
legislative requirements for off site work. A specific plan EHS shall be submitted for approval to OTV prior start of
work (including work on site and work out of site).
The Envrironmental, Health and Safety Plan shall also include the requirements related to:
Electrical Equipment, Pressurised Gases, Personnel Protection, Fire, Fume, Arc Radiation,…
Prior to commence the work, the quality plan with the Inspection and Test Plan shall be submitted to OTV for
approval.
For all the differents type of work and at the different stage, a detailed procedure, method statement and process
verbal shall be issued, submitted to OTV’s representative for approval.
The third party certified ITP, WPS and WPQ shall be submitted by the Subcontractor to OTV for approval.
After approval of the documents by OTV, the Subcontractor shall arrange the independent third party to certify:
OTV’s representative or the third party has the right to disqualify any welder whose performance is not meeting
the required standard, codes and approved procedure.
The Subcontractor shall not start work before having fulfilled these conditions.
9. MATERIALS
9.1. Marking of Materials
Materials shall be, colour coded, stencilled or bar coded to differentiate between austenitic, duplex and super
duplex grades of stainless steel. All coding shall be maintained until a spool is complete and tagged.
Colours shall be painted on in one continual stripe approx 20 mm thick:
Green 316L (Non magnetic)
Blue Duplex (Magnetic)
Yellow Super Duplex (Magnetic)
If such coding is missing or unclear the materials shall be quarantined until identified (via testing) and marked
prior to being used for the permanent works.
Paint coatings or labels shall not be applied to the internal surfaces of pipes or to the external surfaces where
they would subsequently be exposed to permanent immersion in drinking, sea
or brine waters.
In the event that the material cannot be identified it shall not be used for stainless piping service. All short lengths
shall be segregated and coded to ensure that materials are not mixed.
9.3. Consumables
Consumables shall be compatible with the pipe. All consumables shall be preserved in accordance with the
manufacturer’s requirements prior to their use. Opened packs of electrodes and flux should be preserved
according to the manufacturer’s requirements.
9.4. Shield Gases
Only Gas mixtures specified in this specification and that have been approved satisfactory as a result of Welding
procedure Qualifications shall be used.
All shielding gases shall be applied with certification stating purity limits and compliance with permitted
tolerances on composition limits.
Shielding gases shall be kept vertically in containers properly marked and colour coded.
Prior to commence the work, the Subcontractor shall submit a list of the tools which will serve during the
qualifications, production, installation, flushing, pickling, testing for the control, inspection and examination. All
the cost related to these tools shall be born by the Subcontractor.
The tools shall be first quality, calibrated and with certification.
10.FABRICATION
10.1. Iron Contamination
Stainless steel and carbon steel materials shall be stored separately and fabricated separately in such a way that
the stainless steel cannot be contaminated by carbon steel dust or airborne particles.
Cutting shall be performed with mechanical shop tools, plasma arc, laser, or water jet. Carbon arc or iron powder
cutting shall not be used on stainless steel. Edges shall be ground to a smooth, uniform surface by removing
approx 0.5 mm of metal.
Hand wire brushes made of stainless steel could be used. Rotary wire brushing wheels are not permitted.
Grinding and cutting wheels shall be iron free. Hand tools, such as grinders, wire brushes, files used for
fabrication on stainless steel shall be marked for easy identification to avoid contamination.
Carbon steel materials shall not come into contact with stainless steel materials i.e. fabrication aids such as pipe
clamps, stands, benches etc shall be covered to avoid contamination from carbon steel surfaces.
Procedures shall be in place to ensure that stainless steel fabrications cannot be contaminated by windblown or
airborne iron particles from adjacent areas where fabrication, cleaning or blasting of carbon steel is taking place.
Prior start of work, survey shall be done on site by the Subcontractor in order to check and verify if any
discrepancies between the drawing and the site conditions. In case of discrepancies, the Subcontractor shall
submit it to OTV, advise the different adaptation to be done on the isometric drawing.
d>DN500 All ±5 ±1
d = nominal diameter
DN300≤d≤DN500 ±5 ±5 ±5 ±3 ±1 ± 1.5 ±3
d>DN500 ±5 ±5 ±5 ±3 ±1 ± 1.5 ±3
d = nominal diameter
For spools with field welds, if no trim allowance is stated on the isometric drawings, the overall length shall be
approximately 100 mm over length. Bolt holes on flanges shall straddle the horizontal or vertical lines or plant
north/south centre lines when orientation is not given on drawings.
In case of more restrictive tolerance, because specified on the isometric drawing or specified by equipment
supplier, the most restrictive tolerance shall be applied.
10.9. Cleaning
All stainless steel accessible welds shall be cleaned both internally or externally of scale, grease and oil, dirt,
flux, weld spatter, and other contaminates before undertaking the welding process.
Solvent cleaning shall be used to remove grease, oil and foreign matter. Chlorinated solvents shall not be used.
All cleaning solvents shall be approved by OTV. For example the use of “avesta cleaning paste 401” or
equivalent and “avesta pickling & passivating paste 601” or equivalent can be accepted.
11.WELDING
All welding shall be carried out in accordance with the applicable standard ASME IX, ASME B31.3.
All welding shall be done in a protected area, or protected by shelter upon approval of OTV.
11.3.1. General
This clause refers to materials defined in OTV piping materials.
These requirements apply to the welding of duplex and super duplex stainless steel.
The principles given in The Avesta Welding Manual Practice and Products for Stainless Steel Welding and
document “HOW TO WELD duplex stainless steel, or approved equivalent could be used in developing specific
processes in the welding of these materials.
Furthermore the requirements of the standard NORSOK M 601 for welding and inspection of piping superduplex
shall also be applied.
Only GTAW (TIG) is permitted for duplex and superduplex welding processes for the root and cold pass (1rst
and 2nd pass) but also for all filling passes
● A consistent joint fit up as detailed in the qualified WPS shall be used by the Subcontractor, All welded joints
shall be mechanically cleaned for a minimum 2” (50mm) each side of the weld area and degreased using an
approved cleaning fluid.
∙ For duplex Stainless Steel base material, mixture of UNS specifications is not permitted without approval
∙ All welding wire shall be cleaned using an approved cleaning fluid before commencing any welding
operation.
∙ The shielding and backing gas shall be composed of 2% Nitrogen 98% ARGON, and certificate shall be
submitted for approval prior start of the works. The backing flow rate shall be between 12 and 15 ltr/mn.,
∙ The backing gas composition shall be monitored at the joint line using a calibrated portable oxygen monitor
immediately prior to starting or re-starting welding. The purge must be checked before each pass and must be
within the range of maximum 0.5% oxygen. A method statement and daily log shall be done for this purpose by
the Subcontractor and submit for approval to OTV prior start of work.
∙ For all welds purge gas of the root shall be applied for the duration of the complete weld (all passes).
∙ A purge dam shall be inserted within pipe to minimise oxygen content within enclosure. For difficult
accessible areas, plastic flexible soluble disc shall be used or equivalent approved system.
∙ Interpass temperature shall be limited to maximum 100ºC unless a lower temperature is specified by the OEM
for their equipment (e.g. butt weld plug valve). The interpass temperatures shall be monitored using
appropriate tools and controlled by the Subcontractor, and the Subcontractor shall ensure that the maximum
temperature quoted qualified WPS is not exceeded.
∙ To maintain the required interpass temperature forced draught cooling could be employed.
∙ Acceptable Energy Input, travel speed are detailed in the following table for the use in welding procedure
specification:
This table is for information only and parameters should be adapted to welders ability to weld (Travel speed).
Wall Amps Volts Travel speed Min – Max Heat
Thickness p/mn Input KJ/mm
In order to control these value during production, a method statement and daily log shall be done for this
purpose by the Subcontractor and submit for approval to OTV prior start of work
∙ 2nd pass (cold pass) after the root must be of 80% lower heat input than the root pass.
∙ Sequence welding in opposite side to balance the forces applied to the parent metal. Length of run should not
exceed 150 mm.
∙ Post weld pickling & passivation should be performed in all accessible areas.
∙ Welding process or any change in welding process or the combination of welding process
∙ Change in nominal piping diameter (DN) from the following qualified grouping
∙ Repair Welds shall be qualified and tested as per normal butt Welds
∙ In addition to the above a multiple weld repair procedure (i.e. a repair on a repair) shall be qualified. The
repair procedures shall ensure that the heat affected zone from the original weld remains in place and is not
affected by the subsequent thermal cycles of the repair welds.
Filler metal Pitting Resistance Equivalent Number is defined as PREN= Cr(%) + 3,3 x Mo(%) +16 x N(%)
The filler metal PREN in contact with seawater and concentrate (brine) in minimum shall have a Pitting
Resistance Equivalent Number (PREN) shall be as follows:
Charpy V notch testing shall be performed for each welding procedure qualification in accordance with the
following:
∙ Charpy V Notch per ASTM A 370 (3 test specimens per set)
∙ Not applicable where the maximum permissible obtainable Charpy specimen has a width along the notch of
less than 2.5 mm
∙ Charpy samples shall be taken across the weld
∙ Notch placement shall be in the weld centre, FL, FL + 2 mm and FL + 5 mm (total 4 sets per qualification) and
normal to the pipe surface
∙ Absorbed energy shall be 48 J average and 36 J single value minimum per full size specimen
∙ Test temperature shall be -46ºC or MDMT (if lower)
A detailed procedure shall be submitted prior the testing to OTV for approval.
Root runs and the internal surfaces shall be purged to reduce oxygen to < 0.5% by volume before welding.
Grinding of the weld root at start/stop locations introduces air into the purge gas, welding shall only be continued
when the oxygen levels are <0.5% by volume As already mentioned, a purge dam could be used and inserted
within pipe to minimise oxygen content within enclosure, and to limit the purged volume and gas used. For
difficult accessible areas, plastic flexible soluble disc shall be used or equivalent approved system.
Fig 1- Heat tints (weld discolouration) on pickled duplex stainless steel tube butt welds
made with Formier purging gas (NH10) containing known oxygen levels.
11.4.1. General
This refers to materials defined in OTV piping Materials Specifications.
The principles given in The Avesta Welding Manual Practice and Products for Stainless Steel Welding, or
approved equivalent shall be used in developing specific processes in the welding of these materials.
Only GTAW (TIG) is permitted for austenitic stainless steel welding processes for the root and hot pass (1rst and
2nd pass)
For the Fill and capping passes, GTAW can be used, or SMAW.
● For duplex and superduplex, each welder shall be qualified for each essential variable and for the
following destructive (DT) and non destructive testing (NDT):
1) Visual examination
2) Corrosion testing,
3)Impact testing
4)Hardness testing
5) Ferrite level measurement
6) Metallographic examination
7) Dye penetrant tests
8) Radiographic tested (R.T)
● For austenitic stainless steel, each welder shall be qualified for each essential variable and for the
following destructive (DT) and non destructive testing (NDT):
1) Visual examination
2) Dye penetrant tests
3) Radiographic tested (R.T)
Each welder shall be requalified for this project. Copies of welder qualification certificates of the personnel
employed on the welding operations shall be approved first by a third party. And then the certificates shall be
submitted to the OTV’s Representative for approval.
OTV’s Representative will witness Welding Procedure Qualifications, Welder qualifications and be notified 1
week (or at least 72 hrs) prior to commencement of these qualifications.
All weld preparations, welding heat treatments, weld examination, welding equipment, filler wire, electrodes,
welding symbols, terms and definitions shall conform to the Standards.
11.7.1. Inspection
All NDE of welds shall be carried out by a certified authority in accordance with applicable standard ASME B31.3
Normal and Category M Fluid service and as a minimum the following non destructive examination shall be
undertaken:
11.7.2. Rejection
Any rejected welds shall be reported to the OTV’s Representative immediately, an authorised approved weld
repair procedure shall be used. The OTV’s Representative will nominate alternate welds to be examined. Each
weld shall be identified by welder’s name and number. Records of each welder shall be kept including but not
limited to the number of rejected welds, repairs and re examinations.
The severe cyclic service conditions shall be applied to the acceptance criteria of external undercut per ASME
B31.3 Table 341.3.2, for all butt welds.
11.7.3. Manufacturing Data Records
Full manufacturing data records (MDR) shall be provided including the following, but not limited to:
● Initial survey
● Pipework Material certification:
o Material supplied by subcontractor certifications (such as bolting, gasket,…)
o Welding Consumable Certifications,
o Others material certifications,
● Approved Inspection and Test Plans (ITPs)
● Approved Quality Plan
● Approved WPS / WPQR
● Approved Welder Qualifications
● List of tools for examination, inspection,…and technical documentation with certificate
● As Built Drawings (red line mark-ups and in autocad format) including survey dimensional control, spool
register
● Works method statement
● 100% Weld data records including (Weld n°/ position/ Pass n°/ Volts/Amps/Travel Speed/Energy Input)
● Traceability Records / Visual Inspection Reports
● Pressure Test Records
● Pressure test procedure including risk assessment
● NDT, NDE and Mechanical test Reports / Certification
● Passivation / Cleaning Reports
● Flushing record,
● Repair Reports,
● Delivery Dockets
● Miscellaneous Records & Reports
11.8. Cleaning
Surfaces shall be cleaned as required with the appropriate cleaning to ensure all contaminants are removed in
accordance with OTV’s specification.
Cleaner agreed with NORSOK 20%HNO3 + 5%HF @ 60oC for 5 mins and passivated over 24 hours in
atmosphere.
Socket welding on superduplex pipework is not permitted as water is trapped in the interstice area creating a
dead zone with severe corrosion.
For the socket welding on Stainless steel, in order to get proper socket weld fit-up (minimum of 1/16" before
welding as per ASME code), a “gap-a-let” shall be used and grade of material shall be same than the support.
The Subcontractor shall submit for approval one sample, technical documentation and certificate of the gap-a-let
prior to commencement work.
12.3. Marking
Each welder will stamp all his welds with his personal I.D. stamp and the batch number of the welding wires and
electrodes for the purpose of identification and tracing.
The isometric pipe drawing number shall mark on each completed pipe section.
The marking on the pipe section shall be done with an “electric – pencil” or any other marking system approved
by the OTV Quality Control Manager or a third party approved by OTV.
In all the case the pens or paint markers, these must be free of chlorides, sulphides, halides and Zinc.
Certificates of the pens or paint markers shall be submitted and approved by the OTV Quality Control Manager
or a third party approved by OTV.
The location of the marking and stamping will be in a distinct place on the item.
Material supplied by the OTV will be bar coded or similarly identified.
14.INSTALLATION OF PIPING
14.1. Iron Contamination
Refer to the requirements already specified.
14.2. Pipework Erection
All pipes shall be inspected before erection to ensure that they are free from loose scale and contamination. Pipe
spools shall be inspected for damage, contamination or other non-conformance to specification. Pipework shall
be erected on permanent supports designated for the line.
Temporary supports shall be kept to an absolute minimum, but to an extent sufficient to protect nozzles and
adjacent piping from excessive loads during the erection.
Pipework shall be fitted in place without springing or forcing to avoid undue stressing of the line or strain being
placed on a vessel or item of equipment, etc.
Where possible, shop fabricated spools shall be erected before field fabricated spools.
Prefabricated sections shall be fitted into position without damage or distortion.
Threaded pipe and fittings connections shall be avoided for seawater applications.
The instrumentation in line with the piping shall be installed by the Subcontractor according to manufacturer’s
OEM documentation, relevant standard and OTV’s specification.
For the instrumentation like the vortex and magnetic type flowmeter, the earthing shall be done by the
Subcontractor. A work method statement shall be submitted prior start of work.
For DN ≤ 300: The ground cable is in direct connection with the conductive flange coating and is secured by the flange
screws.
For DN ≥350: The ground cable connects directly to the metal transport bracket.
For instrumentation which have direct connection to the piping, the principle shall be as following (see figure): the
Subcontractor shall manufacture, install and test until the isolation valve. Connection of the instrumentation with
block valve shall be done by others.
14.9. Piping for air process
For piping for air process purpose, the earthing shall be done by the Subcontractor. A work method statement
shall be submitted prior start of work.
14.12. Bolting
Fasteners shall be in accordance with the requirements in the piping and valve material Specifications and Data
Sheets.
All stainless steel fasteners shall be coated with an anti seize compound such as Loctite Nickel 771 or approved
equivalent.
Fasteners that are cadmium plated and coated with Xylan shall not be coated with lubricant.
Where the coating is damaged during installation they shall be replaced.
Manually pulled flange bolts and stud bolts shall extend fully through their nuts by at least one thread, but not by
more than 15 mm.
All flanged stud bolts shall be progressively tightened to equalise bolt pressure on the gasket. A detailed
procedure shall be developed prior to flange assembly, which will follow the different step:
a) The required torque value shall be calculated by the subcontractor and submitted to OTV for approval
b) Always use a torque wrench or other controlled-tensioning device (recently calibrated)
c) Tighten nuts loosely by hand in the first instance, according to the cross bolt tightening pattern, then
hand-tighten evenly
d) Using a torque wrench, torque to a maximum of 30% of the full torque first time around, according to
the cross bolt tightening pattern. Check that the flange is bearing uniformly on the gasket
e) Torque to a maximum of 60% of the full torque, according to the cross bolt tightening pattern
f) Torque to the full torque, according to the cross bolt tightening pattern
e) Final pass at full torque, in a clockwise direction on adjacent fasteners.
The tightening operation shall be always done according to the cross bolt tightening pattern.
After the five basic torquing passes are completed, it may be beneficial to repeat pass e) until no further rotation
of the nut is observed. The final tightening must be uniform, with each bolt pulling the same load
The torque necessary shall be confirmed for each bolt size and each pipe specification with threads coated as
specified using a load cell for test work. All torque wrenches shall be calibrated.
Nuts and bolts shall have their grade marks visible after installation. Stud bolts cut from long lengths of studding
shall have material grade stamped on end of each cut.
Coated fasteners shall not be cut but replaced with a fastener of the correct length.
16.PRESSURE TESTS
16.1. General
The design and test pressure and design standard is defined in OTV’s piping material specifications.
Piping shall be subject to a hydrostatic test.
The Subcontractor will perform two pressure tests on each piping section:
▪ First Pressure Test: Will be performed at the end of the prefabrication stage, and after successful all
N.D.T. tests of the welded pipe section.
▪ Second Pressure Test & Leak Test: Will be performed on site after completion of assembly of the
complete piping system, and after successful N.D.T tests for field welds.
The Subcontractor shall do a risk assessment and specific procedure for the pressure test.
Prior to the pressure test on site, a pneumatic test with Azote shall be done at maximum 0,1 bar in order to
detect major leak.
Subcontractor shall develop specific procedures for welded pipes pressure test. The test pressure shall be done
a different step of pressure (20%, 50%, 100% of test pressure and decrease of the pressure at 20% for
example).
Piping designed to ASME B31.3 shall be subject to a hydrostatic leak test in accordance with Clause 345.4,
except as modified in the following sections.
The test pressure shall, unless otherwise specified, be in accordance with the piping specification.
Testing shall not take place with system temperatures of 4°C or less or where the ambient temperature during
test falls by 5°C or more, nor during rain or fog unless under suitable cover.
The following are excluded from pressure tests:
∙ All small bore instrument control piping downstream of the first piping block valve.
∙ Open drains and vents to atmosphere (leak test only)
∙ Closure welds as defined in ASME B31.3 Clause 345.2
16.9. Retest
Should a piping section fail a pressure test, the section shall be retested after rectification of the defect. Details of
failure and rectification method shall be recorded
17.PAINTING OF PIPING
The Subcontractor shall refer to the painting specification. Austenitic stainless steel pipework shall be outside
painted as per the specification.
During start-up of the plant and commissioning, the Subcontractor shall make available on site skilled personal to
assist and correct immediately any failure and leakage which will occur on the system supplied and installed by
the Subcontractor.
20.SPARE-PARTS
The Subcontractor shall supply the list of the quantity, type and diameter of gasket / bolts used for the installation
of piping. The Subcontractor shall supply as a spare parts:
- 5% of gaskets (minimum 4 gaskets/ diameter and Class),
- 1 set of bolts for each diameter,
APPENDIX 1 – MATERIAL HANDLING AND STORAGE
1. All SDSS materials will be stored in clean dry areas apart from other materials and covered to keep
from contamination from other ferrous and non-ferrous alloys.
2. Storage will be carried out within racking either unpainted or protected carbon steel. Painted racking
will cause welding problems however small the contact is and carbon steel unprotected racking will
cause contamination problems.
3. Fittings and Flanges supplied on pallets or in boxes will be stored within the racking system and
remain covered until called for usage.
4. Forklift trucks if used must have the Forks suitably protected to prevent Carbon Steel contact with
the SDSS materials.
5. Pipe Clamps ( Camlocks ) must not be used as the teeth are intended to bite into the surface for grip
but with the hard surface of SDSS this will not be possible and could result in an accident.
6. Cutting of pipes and fittings will be carried out cold using only new and clean good quality tooling
specifically and solely for SDSS use. Machine Cutting with use of lubricant is acceptable but the
pipes and fittings require to be solvent cleaned inside and outside afterwards to remove any traces
of lubricant.
7. Cutting by Plasma is acceptable providing the local HAZ area is removed by grinding. ( 0.5mm )
8. Grinding will be carried out by new discs solely for SDSS use avoiding scorch and burn marks. All
Grinding shall only be carried out in areas isolated from the SDSS material.
9. Flapper Wheels, Files and Wire Brushes must only be for SDSS use only.
10. Power Wire tooling shall be avoided in particular at inner bores as smear contamination of the
surfaces can occur.
11. Material Transfer shall be carried out pre cut and use shall be made of vibro etch engravers.
12. Temporary attachments of any kind will not be allowed on the material.
13. TIG wires shall be wiped clean with acetone or similar prior to use.
14. Work Benches, Vices, Positioner Chuck Jaws etc must all be protected. These areas shall be vacuum
cleaned at regular intervals to remove grinding dust / particles.
16. Markings of material shall be by use of paint markers or pens free of Chloride and Sulphides and
suitable for S.S. use.
18. Work Areas shall be specific for SDSS usage free from potential contamination from other materials
and must be covered and wind free. Continual Good House Keeping Operations shall be carried out
to maintain this Quarantine Area.