VACEADO DE MUROS PANTALLA

Proveedor
ESTADO ACTUAL
Cable Pretens.
INSPECCION DE
CALIDAD
Pedido ocasional
Production Control
Planta de Acero

Proveedor Mat.
Elecst. /Sanit. Pre Mix Plant Programación Semanal

Instalación Cable Instalación Instalación Control Encofrado Control Vaceado Desencofrado Tensión
Postensado Armadura Elec./San. de cables
\O/ 1 \O/ 5 \O/ 1 \O/ 5 \O/ 3
218m2
\O/ 3 \O/ 3 52m2 \O/ 6 218m2 76m2 68m2 65m2 83m2 \O/ 3
4m2

R= 0.5m2/HH R= 2m2/HH R= 6m2/HH R= 80m2/HH R= 12m2/HH R= 80m2/HH R=24m2/HH R= 24m2/HH R= 3m2/HH


(8.75kg/HH) (35kg/HH)
ILC= 75% ILC= 95%
ILC= 80% ILC= 87% ILC= 83%
PTE=75% PTE=90%
PTE=71% PTE=70% PTE=66%
PTP= 15% PTP= 10%
PTP= 8% PTP= 11% PTP= 13%
PM=3% PH=1%
PC=2% PF=5% PMa=2% DV=0% PE= 4%
DV=0% DV=0% DV=0%

CUMPLIMIENTO
PROGRAMA 70%
69% 80% 80% 90%

25% 45%
10% 10% 10%
6% 55% 10% 10%
1 min 3 min 10 min 0 min 4min 3 min 0 min 1 min

3 min 15 min 8min 2min 12 min 2min 11 min 4 min 3 min

Tiempo ciclo total = 82min/m2


Atrasado R= Rendimiento PMa= Pérdida de materiales Tiempo valor agregado= 22min/m2 (26%)
ILC= Índice de labor contributoria PM = Pérdida de madera
En programa PTE= Porcentaje trabajo efectivo PH = Pérdida de Hormigón
PTP= Porcentaje de preparación PE = Pérdida de energía
Adelantado PC= Pérdida de Cable DV= Desvío de vertedero
PF = Pérdida de fierro
VACEADO DE MUROS PANTALLA
Proveedor
ESTADO FUTURO
Cable Pretens.
INSPECCION DE
CALIDAD
Pedido 15 días
Production Control
Planta de Acero

Planificación y control
Proveedor Mat.
Elecst. /Sanit. Pre Mix Plant Programación Semanal
RUTA RUTA
DIARIA 15 DIAS LAST
PLANNER

RUTA RECEPCION
7 DIAS RUTA FIERRO
1 DIAS

Instalación Cable Instalación Instalación Control Encofrado Control Vaceado Desencofrado Tensión
Postensado PEPS Armadura PEPS Elec./San. PEPS PEPS PEPS PEPS PEPS PEPS de cables
\O/ 1 \O/ 5 \O/ 1 \O/ 5 \O/ 3
\O/ 3 \O/ 6 \O/ 8 \O/ 3

PEPS
R= 1m2/HH R= 2m2/HH R= 6m2/HH R= 80m2/HH R= 15m2/HH R= 80m2/HH R=24m2/HH R= 24m2/HH R= 3m2/HH
ET ET
(8.75kg/HH) TQM
(35kg/HH) TQM ET ET ET
ILC= 90% TQM ILC= 95% TQM CTC

ILC= 95% ILC= 95% ILC= 90%


PTE=90% PTE=90%
PTE=90% PTE=95% PTE=90%
PTP= 10% PTP= 10%
PTP= 4% PTP= 5% PTP= 10%
PM=1% PH=1%
PC=1% PF=2% PMa=1% DV=100% PE= 4%
DV=100% DV=100% DV=100% CONTROL PEDIDO
REUSO H
REUTILIZACION REUTILIZACION RECICLAJE CONTROL BOMBEO
MATERIALES MATERIALES
CUMPLIMIENTO RECICLAJE RECICLAJE
PROGRAMA 70%
69% 80% 80% 95%

6% 30%
5% 5% 5%
25% 0% 15% 15%
1 min 3 min 10 min 0 min 4min 3 min 0 min 1 min

3 min 15 min 8min 2min 12 min 2min 11 min 4 min 3 min

Tiempo ciclo total = 82min/m2


Atrasado R= Rendimiento PMa= Pérdida de materiales Tiempo valor agregado= 22min/m2 (26%)
ILC= Índice de labor contributoria PM = Pérdida de madera
En programa PTE= Porcentaje trabajo efectivo PH = Pérdida de Hormigón
PTP= Porcentaje de preparación PE = Pérdida de energía
Adelantado PC= Pérdida de Cable DV= Desvío de vertedero
PF = Pérdida de fierro