REPSOL / TALISMAN SAKAKEMANG B.V.

DAILY REPORT
Date: Thursday, September 3rd 2020 Project Name:
Daily Report No. 015 Topography Survey of Land Valuation and Trees Counting Program –
New Flowline Right of Way

Progress Perimeter Lines Update

Work Description :
1. Measurement Detail of Situation using Total Station.
2. Measurement of ROW Perimeter & Landowner Marking (Margo Mulyo Village)
3. Maesurement of Surface Elevation using Automatic Leveling (Stoped by unsettled activity permit)
4. Coordination with QC Repsol.

WEATHER :
No. TIME REMARK
1 Morning (06.00-10.00 WIB) Clear
2 Noon (10.00-15.00 WIB) Low Intensity Rain
3 Afternoon (15.00-18.00 WIB) High Intensity Rain
4 Night (19.00-21.00 WIB) Low Intensity Rain

LIST OF MANPOWER :
No. NAME POSITION
1 Moch. Fattahillah Pradhana Kusumah Team Leader
2 Tommy Indrawan Project Manager
3 Budi Syihabudin Geodetic Engineer Expert
4 Didi Sugandi HSE Supervisor
5 Danny Widiatmoko Wahyudi Total Station Surveyor
6 Yana Supriatna Total Station Surveyor
7 Yudha Prasetyo GPS Geodetic Surveyor
8 Rivaldo Firman Durohman GPS Geodetic Surveyor
9 Dimas Pradana Putra GPS Geodetic Surveyor
10 Angga Kris Sahara Auto Level Supervisor
11 Simon Kevin Holomoan Total Station Assistant
12 Aighi Choerul Hidayat Total Station Assistant
13 Yoyo Sunaryo Driver
REPSOL / TALISMAN SAKAKEMANG B.V.

14 Sudrajat Driver
15 Jai Sujai B Antawi Helper

LIST OF EQUIPMENT :
No. DESCRIPTION VOLUME
1 Total Station 2 Unit
2 GPS Geodetic 3 Unit
3 Auto Level 1 Unit
4 Laptop 5 Unit
5 LV 2 Unit

GENERAL PROGRESS :
No. DESCRIPTION PROGRESS (%)
1 PREPARATION AND MOBILIZATION
 Personnel Allocation 100%
 Medical Check Up 100%
 Rapid Test (BDO) 100%
 Safety Induction 100%
 Total Station Calibration 100%
 GPS Geodetic Verification 100%
 Auto Level Calibration 100%
 Personnel and Equipment Mobilization to Location 100%
 Rapid Test (PLG) 100%

2 RECONNAISSANCE SURVEY 100%

3 GPS GEODETIC MEASUREMENT


 BM Construction and Installation 80%
 GPS Geodetic Measurement and Processing 70%

4 TOPOGRAPHIC SURVEY
 Total Station Surveying 39%
 Levelling Surveying 46%
 ROW Perimeter & Landowner Marking 20%
 Tree Counting Support 0%
 Data Processing 21%

5 REPORT
 Daily Report 34%
 Drawing (Situation map, long section and cross section) 0%
 Final Report 0%
REPSOL / TALISMAN SAKAKEMANG B.V.

Work Plan for Friday, 4 September 2020:


 Measurement Detail of Situation using Total Station.
 Measurement of ROW Perimeter & Landowner Marking (Margo Mulyo Village ).
 Maesurement of Surface Elevation using Automatic Leveling.

GALLERIES :
DOCUMENTATION