Вы находитесь на странице: 1из 21

YAY TAR SHAY - FIVE STORIES PROJECT

YANGON

REVISION - II

AUGUST 2020

ACMV & FIRE FIGHTING SYSTEM


DESIGN DRAWING

M & E DESIGN

PEARL ROYAL CO., LTD.


Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
Ph: 09-420084410, Email: pearlroyal@contractor.net
26. ALL AIR-CONDITONING SUPPLY AND RETURN AIR DUCT SHALL BE EXTERNALLY INSULATED WITH
ALL CONDENSATE DRAIN DISCHARGE TO THE SURFACE DRAIN SHALL BE PROVIDED WITH INSECT
GENERAL (FOR ALL DRAWINGS) GENERAL NOTES NON-COMBUSTIBLE FIBRE GLASS (OR EQUIVALENT) WITH RESIN BINDER OF MINIMUM DENSITY
43.
NETTING AT THE DISCHARGE POINT OF THE PIPE.
48 KG/CU.M. THE THICKNESS OF THE INSULATION SHALL BE 50 MM THK FOR SUPPLY/RETURN AIR
1. THE CONTRACTOR SHALL TAKE INTO ACCOUNT OF THE REQUIREMENTS IN THESE 1. ALL DIMENSIONS AS SHOWN ON THE PLANS ARE IN IP UNIT , UNLESS OTHERWISE STATED. 44.
DUCT IN FALSE CEILING WITH ROOF ABOVE AND 25 MM FOR SUPPLY/RETURN AIR DUCT IN FALSE ALL PIPES PENETRATE THROUGH BEAMS SHALL BE INSTALLED WITH PIPE SLEEVE.
GENERAL NOTES IN ADDITION TO THE SPECIFICATION, REGARDLESS OF WHETHER 2. ALL INSTALLATIONS CARRIED OUT BY THE CONTRACTORS SHALL COMPLY WITH THE CODES, CEILING WITH NO ROOF ABOVE. THE SUPPLY AIR DUCT SHALL BE INTERNALLY
45. ALL ELECTRICAL WORKS CARRIED-OUT FOR THE ACMV INSTALLATIONS MUST BE TESTED AND
THEY ARE INDICATED ON THE SPECIFICATION DRAWINGS OR EQUIPMENT SCHEDULE. REGULATIONS AND SPECIFICATIONS. INSULATED WITH ACCOUSTIC LINING FOR A MINIMUM DISTANCE OF 3M FOR FAN COIL UNIT AND 5 M
APPROVED BY THE AUTHORITIES BEFORE THE COMMENCEMENT OF COMMISSIONING OF THE
FOR AIR HANDLING UNIT OR AS SHOWN ON PLANS (WHICHEVER IS LONGER) CONNECTING THE UNIT.
2. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE SPECIFIED ON DRAWINGS. 3. ALL DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE SPECIFICATIONS. ALL WORKS ACMV INSTALLATION. ALL TEST REPORTS AND CERTIFICATES MUST BE SUBMITTED TO THE
3. CALLED FOR IN THE TECHNICAL SPECIFICATIONS EVEN THOUGH NOT SHOWN IN THE DRAWINGS 27. DUCTWORKS SUPPLIED FOR KITCHEN EXHAUST SYSTEM SHALL BE HEAVY GAUGE STEEL OF MINIMUM M & E ENGINEER.
DETAIL CONTROL SCHEMATIC SHOP DRAWINGS SHALL BE SUBMITTED FOR APPROVAL.
4. AIR TIGHT ACCESS DOOR C/W GASKETS, CHROME PLATED HINGES AND HANDLES FOR SHALL BE EXECUTED AND DEEM TO HAVE INCLUDED IN THE TENDER PRICE. 1.22 MM THICK OR AUTHORITIES APPROVED MATERIALS. 46. EACH FCU SHALL BE FITTED WITH THEIR OWN TERMINAL OUTSTATION. THE ROOM TEMPERATURE SENSOR,
SETPOINT ADJUSTER AND SPEED CONTROLLER SHALL BE CONNECTED TO THE FCU'S OUTSTATION.
EASY INSPECTION AND ACCESS SHALL BE PROVIDED TO ALL FIRE DAMPERS, NON- 4. LAYOUT/S AS SHOWN ON THE PLANS ARE SERVE AS A GUIDE ONLY AND SUBJECT TO SITE 28. ALL AIRCONDITIONING DUCTWORKS RUNNING OUTSIDE ANY NON-AIRCONDITIONED SPACE SHALL
CO-ORDINATIONS AND ADJUSTMENTS. ANY DISCREPANCIES FOUND ON SITE AND/OR IN THE BE EXTERNALLY INSULATED WITH MIN. 50 MM THICK INSULATION.
RETURN DAMPERS, VOLUME CONTROL DAMPERS AND WHERE NECESSARY.
DRAWINGS SHALL BE REPORTED TO THE M & E ENGINEER IMMEDIATELY BEFORE PROCEEDING
5. UNLESS OTHERWISE INDICATED ALL AIR DUCT BENDS OF CROSS-SECTIONAL AREA FURTHER. 29. ALL MECHANICAL VENTILATION DUCTWORKS RUN WITHIN THE AIR-CONDITIONED SPACE SHALL BE
GREATER THAN 0.25 sq.m. SHALL BE VANE ELBOWS. EXTERNALLY INSULATED WITH MINIMUM 25 MM THK INSULATION.
5. ALL SHOP-DRAWINGS INCLUDING EQUIPMENT TECHNICAL DATAS AND INSTALLATION DETAILS
6. SUBCONTRACTOR SHALL COORDINATE AND SUBMIT ALL ACCESS PANELS POSITIONS MUST BE SUBMITTED TO THE M & E ENGINEER FOR PRIOR APPROVAL BEFORE
30. WHERE NO SILENCER IS PROVIDED FOR MECHANICAL VENTILATION FANS, DUCTWORK CONNECTING
TO THE EMPLOYER FOR ACCEPTANCE. COMMENCEMENT OF WORKS.
TO THE FAN SHALL BE PROVIDED WITH INTERNAL ACCOUSTIC LINING FOR A MINIMUM DISTANCE
7. EMERGENCY STOP BUTTON SHALL BE PROVIDED FOR ALL AIR CONDITIONING AND 6. ALL CONCRETE PLINTHS, HACKING OF OPENING/S THROUGH BEAMS, FLOORS, WALLS ETC. OF 2M.
MECHANICAL VENTILATION EQUIPMENTS. SHALL BE SUBMITTED TO THE STRUCTURE ENGINEER FOR APPROVAL BEFORE COMMENCEMENT
31. ALL FLEXIBLE DUCTWORK INSTALLED SHALL BE COMPLETED WITH INSULATION. THE MAXIMUM
OF WORK. THESE PENETRATIONS SHALL BE FIRE-STOPPED TO FSB'S REQUIREMENTS.
8. ALL PIPE, DUCT, CABLE PENETRATIONS THROUGH FLOOR SLAB & WALL SHALL BE LENGTH OF THESE DUCTWORKS SHALL NOT EXCEED 2M. CODES AND REGULATIONS
MADE GOOD WITH APPROVED FIRE STOP MATERIAL. 7. ALL PLATFORMS AND BRACKETS FOR ACMV EQUIPMENT SHALL BE PROVIDED BY THE
32. ALL BENDS AND ELBOWS SHALL BE CONSTRUCTED WITH LONG RADIUS AND LOW FRICTION ALL ACMV WORKS AS SHOWN ON THE PLANS AS TO BE CARRIED OUT
CONTRACTORS. THE DETAIL/S OF THESE INSTALLATIONS SHALL BE SUBMITTED TO THE
M & E AND STRUCTURE ENGINEERS FOR APPROVAL BEFORE ANY FABRICATION.
LOSS TYPE COMPLETED WITH GUIDE VANES AS RECOMMENDED IN THE STATED CODES. BY THE CONTRACTOR SHALL BE STRICTLY COMPLY WITH THE FOLLOWING
STATUTORY OBLIGATIONS, REGULATIONS AND SPECIFICATIONS TOGETHER
TENDER DRAWING
33. ALL TEES OR BRANCH DUCTS WITH 3 OR MORE OUTLETS SHALL BE INSTALLED WITH WITH ANY AMENDMENTS OF THE LATEST CODES AND STANDARDS OF :-
FAN COIL UNIT 8. ALL EXTERNAL EQUIPMENT AND/OR INSTALLATIONS SHALL BE WEATHER AND CORROSION
SPLITTER DAMPER. REVISION
PROOFED TYPE.
1. THE POWER SUPPLY, PSB, FSSB, BCA AND PWD.
1. UNLESS OTHERWISE SPECIFIED, EACH FAN COIL UNIT SHALL BE EQUIPPED WITH 34. TEST HOLE/S SHALL BE PROVIDED AT THE DOWNSTREAM OF EACH AIR-CONDITIONING AND
9. ALL ACMV EQUIPMENT SHALL BE FACTORY TESTED AND ASSEMBLED.
THERMOSTAT WITH 3 SPEED AND ON/OFF SWITCH. MECHANICAL VENTILATION SYSTEM. 2. SS CP 5 : 1998 - CODE OF PRACTICE FOR WIRING OF NO DATE DESCRIPTION
10. UNLESS OTHERWISE SPECIFIED, ALL FAN COIL UNITS SHALL BE SUPPLIED WITH HIGH ELECTRICAL EQUIPMENT IN BUILDINGS.
2. ALL WALL MOUNTED THERMOSTATS SHALL BE WALL MOUNTED AT 1.5 METER ABOVE 35. UNLESS OTHERWISE STATED, ALL FIRE DAMPERS AND FIRE-RATED DUCT AS SHOWN ON PLANS
EFFICIENCY, WASHABLE AIR FILTER C/W FRAME AND ATTACHMENTS. AT LEAST ONE (1) 3. SS 553 : 2009 - CODE OF PRACTICE FOR MECHANICAL
SHALL BE MINIMUM 2-HRS FIRE RATED AND/OR TO THE SAME INTREGRITY AS THE FIRE
FINISHED FLOOR LEVEL UNLESS OTHERWISE SPECIFIED. EXACT LOCATION OF THERMOSTAT SHALL BE PROVIDED FOR EACH FAN COIL UNIT. COMPARTMENT WALL (WHICHEVER IS HIGHER). VENTILATION AND AIRCONDITIONING IN
THERMOSTATS SHALL BE CONFIRMED WITH THE ARCHITECT. BUILDINGS.
11. ALL DUCTED FAN COIL UNITS SHALL BE PROVIDED WITH INSULATED SECONDARY DRAIN PAN. 36. ALL FIRE RATED DUCTS SHALL BE RATED 2 HRS INTERNALLY AND 2 HRS EXTERNALLY. THESE
3. DUCTS ARE TO BE CONSTRUCTED AND INSULATED IN ACCORDANCE TO FSB REQUIREMENTS 4. THE BUILDING CONTROL ACT.
TOTAL EXTERNAL STATIC PRESSURE DROP FOR FAN COIL UNIT IS THE PRESSURE AND TO BE INSTALLED AT THE UPPER-MOST OF ANY M & E SERVICES.
12. ALL FAN COIL UNIT SHALL BE SUPPLIED WITH BUILT-IN CONDENSATE DRAIN PUMP IF NECESSARY.
DROP THROUGH DUCT WORK, DIFFUSER/GRILLE AND AIR FILTER (EXCLUDING 5. THE BUILDING CONTROL (SPACE, LIGHT AND VENTILATION) REGULATIONS.
13. ALL FAN COIL UNIT OR MECHANICAL VENTILATION FAN SHALL BE INSTALLED WITH ISOLATION 37. ALL FANS FORMING PART OF THE FIRE RATED DUCT SHALL BE ENCLOSED IN AT LEAST 2 HRS
COOLING COIL AND FCU CASING) SHALL BE JUSTIFIED TO ENSURE SUFFICIENT FIRE RATED CONSTRUCTION (OR FIRE RATED TO THE SAME INTREGRITY AS THE FIRE RATED
POWER POINT MOUNTED NOT MORE THAN 1.5M FROM THE EQUIPMENT. 6. CODE OF PRACTICE FOR FIRE PRECAUTIONS IN BUILDINGS. (2007)
DUCTWORK) COMPLETE WITH ACCESS PANEL ACCEPTABLE BY FSB.
AIR FLOW TO EACH DIFFUSERS AND GRILLES.
14. ALL ACMV EQUIPMENT SHALL BE INSTALLED WITH VIBRATION ISOLATOR AND NOISE CONTROL 38. ALL AIR-CONDITIONING PIPEWORKS RUN WITHIN ANY FIRE ESCAPE AREA SHALL BE CONCEALED 7. THE REGULATIONS FOR THE ELECTRICAL EQUIPMENT OF BUILDINGS
4. POWER SUPPLY SHALL BE 230V/1PH/50HZ OR 400V/3PH/50HZ UNLESS IN MINIMUM 2-HRS FIRE RATED ENCLOSURE AND/OR FSB APPROVED MATERIAL. PUBLISHED BY THE INSTITUTION OF ELECTRICAL ENGINEERS (LONDON).
DEVICES.
OTHERWISE SPECIFIED.
15a. ALL DIRECT-DRIVEN AXIAL FANS SUPPLIED SHALL BE OF PITCH-ANGLE ADJUSTABLE TYPE. 8. ENVIRONMENTAL PROTECTION DEPARTMENT.
5. THE INSULATION OF THE DRAIN PAN SHALL BE SURFACE TREATED AND BLACK 39. ALL CONDENSATE DRAIN PIPE SHALL BE HARDDRAWN COPPER IN EXPOSED AREAS AND UPVC
INSTALLATION SHALL INCLUDE ADJUSTMENTS OF THE PITCH ANGLE TO ACHIEVE THE DESIGN
IN CONCEALED AREAS. THE PIPES SHALL BE INSULATED AGAINST CONDENSATION AND SHALL 9. CHARTERED INSTITUTION OF BUILDING SERVICES ENGINEERS. TENDER DRAWING
COLOUR FINISHED. ALL CORNERS SHALL BE SEALED AND PROTECTED. AND AUTHORITIES' REQUIREMENTS OF THE AIR FLOW AND PRESSURE. THE IMPELLER OF
INSTALLED AT A GRADIENT OF NOT LESS THAN 1 : 500. 10. IN THE ABSENCE OF ANY OTHER REQUIREMENTS NOT FOUND IN THE
6. THE FAN SHALL BE MADE OF METAL OR METALLIC ALLOYED.
ENTIRE SUPPLY AIR DUCT OF THE FAN COIL UNIT SHALL BE THE SAME SIZE AS ABOVE THEN THE REQUIREMENTS AS STIPULATED IN SMACNA , OWNER / DEVELOPER
40. ALL CONDENSATE DRAIN WATER SHALL BE DISCHARGE TO THE NEAREST FLOOR TRAP AND/
FAN COIL OUTLET UNLESS OTHERWISE SPECIFIED ON THE SPECIFICATION DRAWINGS. 15b. ALL BELT-DRIVEN FANS SUPPLIED SHALL BE ABLE TO CHANGE THE SPEED BY CHANGING ASHAREA AND/OR ANY OTHER LOCAL AUTHORITY HAVING JURISDICTION.
OR SURFACE DRAIN. THE FLOOR TRAP SHALL BE INSULATED WITH 50 MM INSULATION C/W
7. THE PULLEYS' SIZE. INSTALLATION SHALL INCLUDE CHANGING OF THE PULLEY TO ACHIEVE
AIR FILTER SHALL BE 25 mm THICK, WASHABLE TYPE. JACKETING.
THE DESIGN AND AUTHORITIES' REQUIREMENTS OF THE AIR FLOW AND PRESSURE. THE
IMPELLER OFTHE FAN SHALL BE MADE OF METAL OR METALLIC ALLOYED. 41. WHERE CONDENSATE PIPES RUN WITHIN COMPUTER ROOM, THESE PIPES SHALL BE COMPLETED
8. CONDENSATE DRAIN FROM EACH FAN COIL UNITS SHALL BE DIA 25 mm UNLESS WITH MINIMUM 50 MM THICK INSULATION.
OTHERWISE STATED. 16. ALL CENT-IN-LINE FAN SUPPLIED SHALL BE ENCLOSED IN AN ACCOUSTIC LINED BOX.
42. ALL VERTICAL DROPPER OF CONDENSATE PIPES SHALL BE IN CONCEALED POSITION. ACMV
9. ALL CONDENSATE SHALL BE DRAIN TO THE NEAREST FLOOR TRAP/DRAIN OR 17. THE STATIC PRESSURE AS SHOWN ON THE PLANS AND SCHEDULE ARE ESTIMATED FOR TENDER LOCATION
CONTRACTOR SHALL PROVIDE BOX-UP TO CONCEAL THESE PIPE EVEN THOUGH NOT SHOWN
DRAINAGE STACK. SUFFICIENT GRADIENT SHALL BE MAINTAINED WHENEVER POSSIBLE PURPOSES ONLY. THE CONTRACTORS MUST SUBMIT THE SAID CALCULATIONS BASE ON IN THE DRAWINGS.
CO-ORDINATED DRAWING AND TYPE OF FITTING USED. ALL CATALOGUE AND PERFORMANCE CURVE
FOR GRAVITY FLOW. IF GRAVITY FLOW IS NOT ACHIEVABLE, SUFFICIENT SIZE CONDENSATE YANGON
SELECTION FOR THE ABOVE SHALL BE SUBMITTED TO THE M & E ENGINEER FOR APPROVAL
PUMP SHALL BE PROVIDED FOR DRAINAGE FROM THE FAN COIL UNIT BEFORE PROCEEDING FURTHER.

10. THE LOCATION OF THE THERMOSTAT/FAN SPEED CONTROLLER SHALL BE WIRED TYPE. 18. FRESH AIR FAN (IF ANY) SUPPLIED FOR THE AIR-CONDITIONING SYSTEM SHALL BE LEGENDS
ELECTRICALLY INTERLOCKED WITH ITS RESPECTIVE FAN COIL UNIT. PROJECT TITLE
11. THE FAN & FCU STATIC PRESSURE INDICATED IN THE SCHEDULE ARE FOR GUIDANCE ABBREVIATIONS
DURING TENDERING ONLY, THE CONTRACTOR SHALL BE RESPONSIBLE FOR CHECKING
19. RUNNING SPEED FOR ALL MECHANICAL VENTILATION FANS SHALL NOT EXCEED 1480 RPM YAY TAR SHAY - FIVE STORIES
THE TOTAL PRESSURE LOSS OF EACH SYSTEM BASED ON THE ACTUAL DUCT RUN AND (UNDER NORMAL CONDITION) OR AS STATED IN THE SCHEDULE ( WHICHEVER IS LOWER),
NEW FRESH AIR DUCT AIR CURTAIN
EQUIPMENT OFFERED. FCU FAN COIL UNIT
SPEED CONTROLLER SHALL BE PROVIDED TO ACHIEVE THE DESIGN REQUIREMENTS.
12. ALL RETURN AIR PLENUM BOX FOR FAN COIL UNITS SHALL BE ACOUSTICALLY TREATED WITH NEW SUPPLY AIR DUCT NRD NON RETURN DAMPER
20. ALL MECHANICAL VENTILATION FANS SHALL BE CONTROLLED BY THE FOLLOWING :- WALL MOUNTED FAN ARCHITECT
50mm THK 80 Kg/m3 ROCK WOOL INSULATION.
a) AUTO-OFF-TEST SWITCH WITH RUNNING AND FAULT LIGHTS INDICATES ON THE LOCAL FD FIRE DAMPER
CONTROL PANEL. NEW KITCHEN EXHAUST DUCT
13. LOCAL CONTROL PANEL FOR EVERY FAN COIL UNITS SHALL BE PROVIDED.
b) START-STOP BY TIMER (AS INDICATED IN THE DRAWINGS/SPECIFICATIONS). A/P 600x600/450X450 CEILING ACCESS PANEL
VCD VOLUME CONTROL DAMPER
NEW TOILET EXHAUST AIR DUCT
PIPEWORK AND FITTINGS 21. THE CONTRACTOR/S SHALL LIAISE WITH THE ELECTRICAL CONTRACTOR/S THE POWER SUPPLY
F/A FROM ABOVE
REQUIREMENTS AND LOCATION OF THE POWER POINT FOR ALL ACMV EQUIPMENT. NEW DCUT C/W EXTERNAL & INTERNAL FAN WITH SILENCERS
1. CONDENSATE DRAIN FOR FAN COIL UNITS SHALL BE MINIMUM Ø20mm UNLESS OTHERWISE INSULATION
T/B TO BELOW
STATED AND SHALL BE INDIVIDUALLY RUN TO THE NEAREST FLOOR TRAP WITH SUFFICIENTLY
22. ALL EQUIPMENT SUPPLIED FOR FIRE SERVICES SHALL BE CAPABLE OF OPERATING NEW FLEXIBLE DUCT
GRADIENT FOR GRAVITY FLOW. CONTRACTOR TO CHECK THE EXACT LOCATION OF NEAREST CEILING FAN T/A TO ABOVE
EFFECTIVELY FOR AT LEAST TWO (2) HOURS AND SHALL BE CONNECTED TO A SECONDARY STRUCTURE
AVAILABLE FLOOR TRAPS AND COORDINATE WITH SANITARY PLUMBING CONTRACTOR FOR POWER SUPPLY. ALL LINKING COMPONENTS AND/OR CABLES FOR THE SYSTEM/S SHALL BE
FIRE RATED TO THE SAME INTREGRITY AS THE FANS IN ACCORDANCE TO FSB CODES AND EXISTING DUCT TO BE REMAINED F/B FROM BELOW
WATER INLET PROVISION TO THE FLOOR TRAP. REQUIREMENTS. TOILET EXHAUST FAN
H/L HIGH LEVEL
2. ALL CONDENSATE SHALL BE DRAIN TO THE NEAREST FLOOR TRAP/DRAIN OR OPEN DRAIN. 23. THE CONTRACTOR SHALL ENSURE THE FOLLOWINGS INSTALLATIONS :- EXISTING DUCT TO BE DELETED
3. ALL INSULATED AND UN-INSULATED REFRIGERANT PIPES SHALL BE RUN IN TRUNKING/TRAY. a) ALL FRESH AIR INTAKE SHALL BE LOCATED AT LEAST 5 M AWAY FROM ANY SUPPLY AIR GRILLE L/L LOW LEVEL
HOWEVER, PIPEWORK EXPOSE TO VIEW OR SHALL BE RUN IN SUITABLE SIZE TRUNKING. EXHAUST POINT.
NEW LINEAR SUPPLY AIR DIFFUSER SA SUPPLY AIR
4. PIPE WORKS PENETRATING THE ROOF TERRACE SHALL BE PROVIDED WITH APPROVED b) ALL FRESH AIR INTAKE SHALL BE LOCATED AT LEAST 3 M AWAY FROM NATURALLY (1200MMX2SLOT C/W VCD & PLENUM BOX)
VENTILATED STAIRCASE, SMOKE-STOP LOBBY, FIRE ACCESS PANEL AND/OR FIRE
M&E ENGINEER
METHOD OF WATER PROOFING SEAL TO AVOID WATER SEEPAGE. CEILING CASSETTE FAN COIL UNIT RA RETURN AIR
ESCAPE AREAS.
5. PIPE WORKS PENETRATING THE ROOF INDICATED IN THE DRAWINGS ARE INDICATIVE.
c) ALL EXHAUST AIR DISCHARGE SHALL BE LOCATED AT LEAST 5 M AWAY FROM FRESH DUMMY LINEAR EAL EXHAUST AIR LOUVER
CONTRACTOR TO CHECK ON THE SITE THE CONSTRAINT TO ENSURE THEY ARE VIABLE.
AIR INTAKE AND NATURALLY VENTILATED AREAS.
ALL PIPES PENETRATING THE WALL AND ROOF SHALL BE PROPERLY SEALED AGAINST DUCT FAN COIL UNIT OA OUTSIDE AIR
WATER SEEPAGE AND PROTECT FROM RODENT AND INSECT CRAWL. d) ALL KITCHEN EXHAUST SHALL NOT DISCHARGED DIRECTLY TO ANY ADJACENT PREMISES.
NEW LINEAR RETURN AIR DIFFUSER
e) FRESH AIR SHALL BE PROVIDED FOR ALL AIR-CONDITIONING UNITS IN ACCORDANCE (1200MMX2SLOT C/W VCD & PLENUM BOX) EAF EXHAUST AIR FAN
TO SS-553 (SS CP:13) AND BCD REQUIREMENTS.
FAF FRESH AIR FAN M&E CONTRACTOR
f) ALL ROOMS PROVIDED WITH AIR-CONDITIONING SYSTEM SHALL BE AIR-TIGHT AGAINST DUMMY LINEAR DUCT FAN COIL UNIT
AIR LEAKING. SAD SUPPLY AIR DUCT
ELECTRICAL 150MM WIDE RETURN AIR BAR GRILLE
24. ALL DUCT SIZES INDICATED ARE INTERNAL CLEAR SIZE DIMENSION.
1. ALL THE ELECTRICAL WIRING AND CIRCUIT BREAKER SHALL BE SIZED BASE ON THE WALL MOUNTED FAN COIL UNIT RAD RETURN AIR DUCT PEARL ROYAL Co., Ltd.
APPROVED STANDARD. 25. THE CONTRACTOR SHALL MADE-KNOWN TO THE M & E ENGINEER FOR ANY AIR VOLUME CONTROL DAMPER
Block-C, Room-802,8th Floor,Yadanar Housing,
2. ELECTRICAL POWER SUPPLY SHALL BE PROVIDED BY ELECTRICAL CONTRACTOR AND CHANGE IN DUCT SIZE DUE TO SITE CONSTRAINTS. EAD EXHAUST AIR DUCT
TERMINATED TO THE ISOLATORS NEAR THE FAN COIL UNITS. WIRING FROM THE ISOLATOR SPLITTER DAMPER
13Rd Quarter, South Okkalapa Township, Yangon.
CONDENSING UNIT ( DX SYSTEM )
SHALL BE INCLUDED IN THIS CONTRACT. FAD FRESH AIR DUCT
Ph: 09-420084410, Email: pearlroyal@contractor.net
3. ALL THE CONDUITS BELOW FALSE CEILING SHALL BE CONCEALED IN WALL. NON RETURN DAMPER
CMH AIR QUANTITY (CUBIC METER/HOUR)
CONDENSING UNIT ( DX SYSTEM )
REFRIGERANT PIPE(VRF) l/s AIR QUANTITY (LITER/SECOND)
DRAWING TITLE
D CONDENSATE DRAIN
REFRIGERANT PIPE (DX) REFNET JOINT
C/W COMPLETE WITH
CONDENSATE DRAIN PIPE
NOTES & LEGEND
CH CHILLER

CHWP CHILLED WATER PUMP


DRAWING NO.
MSFD MOTORIZED SMOKE & FIRE DAMPER

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
ND A R Y
SITE BOU
1"
7'-52

Y LINE
SITE BOUNDAR

SITE BOUNDAR
TENDER DRAWING
3'-11"

1 REVISION
A
Y LINE

A-601
NO DATE DESCRIPTION

1 B B
DUCT RISER @ 500mm x500mm
1 NET WGT - KG
DUCT RISER @ 400mm x400mm
800mm x 400mm EAD
NET WGT - KG
93.6 1
SITE BOUNDAR

AC & FIRE
74
A-602 EAF - M&E- AXIAL
A-602
EAF -CP- AXIAL 12000CMH(FM)
600mm x 400mm EAD DUCT RISER @ 300mm x300mm
6000CMH(HM)
7000CMH(FM)
4000CMH(HM)
STAIR-1
13'-9"

LIFT

300mm x300mm FAD

P&S
** FAN TESTED TO BS 7346 - 300'C FOR AT LEAST 1 HOUR AND

ELE & ELV


OPERATES FULLY ON CARBON MONOXIDE LEVEL IS ABOVE 100PPM
** FAN TESTED TO BS 7346 - 300'C FOR AT LEAST 1 HOUR AND BELOW THIS LEVEL , RUNS AT HALF MODE.
OPERATES FULLY ON CARBON MONOXIDE LEVEL IS ABOVE 100PPM
** SECONDARY POWER SUPPLY IS RECOMMENDED.

ELE & ELV


BELOW THIS LEVEL , RUNS AT HALF MODE.
3 4
** SECONDARY POWER SUPPLY IS RECOMMENDED.

FAF - CP- AXIAL


1600CMH 300mm x300mm FAD
TENDER DRAWING
NET WGT - KG
52.6
OWNER / DEVELOPER

2 FAG c/w VCD @ 3nos


400mm x 300mm EAD

5
600mm x 300mm(FS)

400mm x 300mm EAD


350mm(NS) @500CMH EACH

LOCATION
14'-8"

LINEAR BAR GRILLE c/w VCD @ 8nos


1200mm x 200mm(FS) YANGON
47'-11"

@850CMH/ 500CMHEACH M&E RM


LINEAR BAR GRILLE c/w VCD @ 6nos
6 F.F.L -9'-0"
1200mm x 500mm(FS) PROJECT TITLE
CAR PARKING @2000CMH/ 1000CMHEACH
S.F.L -9'-2"
YAY TAR SHAY - FIVE STORIES

NATURAL FRESH AIR INTAKE - 5% OF FLOOR AREA


ARCHITECT
3
Y LINE

2 STRUCTURE
19'-6"

C Ramp Slope = 1:6.5 C

LINE
1 1
A-603 A-603
SITE BOUNDAR

3
F.F.L -9'-0"

Y
S.F.L -9'-2"

2
1
M&E ENGINEER

SITE BOUNDAR
1

4
4 M&E CONTRACTOR
CAR PARKING - 6 NOS
6'-0"

PEARL ROYAL Co., Ltd.


1
A A-601 Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
SITE BOUNDARY LINE SITE BOUNDARY LINE Ph: 09-420084410, Email: pearlroyal@contractor.net

BASEMENT FLOOR PLAN DRAWING TITLE

ACMV DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LIN E

Y LINE
D A RY
SITE BOUN
1"
7'-52

Y LINE
SITE BOUNDAR

SITE BOUNDAR
EXHAUST AIR LOUVER TENDER DRAWING
EXHAUST AIR LOUVER
3'-11"

1 REVISION
A
FRESH AIR LOUVER
Y LINE

NET WGT - KG
A-601
3.9

EAF-WM 600mm x 400mm EAD NO DATE DESCRIPTION


B B
300CMH

DUCT RISER @ 500mm x500mm


1 DUCT RISER @ 400mm x400mm SYSTEM - I 2 SLOT LRBG c/w VCD @ 1nos
1200mm x 600mm(FS)
1 STAIR-1 1

AC & FIRE
2 SLOT LSBG c/w VCD @ 4nos @1400CMH EACH
SITE BOUNDAR

1200mm x 200mm(FS)
A-602 @750CMH EACH A-602
2 SLOT LSBG c/w VCD @ 4nos
DUCT RISER @ 300mm x300mm
1
WC Director Rm
1200mm x 200mm(FS)
@750CMH EACH
FCU-HD-03
Stair Area A/P

31.75mm x 19.05mm
14.2KW
13'-9"

Vault Lift

Reception
A/P 249 SF

P&S

ELE & ELV


NET WGT - KG

400mm x 300mm 125


300mm x 300mm 400mm x 300mm 300mm x 200mm

ELE & ELV


NET WGT - KG
125 18 R @ 0' - 6"

BY JOHNSON
BY JOHNSON

YORK
YORK

CONTROLS
CONTROLS

2 SLOT LRBG c/w VCD @ 1nos

R
R

1200mm x 600mm(FS) FCU-HD-01

15.88mm x 9.52mm
F.F.L ±0'-0" @2800CMH EACH
F.F.L ±0'-0" 14.2KW
TENDER DRAWING
15.88mm x 9.52mm

S.F.L - 0'-2" S.F.L - 0'-2"


OWNER / DEVELOPER
23 R @ 0' - 6"
2 22.2mm x 9.52mm 25.4mm x 12.7mm

Manager Rm2 SLOT LSBG c/w VCD @ 2nos


15.88mm x 9.52mm

22.2mm x 9.52mm
1200mm x 200mm(FS) 2 SLOT LSBG c/w VCD @ 10nos
@600CMH EACH 1200mm x 200mm(FS)
F.F.L ±0'-0" A/P @540CMH EACH F.F.L -3'-0"
S.F.L - 0'-2" FCU-HD-02 NET WGT - KG
14KG EACH
S.F.L -3'-2" LOCATION
28KW
NET WGT - KG
14'-8"

Air Curtain
81

NET WGT - KG
2NOS
2
189
YANGON
BY JOHNSON

Shop Area(Gold & SADDiamond) R - 0' 6"


YORK
CONTROLS

15.88mm x 6.35mm
600mm x 300mm
47'-11"

FCU-HD-04
5.6KW
2 SLOT LRBG c/w VCD @ 2nos
1200mm x 200mm(FS)
F.F.L ±0'-0" T - 1' 0"
@500CMH EACH
A/P

BY JOHNSON
YORK
CONTROLS
PROJECT TITLE

R
S.F.L - 0'-2" F.F.L ±0'-0"
15.88mm x 9.52mm

2 SLOT LRBG c/w VCD @ 2nos S.F.L - 0'-2"


YAY TAR SHAY - FIVE STORIES
SAD

2 SLOT LSBG c/w VCD @ 2nos 1200mm x 600mm(FS)


1200mm x 200mm(FS) @2500CMH EACH
m

@600CMH EACH
00m
x3
mm

ARCHITECT
3 2 SLOT LRBG c/w VCD @ 1nos
400

1200mm x 200mm(FS)
@1000CMH EACH
A/P Staff Dinning
Rm

MAIN ENTRANCE
NET WGT - KG
84
BY JOHNSON
YORK
CONTROLS
R

FCU-HD-05
LINE

7.1KW

STRUCTURE

(IN/OUT)
19'-6"

C Ramp Slope = 1:6.5 C

Y LINE
Y

1 1
A-603 A-603
SITE BOUNDAR

3
WC

2
1
M&E ENGINEER

SITE BOUNDAR
23 R @ 0' - 6 "

4
TEAF-CM
STAIR-2
Stair
EAF-WM
300CMH
500CMH

@100mm DIA; UP
NET WGT - KG
6.5
Area
4 Vent Hood

M&E CONTRACTOR
6'-0"

PEARL ROYAL Co., Ltd.


1
A A-601 Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
SITE BOUNDARY LINE SITE BOUNDARY LINE Ph: 09-420084410, Email: pearlroyal@contractor.net

GROUND FLOOR PLAN DRAWING TITLE

ACMV DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
RY
SITE BOUNDA
1"
7'-52

Y LINE
SITE BOUNDAR

SITE BOUNDAR
TENDER DRAWING
3'-11"

1 REVISION
A
Y LINE

NET WGT - KG
A-601
3.9

EAF-WM
NET WGT - KG NO DATE DESCRIPTION
B B
600CMH 3.9
Vent Hood

1 SYSTEM - I
EAF-WM
200CMH
2 SLOT LSBG c/w VCD @ 2nos
1200mm x 200mm(FS)
1 1

S.F.L+12'-10"

AC & FIRE
ASSUME THAT KITCHEN HOOD SYSTEM IS
STAIR-1
SYSTEM - II @1000CMH EACH
SITE BOUNDAR

F.F.L+13'-0"
A-602 UNDER THE SCOPE OF KITCHEN SPECIALIST. A-602
Bath & WC

100mmDIA
+13'-0"

Bath & WC
Master Bed

31.75mm x 19.05mm
13'-9"

300mm x 300mm
Stair Area
NET WGT - KG
9.4

Lift
NET WGT - KG

Rm Balcony
EAF-WM
6.5
3000CMH

P&S
TEAF-CM

F.F.L+12'-10"

ELE & ELV


300CMH

S.F.L+12'-8"
2 SLOT LRBG c/w VCD @ 1nos
1200mm x 600mm(FS)
F.F.L +12'-8"

ELE & ELV


20 R@ 0'-6 7/8" @1800CMH EACH

Hall
Kitchen CYCLE-CM
S.F.L - 12'-6"
YORK

F.F.L +13'-0"
BY JOHNSON CONTROLS

EAF-CM NET WGT - KG

R
56in BLADE
98 TENDER DRAWING
Store Rm
NET WGT - KG 300CMH @100mm DIA;
7.2
FCU-HD-02

S.F.L - 12'-10" A/P 9KW

28.58mm x 15.88mm
2 SLOT LRBG c/w VCD @ 2nos
1200mm x 600mm(FS)
@2500CMH EACH
NET WGT - KG
6.5
OWNER / DEVELOPER

2 22.2mm x 9.52mm
F.F.L±12'-8"
S.F.L-12'-6"

19.05mm x 9.52mm
2 SLOT LSBG c/w VCD @ 10nos
1200mm x 200mm(FS)
A/P 19.05mm x 9.52mm 19.05mm x 9.52mm
15.88mm x 9.52mm

F.F.L +13'-0"
15.88mm x 9.52mm
A/P
Wide Passageway @500CMH EACH
YARD

FCU-HD-04
NET WGT - KG
NET WGT - KG
LOCATION
22.4KW
104
S.F.L +12'-10" 81
14'-8"

300mm x 200mm
R

YORK
BY JOHNSON CONTROLS

300mm x 200mm SAD

Family Rm YANGON

BY JOHNSON
@100mm DIA;
F.F.L +13'-0"

YORK
CONTROLS
47'-11"

R
FCU-HD-03

600mm x 300mm SAD


Vent Hood 40
0m
mx 7.1KW

Bath & WC 30
0m
m
S.F.L +12'-10"
PROJECT TITLE
A/P SA
D

15.88mm x 9.52mm
@100mm DIA;

2 SLOT LSBG c/w VCD @ 2nos


NET WGT - KG 400mm x 300mm SAD 1200mm x 200mm(FS)
FCU-HD-05 189 @600CMH EACH
28KW
YORK
BY JOHNSON CONTROLS
R

2 SLOT LRBG c/w VCD @ 1nos


YAY TAR SHAY - FIVE STORIES
1200mm x 600mm(FS)
@1000CMH EACH
2 SLOT LRBG c/w VCD @ 2nos
1200mm x 600mm(FS)
ARCHITECT
3 @2500CMH EACH
EAF-CM
600mm x 300mm

500CMH

400mm x 300mm
NET WGT - KG
6.5

YORK
CONTROLS
BY JOHNSON
20 R @ 0' - 6 7/8"

F.F.L +13'-0" 400mm x 300mm 300mm x 300mm 2 SLOT LSBG c/w VCD @ 2nos
NET WGT - KG

Stair Area S.F.L +12'-10"


125 1200mm x 200mm(FS)
@600CMH EACH
Y LINE

A/P Study Rm
400mm x 300mm SAD

STRUCTURE
19'-6"

FCU-HD-01

C 300mm x 300mm SAD


Master Bed Rm 7.1KW
C

Y LINE
1
Living Area 2 SLOT LRBG c/w VCD @ 1nos
1200mm x 600mm(FS)
1
@1000CMH EACH
A-603 A-603
SITE BOUNDAR

2
1
M&E ENGINEER

SITE BOUNDAR
2 SLOT LSBG c/w VCD @ 5nos
1200mm x 200mm(FS)
Balcony

4
@1000CMH EACH

STAIR-2 F.F.L +12'-8"


S.F.L +12'-6"
4 M&E CONTRACTOR
6'-0"

SEC
B 4-002
PEARL ROYAL Co., Ltd.
Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
SITE BOUNDARY LINE SITE BOUNDARY LINE Ph: 09-420084410, Email: pearlroyal@contractor.net

FIRST FLOOR PLAN DRAWING TITLE

ACMV DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI NE

Y LINE
D AR Y
SITE BOUN
1"
7'-52

Y LINE
SITE BOUNDAR

SITE BOUNDAR
TENDER DRAWING
3'-11"

1 REVISION
A
Y LINE

NET WGT - KG
A-601
3.9

EAF-WM
NO DATE DESCRIPTION
B A
600CMH

1 SYSTEM - I
1 ASSUME THAT KITCHEN HOOD SYSTEM IS SEC
STAIR-1

AC & FIRE
SYSTEM - II
SITE BOUNDAR

UNDER THE SCOPE OF KITCHEN SPECIALIST.


A-602 SYSTEM - III
A/P 4-001

Stair Area
NET WGT - KG
7.2
22.2mm x 9.52mm
CYCLE-CM FCU-HD-01

S.F.L +24'-0"
F.F.L +24'-2"
2 SLOT LRBG c/w VCD @ 2nos
13'-9"

NET WGT - KG 56in BLADE 28KW

31.75mm x 19.05mm
NET WGT - KG

lift
9.4 1200mm x 600mm(FS)
189 R

YORK

@2500CMH EACH
CONTROLS BY JOHNSON

EAF-WM
3000CMH

P&S

ELE & ELV


yard

ELE & ELV


Kitchen

600mm x 300mm
22.2mm x 9.52mm 28.58mm x 15.88mm
20 R @ 0' - 6 7/8" 2 SLOT LSBG c/w VCD @ 6nos
1200mm x 200mm(FS)
TENDER DRAWING

19.05mm x 9.52mm
@850CMH EACH

OWNER / DEVELOPER

2
S.F.L - 24'-0"
F.F.L +24'-2"

2 SLOT LSBG c/w VCD @ 8nos 2 SLOT LRBG c/w VCD @ 2nos

A/P
22.2mm x 9.52mm

1200mm x 200mm(FS) 1200mm x 600mm(FS)


@650CMH EACH @2500CMH EACH 300mm x 300mm

400mm x 300mm SAD


FCU-HD-03
Yard

NET WGT - KG
22.4KW

Circulation

R
YORK
BY JOHNSON CONTROLS

104

Wide Passageway LOCATION


Living Area

22.2mm x 9.52mm
14'-8"

300mm x 200mm SAD


F.F.L +24'-6" YANGON
100mmDIA 40

600mm x 300mm SAD


47'-11"

0m
Vent Hood
m x3
00
mm
S.F.L +24'-4"
SA
Bath & WC D
PROJECT TITLE
A/P
100mmDIA

NET WGT - KG
FCU-HD-04 189
28KW
YORK
BY JOHNSON CONTROLS
R
YAY TAR SHAY - FIVE STORIES

2 SLOT LRBG c/w VCD @ 2nos


1200mm x 600mm(FS)
ARCHITECT
3 @2500CMH EACH
EAF-CM
600mm x 300mm

500CMH 2 SLOT LRBG c/w VCD @ 2nos


1200mm x 600mm(FS)

Stair Area
NET WGT - KG
@2500CMH EACH
Bath & WC
6.5
NET WGT - KG
FCU-HD-02 189
28KW
YORK
BY JOHNSON CONTROLS
R

A/P
NET WGT - KG
6.5

DN
R @ 0' - 6 7/8"

UP TEAF-CM
400CMH
Master Bed Rm
Y LINE

Balcony
400mm x 300mm SAD

600mm x 300mm
S.F.L - 24'-0"
F.F.L +24'-2"

STRUCTURE
19'-6"

C 300mm x 300mm SAD


C

S.F.L +24'-0"
F.F.L +24'-2"

Y LINE
1 1
A-603 Master Bed Rm A-603
SITE BOUNDAR

3
100mmDIA

400mm x 300mm
Balcony

2
1
300mm x 300mm SAD M&E ENGINEER

SITE BOUNDAR
2 SLOT LSBG c/w VCD @ 5nos 2 SLOT LSBG c/w VCD @ 5nos
20

1200mm x 200mm(FS) 1200mm x 200mm(FS)

4
@1000CMH EACH @1000CMH EACH

STAIR-2
4 Vent Hood
M&E CONTRACTOR
6'-0"

1
A A-601 PEARL ROYAL Co., Ltd.
Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
SITE BOUNDARY LINE SITE BOUNDARY LINE Ph: 09-420084410, Email: pearlroyal@contractor.net

SECOND FLOOR PLAN DRAWING TITLE

ACMV DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
U ND AR Y
SITE BO
1"
7'-52

Y LINE
SITE BOUNDAR

SITE BOUNDAR
TENDER DRAWING
3'-11"

1 REVISION
A
Y LINE

A-601
NET WGT - KG NET WGT - KG NET WGT - KG
NET WGT - KG
3.9
EAF-WM
3.9
EAF-WM 20 R @ 0' - 6 7/8" 3.9
EAF-WM EAF-WM
3.9
NO DATE DESCRIPTION
B A
1000CMH 600CMH 400CMH
200CMH

1 Vent Hood

1 Bath & WC Laundary SYSTEM - I


SYSTEM - II SEC

AC & FIRE
STAIR-1
SITE BOUNDAR

FCU-HD-08
A-602 SYSTEM - III 4-001
9KW
& Yard DN SYSTEM - IV
R
YORK
CONTROLS

Sauna
BY JOHNSON

Bath & WC

22.2mm x 9.52mm
NET WGT - KG

S.F.L +35'-10"
98
13'-9"

Stair Area

F.F.L +36'-0"
2 SLOT LRBG c/w VCD @ 1nos
lift

P&S
1200mm x 600mm(FS)

Maid
A/PRm

ELE & ELV


2 SLOT LSBG c/w VCD @ 2nos @1800CMH EACH

@100mm DIA;
UP
1200mm x 200mm(FS)
@1000CMH EACH

ELE & ELV


S.F.L +35'-6"
F.F.L +35'-8"
28.58mm x 12.7mm
FCU-HD-13
14.2KW
15.88mm x 9.52mm
15.88mm x 9.52mm
19.05mm x 9.52mm
A/P NET WGT - KG
TENDER DRAWING

15.88mm x 6.35mm
25.4mm x 12.7mm 125

Lift Lobby Walk-in Wardrobe


Home Theater
2 SLOT LRBG c/w VCD @ 1nos
1200mm x 200mm(FS)
400mm x 300mm

OWNER / DEVELOPER
@1000CMH EACH
A/P
F.F.L +36'-0"
2

BY JOHNSON
YORK
CONTROLS
R
2 SLOT LRBG c/w VCD @ 1nos NET WGT - KG 2 SLOT LSBG c/w VCD @ 5nos

15.88mm x 9.52mm
81
1200mm x 600mm(FS)
ASSUME THAT KITCHEN HOOD SYSTEM IS FCU-HD-11
S.F.L +35'-10" 1200mm x 200mm(FS)
15.88mm x 9.52mm

NET WGT - KG @2500CMH EACH @600CMH EACH


5.6KW

300mm x 300mm SAD


UNDER THE SCOPE OF KITCHEN SPECIALIST.

Shoe Cabinet
6.5 R

YORKCONTROLS BY JOHNSON

EAF-CM
300CMH

S.F.L +35'-10"
F.F.L +36'-0"
Wet Kitchen LOCATION
Powder Rm

2 SLOT LRBG c/w VCD @ 1nos


1200mm x 600mm(FS)
F.F.L +36'-0"
14'-8"

@2500CMH EACH
S.F.L +35'-10" Master Bed Rm
S.F.L +34'-10"

F.F.L +36'-0"
F.F.L +35'-0"

YANGON

15.88mm x 9.52mm
A/P
S.F.L +35'-10"
47'-11"

FCU-HD-10
2 SLOT LSBG c/w VCD @ 2nos

14.2KW
NET WGT - KG

1200mm x 200mm(FS)
125

@600CMH EACH
YORK
BY JOHNSON CONTROLS
R

PROJECT TITLE

A/P Circulation
FCU-HD-09 YAY TAR SHAY - FIVE STORIES
14.2KW NET WGT - KG
125
R

YORK
BY JOHNSON CONTROLS
400mm x 300mm SAD

2 SLOT LRBG c/w VCD @ 1nos


F.F.L +36'-0"
ARCHITECT
3 Dry Kitchen
1200mm x 600mm(FS)
@2500CMH EACH
S.F.L +35'-10"

22 R @ 0' - 6" Walk-in Wardrobe 2 SLOT LSBG c/w VCD @ 4nos

UP
400mm x 300mm SAD

1200mm x 200mm(FS)

A/P @750CMH EACH

FCU-HD-12 NET WGT - KG

14.2KW 125

R
YORK
BY JOHNSON CONTROLS

F.F.L +36'-0"
2 SLOT LSBG c/w VCD @ 5nos
Master Bed Rm
Y LINE

1200mm x 200mm(FS)
S.F.L +35'-10"
300mm x 300mm

@600CMH EACH

S.F.L +35'-6"
2 SLOT LRBG c/w VCD @ 1nos
STRUCTURE

F.F.L +35'-8"
19'-6"

1200mm x 600mm(FS)

400mm x 300mm
@2500CMH EACH

C C

Balcony

Y LINE
1 1
A-603 A-603
SITE BOUNDAR

300mm x 200mm SAD

3
300mm x 300mm
Dinning Area Bath & WC

2
1
NET WGT - KG

Living Area 6.5


M&E ENGINEER

SITE BOUNDAR
Stair Area

4
EAF-CM
2 SLOT LSBG c/w VCD @ 5nos
400CMH
1200mm x 200mm(FS)

@100mm DIA;
@600CMH EACH

STAIR-2
4 M&E CONTRACTOR
6'-0"

Vent Hood

1
A A-601 PEARL ROYAL Co., Ltd.
Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
SITE BOUNDARY LINE SITE BOUNDARY LINE Ph: 09-420084410, Email: pearlroyal@contractor.net

THIRD FLOOR PLAN DRAWING TITLE

ACMV DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LIN E

Y LINE
NDA R Y
SITE BOU
1"
7'-52

Y LINE
SITE BOUNDAR

SITE BOUNDAR
TENDER DRAWING
3'-11"

SEC REVISION
B
LINE

4-002
NET WGT - KG NET WGT - KG NET WGT - KG
3.9
EAF-WM
3.9
EAF-WM
3.9
EAF-WM
NO DATE DESCRIPTION
B A
250CMH 200CMH 200CMH
2 SLOT LRBG c/w VCD @ 2nos

1
Vent Hood
1200mm x 200mm(FS)
@2000CMH EACH
Y

Balcony

S.F.L +47'-2"
F.F.L +47'-4"
SYSTEM - I
1 Balcony SEC

AC & FIRE
SYSTEM - II
STAIR-1
SITE BOUNDAR

A-602 SYSTEM - III 4-001


DN

Bath & WC
SYSTEM - IV 2 SLOT LSBG c/w VCD @ 5nos
1200mm x 200mm(FS)
SYSTEM - V @800CMH EACH

Master Bed Rm

31.75mm x 19.05mm
Stair Area Bath & WC
13'-9"

Lift F.F.L +47'-6"

100mmDIA
P&S
S.F.L +47'-4"

ELE & ELV


A/P

300mm x 300mm
NET WGT - KG
144
15.88mm x 9.52mm
UP

ELE & ELV


FCU-HD-03
16KW
R

YORK
BY JOHNSON CONTROLS

22.2mm x 9.52mm 28.58mm x 12.7mm 25.4mm x 12.7mm

Lift Lobby NET WGT - KG


6.5
TENDER DRAWING
TEAF-CM
250CMH

Store Rm
NET WGT - KG

OWNER / DEVELOPER
Master Bed Rm
6.5

400mm x 300mm
400mm x 300mm

EAF-CM
2 SLOT LSBG c/w VCD @ 4nos

2
300CMH
1200mm x 200mm(FS)

Wardrobe
@1000CMH EACH
2 SLOT LRBG c/w VCD @ 1nos F.F.L +47'-6" @100mm DIA;
F.F.L +47'-6"
Walk-in
2 SLOT LSBG c/w VCD @ 1nos 1200mm x 600mm(FS)
@2500CMH EACH

15.88mm x 9.52mm
1200mm x 200mm(FS)
200mm x 200mm @200CMH EACH S.F.L +47'-4"
S.F.L +47'-4" 2 SLOT LRBG c/w VCD @ 2nos
1200mm x 600mm(FS)
300mm x 300mm

CONTROLS BY JOHNSON
YORK

R
@2000CMH EACH

Walk-inA/P
Wardrobe
NET WGT - KG
144 LOCATION
15.88mm x 9.52mm

15.88mm x 9.52mm
14'-8"

FCU-HD-06
16KW
YANGON
47'-11"

15.88mm x 9.52mm
A/P
NET WGT - KG FCU-HD-05
14.2KW
PROJECT TITLE
Vent Hood

125 YORK
BY JOHNSON CONTROLS
R

@100mm DIA;

Circulation YAY TAR SHAY - FIVE STORIES


A/P
Walk-in Wardrobe
400mm x 300mm

EAF-CM FCU-HD-07 144


400CMH 16KW NET WGT - KG

A/P

R
NET WGT - KG YORK

Bath & WC
CONTROLS BY JOHNSON

ARCHITECT
3
6.5

FCU-HD-04
14.2KW 2 SLOT LRBG c/w VCD @ 1nos
22 R @ 0' - 6 1/4" 2 SLOT LRBG c/w VCD @ 2nos
1200mm x 600mm(FS)
NET WGT - KG
F.F.L +47'-6"
UP
R

YORK

1200mm x 600mm(FS)
BY JOHNSON CONTROLS

125
@12000CMH EACH
@2400CMH EACH

DN

400mm x 300mm
S.F.L +47'-4"
300mm x 300mm SAD
400mm x 300mm
Walk-in Wardrobe
Y LINE

Master Bed Rm STRUCTURE

S.F.L +47'-0"
F.F.L +47'-2"
F.F.L +47'-6"
19'-6"

300mm x 300mm
C S.F.L +47'-4"
2 SLOT LSBG c/w VCD @ 5nos A

Balcony
F.F.L +47'-6" 300mm x 300mm SAD Stair
2 SLOT LSBG c/w VCD @ 4nos

LINE
1200mm x 200mm(FS) 1200mm x 200mm(FS)
@700CMH EACH @800CMH EACH

1 S.F.L +47'-4" Shrine SEC


A-603 Area Master Bed Rm 4-001
SITE BOUNDAR

3
NET WGT - KG
6.5

Bath & WC

Y
EAF-CM

2
1
400CMH
M&E ENGINEER

SITE BOUNDAR
4
2 SLOT LSBG c/w VCD @ 6nos
1200mm x 200mm(FS)

@100mm DIA;
@500CMH EACH

STAIR-2
4 M&E CONTRACTOR
6'-0"

Vent Hood

SEC
B 4-002 PEARL ROYAL Co., Ltd.
Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
SITE BOUNDARY LINE SITE BOUNDARY LINE Ph: 09-420084410, Email: pearlroyal@contractor.net

FOURTH FLOOR PLAN DRAWING TITLE

ACMV DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI NE

Y LINE
RY
SITE BOUNDA
1"
7'-52

Y LINE
SITE BOUNDAR

SITE BOUNDAR
TENDER DRAWING
3'-11"

SEC
B
LINE

4-002 REVISION

1 A A NO DATE DESCRIPTION
Y

SEC STAIR-1
SYSTEM - I SEC
SITE BOUNDAR

4-001 NET WGT - KG NET WGT - KG NET WGT - KG


SYSTEM - II 4-001
DN

AC & FIRE
327+240+240 327+240 327+327
SYSTEM - III
Lift

SYSTEM - V ( 14HP + 14HP )


SYSTEM - IV ( 14HP + 12HP )
31.75mm x 19.05mm
SYSTEM - III ( 14HP + 12HP +12HP)

SYSTEM - IV
Stair SYSTEM - V
machine
13'-9"

31.75mm x 19.05mm
Area
room 38.1mm x 19.05mm

ELE & ELV


20 R @ 0' - 6 7/8" 28.58mm x 12.7mm

31.75mm x 19.05mm

TENDER DRAWING

F.F.L +58-8" OWNER / DEVELOPER


2 S.F.L +58'-6" NET WGT - KG
327+327
NET WGT - KG
327+240
SYSTEM - II ( 14HP + 14HP )

Overhead Water Tank and Fire Fighting Tank Area


SYSTEM - I ( 14HP + 12HP )

LOCATION
14'-8"

YANGON
47'-11"

PROJECT TITLE

YAY TAR SHAY - FIVE STORIES


WaterTank WaterTank
3 ARCHITECT
Y LINE
19'-6"

STRUCTURE
A A

Y LINE
SEC SEC
4-001 4-001
SITE BOUNDAR

2
1

SITE BOUNDAR
M&E ENGINEER

4
4
6'-0"

M&E CONTRACTOR

SEC
B 4-002
PEARL ROYAL Co., Ltd.
Block-C, Room-802,8th Floor,Yadanar Housing,
SITE BOUNDARY LINE SITE BOUNDARY LINE 13Rd Quarter, South Okkalapa Township, Yangon.
Ph: 09-420084410, Email: pearlroyal@contractor.net

FIFTH FLOOR PLAN DRAWING TITLE

ACMV DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


+75'-6" FFL
Lift Machine Roof Level

Cooling: 63.3kW
Cooling: 70.4kW
+72'-0" FFL
Heating: 0.0kW Cooling: 101.9kW Cooling: 67.5kW Cooling: 76.4kW
Heating: 0.0kW
Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW
SYS1 [JTOH260VPEM-0AQ1]
SYS2 [JTOH280VPEM-0AQ1] SYS3 [JTOH380VPEM-0AQ1] SYS4 [JTOH260VPEM-0AQ1]
Roof Level
JTOH140VPEM-0AQ1 JTOH120VPEM-0AQ1 SYS5 [JTOH280VPEM-0AQ1]
JTOH140VPEM-0AQ1 JTOH140VPEM-0AQ1 JTOH140VPEM-0AQ1 JTOH120VPEM-0AQ1 JTOH120VPEM-0AQ1 JTOH140VPEM-0AQ1 JTOH120VPEM-0AQ1 JTOH140VPEM-0AQ1 JTOH140VPEM-0AQ1

0.5m 1m
f25.4mm f25.4mm 0.5m 0.5m 1m
0.5m 1m
f12.7mm f12.7mm f25.4mm f25.4mm f25.4mm f25.4mm f25.4mm
JM-30SNQE f12.7mm f12.7mm f12.7mm f25.4mm f25.4mm f25.4mm f25.4mm
f12.7mm f12.7mm 0.5m
f12.7mm 1m
f12.7mm 0.5m
f12.7mm 1m
f12.7mm
JM-30SNQE JM-30SNQE

0.5m
f28.58mm JM-30SNQE JM-30SNQE JM-30SNQE
f15.88mm
+62'-0" FFL
5th Floor Level
f31.75mm JE-302SNQ JE-162SNQ JE-102SNQ
f19.05mm Piping Correction Factor(Cooling): 0.933
23m
f28.58mm f22.2mm Piping Correction Factor(Heating): 0.968
f25.4mm f12.7mm f9.52mm
f12.7mm JE-162SNQ Additional Refrigerant Charge: 10.8kg
6m 6m
5m
Ind23 Ind24 Ind25 Gas pipe : Red
Ind21 Ind22
JTDH160H0NN0AQ JTDH160H0NN0AQ JTDH142H0NN0AQ JTDH160H0NN0AQ JTDH142H0NN0AQ Liquid pipe : Green
TENDER DRAWING
f15.88mm f15.88mm f15.88mm f15.88mm f15.88mm
f9.52mm f9.52mm f9.52mm f9.52mm f9.52mm REVISION
5.5m 6.5m 5.5m 8m
Cooling: 16.4kW Cooling: 16.4kW Cooling: 13.6kW Cooling: 16.4kW Cooling: 13.6kW
Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW
NO DATE DESCRIPTION
7.5m
Sensible Cooling: 11.9kW Sensible Cooling: 11.9kW Sensible Cooling: 9.8kW Sensible Cooling: 11.9kW Sensible Cooling: 9.8kW
+50'-6" FFL
JE-302SNQ JE-162SNQ JE-162SNQ JE-102SNQ
Piping Correction Factor(Cooling): 0.928
4th Floor Level
f31.75mm f28.58mm f25.4mm f19.05mm Piping Correction Factor(Heating): 0.966
f19.05mm f22.2mm f12.7mm f12.7mm f9.52mm
25m f9.52mm JE-102SNQ 3m 5.5m 4.5m Additional Refrigerant Charge: 10.9kg
2m
Gas pipe : Red
Ind15 Ind16 Ind17 Ind18 Ind19 Ind20
JTDM056H0NN0AQ JTDH142H0NN0AQ JTDH090H0NN0AQ JTDH142H0NN0AQ Liquid pipe : Green
JTDH142H0NN0AQ JTDH142H0NN0AQ

f15.88mm f15.88mm f15.88mm f15.88mm f15.88mm f15.88mm TENDER DRAWING


f9.52mm f9.52mm f6.35mm f9.52mm f9.52mm f9.52mm
4m 12.8m 3m 6.5m 7m 7m
Cooling: 5.3kW Cooling: 13.3kW Cooling: 8.8kW Cooling: 13.3kW
Cooling: 13.3kW Cooling: 13.3kW OWNER / DEVELOPER
Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW
Sensible Cooling: 9.6kW Sensible Cooling: 9.6kW Sensible Cooling: 3.8kW Sensible Cooling: 9.6kW Sensible Cooling: 6.2kW Sensible Cooling: 9.6kW

+39'-0" FFL

JE-302SNQ JE-302SNQ JE-242SNQ


3rd Floor Level LOCATION

f38.1mm f31.75mm f28.58mm Piping Correction Factor(Cooling): 0.913


f19.05mm Ind11 f19.05mm Ind12 f15.88mm Ind13 Ind14 YANGON
Piping Correction Factor(Heating): 0.959
30m JTDH280H0NM0AQ 3m JTDH280H0NM0AQ 5m JTDH224H0NM0AQ JTDH280H0NM0AQ
Additional Refrigerant Charge: 17.0kg
f22.2mm f22.2mm f19.05mm f22.2mm
Gas pipe : Red
f9.52mm f9.52mm
7.5m
f9.52mm f9.52mm PROJECT TITLE
6m 3m 16m
Liquid pipe : Green

Cooling: 26.8kW Cooling: 26.8kW Cooling: 21.5kW Cooling: 26.8kW YAY TAR SHAY - FIVE STORIES
Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW
Sensible Cooling: 18.9kW Sensible Cooling: 18.9kW Sensible Cooling: 15.4kW Sensible Cooling: 18.9kW

ARCHITECT

+27'-6" FFL
JE-302SNQ JE-242SNQ
Piping Correction Factor(Cooling): 0.916 2nd Floor Level
f31.75mm f28.58mm
f19.05mm f19.05mm f15.88mm Piping Correction Factor(Heating): 0.960
33m f9.52mm JE-102SNQ JE-102SNQ 3.5m
4.5m Additional Refrigerant Charge: 14.6kg

f19.05mm Gas pipe : Red STRUCTURE


Ind6 f9.52mm Ind7 Ind8 Liquid pipe : Green
2.5m Ind9 Ind10
JTDM071H0NN0AQ JTDH090H0NN0AQ JTDM071H0NN0AQ
f15.88mm f15.88mm f15.88mm JTDH224H0NM0AQ JTDH280H0NM0AQ
f9.52mm f9.52mm f9.52mm
7.5m 3.6m 4.5m

f19.05mm f22.2mm
f9.52mm f9.52mm
3m 16.5m
Cooling: 6.7kW Cooling: 8.8kW Cooling: 6.7kW
Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW Cooling: 21.4kW Cooling: 26.8kW M&E ENGINEER
Sensible Cooling: 4.7kW Sensible Cooling: 6.2kW Sensible Cooling: 4.7kW Heating: 0.0kW Heating: 0.0kW
Sensible Cooling: 15.3kW Sensible Cooling: 18.9kW

+16'-0" FFL
JE-302SNQ JE-102SNQ JE-102SNQ

f31.75mm f22.2mm f15.88mm Piping Correction Factor(Cooling): 0.899


First Floor Level
f19.05mm f9.52mm f9.52mm
f25.4mm Piping Correction Factor(Heating): 0.952
38m 9.5m 4m
f12.7mm JE-162SNQ
4m Ind3 Ind4 Ind5 Additional Refrigerant Charge: 14.9kg M&E CONTRACTOR
JTDH142H0NN0AQ JTDM056H0NN0AQ JTDM071H0NN0AQ
Gas pipe : Red
Ind1 Ind2
JTDH142H0NN0AQ JTDH280H0NM0AQ Liquid pipe : Green
f15.88mm f15.88mm f15.88mm PEARL ROYAL Co., Ltd.
f9.52mm f6.35mm f9.52mm
6m 3m 10m Block-C, Room-802,8th Floor,Yadanar Housing,
f15.88mm f22.2mm
f9.52mm f9.52mm Cooling: 12.9kW Cooling: 5.2kW Cooling: 6.5kW 13Rd Quarter, South Okkalapa Township, Yangon.
7m 5m Heating: 0.0kW Heating: 0.0kW Heating: 0.0kW
Cooling: 12.9kW Cooling: 25.8kW Sensible Cooling: 9.3kW Sensible Cooling: 3.7kW Sensible Cooling: 4.5kW Ph: 09-420084410, Email: pearlroyal@contractor.net
Heating: 0.0kW Heating: 0.0kW
Sensible Cooling: 9.3kW Sensible Cooling: 18.2kW
DRAWING TITLE
+3'-0" FFL
ACMV - VRF SCHEMATIC
Ground Floor Level

DRAWING NO.
REV - II

VRF SYSTEM SCHEMATIC DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


SCHEDULE OF NECK SIZE FOR GRILLES AND DIFFUSERS

AIR QUANTITY ( CMH ) NECK SIZE ( mm x mm )


0 - 68 100 X 100
69 - 162 150 X 150
163 - 280 200 X 200
250 X 250

X
281 - 442
A A 443 - 638 300 X 300

Y
639 - 867 350 X 350
868 - 1130 400 X 400
1131 - 1435 450 X 450
1436 - 1768 500 X 500
1769 - 2250 550 X 550
NOTES:
1) ALL FACE SIZE (DIFFUSER & GRILLE SIZE) TO BE 600 X 600 MM
TO SUIT CEILING PATTERN UNLESS OTHERWISE STATED
- ALL FACE VELOCITY NOT MORE THAN 2.5 M/S ( 500 FPM ).

2) ALL DIFFUSERS & GRILLES SHALL BE ANODIZED ALUMINUM TYPE


AND C/W OPPOSED BLADE VOLUME CONTROL DAMPER.
ALL DIFFUSER & GRILLE FACE COVERS SHALL BE
DETACHABLE TYPE FOR MAINTENANCE PURPOSES.

o o

50mm

TENDER DRAWING

REVISION

NO DATE DESCRIPTION

1 1
4 7

1 1
TENDER DRAWING
4 7

35°
OWNER / DEVELOPER

EQ EQ

1200

LOCATION

YANGON
25 MM THK. FIBERGLASS ACOUSTICAL
NOTE:
DUCT LINER WITH NEOPRENE SURFACE COATING
ALL DUCTS AT PLANT ROOM AND THOSE
EXPOSED TO WEATHER SHALL BE COVERED
W/ GAGE 26 ALUMINUM SHEET CLADDING.
WASHER GAGE 24 G.I. SHEET MECHANICAL CLIPS DUCT
152.4 WIDE GALVANIZED
STEEL CORNER BEAD PLASTIC STRAP BAND
WITH WASHER ADHERED TO DUCT (TYPICAL)
PROJECT TITLE
25.4mm THICK INSULATION
W/ FIRE RESISTANT GLASS FABRIC
TAPE 1
VAPOR BARRIER

YAY TAR SHAY - FIVE STORIES


ALL ENDS OF LINER TO BE
G.I. WIRE MESH WITH TREATED WITH ADHESIVE
25mm x 25mm (1" x 1") OPENING
NOT MORE THAN 75mm(3")
NON-FLAMMABLE FROM EDGE OF LINER
METAL SEALER
OVER ALL JOINTS NOTES: ARCHITECT
& MECH'L CLIP
PERFORATION
1. INSTALL SURFACE W/ NEOPRENE COATING ON AIR STREAM SIDE TYPICAL INSTALLATION DETAIL FOR FAN
TYPICAL DETAIL FOR CONDENSATE DRAIN PIPE CONNECTION TO FLOOR TRAP
MECHANICAL NON-FLAMMABLE 2. APPLY ADHESIVE ON 100% OF DUCT SURFACE FOR ATTACHMENT
CLIPS 30 O.C.B.W. ADHESIVE MASTIC OF THE ACOUSTICAL DUCT LINER
TYPICAL FLEXIBLE DUCT SUPPORTING DETAIL DUCT INSULATION DETAIL ACOUSTICAL DUCT LINER MOUNTING DETAIL

75(MINI)
45

--------- ---------

SCHEDULE OF FLEXIBLE DUCT DETAIL - A


A B
STRUCTURE

75 75
45 MINI

WALL SUPPORT DETAIL TYPICAL HANGER DETAIL FOR DUCTING


TYPICAL INSTALLATION DETAIL FOR AIR GRILLES/DIFFUSERS
ON EXPOSED T-GRID REMOVABLE CEILING PANELS
M&E ENGINEER

M&E CONTRACTOR

FLOOR SLAB

PEARL ROYAL Co., Ltd.


FAN COIL UNIT
(DUCTED TYPE) Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
FALSE CEILING
Ph: 09-420084410, Email: pearlroyal@contractor.net
REFER DETAIL 'A'

DRAWING TITLE
TYPICAL LINEAR DIFFUSER
FALSE CEILING INSTALLATION DETAIL
DETAIL 'A'

DETAIL

DRAWING NO.

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


GENERAL NOTES
LEGEND 1. THE REQUIREMENTS FOR PENETRATIONS THROUGH R.C BEAMS , WALLS , FLOOR SLABS ETC.
SHALL BE SUBMITTED IN ADVANCE TO THE STRUCTURAL ENGINEER FOR APPROVAL PRIOR TO
CONSTRUCTION . ANY COST OF REMEDIAL WORKS ARISING FROM FAILURE TO DO SO SHALL
BE BORNE BY THE FIRE PROTECTION CONTRACTOR .

2. THE FIRE PROTECTION CONTRACTOR SHALL CO-ORDINATE WITH OTHER SERVICES FOR RUNNING
OF PIPES / CABLES .

PLAN SCHEMATIC 3. THE ACTUAL POSITION OF ALL FIRE HYDRANTS / HOSE REEL / DRY RISER /
SHALL BE BASED ON ARCHITECT'S APPROVED BUILDING PANS.

4. THE DRY / WET RISING MAIN SHALL BE INSTALLED PROGRESSIVELY AS THE BUILDING GAINS
HEIGHT DURING THE COURSE OF CONSTRUCTION , C/W LANDING VALVES , AIR RELEASE VALVE
AND FIRE BRIGADE INLETS AND SHALL BE MAINTAINED IN AN OPERATIONAL CONDITION.
SPRINKLER ( PENDENT TYPE ) SPRINKLER
5. ELECTRICAL WORKS SHALL BE CARRIED OUT IN ACCORDANCE WITH CP 5 .

SPRINKLER ( SIDE WALL TYPE )


HOSE REEL
EXTERNAL FIRE HYDRANT , DRY RISER AND HOSE REEL SYSTEM
HOSE REEL 1. THE EXTERNAL FIRE HYDRANT, DRY RISER AND HOSE-REEL SYSTEM SHALL BE DESIGNED ,
INSTALLED AND TESTED IN ACCORDANCE WITH THE ACCEPTED CODE OF PRACTICE SINGAPORE TENDER DRAWING
STANDARD SS 575;2012 AND HANDBOOK ON FIRE CODE 2013 CHAPTER 6 .
2 WAY BREECHING INLET REVISION
FIRE HYDRANT
2. PIPES AND FITTINGS
NO DATE DESCRIPTION
a) PIPES MATERIAL / STANDARDS ;
(1) DRY RISING MAIN SHALL BE GALVANIZED STEEL TO BS 1387 ( HEAVY GRADE ) .
5
2 WAY BREECHING INLET LANDING VALVE (2) HOSE REEL PIPES SHALL BE GALVANIZED STEEL TO BS 1387 ( MEDIUM GRADE ) .
b) THE FIRE TRADE CONTRACTOR SHALL INCLUDE IN THIS CONTRACT , ALL EXPOSED PIPES 4
TO BE PAINTED SUBJECT TO FSSD APPROVAL .
3
c) APPROVED MECHANICAL COUPLING FITTINGS SHALL BE USED FOR DRY RISING MAIN AND
LANDING VALVE 3KG ABC DRY POWDER FIRE EXTINGUISHER HOSE REEL PIPES. THE RATING OF FITTINGS SHALL BE CAPABLE TO WITHSTAND THE SYSTEM 2
WORKING PRESSURE. ALL VALVES 65MMDIA; AND ABOVE SHALL BE FLANGED TO BS4504.
1
d) THE FIRE TRADE CONTRACTOR SHALL INCLUDE THE FOLLOWING PROVISION FOR ALL FIRE SERVICES
AND NOT LIMITED TO ; 0 TENDER DRAWING
4.5KG ABC DRY POWDER FIRE EXTINGUISHER
(1) DRAIN VALVES SHALL BE PROVIDED AT EACH TRAP SECTION OF PIPING SYSTEM
CHECK VALVE TO MEET THE LATEST RELEVANT FIRE CODE REQUIREMENTS. OWNER / DEVELOPER

(2) ALL DRAIN COCKS SHALL BE STRAPPED AND PADLOCKED WITH MASTER KEY LOCK IN ''CLOSED" POSITION.

CHECK VALVE (3) AUTOMATIC AIR RELEASE VALVE SHALL BE PROVIDED AT THE HIGHEST POINT OF EACH INSTALLATION . ( DRY RISER SYSTEM )
GATE VALVE
(4) ALL SYSTEM DRAINAGE SHALL BE DISCHARGED TO OPEN DRAIN .
LOCATION
MILD STEEL CABINETS SHALL BE STAINLESS STEEL.

GATE VALVE M
3. FIRE SERVICES BREECHING INLETS YANGON
4. FIRE SERVICES INLET OF 100MMDIA; 2-WAY OR 4-WAY C/W CHECK VALVES SHALL BE
MODULATING VALVE
PROVIDED TO SUPPLEMENT WATER SUPPLY TO EACH DRY RISER MAN .
INDIVIDUAL EARTHING PIT SHALL BE PROVIDED FOR EACH BREECHING INLETA . PROJECT TITLE
M THE GRAVITY FEED PIPING SYSTEM ALSO SHALL BE INDIVIDUALLY ELECTRICAL EARTHED .
MODULATING VALVE PRV LIGHTING PROTECTION SHALL BE PROVIDED WHERE RISING MAIN INSTALLED AT THE
PRESSURE RELEASE VALVE HIGHEST FLOOR / OPEN ROOF AREA .

5. FIRE RATING ENCLOSURE ARCHITECT


PRV
a) 2 HRS , FIRE RATING CONSTRUCTION SHALL BE PROVIDED WHERE DRY RISING
PRESSURE RELEASE VALVE RUNS OUTSIDE THE COMPARTMENT SHAFT .
FS
FLOW SWITCH b) THE FIRE TRADE CONTRACTOR SHALL ENSURE NO OTHER M&E SERVICES ARE INSTALLED
ABOVE THE FIRE RATED PIPES

FS 6. TYPE OF CABINETS FOR THE FOLLOWING SHALL BE PROVIDED ;


FLOW SWITCH a) MILD STEEL CABINET FOR ALL BREECHING INLET STRUCTURE
b) ELECTRO-GALVANIZED CABINET FOR AL EXPOSED HOSE-REELS
FLEXIBLE CONNECTOR c) WEATHER PROOF CABINET FOR ALL STEEL CABINETS EXPOSED TO WEATHER ( Eg ; ROOF , ETC )
d) ELECTRO-GALVANIZED CABINET FOR ALL EXPOSED STANDBY FIRE HOSES.
FLEXIBLE CONNECTOR
7. CONCRETE PLINTH FOR TANKS AND PUMPS INCLUDING STUMP FOR PIPE SUPPORT AND M.S
AUTOMATIC AIR RELEASE VALVE PLATFORM SHALL BE PROVIDED BY THE MAIN CONTRACTOR ( BUILDER )
M&E ENGINEER
8. WATER TANK
FIRE PUMP a) EFFECTIVE WATER CAPACITY SHALL BE STATED AT THE SIDE OF THE TANK.
b) THE FIRE TRADE CONTRACTOR SHALL INCLUDE IN THIS CONTRACT ALL THE TANK ACCESSORIES SUCH AS VALVES , PIPES,
FITTINGS , LEVEL INDICATORS AND LABELLING ; ETC .
FIRE HOSE REEL PUMP
c) WARNING AND INSTRUCTION SIGN PLATE INCLUDING AND LABELLING ; ETC;
M&E CONTRACTOR
PRESSURE VESSEL 9. MONITORED ISOLATOR VALVES
a) ALL MONITORED ISOLATION VALVES SHALL BE LINKED TO MAIN ALARM PANEL (MAP) TO GIVE A AUDIO
AND VISUAL INDICATION AT FIRE COMMAND CENTER PINPOINTING THE VALVE IS CLOSED .
FIRE SPRINKLER PUMP 10. TO PROVIDE DRAIN VALVE AT EACH TRAP-SECTION OF DRY RISER MAIN.
PEARL ROYAL Co., Ltd.
Block-C, Room-802,8th Floor,Yadanar Housing,
SPRINKLER PIPE
13Rd Quarter, South Okkalapa Township, Yangon.
11. FIRE HYDRANT AND DRY RISER SYSTEM SHALL BE TESTED HYDROSTATICALLY AT 13.8 BAR PRESSURE
FOR 2 HOURS OR AT 3.5 BAR IN EXCESS OF 10.3 BAR. THE HYDROSTATIC TEST PRESSURE SHALL BE Ph: 09-420084410, Email: pearlroyal@contractor.net
MEASURED AT THE LOWEST POINT OF THE SYSTEM.

PRESSURE VESSEL DRAWING TITLE


HOSE-REEL PIPE
FIRE FIGHTING SYSTEM
LEGENDS
HYDRANT PIPE FIRE HYDRANT
DRAWING NO.

DESIGNED BY HPT

CHECKED BY HL

DATE
TENDER DRAWING

REVISION

NO DATE DESCRIPTION

5
PENDENT WITH ESCUTHCION PLATE TYPICAL INSTALLATION OF PENDENT TYPE UPRIGHT SPRINKLER HEAD DETAIL
SPRINKLER HEAD DETAIL SPRINKLER HEAD ON AREAS W/OUT CEIL.ING TYPICAL SIDE WALL TYPE TYPICAL RECESSED PENDENT TYPE TYPICAL CUT-OFF SPRINKLER DETAIL SPRINKLER IN SPACE & BELOW CEILING
4

NOTE: 3

ACTUATOR COVER
2
MOUNTING PLATE

NUT (TYPICAL)

DIRECTION OF FLOW 1
PIPE ARROW
SADDLE

0 TENDER DRAWING
MAXIMUM ALLOWABLE
DISTANCE OF DEFLECTOR VANE
DISTANCE FROM SPRINKLER TO ABOVE BOTTOM OF
BRANCHLINE
SIDE OF OBSTRUCTION (A) OBSTRUCTION (in.) (B)
LESS
1 ft.
THAN 1 FEET (305 mm)
(305 mm) TO LESS THAN 1 ft. 6 in. (457.2 mm) 2
0
1/2 (63 mm)
OWNER / DEVELOPER
1 ft. 6 in. (457.2 mm) TO LESS THAN 2 ft. (610 mm) 3 1/2 (89 mm)
2 ft. (610 mm) TO LESS THAN 2 ft. 6 in. (762 mm) 5 1/2 (140 mm)
2 ft. 6 in. (762 mm) TO LESS THAN 3 ft. (915 mm) 7 1/2 (190 mm)
FEEDMAN
3 ft. (915 mm) TO LESS THAN 3 ft. 6 in. (1066.8 mm) 9 1/2 (241 mm) PIPE
3 ft. 6 in. (1066.8 mm) TO LESS THAN 4 ft. (1220 mm) 12 (305 mm)
4 ft. (1220 mm) TO LESS THAN 4 ft. 6 in. (1371.6 mm) 14 (355 mm)

DRAIN

TEST
4 ft. 6 in. (1371.6 mm) TO LESS THAN 5 ft. (1525 mm) 16 1/2 (419 mm)

DRAIN

TEST
5 ft. (1525 mm) TO LESS THAN 5 ft. 6 in. (1676.4 mm) 18 (457 mm)
5 ft. 6 in. (1676.4 mm) TO LESS THAN 6 ft. (1830 mm) 20 (508 mm)
6 ft.
6 ft.
(1830 mm) TO LESS THAN 6 ft. 6 in. (1981.2 mm)
6 in. (1981.2 mm) TO LESS THAN 7 ft. (2135 mm)
24 (610 mm)
30 (762 mm)
LOCATION
7 ft. (2135 mm) TO LESS THAN 7 ft. 6 in. (2286 mm) 35 (889 mm)

YANGON
BRANCH TO SPRINKLLER CONNECTION DETAIL INSTALLATION OF SPRINKLER HEAD NEAR FIXED OBSTRUCTION TYPICAL DETAIL OF 4.5 kg. (10 LBS.) PORTABLE FLOOR CONTROL VALVE ASSEMBLY FLOW SWITCH INSTALLATION DETAIL
ACCEPTABLE TYPE OF HANGERS
EXTINGUISHER MOUNTING
PROJECT TITLE

ARCHITECT

STRUCTURE

SECTIONAL ELEVATION OF HYDRANT WATER STORAGE TANK WET RISER LANDING VALV WITHIN THE SHAFT
ALARM GONG DETAIL C/W SLOPING ROOF

M&E ENGINEER

M&E CONTRACTOR

PEARL ROYAL Co., Ltd.


FRONT VIEW SIDE VIEW Block-C, Room-802,8th Floor,Yadanar Housing,
FRONT VIEW SIDE VIEW
13Rd Quarter, South Okkalapa Township, Yangon.
FIRE HYDRANT INSTALLATION DETAIL Ph: 09-420084410, Email: pearlroyal@contractor.net

TYPICALSPRINKLER CONTROL VALVE INSTALLATION TYPICAL PIPE HANGER IN PUMP ROOM TYPICAL INSTALLATION FOR HOSEREEL, ALARM BELL & DETAIL OF 2 WAY FIRE DEPARTMENT CONNECTION DRAWING TITLE
MANUAL CALL POINT

FIRE FIGHTING SYSTEM


DETAIL

DRAWING NO.

DESIGNED BY HPT

CHECKED BY HL

DATE
A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
N D A R Y
SITE BOU
1"
7'-52

TENDER DRAWING
Y LINE
SITE BOUNDAR

SITE BOUNDAR
REVISION
3'-11"

1 NO DATE DESCRIPTION
A
Y LINE

A-601

1 B B
1 1
SITE BOUNDAR

AC & FIRE
A-602 A-602

STAIR-1
13'-9"

LIFT

ELE & ELV


3 4 TENDER DRAWING

NET WGT - KG OWNER / DEVELOPER


19.4

2
5
LOCATION

YANGON
14'-8"
47'-11"

PROJECT TITLE
M&E RM
6 F.F.L -9'-0" YAY TAR SHAY - FIVE STORIES
CAR PARKING
S.F.L -9'-2"
ARCHITECT

STRUCTURE
Y LINE

2
19'-6"

C Ramp Slope = 1:6.5 C

LINE
1 1
A-603 A-603
SITE BOUNDAR

3
F.F.L -9'-0" M&E ENGINEER

Y
S.F.L -9'-2"

2
1

SITE BOUNDAR
1

4
M&E CONTRACTOR
4
CAR PARKING - 6 NOS
6'-0"

PEARL ROYAL Co., Ltd.


Block-C, Room-802,8th Floor,Yadanar Housing,
1 13Rd Quarter, South Okkalapa Township, Yangon.
A A-601 Ph: 09-420084410, Email: pearlroyal@contractor.net

SITE BOUNDARY LINE SITE BOUNDARY LINE


DRAWING TITLE

BASEMENT FLOOR PLAN FIRE FIGHTING DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
RY
SITE BOUNDA
1"
7'-52

TENDER DRAWING
Y LINE
SITE BOUNDAR

SITE BOUNDAR
REVISION
3'-11"

1 NO DATE DESCRIPTION
A
Y LINE

A-601

1 B B
1 STAIR-1 1

AC & FIRE
SITE BOUNDAR

A-602 A-602
1
WC Director Rm Stair Area
13'-9"

Vault Lift

Reception
249 SF

ELE & ELV


18 R @ 0' - 6" TENDER DRAWING

F.F.L ±0'-0" F.F.L ±0'-0" OWNER / DEVELOPER


S.F.L - 0'-2" S.F.L - 0'-2"
23 R @ 0' - 6"
2
Manager Rm NET WGT - KG
19.4

LOCATION
F.F.L ±0'-0" F.F.L -3'-0"
S.F.L - 0'-2" S.F.L -3'-2" YANGON
14'-8"

2
Shop Area(Gold & Diamond) R - 0' 6"
47'-11"

PROJECT TITLE
F.F.L ±0'-0" T - 1' 0"
S.F.L - 0'-2" F.F.L ±0'-0" YAY TAR SHAY - FIVE STORIES
S.F.L - 0'-2"
ARCHITECT

3 Staff Dinning
Rm

MAIN ENTRANCE
STRUCTURE
Y LINE

(IN/OUT)
19'-6"

C Ramp Slope = 1:6.5 C

Y LINE
1 1
A-603 A-603
SITE BOUNDAR

3
WC M&E ENGINEER

2
1

SITE BOUNDAR
23 R @ 0' - 6 "

4
STAIR-2
UP Stair
Area M&E CONTRACTOR
4
6'-0"

PEARL ROYAL Co., Ltd.


Block-C, Room-802,8th Floor,Yadanar Housing,
1 13Rd Quarter, South Okkalapa Township, Yangon.
A A-601 Ph: 09-420084410, Email: pearlroyal@contractor.net

SITE BOUNDARY LINE SITE BOUNDARY LINE


DRAWING TITLE

GROUND FLOOR PLAN FIRE FIGHTING DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
A R Y
SITE BOUND
1"
7'-52

TENDER DRAWING
RY LINE
SITE BOUNDA

SITE BOUNDAR
REVISION
3'-11"

1 NO DATE DESCRIPTION
A
Y LINE

A-601

1 B B
1 1

S.F.L+12'-10"

AC & FIRE
STAIR-1
SITE BOUNDAR

F.F.L+13'-0"
A-602 A-602
+13'-0" Bath & WC

Bath & WC
Master Bed
13'-9"

Lift Stair Area


Rm Balcony

F.F.L+12'-10"

ELE & ELV


S.F.L+12'-8"
F.F.L +12'-8"
20 R@ 0'-6 7/8" Hall TENDER DRAWING
Kitchen NET WGT - KG
19.4
S.F.L - 12'-6"
F.F.L +13'-0" OWNER / DEVELOPER
Store Rm S.F.L - 12'-10"

2
F.F.L±12'-8"
S.F.L-12'-6"

LOCATION
F.F.L +13'-0"
Wide Passageway
YARD

S.F.L +12'-10" YANGON


14'-8"

Family Rm
F.F.L +13'-0"
47'-11"

PROJECT TITLE

Bath & WC S.F.L +12'-10"


YAY TAR SHAY - FIVE STORIES

ARCHITECT

20 R @ 0' - 6 7/8"
F.F.L +13'-0"
STRUCTURE
Stair Area S.F.L +12'-10"
Y LINE

Study Rm
19'-6"

C Master Bed Rm C

Y LINE
1
Living Area 1
A-603 A-603
SITE BOUNDAR

3
M&E ENGINEER

2
1

SITE BOUNDAR
Balcony

4
STAIR-2 F.F.L +12'-8"
S.F.L +12'-6"
M&E CONTRACTOR
4
6'-0"

SEC PEARL ROYAL Co., Ltd.


B 4-002 Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
Ph: 09-420084410, Email: pearlroyal@contractor.net

SITE BOUNDARY LINE SITE BOUNDARY LINE


DRAWING TITLE

FIRST FLOOR PLAN FIRE FIGHTING DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
RY
SITE BOUNDA
1"
7'-52

TENDER DRAWING
Y LINE
SITE BOUNDAR

SITE BOUNDAR
REVISION
3'-11"

1 NO DATE DESCRIPTION
A
Y LINE

A-601

1 B A
1 SEC
STAIR-1

AC & FIRE
SITE BOUNDAR

A-602 4-001

Stair Area
S.F.L +24'-0"
F.F.L +24'-2"
13'-9"

lift

ELE & ELV


yard
TENDER DRAWING
Kitchen
20 R @ 0' - 6 7/8"
NET WGT - KG
19.4 OWNER / DEVELOPER

2
S.F.L - 24'-0"
F.F.L +24'-2"

LOCATION
Yard

Circulation
Wide Passageway
Living Area YANGON
14'-8"

F.F.L +24'-6"
47'-11"

S.F.L +24'-4" PROJECT TITLE

Bath & WC
YAY TAR SHAY - FIVE STORIES

ARCHITECT

3
Stair Area Bath & WC

DN STRUCTURE
R @ 0' - 6 7/8"

UP Master Bed Rm
Y LINE

Balcony
S.F.L - 24'-0"
F.F.L +24'-2"
19'-6"

C C

S.F.L +24'-0"
F.F.L +24'-2"

Y LINE
1 1
A-603 Master Bed Rm A-603
SITE BOUNDAR

3
M&E ENGINEER
Balcony

2
1

SITE BOUNDAR
20

4
STAIR-2 M&E CONTRACTOR
4
6'-0"

PEARL ROYAL Co., Ltd.


1 Block-C, Room-802,8th Floor,Yadanar Housing,
A A-601 13Rd Quarter, South Okkalapa Township, Yangon.
Ph: 09-420084410, Email: pearlroyal@contractor.net

SITE BOUNDARY LINE SITE BOUNDARY LINE


DRAWING TITLE

SECOND FLOOR PLAN FIRE FIGHTING DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

Y LINE
N D A R Y
SITE BOU
1"
7'-52

TENDER DRAWING
Y LINE
SITE BOUNDAR

SITE BOUNDAR
REVISION
3'-11"

1 NO DATE DESCRIPTION
A
Y LINE

A-601
20 R @ 0' - 6 7/8"
1 B A
1 Bath & WC Laundary SEC

AC & FIRE
STAIR-1
SITE BOUNDAR

A-602 4-001
& Yard DN
Sauna Bath & WC

S.F.L +35'-10"
13'-9"

Stair Area

F.F.L +36'-0"
lift
Maid Rm

ELE & ELV


UP
TENDER DRAWING

S.F.L +35'-6"
F.F.L +35'-8"
NET WGT - KG
19.4

OWNER / DEVELOPER
Lift Lobby Walk-in Wardrobe
Home Theater
F.F.L +36'-0"
2 S.F.L +35'-10"

Shoe Cabinet
LOCATION

S.F.L +35'-10"
F.F.L +36'-0"
Wet Kitchen
Powder Rm

F.F.L +36'-0" YANGON


14'-8"

S.F.L +35'-10" Master Bed Rm


S.F.L +34'-10"

F.F.L +36'-0"
F.F.L +35'-0"

S.F.L +35'-10"
47'-11"

PROJECT TITLE

Circulation YAY TAR SHAY - FIVE STORIES

ARCHITECT
F.F.L +36'-0"

3 Dry Kitchen
S.F.L +35'-10"

22 R @ 0' - 6" Walk-in Wardrobe


UP

F.F.L +36'-0" STRUCTURE


Master Bed Rm
Y LINE

S.F.L +35'-10"

S.F.L +35'-6"
F.F.L +35'-8"
19'-6"

C C

Balcony

Y LINE
1 1
A-603 A-603
SITE BOUNDAR

3
M&E ENGINEER
Dinning Area Bath & WC

2
1
Living Area

SITE BOUNDAR
Stair Area

4
STAIR-2
M&E CONTRACTOR
4
6'-0"

PEARL ROYAL Co., Ltd.


1 Block-C, Room-802,8th Floor,Yadanar Housing,
A A-601 13Rd Quarter, South Okkalapa Township, Yangon.
Ph: 09-420084410, Email: pearlroyal@contractor.net

SITE BOUNDARY LINE SITE BOUNDARY LINE


DRAWING TITLE

THIRD FLOOR PLAN FIRE FIGHTING DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
1
4'-32" 5'-53 11'-73
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6"
N E 4" 5'-0"
LI

Y LINE
D A R Y
SITE BOUN
1"
7'-52

TENDER DRAWING
Y LINE
SITE BOUNDAR

SITE BOUNDAR
REVISION
3'-11"

SEC NO DATE DESCRIPTION


B
Y LINE

4-002

1 B A
Balcony

S.F.L +47'-2"
F.F.L +47'-4"
1 Balcony SEC

AC & FIRE
STAIR-1
SITE BOUNDAR

A-602 4-001
DN

Bath & WC
Stair Area Bath & WC Master Bed Rm
13'-9"

Lift F.F.L +47'-6"


S.F.L +47'-4"

ELE & ELV


UP
NET WGT - KG
TENDER DRAWING
19.4

Lift Lobby OWNER / DEVELOPER

Master Bed Rm Store Rm


2

Wardrobe
F.F.L +47'-6"
F.F.L +47'-6"
Walk-in
S.F.L +47'-4" LOCATION
S.F.L +47'-4"
Walk-in Wardrobe YANGON
14'-8"
47'-11"

PROJECT TITLE

YAY TAR SHAY - FIVE STORIES


Circulation
Walk-in Wardrobe ARCHITECT

3 Bath & WC
22 R @ 0' - 6 1/4"
F.F.L +47'-6"
UP
S.F.L +47'-4" DN

STRUCTURE
Walk-in Wardrobe
Y LINE

Master Bed Rm

S.F.L +47'-0"
F.F.L +47'-2"
F.F.L +47'-6"
19'-6"

C S.F.L +47'-4" A

Balcony
F.F.L +47'-6" Stair

Y LINE
1 S.F.L +47'-4" Shrine SEC
A-603 Area Master Bed Rm 4-001
SITE BOUNDAR

3
M&E ENGINEER
Bath & WC

2
1

SITE BOUNDAR
4
STAIR-2 M&E CONTRACTOR
4
6'-0"

PEARL ROYAL Co., Ltd.


SEC Block-C, Room-802,8th Floor,Yadanar Housing,
B 4-002 13Rd Quarter, South Okkalapa Township, Yangon.
Ph: 09-420084410, Email: pearlroyal@contractor.net

SITE BOUNDARY LINE SITE BOUNDARY LINE


DRAWING TITLE

FOURTH FLOOR PLAN FIRE FIGHTING DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


A A' B C C' D E F G N
9'-9" 78'-6" 16'-8"
4'-32" 5'-53
1
4" 5'-5" 14'-7" 6'-4" 7'-1" 5'-3" 12'-6" 18'-10" 8'-6" 11'-73
4" 5'-0"
LI N E

LINE
R Y
SITE BOUNDA
1"
7'-52

TENDER DRAWING
Y LINE

Y
SITE BOUNDAR

SITE BOUNDAR
REVISION
3'-11"

SEC NO DATE DESCRIPTION


B
Y LINE

4-002

1 A A
SEC STAIR-1 SEC
SITE BOUNDAR

4-001 4-001
DN

AC & FIRE
Lift
Stair
machine
13'-9"

Area
room

HRP - 02 -STANDBY P
ELE & ELV

HRP - 01 -DUTY
20 R @ 0' - 6 7/8" TENDER DRAWING

P
RAW WATER TANK ( DOMESTIC & FIRE ) 2 NOS.OF HOSE REEL PUMP
(1 DUTY & 1 STANDBY)
FLOW RATE : 2.5 l/s
PUMP HEAD : 40 m (Est.)
OWNER / DEVELOPER
DESIGN CAPACITY ; 12.5Cu.M
TREATED WATER TANK ( DOMESTIC ) NET WGT - KG
27.5KG EACH
EFF CAP ; 10Cu.M
DESIGN CAPACITY ; 12.5Cu.M
F.F.L +58-8" Gallon ; 2200( Half-Day Storage )
EFF CAP ; 10Cu.M

2 S.F.L +58'-6" (2.5 x 2.5 x 2) m

12500KG
Gallon ; 2200( One Half-Day Storage )

(2.5 x 2.5 x 2) m

12500KG
LOCATION

YANGON
14'-8"

PROJECT TITLE
47'-11"

YAY TAR SHAY - FIVE STORIES


WaterTank WATER TREATMENT SYSTEM WaterTank
ARCHITECT

OVERHEAD TANK CONCRETE PLINTH


6nos ( 2.8m x 0.4m X 0.6m )

9738KG STRUCTURE
Y LINE
19'-6"

A A

Y LINE
SEC SEC
4-001 4-001
SITE BOUNDAR

3
M&E ENGINEER

2
1

SITE BOUNDAR
4
M&E CONTRACTOR
4
6'-0"

PEARL ROYAL Co., Ltd.


SEC Block-C, Room-802,8th Floor,Yadanar Housing,
B 4-002 13Rd Quarter, South Okkalapa Township, Yangon.
Ph: 09-420084410, Email: pearlroyal@contractor.net

SITE BOUNDARY LINE SITE BOUNDARY LINE


DRAWING TITLE

FIFTH FLOOR PLAN FIRE FIGHTING DESIGN UPDATED

DRAWING NO.
REV - II

DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020


RAW WATER TANK ( DOMESTIC & FIRE ) +75'-6" FFL
DESIGN CAPACITY ; 12.5Cu.M 2 NOS. OF HOSE REEL PUMPS
EFF CAP ; 10Cu.M (1 DUTY, 1 STANDBY)
Lift Machine Roof Level
Gallon ; 2200( Half-Day Storage ) HRP-01 & HRP-02
(2.5 x 2.5 x 2) m FLOW RATE : 2.5 l/s EACH +72'-0" FFL
TRANSFER PIPE
12500KG PUMP HEAD : 40 m EACH (Est.) Roof Level
PV@100Litres AAV
P HOSEREEL PUMP 1 P

AAV
P HOSEREEL PUMP 2 P

+62'-0" FFL
5th Floor Level

4.5Kg ABC DRY CHEMICAL


FIRE EXTINGUISHER @ 1NOS TENDER DRAWING
+50'-6" FFL REVISION

4th Floor Level NO DATE DESCRIPTION

4.5Kg ABC DRY CHEMICAL


FIRE EXTINGUISHER @ 2NOS
+39'-0" FFL
3rd Floor Level TENDER DRAWING

OWNER / DEVELOPER

4.5Kg ABC DRY CHEMICAL


FIRE EXTINGUISHER @ 1NOS
+27'-6" FFL LOCATION

2nd Floor Level YANGON

PROJECT TITLE

YAY TAR SHAY - FIVE STORIES


4.5Kg ABC DRY CHEMICAL
FIRE EXTINGUISHER @ 2NOS
+16'-0" FFL ARCHITECT

First Floor Level

STRUCTURE

4.5Kg ABC DRY CHEMICAL


FIRE EXTINGUISHER @ 1NOS
+3'-0" FFL
M&E ENGINEER
Ground Floor Level

M&E CONTRACTOR

4.5Kg ABC DRY CHEMICAL PEARL ROYAL Co., Ltd.


FIRE EXTINGUISHER @ 2NOS Block-C, Room-802,8th Floor,Yadanar Housing,
13Rd Quarter, South Okkalapa Township, Yangon.
----- FFL
Ph: 09-420084410, Email: pearlroyal@contractor.net

Underground Floor Level


DRAWING TITLE

DV DV
FIRE FIGHTING SYSTEM
SCHEMATIC DIAGRAM

DRAWING NO.
REV - II

FIRE FIGHTING SYSTEM SCHEMATIC DIAGRAM DESIGNED BY HPT

CHECKED BY HL

DATE 11ST AUG 2020

Вам также может понравиться