Академический Документы
Профессиональный Документы
Культура Документы
Technical Specifications
Prepared by:
Vladimir M. Longid
Architect / PRC no. : 0015959
1
TECHNICAL SPECIFICATIONS
GENERAL NOTE:
1.0 SITEWORKS
1.3 Earthworks
2
b. Backfill around structures only after the concrete attained
sufficient strength to resist lateral pressure resulting from the
backfill.
C. Soil Compaction
Filling materials to be used inside the building shall be placed in
200mm (8” THK) in loose layers. Each layer shall be moisture-
conditioned and compacted with 95% maximum dry density by
modified proctor test (ASTM D1557).
D. Capillary water sieves and barrier; uniformly graded or sized, non-
porous aggregates or stones respectively.
1.3.1 Protection
3
Stripping
a. Strip top soil only in areas required as shown in plans. Remove top soil to
depth indicated or as required by the Architect but in no case less than
150mm (6”) in depth, prior to start of regular excavation or backfilling work.
b. Stock pile removed top soil separate from other excavation material
Site Grading
a. Cut or fill and machine grade the site area. Deposit material in loose layers
not exceeding 200mm (8”) in depth and compact to at least 95% of
maximum dry density. Rough grade elevations on levels shall be
approximately 150mm (6”) below finish grade in areas to be lawn seeded
or landscaped.
Backfilling
a. Prior to backfilling around structures, remove all forms, trash and debris.
Use only approved backfill material and place systematically on all sides in
layers, compacted in accordance with soil compaction.
b. Backfill around structures only after the concrete attained sufficient
strength to resist lateral pressure resulting from backfill.
Building Layouts
A. Building lines shall be staked out and all lines and grades shown in the
drawings established before any excavation is started.
B. Batterboards and reference marks shall be erected at such places
where they will not be disturbed during the excavation of the building.
C. Construct two permanent bench marks of previously known elevations
near the site of construction.
Soil Poisoning
4
C. Foundation treatment: prior to pouring foundation, apply four (4) liters
of the solution per square meter of surface (bottom and sides) of
excavations for footings and foundations.
D. Backfill treatment: apply four (4) liter per linear meter per 300mm (12”)
height of backfill materials as it is being placed and compacted starting
from top of footing foundation slab up to the bottom of the floor slab.
E. Floor slab treatment: prior to placing of vapor barrier, apply four (4)
liters of soil poison per square meter of the sand building.
F. Building exterior treatment: apply three (3) liters per linear meter in a
100 x 200mm (4”x8”) deep trenching dug along the exterior wall of the
building.
G. Treatment for other areas: treat all voids found in masonry wall such as
in concrete hollow blocks and all surfaces before veneer finished are
placed with four (4) liters per ten (10) linear meters.
H. Wood treatment: untreated lumber to be used for ceiling joint runners,
nailers, etc., shall be immersed in chlordane 75EC of 1:100
concentration for at least 25 hours before installation.
I. Termite mounds: demolish and treat all termite mounds within the
property, if any.
J. “Bukbok” proofing: dried wood, plywood, tanguile, apitong, cabinets,
dividers, and paneling shall be brushed with pentachloride of 1:100
concentration before painting or varnishing.
K. The contractor shall submit to the Architect for approval a copy of the
pest control company’s proposal and chemical application
method/procedure including the description of the equipment to be
used before start of work.
2.1 Responsibility
2.2 Materials
3 FORMWORKS
3.2 Preparation
A. Check all forms to conform to the shape, lines and dimensions of the
members as called for in the plans.
B. Provide openings in column forms for cleaning and inspection
preferably at lowest points of pour lifts.
6
C. Provide camber for cantilever and long spans or as indicated in
construction notes.
D. Coat all forms with form oil before reinforcement is placed. Remove all
surplus oil on form surfaces.
3.3 Removal
A. Remove forms only upon approval of the Engineer in such manner and
at such time as to insure the complete safety of the structure.
B. In no case shall the supporting forms and shorings be removed until
the members have attained sufficient strength to support safely their
weight and load thereon.
C. The results of suitable control tests shall be used as evidence that the
concrete has attained sufficient strength to permit removal of shorings
and supporting forms.
D. Cylinders required for control tests shall be made in addition to those
required by these specifications.
4 CONCRETE WORKS
4.1Cast-in-Place Concrete
B. Aggregates:
a. Gravel-crushed gravel hard uncoated grain, strong, and durable
reasonably clean rocks. Use 25mm (1”) maximum for footing,
19mm (3/4”) for all beams, slabs, columns, and 25mm (1”) for
compacted gravel bed for slab on fill.
b. Sand: clean, washed sand. Sand from salt water is not allowed.
c. Water: Fresh and fit for drinking, free from injurious amount of
oil, acids, alkali, organic materials, and other deleterious
substances.
C. Water: Use only water that is clean and free from injurious amounts of
oils, acids, alkali, organic materials or other deleterious substances.
D. Sand: Clean river sand, free from organic and other deleterious matter.
Sand from salt water is not allowed.
7
4.2 Mixing Concrete
A. Keep concrete continuously wet or moist for at least one week after
placing.
B. Floors and vertical surface may be sprayed with an approved retarder
C. Curing shall begin as soon as concrete has attained initial set.
D. Roof deck and terraces shall be moist cured at least seven days
irrespective of whether curing additives is used or not.
5 MASONRY WORKS
5.1 Masonry
A. Concrete Hollow Blocks (CHB): Use 125mm (5”) thick for all perimeter
walls, 4” (100mm), 450 psi for non-load bearing capacity for interior
wall partitions.
B. All concrete hollow blocks shall be laid out with cement mortar as
specified with vertical joints breaking halfway over course below unless
otherwise shown on plans. Bed joints (horizontal) and joints (vertical)
must be filled with mortar thoroughly to avoid leakage or moisture.
C. All concrete hollow block walls shall be built plumbed, true to the given
dimension with blocks always set to bond and breaking joints.
D. Class A – 1:2, 13.30 Mpa. (2,000psi) as concrete mortar works with
mix texture as required. Cement mortar shall be one (1) part Portland
Cement and shall be done in one (1) part lime putty and four and one-
8
half (4 ½) parts sand by volume, but not more than one (1) part
Portland Cement. No cement shall be used for exceeding one hour.
Mortar which shows tendency to become dry this time shall have
added to it and mixed.
E. Mortar and Plaster Works: Mixture at 1:2.Plastering of walls shall be
ROUGH (not smooth fine finish) and shall be done with installed
concrete plaster guides and flattened with 3meter aluminum bar.
F. Plaster Bond: N & H PLASTER BOND or approved equal. Apply at all
wall areas prior to plastering.
G. Lintel beams and stiffener columns shall be provided for all steel works.
6 METALS
D. All Structural steel frames (columns, beams, and roof framing) shall
conform to ASTM A-36 steel with a minimum of 36,000 psi strength
capacity.
E. All arc-welding electrodes shall conform to AWS Specification for iron
and Steel Arc Welding Electrodes latest edition. Electrodes for arc-
welding shall be E-60 and E-70 series.
F. All bolts, nuts and washers shall conform to ASTM A-36 specifications.
6.4All gates: Shall be the type shown on the drawing. Latch end member of
gate frames shall be extended sufficiently above the top member. Gate less
than 2400mm (8 feet) wide shall have truss rods or intermediate braces. Gate
shall be attached to the gate frame by method standard recommended by the
manufacturer except that welding will not be permitted.
9
6.5 Welding Technique
b. Make surfaces to be welded free from loose scale, slag, grease, paint,
and any other foregoing material except that mill scale which
withstands vigorous wire brushing may remain.
d. Let gas cut edges which will be subjected to substantial stress or which
are to have weld metal deposited on them be free from gouges.
Remove by grinding any gouge that remain from cutting.
6.6 Miscellaneous
6.7 Note:
a. All materials to be approved by the Architect and Owner before
installation.
7.1 Submittals
7.2 Waterproofing
10
height from finish floor line to ensure that no leaks shall occur to lower
floor being served.
b. Flood testing: All areas requiring shall be subjected to minimum of 24
hours flood testing; depth of water/flooding shall be monitored and
certified by applicator prior to finishing of said areas.
c. Roof deck and Deck roof: Provide with membrane type waterproofing
of approved brand and quality.
d. Toilets: Provide with cementitious waterproofing compound; brush
applied.
8 WOODS
8.1 Lumber: All lumber shall be of approved quality of the respective kinds
required for the various parts of the works and shall be well-seasoned, free
from large saps, loose knots, shakes or other imperfections impairing its
strength and durability. All exposed surfaces shall smoothly dressed and
dried.
11
E. Fastening: Fastening shall be common nails flathead wood screws
(R.H.W.S), bolts or lag screws where specifically called for. Conceal
fastening as far as possible, locate them in inconspicuous place.
Where nailing is permitted through woodwork face, conceal nail heads.
F. Hardware and Fasteners: use metal nails, screws, bolts, miscellaneous
fasteners or anchorage concealed or countersunk whenever called for,
with size, shape, and type to members in place. Use approved water-
resistant glue for cabinet framing joints.
G. All installed wood components shall be submitted for material approval
before installation. Shop drawings and methodology of installation shall
also be required before installation.
A. Rough lumber for framing and siding boards shall be air-dried or sun-
dried such that its moisture content shall not exceed 22%.
B. Dressed lumber for exterior and interior finishing for doors and
windows, mill work, cabinet work, and flooring boards shall be kiln-
dried having no moisture content in excess of 14% at the time of its
installation.
8.3 Fasteners
Nails, screw, bolts, and straps shall be provided and used where
suitable for fixing carpentry and joinery works. All fasteners shall be brand
new and of adequate size to ensure rigidity of connections.
8.4 Note:
All materials to be approved by the Architect and Owner before
installation.
9.1 Doors
12
d. All lumber for wooden doors including door jambs, and all
wood work of similar nature, shall be kiln-dried with not more
than 12% moisture content.
e. All wooden doors shall be manufactured with wood stiffener,
and of the lumber specified herein, the plywood edge
projection shall consists in rabbeting it around into the
outside frame of the door in order to prevent “peeling-off” of
the plywood at the edges.
f. All wood doors must be guaranteed against warping, twisting
or cracking. This obligates the Contractor to make good such
defects and/or replace entirely any and all defective doors.
E. Pocket Door
E.1. Second Floor (D-8)
a. Install and provide solid pocket door for office.
b. Solid pocket door shall be of 1000mm width, 2150mm height,
and 45mm thickness.
c. Tubular lever set door knob shall be used. Alternatives may be
used provided that there are submittals and corresponding
approvals by the procuring identity.
F. Panel Door
F.1 Ground Floor (D-3)
a. Install and provide Panel door for the guest bedroom as
indicated on plan.
b. All Panel door shall be installed with 2”x6” wood jamb.
c. Panel door shall be of 900mm width, 2150mm height.
a. Install and provide wood flush door for maid’s bathroom, powder
room and third floor toilet and bath as indicated on plan.
b. All wood flush door shall be installed with 2”x6” wood jamb.
c. Wood flush door shall be of 800mm width, 2150mm height.
15
K. Surface mounted Sliding Door with Towel Rail
9.2 Windows
A. Fixed window
A.1 (W-1)
a. Install and provide fixed window with six sets awning
window with analoc-aluminum framing for areas indicated in
plan.
b. All fixed windows with analoc-aluminum framing shall be
2750mm in width, 1900mm in height. All awning window
shall be 900mm in width, 600mm in height.
c. Fixed window shall be installed with ¼” thick clear glass with
analoc-aluminum frame finish.
16
A.2 (W-2)
a. Install and provide fixed window with six sets awning
window with analoc-aluminum framing for areas indicated
in plan.
b. All fixed windows with analoc-aluminum framing shall be
4100mm in width, 1200mm in height. All awning window
shall be 700mm in width, 550mm in height.
c. Fixed window shall be installed with ¼” thick clear glass
with analoc-aluminum frame finish.
A.3 (W-4)
a. Install and provide fixed window with analoc -aluminum
framing for areas indicated in plan.
b. All fixed windows with analoc-aluminum framing shall be
600mm in width, 1100mm in height.
c. Fixed window shall be installed with ¼” thick clear glass
with analoc-aluminum frame finish.
A.4 (W-5)
a. Install and provide fixed window with three sets awning
window with analoc-aluminum framing for areas indicated
in plan.
b. All fixed windows with analoc-aluminum framing shall be
1500mm in width, 1800mm in height. All awning window
shall be 900mm in width, 617mm in height.
c. Fixed window shall be installed with ¼” thick clear glass
with analoc-aluminum frame finish.
A.5 (W-7)
a. Install and provide awning analoc window for areas
indicated in plan.
b. All fawning analoc windows shall be 500mm in width,
700mm in height.
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.6 (W-8)
a. Install and provide fixed analoc with six sets awning
window for areas indicated in plan.
b. All fixed analoc windows shall be 600mm in width,
1200mm in height & all awning windows shall be 500mm
in width, 600mm in height.
17
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.7 (W-9)
a. Install and provide fixed analoc with six sets awning
window for areas indicated in plan.
b. All fixed analoc windows shall be 800mm in width,
1200mm in height & all awning windows shall be 500mm
in width, 600mm in height.
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.8 (W-10)
a. Install and provide fixed-pivot analoc window for areas
indicated in plan.
b. All fixed analoc windows shall be 800mm in width,
2000mm in height & pivot window shall be 600mm in
width, 667mm in height
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.9 (W-11)
a. Install and provide fixed analoc window with two sets
awning window for areas indicated in plan.
b. All fixed analoc windows shall be 500mm in width,
900mm in height & all awning window shall be 700mm in
width, 900mm in height
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.10 (W-12)
a. Install and provide fixed analoc window with two sets
awning window for areas indicated in plan.
b. All fixed analoc windows framing shall be 700mm in
width, 500mm in height & awning windows shall be
700mm in width, 700mm in height
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.11 (W-13)
a. Install and provide corner-fixed analoc window for areas
indicated in plan.
b. All corner-fixed windows with analoc framing shall be
1600mm in width, 3450mm in height.
18
c. Corner-Fixed analoc window shall be installed with ¼”
thick clear glass with analoc finish.
A.12 (W-14)
a. Install and provide fixed analoc window with four sets
awning window for areas indicated in plan.
b. All fixed analoc windows with analoc framing shall be
400mm in width, 900mm in height.
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.13 (W-15)
a. Install and provide corner-fixed analoc for areas indicated
in plan.
b. Corner-fixed analoc window shall be 1500mm in width,
2400mm in height.
c. Corner-Fixed window shall be installed with ¼” thick clear
glass with analoc finish.
A.14 (W-16)
a. Install and provide fixed analoc with six sets awning
window for areas indicated in plan.
b. All fixed analoc windows shall be 900mm in width,
2100mm in height & all awning windows shall be 500mm
in width, 900mm in height.
c. Fixed analoc with awning windows shall be installed with
¼” thick clear glass with analoc finish.
A.15 (W-17)
a. Install and provide fixed analoc window for areas
indicated in plan.
b. All fixed analoc windows shall be 500mm in width,
2400mm in height.
c. Fixed analoc window shall be installed with ¼” thick clear
glass with analoc finish.
A.16 (W-18)
a. Install and provide awning window with analoc framing for
areas indicated in plan.
b. All awning windows with analoc framing shall be 600mm
in width, 600mm in height.
c. Awning window shall be installed with ¼” thick clear glass
with analoc finish.
19
A.17 (W-19)
a. Install and provide fixed analoc window for areas
indicated in plan.
b. All fixed analoc windows shall be 665mm in width,
1300mm in height.
c. Fixed window shall be installed with ¼” thick clear glass
with analoc finish.
A.18 (W-20)
a. Install and provide awning window with analoc for areas
indicated in plan.
b. All awning windows with analoc framing shall be 700mm
in width, 800mm in height.
c. Awning window shall be installed with ¼” thick clear glass
with analoc finish.
A.19 (W-21)
a. Install and provide fixed analoc with two sets awning
window with analoc framing for areas indicated in plan.
b. All fixed analoc windows shall be 500mm in width,
1400mm in height & awning windows shall be 500mm in
width, 500mm in height.
c. Fixed analoc with awning window shall be installed with
¼” thick clear glass with analoc finish.
B. Awning Window
B.1. (W-1)
B.2. (W-2)
B.3. (W-3)
C. Sliding Window
C.2. (W-6)
A. Locksets:
a. Door locksets to be used are tubular lever set doorknobs.
b. Builder to submit to Architect material samples for approval.
B. Hinges:
a. 4 x 4” Heavy duty stainless steel hinges for all wood and
metal panel doors.
b. Builder to submit to Architect material samples for approval.
10 FINISHES
A. Ground Floor
a. Plain Concrete: Provide score joints whenever required for all
stairs and parking.
b. Floor Tiles: Provide 300mm x 300mm x 10.35 Ceramic Tiles for
Toilets and shower, powder room, dirty kitchen and laundry.
21
c. Floor Tiles: Provide 600mm x 600mm x 10.35 Ceramic Tiles for
living, dining, kitchen, guest room, maid's room, hallway, porch
and lanai.
B. Second Floor
a. Plain Concrete: Provide score joints whenever required for all
stairs.
b. Floor Tiles: Provide 300mm x 300mm x 10.35 Ceramic Tiles for
Toilets.
c. Floor Tiles: Provide 600mm x 600mm x 10.35 Ceramic Tiles for
hallway, master's bedroom, office, walk-in-closet, entertainment
room and balcony.
C. Third Floor
a. Plain Concrete: Provide score joints whenever required for all
stairs.
b. Floor Tiles: Provide 300mm x 300mm x 10.35 Ceramic Tiles for
Toilets.
c. Floor Tiles: Provide 600mm x 600mm x 10.35 Ceramic Tiles for
hallway, bedroom 01 and 02, family room/gym, balcony and
storage.
D. Floor tiles, where required on plan, shall be installed with tile adhesive.
A. Ground Floor
a. Concrete hollow block smooth, plain cement plaster, semi-gloss
latex paint finish for interior spaces.
b. Ceramic tiles, 300mm x 300mm x 7.35mm thick unglazed
ceramic wall tiles at finish ceiling high level, rest in plain cement
finish, for toilets and shower and powder room.
c. Dry wall, paint finish located at living, guest room and dining
area.
B. Second Floor
a. Concrete hollow block smooth, plain cement plaster, semi-gloss
latex paint finish interior spaces.
b. Ceramic tiles, 300mm x 300mm x 7.35mm thick unglazed
ceramic wall tiles at finish ceiling high level, rest in plain cement
finish, for toilets and shower.
22
c. Dry wall, paint finish located at master's bedroom and
entertainment room.
C. Third Floor
a. Concrete hollow block smooth, plain cement plaster, semi-gloss
latex paint finish for interior spaces.
b. Ceramic tiles, 300mm x 300mm x 7.35mm thick unglazed
ceramic wall tiles at finish ceiling high level, rest in plain cement
finish, for toilets and shower.
c. Dry wall, paint finish located at bedroom 01 and 02.
A. Ground Floor
a. Smooth formed, smooth rubbed concrete with flat latex paint
finish for stairs.
a. Gypsum panel, 9mm thick for the rest of the area.
b. Use of cove lighting for dining, kitchen and guest room.
B. Second Floor
a. Smooth formed, smooth rubbed concrete with flat latex paint
finish for stairs.
c. Gypsum panel, 9mm thick for the rest of the area.
d. Use of cove lighting for master's bedroom and entertainment
room.
C. Third Floor
a. Smooth formed, smooth rubbed concrete with flat latex paint
finish for stairs.
b. Gypsum panel, 9mm thick for the rest of the area.
c. Use of cove lighting for bedroom 01 and 02 and family
room/gym.
11.0 PLUMBING
A. Ground Floor
23
a. Piping shall be of Polypropylene type (PPR) PN 20, duly by the
Department of Science and Technology (DOST) and conforms
to International Organization for Standardization. Threaded at
joints and provided with adequate anchorage, hangers and
fastenings as required.
a.1 Use 1 ½” Ø pipe as Main Feeder to account for the water
features.
a.2 Use 1” Ø pipe as Secondary Feeder (or Header) located
above the ceiling.
a.3 Use ½” Ø pipe as connection to fixtures
B. Second Floor
C. Third Floor
11.3 Sanitary
25
c. Use 4” Ø PVC-U for soil pipe lines.
d. Use 2” Ø PVC-U pipes for sewer pipe lines.
e. Use 2” Ø PVC-U pipes for vent pipe lines.
B. Sanitary lines: PVC PIPES WITH APPROVED FITTINGS
a. Use 12” Ø PVC-U pipe fittings for storm drainage pipe lines.
b. Use 3” Ø PVC-U pipe fittings for down spout pipe lines.
c. Use 4” Ø PVC-U pipe fittings for soil pipe lines.
d. Use 2” Ø PVC-U pipe fittings for sewer pipe lines.
e. Use 2” Ø PVC-U pipe fittings for vent pipe lines.
f. Use 4” Ø PVC-U Wye pipe fittings for soil pipes.
g. Use 4” Ø – 2” Ø PVC-U wye reducer pipe fittings for sewer
pipe lines.
C. All horizontal lines shall be provided with a minimum 2% slope.
D. Adequate clean-outs for every change in direction and for
maintenance should be provided as shown on plans.
11.4 Fixtures
A. Water Closets: Vertical tank type, flush saver, dual flush for all
toilets.
B. Lavatories: Wall-hung lavatory.
C. Accessories:
a. Faucet: Stainless steel; model to be approved
b. Toilet Paper Holder: complete with concealed brackets and
screws
c. Soap Holder: complete with concealed brackets and screws
d. Floor drain: Stainless steel: model to be approved
e. Shower head: single point heater w/ telephone shower:
model to be approved
f. Gate valve: brass; model to be approved.
g. Angle valve: stainless steel; model to be approved
D. Note: All materials to be approved by the Architect and Owner
before installation.
12 ELECTRICAL
26
C. Furnishing and installation of feeder and branch circuit conductors with
the necessary conduits, approved typed of fittings and devices as
indicated in the electrical plans.
27
a. F1:
Use: 2-100 mm2 THW/THHN copper wire and 1-50 mm2
color green copper wire for main and grounding feeders
respectively in 65 mmØ RNC encased in concrete.
12.4 Fixtures
13.0 MECHANICAL
28
C. All electrical power wiring for the HVAC equipments including low voltage
control wiring will be others.
D. All wall and roof openings shall be water proofed and air tight sealed and
shall be provided by the mechanical contractor.
E. All ducts shall be fabricated of galvanized lock forming quality steel, and
installed in strict compliance with the codes and standards applicable.
F. All duct dimensions shown are outside metal dimensions and are in
inches. Duct sizes have been increased, where required, to allow for
lining.
G. Mechanical contractor shall take actual measurements in the field before
fabricating and sheet metal work and shall observe and allow for
clearances and space requirements for piping and equipment or other
obstructions.
H. The ductwork shall include furnishing and installing galvanized sheet metal
ducts flexible connections roof/wall exhaust cap, duct supports, registers,
grilles, dampers, bracing and other accessories to make a complete and
operable system.
I. All joints in ducts, casings, and plenums shall be sealed to prevent air
leakage. All sealant and tapes shall have a flame rating under 25 and a
smoke developed rating under 50. Duct sealant shall be iron grip water
base duct sealant, united sheet metal duct sealer or approved equal,
ductwork tape shall be hardcast, Inc., type DT-5300 or DT-5400 or
approved equal. Tape adhesive shall be hardcast, Inc. type FTA-20 or
approved equal.
J. All interior ducts (supply, return and outside air) shall be internally lined
with 1” thick, 3 PCF density mat-faced fiberglass duct liner. The liner shall
have fire resistant air stream surface treatments designed to withstand
erosion and minimum friction loss.
K. Mechanical contractor shall provide return air opening above ceilings in
rooms where walls extends to the bottom of deck.
L. Installation of all mechanical equipment shall be in accordance with the
manufacturer recommendations.
M. Furnish and install full size coil condensate drain lines from all air
conditioning units piped to floor drains, or hub drains as indicated on the
mechanical and plumbing drawings. Installation and routing of these lines
to be checked with and approved by the general contractor. Pipe shall be
schedule 40 galvanized steel pipe, a53 grade B assembled with 150
pound screwed galvanized malleable iron with copper to copper ground
joint. Drain pipe insulation shall be ½ inch closed cell material similar to
Armstrong armaflex. Butt joints and seams shall be sealed with 520
adhesive.
N. Mechanical contractors qualified test personnel shall properly startup, test,
adjust and balance all systems installed and shall provide labor,
instruments and test equipment, as required.
29
O. Mechanical contractor shall furnish submittals containing equipment,
ductwork, shop drawing, and control drawings for approval prior to
ordering any equipment, or material.
P. Mechanical contractor shall provide owners’ representative a detailed
operational demonstration at the job site of each system. Written
operations manual and as-built drawings shall be submitted before retainer
is paid.
14 AUXILIARY
A. CABLES
All telecommunications cabling inside the dwelling unit shall be UL listed and
marked type CM, CMR, CMP, CATV, CATVR or CATVP and shall be installed
in accordance with Philippine Electronics Code.
B. All fiber optic cable inside the dwelling unit shall be UL listed and marked
type OFN, OFNR, or OFNP and shall be installed in accordance with
Philippine Electronics Code.
B.CCTV
System shall use video signals from various types of indoor/outdoor CCD
colour cameras installed at different locations, process them for viewing on
workstations/monitors at Central Control Room/local control rooms and
simultaneously record all the cameras after compression using MPEG 4 or
better standard. Joystick or Mouse-Keyboard controllers shall be used for
Pan, Tilt, Zoom, and other functions of desired cameras.
System shall have combination of Digital CCD Colour video Cameras with
individual IP address, analog CCD Colour Video Cameras with Fixed or P/T/Z
Lens, encoders / decoders, Network Video recorders (NVR/CAMERA
SERVER), Network attached storage (NAS) / Raid backup device for
recording, Application software, Colour Video Monitors, Keyboards with
Joystick controllers / Mouse-Keyboard, software based Video Matrix Switcher,
workstation for System Administration / Management / Maintenance etc.
30
Network Video Recorder shall offer both video stream management and video
stream storage management. Recording frame rate & resolution in respect of
individual channel shall be programmable.
System should ensure that once recorded, the video cannot be altered,
ensuring the audit trail is intact for evidential purposes.
System shall provide sufficient storage of all the camera recordings for a
period of 30 days or more @ 25 FPS, at 4 CIF or better quality using
necessary compression techniques for all cameras (extended capacity of
cameras i.e. present capacity + 25 %).
Encoders shall digitize analog video, compress the digital video using various
compression algorithms (MPEG - 4 or better standard), and transmit the
compressed digital video over packet-based IP network. Encoders shall have
less than 200 ms of latency and shall support dual stream – MPEG 4. 2
The recording resolution and frame rate for each camera shall be user
programmable. 2.11. The Area under surveillance shall be monitored and
controlled from Central/Local Control Room(s) through workstations and
Joystick controllers.
31
C. EMERGENCY LIGHTS
Indicate the escape routes clearly with exit signs so there is no doubt which is
the way out
Illuminate open areas used in an escape route so that obstacles such as
equipment or furniture can be avoided
Ensure fire alarm call points & fire-fighting equipment can be readily located
Provide illumination for high-risk areas to allow machinery processes to be
shut down safely
32