C.

BULAONG
2020.08.06 FIRST ISSUE FOR APPROVAL
REV drawn Checked Approved MODIFICATIONS STATUS
Date Date Date
Owner

Approved by:
UPSI Sign:
Date:
Contractor:

Approved by: Sign:


Date:
BATTERY ENERGY STORAGE SYSTEM
(BESS) FACILITY
Project Location:
SAN MANUEL, PANGASINAN
Document Title:

METHOD OF STATEMENT – CABLE TESTING


Date Name Sign Subcontractor :
Drawn CB

Checked

Approved

Scale Size Document No.


NTS A4 (4)BESS-SM-3Q90041-QAMS-004

Page No. Total Page


1 5
(4)BESS-SM-3Q90041-QAMS-004 METHOD OF STATEMENT -CABLE TESTING.docx
C:\UserData\z0047aud\Documents\ENG20012 SIEMENS SAN MANUEL\600 Output\METHOD OF
STATEMENT\(4)BESS-SM-3Q90041-QAMS-004 METHOD OF STATEMENT -CABLE TESTING.docx

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-004
(BESS) FACILITY
Title Rev. page of
A 2 5
METHOD OF STATEMENT – CABLE TESTING

REVISION HISTORY

PAGE NO. REVISIONS REMARKS

A B

All x First issued

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-004
(BESS) FACILITY
Title Rev. page of
A 3 5
METHOD OF STATEMENT – CABLE TESTING

Description of CABLE TESTING


the Task /
Activity
Manpower Testing Engineer, Technician
Required
Tools and Multi-Tester, Insulation Resistance Tester, High Potential Tester, Wire
Equipment Stripper, Electrician Knife
Required
Average
Output
(Manpower and
Equipment)

Materials None
Required
Other (i.e. access platforms, winches, ladders, etc.)

None
Essential
Equipment
Specific Physical Hazard
Identified
Residual
Hazards
Specific Staff Construction Occupational Safety and Health, TESDA Certificate NCII
Training
Requirements
Predecessor Wire Pulling
Activity
Low Voltage Cable:
1. Perform continuity test to ensure correct cable connection.
2. Perform insulation resistance test on each conductor with respect to ground
and adjacent conductor. Apply potential shall be 1000VDC for 600V cable.
Test duration should be 1 minute.

Work Method
(Specifying methods of Medium Voltage Cable:
working, tools, materials
and equipment utilized) 1. Perform shield continuity test in each cable.
2. Perform insulation resistance test on each conductor with respect to ground
and adjacent conductor and shields grounded. Apply voltage in accordance
with manufacturer’s data. In the absence of manufacturers’ published data
use NETA table 100.1

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-004
(BESS) FACILITY
Title Rev. page of
A 4 5
METHOD OF STATEMENT – CABLE TESTING

Temporary (If none, state none.)

None
Support and
Props
needed to
facilitate the
works
Fall (i.e. Guard Rails/ Toe Boards/ Brick Guards/ Safety Harnesses/ Exclusion Zones etc)

Protection
Safety Harness
Measures
(Where work at height
cannot be eliminated –
consider both Personnel
& Materials)
(i.e. Lubricants/ Solvents/ Flammable Materials/ Refrigerants/ Welding Gases etc)

None

Hazardous
Substances

Very Toxic Harmful / Corrosive Dangerous Oxidizing Highly Explosive


Irritant for the Flammable
environment
N N N N N N N
Applicable
(Y/N)
Safe Working (Detail any limits on the loading applicable to temporary plant/equipment or fixed elements of the structure where the work is
taking place.)
Load 1 Person/Ladder, At least 30A Circuit Breaker protection for power
source.
Required Other:

Personnel 1.
Protective 2.
3.
Equipment Safety Hard Safety Hearing Respiratory Eye
Boots Hats Gloves Protection Protection Protection
Y Y Y N N N
Applicable
(Y/N)
Emergency FIRE – Fire extinguisher should be available all the time.
Procedures In case of fire implement:
• Pull the pin.
• Aim the extinguisher at the base of the fire.
• Squeeze the handle.
• Sweep the extinguisher from side to side.
And
• Remove anyone from immediate danger
• Activate the building fire alarm system and call 911

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-004
(BESS) FACILITY
Title Rev. page of
A 5 5
METHOD OF STATEMENT – CABLE TESTING

• Confine the fire by closing all windows and doors


• Evacuate, leave the building

ACCIDENT – In case of work related accident.


1. Rescue the injured.
2. Cordon the place.
3. Prepare an incident report.
4. Establish a return-to-work program.

Unrestricted