Project Title:
Location:
Item No. Work
Estimated Quantity: 5322.00 SqM Decription: PAINT FINISH - CONCRETE
1. QUANTITY TAKE-OFF
Ground Floor:
Front Side 1 49.00 3.60 176.40 D1 24 0.90 2.10 45.36
Rear Side 1 49.00 3.60 176.40 D2 4 0.90 2.10 7.56
Left/Right Side 2 10.00 3.60 72.00 D3 0.00
Second Floor: W1 24 2.40 1.20 69.12
Front Side 1 49.00 3.20 156.80 W2 24 1.50 1.20 43.20
Rear Side 1 49.00 3.20 156.80 W3 4 2.40 0.60 5.76
Left/Right Side 2 10.00 3.20 64.00
No Bldgs 2
2. MATERIALS No Face 2
3. LABOR
No. Of Men Per Team = 3
Output Per Team = 25 SqM/Day
Production
No Of Men Rate / Day SqM/Day No Of Days say
1,108.77
2,217.54
say
4435.08 5322 SqM
Quantity say
66.53 67
266.10 267
532.20 533