INSTALLATION DEPARTMENT
PRE MOBILIZATION SHEET
DATE: 8/14/2018
JO NO. 111416
PROJECT NAME: GRIFFIN SUITES
LOCATION: Gov. M. Roa Street, Brgy. Capitol Site, Cebu City
ELEV/ESC NO. PE1~PE2
BRIEF SPECS: 2 x Nexiez MR Series, 700Kgs. (P10), 105 m/min, 11 s/o
CONTRACT PRICE: IP: Php 960,000.00 LSM: Php 688,000.00
PERSON IN CHARGE: CKMC SUBCON: RNL
I. INSTALLATION
A. LABOR
BASE 54 x 2 108.00
PER S/O 5 x 22 110.00
SUBTOTAL 218.00
ADDITIONAL MANDAYS:
F. WITH TRANSOM PANEL 1 x 2= 2
G. WIDE JAMB @Gfloor only 1 x 2= 2
I. MELD 3 x 2= 6
TOTAL 228.00
P 430.00 x 228.00 M.D._ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _P 98,040.00
Additional 10% (Facilities, supervision. etc.)_ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ P 9,804.00
TOTAL LABOR _____________P 107,844.00
B. MATERIALS
BASE : (P 2,963.00 x 2.00 unit/s = 5,926.00
PER STOP : (P 269.00 x 22.00 s/o = 5,918.00
NON STOP : (P 205.00 x - n/s, rear opening = -
DATE: 11/24/2018
JO NO. 111416
PROJECT NAME: GRIFFIN SUITES
LOCATION: Gov. M. Roa Street, Brgy. Capitol Site, Cebu City
ELEV/ESC NO. PE1~PE2
BRIEF SPECS: 2 x Nexiez MR Series, 700Kgs. (P10), 105 m/min, 11 s/o
CONTRACT PRICE: IP: 960,000.00 LSM: 688,000.00
PERSON IN CHARGE: CKMC SUBCON: RNL
INSTALLATION
SALES BUDGET % RATIO ACTUAL EXPENSE % RATIO
BUDGET
INSTALLATION P 395,688.47 P P
Subcon 176,585.20
Materials
Labor