31.5.

2010

1
31.5.2010

1. Subbase........................................................................3
1.1 Subbase 1, 2, 3 and drive-up ramps................................4
1.2 Subbase below pipehandler............................................6

2. Mud system................................................................9
2.1 Mud tanks.....................................................................10
2.2 Mud cleaning system....................................................12
2.3 Aireated drilling and mudcooling..................................14

3. Mud pumps...................... ..............................................17


3.1 Mud pumps.......................................................................18

4. Semi trailer rig.........................................................21


4.1 Semi trailer rig and fundamentals ............................22
4.2 Rotarytable and supports........................................24
4.3 Supports under control cabin and workshop...........26
4.4 Control cabin and upper workshop..........................28
4.5 Control panel for hoisting the rig.............................30
4.6 Control panel for raising/lowering the mast............32

5. Pipehandler................................................................35
5.1 Pipe handler..................................................................36
5.2 Pipebins back support..................................................38
5.3 Drillpipe rackking beams raised....................................40
5.4 Fastening of drillpipe bins.............................................42

6. Power system and camps...........................................45


6.1 P.C.R container and generators.....................................46
6.2 H.P.U. and lower workshop...........................................48
6.3 Storage- and accomodation containers .......................50

2
31.5.2010

3
31.5.2010

1.1 HH-220, Subbase 1, 2 ,3 and drive op ramps.


Item Description Device Hoisting equipment Dimensions Pic no. Comments/Risk
Subbase no. 1 On this subbase is hole for the mousehole and it 13 mm chain slings, 10m long. 11,8m x 1,97m x 0,4m 7 Pic no.1,2 and 3 Important that subbase is centralized correctly

80 ton crane and 10t telescopic forklift.


is used to centralizing the rig over the holetop. tons over holetop./No risk but heavy.

Subbase no. 2 On this subbase is a base for rig jack ups. 13 mm chain slings, 10m long. 11,74m x 1,5m x 0,65m 4 Pic no 4, 6 og 7. As subbase 1 important to cenralize
tons correctly./ no risk but heavy.
Distance frame In between subbase 1 and 2. 13 mm chain slings, 10m long. 1,5x2x0,1m Pic 5 No risk
0,15tonn
Rear driveup ramps x 2 On these ramps are diagonal support beams for 13 mm chain slings, 10m long. 6,92m x 1,06m x 0,54m Pic 8. No risk
rig.
subbase no. 3 Crosses between drive up ramps. 13 mm chain slings, 10m long. 11,53m x 1,05m x 0,56m Pic 8. No risk
Front driveup ramps x 2 Crosses subbase 3 in extension off rear drive up 13 mm chain slings, 10m long. 11,89m x 1,05m x 0,31m pic 9,10 og 11. No risk
ramps.

4
31.5.2010

Pic1, Subbase 1 Pic 2, shackels in corners. Pic 3, 16mm shackels SWL 3,5t.

Pic 4, Subbase2 Pic 5, distance frame Pic 6, centralizing

Crane positon for rig up the subbase.

Pic 7, subbase centralized Pic 8, rear drive up ramps Pic 9, padeyes on drive-up ramps.

Pic 10, front drive up ramps. Pic 11, pinned together. Pic 12, subbase.

5
31.5.2010

1.2 HH-220, Subbase below pipehandler


Items Descriptions Device Lifting equipment LxWxH, weight Pic. nr. Comment/Risk
subbase for drilling fluid Subbase for fluid manifold and supportleg under 13 mm chain slings, 10m long. 2,5 x 2,3m x 0,5m Pic 13. No risk.
manifold. doghouse. 0,25 tons

80t. crane , 10 t. telescopic forklift


Subbase under pipehandler. On this subbase is the fastening for the 13 mm chain slings, 10m long. 10m x 3,2m x 1m Pic. 14-19 To save time when rigging up it is better to
pipehandler and cabletray for the pipehandler. 10 tons put in the upper pins first (see pic. 18 and 19)/
No risk but it is heavy.

Subbase under catwalk On this subbase is the fastening for the catwalk. 13 mm chain slings, 10m long. 10m x 3,2m x 1m Pic. 14-19 To save time when rigging up it is better to
10 tons put in the upper pins first (see pic. 18 and 19)/
No risk but it is heavy.

Semi trailer rig 5 axle trailer, carrier for the rig. 3 axle truck, with 3" pin. 17m x 2,8m x 4,4m Pic. 21. Important that the trailer is in the middle of
65 tons the ramps, and seat for the hydraulic lifting
cylinder is in the middle of their seat in the
subbase./ no risk

6
31.5.2010

Pic 13, subbase for fluid manifold. Pic 14, subbase under pipehandler. Pic 15

Pic 16, 16mm shackle. Pic 17, padeyes w. shackles. Pic 18, put in upper pins first.

Crane positon for rig up the subbase.

Pic 19, if you pull easier to put in pin

Pic 20, from this position you can lay down the whole subbase.

Pic 21, rig in the middle of the


driveup ramps

7
31.5.2010

Directions on Drillmec, HH series rig.

Hægri
Right
Recht

Aftan
Framan
Rear
Front
Heck
Front

Vinstri
Left
Links

8
31.5.2010

9
31.5.2010

2.1 HH-220, Mudtanks.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Mudtank 1 Trailer with mudtank, with space for the 16 mm chainslings, 10m long 13,75m x 2,5mx3,3m, 22tons. Pic nr. 1-5 Important to have correct position, use

80t. crane, 10t. telesc. forklift


shaleshakers on top of it. SWL 10t p/leg. 5 distance bars from subbase/ No risk but
tons websling. heavy.
Mudtank 2 Trailer with mudtank, with suction for the 16 mm chainslings, 10m long 13,75m x 2,5mx3,3m, 22tons. Pic nr. 6-7 On mudtank 1 are distance bars for
mudpumps on one side. SWL 10t p/leg. 5 positioning, very important so you can lay
tons websling. down walkways between tanks/no risk.

Mud mixing tank Includes pumps for mud cleaning, mud mixing 16 mm chainslings, 10m long 13,75m x 2,5mx3,3m, 36tons. Pic nr. 8-10 If not possible to lay down w. crane use the
and mudcooler. SWL 10t p/leg. 5 truck to positioning and use the crane to free
tons websling. from the truck. / no risk

Shale shaker 1 Includes shaleshaker and connection from the 16 mm chainslings, 10m long 4m x 2,8m x 1,8m, Pic nr 11 and 12 Positon on the top off the pits next to the rig.
flowline. SWL 10t p/leg. 6tons. Sit on pins on top pff the mudtank (see pic.
14). No risk

10
31.5.2010

Pic 1, 5t web sling. pic 2, 16mm chain sling Pic 3, telescopic padeye.

Pic 4, distance pars Pic 5, line up from subbase Pic 6, distanc bars between tanks

Pic 7, Pic 8, Mud mixing position w. truck Pic 9, 10t roundsling.

Crane position

Pic 10, pipes from mudmixer Pic 11, shaleshaker 1. Pic 12, 13mm chainsling.

11
31.5.2010

2.2 HH-220, Mud cleaning system.


Items Descriptions Device Lifting equipment LxWxH, weight Pic. nr. Comment/Risk
Shaleshaker + mud cleaning Includes shale shaker, desander and desilter. 13 mm chain slings, 10m long. 4 m x 2,8m x 2,5m, Pic nr. 17-19 Next to shaleshaker 2 and sits in pins on top of

80 t crane, 10t telesc. forklift.


system. SWL 6,5t p/leg. 8tons. mudtank 1 (see pic 14)./ no risk

Walkway between shale Sits between Shaleshakers 1 and 2. 13 mm chain slings, 10m long. 1,9m x 1,15m x 0,2m Pic nr 20 og 21. Goes in seats between the shakers./ no risk
shakers. SWL 6,5t p/leg. 0,28tons
Walkways between mudpits. Sits between mudtank 1 and mudtank 2, 13 mm chain slings, 10m long. 1,95m x 1,95m x 0,18m Pic nr. 16 Goes in seats between the shakers./ no risk
ditance between tanks important. SWL 6,5t p/leg. 0,38 tons
Flowline Comes from shaleshaker 1 in 2 joints connects Pic nr. 22-24 No risk
to wellhead.

12
31.5.2010

Pic 13, Shale shaker 1 Pic 14, positioning pin f. shakers Pic 15,

Pic 16, walkways between mudtanks. Pic 17, diverter between shakers Pic 18, shale shaker 2

Pic 19, Pic 20, walkways between shakers Pic 21, walkways between shakers

Position of crane (Mud tank2, pos for mud tank 1 is 2-3m


closer to mudtank 1).

Pic 22, flowline Pic 23, flowlin Pic 24, puller f. flowline

13
31.5.2010

2.3 HH-220, Aireated drilling and mudcooling.


Items Descriptions Tæki Lifting equipment LxWxH, weight Mynd nr. Comment/Risk
Separator Container frame includes tank to seperate air 16 mm chainslings, 10m long 8m x 2,42m x 2,6m, Pic nr. 25-27 Sits on beamframe on top of mudtanks./ risk,
and fluid while aireated drilling. SWL 10t p/leg. 8t. falling.

80 ton crane
Mud cooling system Container frame includes fan to cool mud. 16 mm chainslings, 10m long 6m x 2,6m x 2,6m, Pic nr. 28-29 Sits in container locks on top of mudmixer./
SWL 10t p/leg. 8tons. risk, falling.

14
31.5.2010

Pic 25, separator Pic 26, position of separator Pic 27, beam frame for separator

Pic 28, mud cooler Pic 29, container seat. Pic 30,

pic 31, standard container lassing


corner.

Position of crane

Pic 32, Pic 33,

15
31.5.2010

17
31.5.2010

3.1 HH-220, Mudpumps.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Mudpump 1 Mudpump and electrical motor 16mm chainsling , 9,3m x 2,55m x 3,05m, Pic nr. 1-5 Very important that footprint is levelled and
SWL 10t p/leg, 9m 34tons. can take heavy load./ Risk, very heavy load.
long spreader beam with container
twistlocks.

80 t crane
Mudpump 2 Mudpump and electrical motor 16mm chainsling , 9,3m x 2,55m x 3,05m, Pic nr. 6-8 Very important that footprint is levelled and
SWL 10t p/leg, 9m 34tons. can take heavy load./ Risk, very heavy load.
long spreader beam with container
twistlocks.

18
31.5.2010

Pic 1, 16 mm chain slings Pic 2, twistlocks Pic 3, on motorside, 4 links shorter

Pic 4, pos. 40 cm from mudtanks Pic 5, distance bars Pic 6,

Crane pos. for mudpump 2 (w. 80t crane it have to be 3m closer


mudpump 1). Pic 7, distance bars Pic 8, standpipe + killline. Pic 9, sucction manifold, pos.

Pic 10, storage fordistance bars Pic 11, storage for distance bars.

19
31.5.2010

20
31.5.2010

21
31.5.2010

4.1 HH-220, Semi trailer Rig and fundamentals.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Semi trailer Rig Trailer with 5 axle includes drilling mast and 17m x 2,8m x 4,4m Pic 1 og 2 Important that the trailer is inn the middle of

80t crane, 10t telesc.forklift


toppdrive. 65 tons the ramps, and seat for the hydraulic lifting
cylinder is in the middle of their seat in the
subbase./ no risk(see pic 6).

Lifting Cylinder x4 Lifting cylindir to lift up semi trailer rig 13 mm chainsling(see pic. 3). 5m x 0,6m x 0,6m Pic 3-6 No risk
2,5 tons.
Walkways x8 Walkways around rig. Walkways are in three 13 mm chain slings, 10m long. 2,94-5,37m x 1,83m x 0,68m Pic 8-12 Very good to use crane but its als no problem
diffrent lengths, 2,94m, 4,1m og 5,37m. SWL 6,5t p/leg. to use telesc. forklift as well./Enginn áhætta.

22
31.5.2010

Pic 1, trailer rig in middle of ramps Pic 2, seat for lifting cylinder pic 3, 13mm chainsling on cyl.

Pic4, Lifting cylinder. Pic 5 , lifting cyl. in seat. Pic 6, cups for lifting cylinders.

From this position you can put up


everything attached to the rig.

Pic7, telesc. diagonal supports Pic 8, walkways Pic 9

Pic 10, fork lift used for walkways Pic 11 Pic 12

23
31.5.2010

4.2 HH-220, Rotarytable and supports.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Rotary table. Rotarytable with bushings. 13 mm chain slings, 10m long. 3,4m x 2,45m x 3,5m Pic 13 - 18 Very important to put in rear pin first./ not

80 t krani, 10t skotb.lyftari


SWL 6,5t p/leg. 9tons. much risk.
Supporting frame under Supporting frame under upper workshop 13 mm chain slings, 10m long. 5,3m x 2,34m x 0,53m Pic 19 and 20 Risk, falling
upper workshop connected to rotarytable w. lockking pins. SWL 6,5t p/leg. >1 tons

Supporting frame 1 under Supporting frame under doghouse connected 13 mm chain slings, 10m long. 6,2m x 2,5m x 0,66m Pic 20 Risk, falling
doghouse. to rotarytable w. locking pins. SWL 6,5t p/leg. >1000kg

Supporting frame 2 under Supporting frame under doghouse connected 13 mm chain slings, 10m long. 2,5m x 2,2m x 0,6m Pic 22-27 Risk, falling
doghouse. to supporting frame 1 w. locking pins. 2 legs SWL 6,5t p/leg. >1500kg.
to subbase.

24
31.5.2010

Pic 13, rear padeyes rotarytable. Pic 14, front padeyes rotarytable. Pic15

Pic 16, pos. rear end of rig Pic17 Pic 18, important put rear pin first

Pic 19, support frame upper worksh. Pic 20, right side of rotarytable Pic 21, support frame 1 doghouse
From this position you can put up

Pic 22, support frame 2, doghouse Pic 23, Pic24,

25
31.5.2010

4.3 HH-220, Supports under control cabin and workshop.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Rigfloor in front of doghouse Sits between rotary table and doghouse. 13 mm chain slings, 10m long. 7,62m x 2,13m x 0,85m Pic 28-30 Risk, falling working from stairs.
SWL 6,5t p/leg. >2tons

80 ton crane
Rigfloor in front of upper Sits between rotary tabke and upper 13 mm chain slings, 10m long. 6,07m x 2,6m x 0,53m Pic 31-36 Risk, falling working from stairs.
workshop. workshop. Fingers to storage collars. SWL 6,5t p/leg. >2tons

26
31.5.2010

Pic 25, support legs for doghouse Pic 26, cylinders in supp.legs are Pic 27
driven by forklift.

Pic 28, rigfloor in front of doghouse. Pic 29, rigfloor in front of doghouse Pic 30, pinned, work from stairs

Pic 31, rigfloor in front of worksh. Pic32, Rigfloor storage foor collars. Pic 33, pinned, work from stairs
From this position you can put up
everything attached to the rig.

Pic 34, padeyes on rigfloor. Pic 35, Pic 36,

27
31.5.2010

4.4 HH-220, Control cabin and upper workshop.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Supporting legs x2 supporting legs under rotary table, goes 13 mm chain slings, 10m long. 5m x 0,25m x 0,25m Pic 37--39 Cylinder driven pins driven with forklift./Risk,
through the table down to subbase. SWL 6,5t p/leg. >1ton falling, working from stairs.
Doghouse(drillers cabin) 20´ container with controlpanel for rig. Comes 13 mm chain slings, 10m long. 6,55m x2,6m x 3,5m 7 Pic 40-45 Risk, falling, working from stairs.

80 ton crane
on left side of rotarytable. SWL 6,5t p/leg. tons
Upper workshop (rigfloor´s 10´ container is located in right hand side of 13 mm chain slings, 10m long. 3,5m x 2,5m x 3m Pic 46-48 Risk, falling, working from stairs.
workshop) rotary table. SWL 6,5t p/leg. >5tons

28
31.5.2010

Front

Pic 37, support legs. Pic 38, pin cylinder f. support legs Pic 39, support through rotary table.

Pic 40, important, hook inside out. Pic 41 Pic 42, left side of rotary table

Right hand
Left hand

Pic 43, pins, working from stairs. Pic 44, pins, working from stairs. Pic 45, close up

Rear
Pic 46, upper workshop. Pic 47, right han side of rotary Pic 48, pinholes for workshop and
doghouse.

29
31.5.2010

4.5 HH-220, Control panel for hoisting the rig.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Mast safety handrails Pinned on top of stairways. Roundsling >200kg Pic nr. 49 Risk falling.
Controlpanel for lifting the Located right side close to lifting cylinder. Pic 51-52

10 t. telesc. forklift.
semitrailer rig Controlpanel for lifting cylinders and cylinders
to raise teh mast.

Locking plates for cylinders. Locks goes to seat in cylinder. You can level Pic 53
the rig with metal thins you put in the lock.

Fluid manifold. Includes fluid manifold, pressuremeters for 13 mm chain slings, 10m long. 9,45m x 1,84m x 1,3m, Pic 58-60 Locks with pins in doghouse./ Falling.
rig. SWL 6,5t p/leg. 2tons

30
31.5.2010

Pic 49, Pic 50, Pic51, for level the rig.

Pic52, control panel for liftingcyl. Pic 53, locking plate f. liftingcyl. Pic 54, seats f. locks.

From this position you can put up Pic 55, lock in. Pic 56, telesc. diagonal supports. Pic 57, rig lifted up.
everything attached to the rig.

Pic 58, fluid manifold group Pic 59, position of fluid manifold Pic 60, subbase for fluid manifold

31
31.5.2010

4.6 HH-220, Control panel for raising/lowering the mast.


Items Descriptions Device Lifting equipment LxWxH, weight Pic. nr. Comment/Risk
Mast Mast with topdrive. Pic. nr.61-63 Important to free topdrive from rig move
locks.

Pic. 61, raising control pos. Pic 62, when mast up, bolts for mast Pic 63, controlpanel for lifing mast.

32
31.5.2010

33
31.5.2010

5.1 HH-220, Pipe handler


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk

80t crane, 10t telesc. forklift


Pipehandler In transport it is moved on 2 axle trailer. 16 mm chainslings, 10m long 19,3m x 2,7m x 5,3m Pic 1-15 Important, sling 10 links shorter in upper
SWL 10t p/leg. 25tons. padeyes(closer to crane). / small risk, heavy.

Support leg for pipehandler. Leg only used when pipehandler is in horizonal 1,5m x 2m x 0,2m Pic 5 It is not important to remove this leg but it is
position. 100 kg important to change his posistion.

Raising sheave Sheave to pull when pipehandler is raised. Pic 7-9 Important to have pins in correct position.

34
31.5.2010

Pic. 1, 10 links shorter. Pic. 2, padeyes for pipehandler. Pic. 3, Position for pipehandler.

Pic. 4, pinholes for support leg. Pic. 5, support leg. Pic 6, raisingwire for pipehandler.

Position of crane when working on pipehandler

Pic 7, sheave for raising th pipehandl. Pic 8, important that pins are correct Pic 9, sheave locked to rotary table.

Pic 10, connection of cran wire and Pic 11, raising pipehandler. Pic 12, control for pipehandler raising.
raising wire

35
31.5.2010

5.2 HH-220, Pipe bins back support.


Items Descriptions Device Lifting equipment LxWxH, weight Pic. nr. Comment/Risk
Back support for Backsupport supporting the drillpipebins when 13 mm chain slings, 10m long. 5,6m x 3,25m x 1m, Pic. 16-21 No risk, use forklift with manbasket to release

80t crane, 10t telesc. forklift


drillpipesbins x4. they are raised. SWL 6,5t p/leg. >2tons fro crane.

Drillpipe bins x 13. Drillpipebins for 14 pc. of 5" drillpipes. 13mm chainsling,10m long. 13,55m x 0,77m x 1,55m, 8 Pic 22-24 No risk.
5ton roundsling. tons if drillpipes included.

36
31.5.2010

Pic 13, cylinder to damp. Pic 14, pipehandler´s fastening. Pic 15, important position for pins.

Pic 16, backsupport Pic 17, marked together with letters Pic 18, eyepads for backsupport.

Position of crane when working on pipehandler


Pic 19, backsupport Pic 20, fastened with pins.

Pic 22, drillpipe bins. Pic 23, 5 ton roundsling Pic 24, crane position

37
31.5.2010

5.3 HH-220, Drillpipe bins raised.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Drillpipe bins x13. Drillpipe bins for 14 pc. of 5" drillpipes. Special made spread beam(see pic. 13,55m x 0,77m x 1,55m, Pic 27-36 Drillpipe bins are marked to subbase with

80t crane, rigkrane


27). 8tons, if including drillpipes numbers./Not much risk

38
31.5.2010

Pic 25, safety pins Pic 26, Pic 27, spread beam for hoist pipebin

Pic 28, hokk inside out. Pic 29, start to lift pipebin. Pic 30, operator pos.

Position of crane when working on pipehandler

Pic 31, hoisting a drillpipe bin. Pic 32, positioning a drillpipe bin. pic 33, marked w. numbers.

Pic 34, upper seat for drillpipebin. Pic 35, lower seat for drillpipebin Pic 36, upper seat.

39
31.5.2010

5.4 HH-220, Fastening of drillpipe bins.


Items Descriptions Device Lifting equipment LxWxH, weight Pic. nr. Comment/Risk

Borkrani

40
31.5.2010

Pic 37, Pic 38, fastening pins Pic39, important to hook correctly
upper wire outside.

Pic 38, rear backsupport is put in after you have filled the others
with drillpipebins.

41
31.5.2010

42
31.5.2010

43
31.5.2010

6.1 HH-220, P.C.R. container and generators.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Cable trays for pipehandler Cable trays for mudtanks and pipehandler, lies 13 mm chain slings, 10m long. 8,39m x 0,82m x 0,65m Pic 1-3 Usually those cabletraays is laid down when

80t crane, 10t telesc. forklift


x2 from P.C.R.(Bentec) along rig to pipehandler. SWL 6,5t p/leg. working on subbase or rig.

P.C.R.(Bentec) 40´ container with rigs power control. 16 mm chainslings, 10m long 12m x 3m x 3.02, Pic. 4-7 There is distance bars from mudpumps to
SWL 10t p/leg. 22 tons PCR, rule of thumb is that you can lay down 2
cable trays in between. /no risk but heavy.

Genarators (Caterpillar) 40´container including 1150 kw generators. 16 mm chainslings, 10m long 12m x 3,15m x 3,15m Pic. 8-12 Distance bars to lay down./Not much risk but
SWL 10t p/leg. 28 tons heavy.

44
31.5.2010

Pic 1, cable trays for pipehandler. Pic 2, eyepads for cabletrays. Pic 3, color marking.

Crane position for PCR

Pic 4, PCR (Bentec). Pic 5, hokks inside out. Pic 6, Distance bars.

crane pos 3

Pic 7, little more than 2 cabletrays. Pic 8, Genarator 1 Pic 9, distance bars.

crane pos 2

crane pos 1

Crane pos. for generators, due to small


crane it should be as close to genarators
Pic 10, use forklift and safety Pic 11, genarator 2. Pic 12, genarator 3.
manbasket.

45
31.5.2010
manbasket.

6.2 HH-220, H.P.U. and lower workshop.


Items Descriptions Device Lifting equipment LxWxH, weight Pic. nr. Comment/Risk
Glussavagn (HPU) Hydraulic power trailer for rig 13,68m x 2,55m x 4,2m Pic. 13 and 14 Lined up in one side of rig. / No risk

80t crane, 10t telesc. forklift


40 tons
Cable trays Cable tray in between PCR and mudpumps 2,10m x 0,5m x 0,3m Pic. 15-19 No risk
and PCR and genarator and lies over to mud
mixer container
Storage container and air 20´ containers includes rig spare parts and rig 16 mm chainslings, 10m long 6m x 2,5m x 2,55m 7- Pic. 22 No risk but heavy
comressor container. aircompressors. SWL 10t p/leg. 15 tons.

Lower workshop 40´ container including workshop and welding 16 mm chainslings, 10m long 12m x 3m x 2,88m, Pic. 23 and 24 No risk but heavy
for rig. SWL 10t p/leg. 15 tons

46
31.5.2010

Pic. 13, HPU (Hydrolic power unit) Pic 14, position to rig Pic 15, cable trays to mud mixing.

Pic 16, cable trays to mud mixing. Pic 17, cable to mudmixing cont. Pic 18, cable trays mudpumps.

Crane position for camp and workshop Pic 19, cable trays genarators. Pic 20 overview PCR and genarators. Pic 21, overview HPU.

Pic 22, overview Pic 23, hooks inside out. Pic 24, lower workshop.

47
31.5.2010

6.3 HH-220, Storage- and accommodation containers.


Items Descriptions Device Lifting equipment LxWxH, weight Pic nr. Comment/Risk
Storage container x2 Storage container, mud chemicals and mud 16 mm chainslings, 10m long 6m x 2,5m x 2,55m Pic. 25 Not much risk but heavy.

80t crane, 10t telesc. forklift


pump spare parts. SWL 10t p/leg. 10 - 20 tons
Accommodation x4 Containers including crew facility, WC, 16 mm chainslings, 10m long 12m x 3m x 2,88m, Pic. 26 - 31 Crew facility and toolpushers office is on 2nd
toolpushers- and mechanics office and SWL 10t p/leg. 10-12 tons level./ Risk, falling, use forklift with safety
cantine. basket.

48
31.5.2010

Pic25, chemicals and mudp. parts Pic 26, work safely Pic27, crew facility 2nd floor

Pic 28, overview accommodation. Pic 29, accommodat.side-to-side w. rig

Crane position for accommodation and workshop.

Pic 31, Accommodation and storage container on rigs safety plan.

49