Академический Документы
Профессиональный Документы
Культура Документы
Item No.
1 CYCLONE FABRICATION
2 CYCLONE FABRICATION
3
Connection Channel Between The Twin Cyclones
4 DUCT FROM CYCLONES TO FAN-287
7
8
9 Duct from Fan to V-Seperator 288
10
11
12 By Bass Duct 290
13 GAINTRY GRIDER SUPPORTER
TOTAL
Labor Cost
Total Weight
(Ton) Unit Price
Erection Dimensions
صور في الواقع Level M Width (m)
Labor Cost Tool/ consumable cost Equipment Cost Direct Total Cost
Amount unit price Amount unit price Amount Unit Price
327
34042.8391283595 186.6280521
513
Manhours
Total M.H
(11)='(1)*'(10)
720
3392
6876
2808
333
3114
5355
387
531
23516
Price of dollars at this time 450.00 .ي.ر SUMMARY OF AVERAGE COST FOR FABRICATION
CYCLONE DUCT 287 DUCT 285 DUCT289 Labor Tool/ Consumable Equip. Cost Total Direct cost Man Hour
Total weight
Item (Ton) Total Man
TOTAL WEIGHT (TON) 25.71 17.605 3.952 unit cost total cost unit cost total cost unit cost tptal cost unit Total unit MH Hour
5.33
FAB WELDER FIT RIG HELPER FAB WELDER FIT RIG HELPER FAB WELDER FIT RIG HELPER FAB WELDER FIT RIG HELPER Duct Fabrication 74.632 $ 216.35 $ 16,146.87 $ 84.86 $ 6,333 $ 30.75 $ 2,295 $ 331.96 $ 24,774.9 225 16812
NOS. 93 149 96 60 262 100 158 99 2 215 32 19 8 1 37 24 18 6 3 24 structure Fabrication 3.808 $ 115.37 $ 439.31 $ 73.79 $ 281 $ 2.63 $ 10 $ 191.78 $ 730.31 125 477
UNIT PRICE 4615.38 4615.38 3846 3846 3076.92 4615.38 4615.38 3846 3846 3076.92 4615.38 4615.38 3846 3846 3076.92 4615.38 4615.38 3846 3846 3076.92
Labor
AMOUNT 429230.34 687691.6 369216 230760 806153 461538 729230 380754 7692 661537.8 147692.16 87692.22 30768 3846 113846 110769.1 83076.84 23076 11538 73846.08
Total Amount $ 5,606.78 $ 4,979.45 $ 852.99 $ 671.79
welding rodes $ 1,628 $ 600 $ 300 $ 125
$ 17,118
DUCT 286 DUCT 288 DUCT 290 GANITERY GRIDER SUPPORT
TOTAL WEIGHT (TON) 3.168 18.51 0.357 2.758
FAB WELDER FIT RIG HELPER FAB WELDER FIT RIG HELPER FAB WELDER FIT RIG HELPER FAB WELDER FIT RIG HELPER
NOS. 18 15 0 8 20 81 84 69 24 130 3 4 1 1 4 7 0 7 0 20
UNIT PRICE 4615.38 4615.38 3846 3846 3076.92 4615.38 4615.38 3846 3846 3076.92 4615.38 4615.38 3846 3846 3076.92 4615.38 4615.38 3846 3846 3076.92
Labor
AMOUNT 83076.84 69230.7 0 30768 61538.4 373845.8 387691.9 265374 92304 399999.6 13846.14 18461.52 3846 3846 12307.68 32307.66 0 26922 0 61538.4
Total Amount $ 543.59 $ 3,376.03 $ 116.24 $ 268.37
welding rodes $ 75 $ 500 $ 12 $ 25
cutting wheels $ 30 $ 55 $ 5 $ -
Tool/ Grinding wheels $ 3 $ 5 $ 5 $ 6
Consumable oxygen/ LPG $ 15 $ 75 $ - $ 200
Cost Others $ 5 $ 20 $ - $ - 0.016
welding machine $ - $ - $ - $ -
Total Amount $ 128 $ 655 $ 22 $ 231
Crane 50 Tonnes $ - $ - $ - $ -
Equipment Hydera 14 Tonnes $ 10 $ 50 $ 5 $ 10
Total Amount $ 10 $ 50 $ 5 $ 10
Man Hour/ Ton 173 189 328 111
Manhours
Total MH 549 3492 117 306
item name
Erection fabricated work
s/n equipment no صور في الواقع
3 V-seperator
11 3.21 $ 79 $ 253 $ - $ -
32 7.40 $ 109 $ 807 $ 28 $ 210
32 6.89 $ 51 $ 350 $ 15 $ 100
16.4 7.44 $ 55 $ 410 $ 7 $ 50
32 3.323 $ 58 $ 193 $ 33 $ 110
32 0.932 $ 105 $ 97 $ 80 $ 75
32 2.5 $ 136 $ 340 $ 19 $ 47
29 2.68 $ 120 $ 322 $ 18 $ 49
22 3.05 $ 112 $ 342 $ 17 $ 52
22-15 3.25 $ 148 $ 480 $ 17 $ 55
22-28 3.73 $ 229 $ 855 $ 17 $ 62
7 3.05 $ 215 $ 655 $ 17 $ 53
7 2.147 $ 272 $ 584 $ 20 $ 42
42 3.05 $ 212 $ 648 $ 17 $ 53
4.395 $ 470 $ 2,066 $ 40 $ 174
487.4 $ 25,982 $ 6,220
Equipment Cost Direct Total Cost Manhours
unit price Amount Unit Price Amount Unit M.H Total M.H
(6) (7)='(1)*'(6) (8)='(2)+'(4)+'(6) (9)='(1)*'(8) (10) (11)='(1)*'(10)
$ 128 $ 33,176 $ 173 $ 44,969 38 9774
$ 126 $ 9,080 $ 180 $ 13,000 45 3243
$ 9 $ 30 $ 88 $ 283 84 270
$ 8 $ 60 $ 145 $ 1,077 109 807
$ 9 $ 60 $ 74 $ 510 55 379
$ 9 $ 70 $ 71 $ 530 58 432
$ 6 $ 20 $ 97 $ 323 60 199
$ 10 $ 9 $ 195 $ 182 106 99
$ 5 $ 12 $ 160 $ 399 144 360
$ 7 $ 20 $ 146 $ 391 128 343
$ 16 $ 50 $ 146 $ 444 112 342
$ 18 $ 60 $ 183 $ 595 158 514
$ 16 $ 60 $ 262 $ 978 244 910
$ 16 $ 50 $ 248 $ 758 227 692
$ 5 $ 10 $ 296 $ 636 290 623
$ 14 $ 43 $ 244 $ 744 212 647
$ 45 $ 198 $ 555 $ 2,438 460 2022
$ 47,848 $ 80,050 27386
$ 164.24
Erection fabricated work
s/n equipment no صور في الواقع
1 5316AS1
2 5316AS2
2 5316AS3
3 4925AS1
4 4925AS2
5 4625AS2
4625AS3
6 4516AS1
4516AS2
7 COMPRESSED AIR PIPING
8 COOLING WATER PIPING FOR ROLLER PRESS
Total
Fabrication & Erection with supprots Piping- Cement Mill
2070
Erection fabricated work
s/n equipment no صور في الواقع
1 DUCT 287
2 DUCT 288
2 DUCT 289
3 DUCT 290
8
13
Labor Cost Tool/ consumable cost
TOTAL AREA (M2)
Unit Price Amount unit price Amount
Level M
(1) (2) (3)='(1)*'(2) (4) (5)='(4)*'(1)
47 790.0 7.3 5798.6 0.73 577
16 430.0 2.6 1135.2 0.56 241
25 420.0 2.4 1012.2 0.33 139
16 70.0 1.4 95.9 0.11 8
0.0 0
1710.0 8041.9 963.8
Equipment Cost Direct Total Cost Manhours
unit price Amount Unit Price Amount Unit M.H Total M.H
(6) (7)='(1)*'(6) (8)='(2)+'(4)+'(6) (9)='(1)*'(8) (10) (11)='(1)*'(10)
0.15 119 8.2 6494 7.2 5704
0.02 9 3.2 1385 2.6 1120
0.02 8 2.8 1159 2.3 983
0.01 1 1.5 104 1.4 96
0 0.0 0 0
136 0 9142 7903
5.34614035088
338.571068421