Вы находитесь на странице: 1из 5

Energy Metering For Distribution Loss Estimation- Problems and Solution

S. Shyam Sundar K. Devender Rao J. Sreedevi R.Raghunatha

R.S.Shivakumara Aradhya R.K.Hegde

Power Systems Division


Central Power Research Institute
P.B.No.8066,Sadhashivanagar,
Bangalore – 560 080
shyamsundar@powersearch.cpri.res.in

Abstract- This paper presents the problems and errors maximum demand, voltage, current, power factor, kWh,
encountered by the authors during recording data with kVArh etc. are recorded over a period of, say, one month at
electronic energy meters on 11kV feeders & LT circuits of fixed time interval of 30 minutes. This data is known as
distribution system as a part of loss estimation. It emphasizes Load Survey data (LS data).
the requirement of standardization in this area .The paper also
presents important features of software developed to circumvent
the problem faced. CPRI has been recording LS data of about 46
number 11 kV feeders with more than 2000 number LT
Keywords: Electrical network, distribution losses, load survey feeders in a distribution company for more than one year.
data, electronic energy mete, discrepancies, software During the course of the recording, numerous problems
were encountered almost jeopardizing the ambitious attempt
1. INTRODUCTION of estimating annual energy loss for a large distribution
company network taking into account seasonal variation of
load.
The Indian Power Sector has challenging task to
face during the coming years. The Generation and This paper presents the problems faced while
Transmission is well managed with regard to future recording the LS data required for loss estimation using
requirements and maintenance in the country. The electronic energy meters, downloading the recorded data into a
Distribution sector is facing a big challenge as the cost of common meter reading instrument. Corrective measures
generation, transmission and distribution is not recovered in adopted while using the data for loss estimation is presented in
spite of higher tariff. detail.

There are various schemes undertaken by the 2. ENERGY METERING FOR LOSS ESTIMATION
Government of India such as APDRP (Accelerated Power
Development Reform Programme) and other training Distribution loss involves both technical and
Programmes such as DRUM (Distribution Reforms and up commercial loss. The later may comprise of pilferage, theft,
gradation Management) to improve the efficiency of meter malfunctioning etc. Technical loss estimation involves
distribution network. The first requirement under the calculation of resistive loss for peak load condition and
reforms would be to understand the type of losses in power correcting it with the Loss Load Factor .Commercial loss is
distribution network and to find the factors influencing the determined by the difference between the input energy to a
losses. If 11 kV & LT feeder loss estimation is done certain feeder and deducting the sum of the metered energy at
accurately and segregated feeder category and Ampere- the consumer end and the technical loss for the feeder.
kilometer wise, it would lead to a better understanding of
the technical and commercial losses. If technical losses are It is to be recognized that there exists a need for time
found to be higher, it could be controlled by various synchronized recording of data of all the energy meters in the
technical methods Distribution feeder, namely, at the sending end of the feeder,
such as refurbishment/bifurcation of lines, introducing new LT side of the distribution transformer & consumer
transformers/capacitors etc. On any electrical network, for premises.As providing such sophisticated meters at the
the purpose of loss estimation, feeder parameters such as consumer end, in particular for LT consumer is expensive,
at least the feeder and the DTR meters shall have capability to might cause a problem if those data becomes a requisite for
store the LS data at the pre-defined time interval. the estimation of losses and may lead to error in the results.
In order to facilitate adoption of automated
information and data processing to carryout load flow 3.3 Missing data:
calculations, it is essential that the LS data collection by all the The LS data is in the present exercise is to be
energy meters shall be: logged every 30 minutes .Table 2 shows the missing data
i. With standard data format from 00.00 Hrs of 2.9.2005 to 18.30 Hrs of 6.9.2005.
ii. free from missing data
iii. time synchronized 3.4 Technical difficulties:
iv. free from technical difficulties and
v. free from storing abnormal values 3.4.1. Incompatibility between probe and meter data
output port :
In addition it is essential that all the meters are working
for the total duration of the loss measurement exercise, a Optic probes are used for downloading the LS
minimum of one year. data from the energy meter to Common Meter Reading
Instrument (CMRI). Firstly, these are different for
3 PROBLEMS ENCOUNTERED different manufacturers. Moreover it was initially
experienced that meters of Manufacturer B with 45% of
3.1 Lack of standardization of data format: the meters in a feeder exhibited communication error due
to incompatibility between probe and the meter optic
The general observation is that the LS data circuits. Hence a case for standardization of optic probes
parameters to be recorded in the energy meter for loss technology and their physical dimension to enhance the
estimation are not standardized either by the meter compatibility between the probes and the meter. From the
manufacturers or by the utilities. Below is a reference to the interest of the work, we recommend a common probe for
case where four different manufacturer’s meters are found in a all the meters in the market.
particular distribution circle, where, the LS data is recorded
for loss estimation. 3.4.2 Software versions:

i. Manufacturer A gives the Parameters in MVA, MW, As the utilities in general, fail to keep track of
MVAr+, MVAR-. the batch of manufacturing of the meter deployed in a
ii. Manufacturer B has interchanged the rows and particular area, it often becomes difficult to use
columns giving the parameters as Kwh_Imp, appropriate version of the Base Computer Software
KVARh_Lg_Imp, KVARh_Ld_Imp, KW_D-Imp, required to upload the recorded data from CMRI to the
KVA_D_Imp & APF. computer. One manufacturer provided at least three
iii. Manufacturer C gives the parameters as Energy versions of the software. It was also experienced that
(kWh), Energy ( KVArh), Energy (kVAh), Demand unless proper version of software is used, the uploading
(kW) & APF. takes more time. This process becomes a bottleneck if the
iv. Manufacturer D gives two PF’s, Voltage in V and numbers of energy meters to be downloaded per day are
current in Amp. more in number.

At least there will be two different types of meters for Obtaining the correct version of the CMRI
a feeder, one type for feeder input measurement and the other software for all the manufacturer’s meters took CPRI
type for DTR output measurement. Print out of the recorded almost one year wasting valuable time, resources and
data for the above meters are given in Table 1. Showing money. Hence standardization of the CMRI software and
different formats for data recording and storage. base Computer Software will also help Energy Audit
work and make it simpler.

3.2 Time synchronization: 3.5 Abnormal values in stored data:

Real Time Clock (RTC) errors were noticed in The recorded data on inspection showed
many of the meters of manufacturer C. It was noticed that abnormally high values for some of the parameters. Table
the date and time on the display of the energy meter to be 3 shows a value of 3439.4 kWh recorded at the output of
different from the actual date and time of data recording. As 100 kVA distribution transformer, which is again a tough
seen from Table 2 the recorded data gives date and time task to physically verify in such a huge data base.
which is unrealistic such as year 2005 instead of the current
year 2006. Some times the data for few hours or days might 3.6 Meters not working in the feeder:
be missing from the date and time of downloading which
During the course of the monitoring, it was found viii.Where the sending end Feeder meter data is
that initially that 21 % of the total meters were not working completely available for the study period under
for 14 feeders in which 12 % of meters belong to consideration, the peak demand date and time is
Manufacturer B, 5% of meters belong to Manufacturer C determined based on the peak demand recorded by
and 4.3% of meters belong to Manufacturer D. It is to be the feeder meter during the specified period. The
recognized that accuracy of the loss estimation directly software prepares a load flow data based on the
depends on the number of meter correctly working during corresponding date and time using the load survey
the whole period of data recoding. data of the DTR meters and feeder meter. While
preparing the load flow data missing data of any
4. ATTEMPT TO OVERCOME THE PROBLEMS DTR meters are appropriately estimated based on
the corresponding transformer ratings. Further, the
With the current experience of performing Energy software computes the Loss Load Factor (LLF) and
Loss Estimation in a large distribution network CPRI is Load Factors (LF) for the corresponding period and
circumventing the problems faced by modifying the energy for the specific feeder under consideration. The
loss calculation software to take care of the problem faced. software also performs the energy summation at
the following is the main feature of the software : each meter for the period of interest for use in the
energy audit.
i.Provides an indexed access and storage of the load ix.The software automatically executes the power
survey data based on feeder under consideration, flow based on the load flow data prepared at step
meter type (4 different manufacturers, Feeder viii, computes the technical and commercial losses
meter or DTR meter), date, time, measured unit and generates the corresponding reports. The single
(KW, KVAR, PF, Volts, Amps etc.). The database line diagram of the distribution network is
can be appended by successive months load survey automatically generated and the results of the load
data. flow are displayed on the same.
ii.Have different drivers to store Load Survey data of
different type of meters into a common database
and in a common data format.
iii.Has built in limit checks and filtering mechanisms 5 CONCLUSION
to filter out abnormal data from the Load survey
data, data during power failure conditions and to CPRI has undertaken a loss estimation study for
convert the load survey data into a common data one of the distribution utilities in the country. It has
format suitable for energy audit and analysis encountered the problems mentioned in this paper during
iv.Synchronizes the load survey data considering the the data collection exercise required for loss estimation.
time span difference between the actual date and These have been presented to draw the attention of other
time and the date and time recorded in the meter investigators in the loss estimation area. Software has been
under consideration. developed in-house to overcome these problems as it is
v.Synchronizes the first sample of the day of obvious that it cannot be expected that all the meters would
different type of meters where there is a difference be working at any given point of time and replacing the
in definition of first sample. As an example some faulty meters is herculean task.
meters provide the first sample corresponding to
0:00 hours of the day and some other meters
provide the first sample corresponding to 0:30
hours.
vi.Provides facilities to specify multiplication factor
for each meter to correct the load survey data due
to errors in CT, PT ratios recorded in the meter.
vii.Provides a window of time frame for which the
energy audit studies are needed. User may select
the starting date and ending date defining the time
period for which energy audit calculations are
needed. The software determines the peak load
conditions within specified duration by using two
distinct processes as explained in subsequent
sections
Table1: Data recorded in 4 different manufacturer's meters showing different formats

A. Data from meter of Manufacturer A used as 11 kV feeder meter

[DATA]
Date : 2/7/2006
Time For.MVA For.MW For.MVAr+ For.MVAr-

0:30 0.3075 0.2549 0.1719 0


1:00 0.2922 0.2442 0.1606 0
1:30 0.2881 0.2401 0.1592 0
2:00 0.2851 0.2375 0.1576 0

B. Data from Manufacturer B used as LT/CT Meter

Read On : 23/04/2006 10:44:27

DATE UNIT 0:00 0:30 1:00 1:30 2:00

3/19/2006 KWh_Imp 0.75 0.74 0.74 0.75 0.75


3/19/2006 KVARh_Lg_Imp 0 0 0 0 0
3/19/2006 KVARh_Ld_Imp 1.8 1.76 1.77 1.78 1.76
3/19/2006 KW_D_Imp 1.5 1.47 1.49 1.5 1.5
3/19/2006 KVA_D_Imp 1.54 1.5 1.52 1.52 1.52
3/19/2006 APF 0 0 0 0 0

Observations: Average PF = 0

C. Data from meter Manufacturer C used as LT/CT meter

Date Time EGY(kWh) EGY(kVArh) EGY(kVAh) Demand(kW) APF


27--02--06 13:30 11820 1332.5 12727.5 5 0.87
27--02--06 14:00 11820 1332.5 12730 0 0.84
27--02--06 14:30 11820 1332.5 12730 0 0.82
27--02--06 15:00 11820 1332.5 12730 0 0.81
27--02--06 17:30 11820 1332.5 12730 0 0.99
27--02--06 18:00 11820 1332.5 12730 0 0.73
27--02--06 18:30 11820 1332.5 12730 0 0.67
27--02--06 19:00 11822.5 1332.5 12732.5 5 0.94
27--02--06 19:30 11825 1332.5 12735 5 0.95
27--02--06 20:00 11825 1332.5 12737.5 0 0.96
27--02--06 20:30 11827.5 1332.5 12737.5 5 0.94
27--02--06 21:00 11830 1332.5 12740 5 0.96

Observations: a) Demand is always shown as 5 kW or 0 kW


b) Repetitive values for Kwh,kVarh,kVAh

D. Data from meter of Manufacturer D used as feeder meter

DATE UNIT 0:30 1:00 1:30 2:00


4/21/2006 PF 0.903 1 1 0.99
4/21/2006 14 14 15.5 99.5
4/21/2006 PF 15.5 14 15.5 100.5
4/21/2006 V 6667.5 6667.5 6688.67 6604
4/21/2006 Amp 0.1333 0.1333 0.1333 1

Observations: a) Value of 15.5 is shown against PF


b) No unit is mentioned to a few rows of data
Table 2 : Missing Data in Load Survey data

LOAD SURVEY DETAILS of Manufacturer C

Meter Number 000000 CMRI Number : 0408-32687

Consumer Name : CMRI Date&Time : 13-03-2006 12:38:54

Consumer Number : From : 15/09/05 To 20/09/05

Date Time in Cum. Energy Cum. Energy DEMAN DEMAND APF


Cum. Energy
hh:mm Energy Consumed Energy Consumed D (kVA)
Energy Consumed
(kVArh) (kVArh) (kVAh) (kVAh) (kW)
(kWh) (kWh)

15/09/05 12:30 00000.000 00000.000 00005.000 00002.500 00037.500 00037.500 0.000 75.000 .99

16/09/05 04:30 00000.000 00000.000 00005.000 00000.000 00040.000 00002.500 0.000 5.000 .99

02/02/05 12:00 00002.500 00002.500 00005.000 00000.000 00002.500 00000.000 5.000 0.000 .99

02/09/05 00:00 00002.500 00000.000 00005.000 00000.000 00045.000 00042.500 0.000 85.000 .99

06/09/05 18:30 00002.500 00000.000 00005.000 00000.000 00002.500 00000.000 0.000 0.000 .99

06/09/05 19:00 00002.500 00000.000 00005.000 00000.000 00002.500 00000.000 0.000 0.000 .99

06/09/05 19:30 00002.500 00000.000 00005.000 00000.000 00002.500 00000.000 0.000 0.000 .99

06/09/05 20:00 00002.500 00000.000 00005.000 00000.000 00002.500 00000.000 0.000 0.000 .99

Table 3: Abnormal Values

Вам также может понравиться