Академический Документы
Профессиональный Документы
Культура Документы
PROJECT
Page 1 of 45
PC Construction
Title Method Statement with Job Safety Analysis for Road, Drains, Culverts, Paver Block At
Lorry Parking Area
Document No.
Contract No.
Contractor PC CONSTRUCTION
0
Rev Remarks Prepared By Prepared Checked By Checked Approved By Approved
No. Date Date Date
TABLE OF CONTENTS
Sr. No. Description
1.0 PURPOSE
2.0 SCOPE
4.0 GENERAL
5.0 METHODOLOGY
All ignition sources shall be kept off as far as possible. Tool- Box
Talk is a must before start of the job on a daily basis, as the
situation, working / operating condition may change overnight or
changes in shift.
1. Contract Document
2. Lay Out covering Drains, Roads and Culvert.
4.0 GENERAL
1. Surface Preparation
2. Road Embankment
3. Sub Grade
4. Laying of Kerbstones (as need)
5. Sub-Base
6. Aggregate Base Course
7. Prime coat
8. Bituminous Base Course or Binder Course
9. Tack / Seal Coat
10. Joints
11. Compaction of Mixtures
12. Thickness of Cores & Testing
Concrete components
Concrete mixing
Concrete testing
Formwork for foundation elements
Formwork for Skelton elements;
Work sequence for all elements.
b. Procedure:
Drawing Approval
Excavation
Cement:
Aggregates:
Water:
Mixed Concrete:
Concrete mixing
Concrete mixing shall be done in one of the central batch
plants approved by the Engineer; it shall be transported in
Truck mixers fulfilling the Specifications, codes and
approved design mix requirements.
Concrete Curing:
Equipments:
Number of equipment mentioned in this section is minimum,
exact number shall be defined based on the exact quantities
to be poured per day or per item.
Equipment:
Shovel
Spreader
Trucks
Sprit Level
Plumb bob
Drilling Machine
Hammer
Measuring Tapes
Surface Preparation
o The surveyor shall mark the road center line and width of
the embankment prior to starting of any road works; The
Site Engineer shall make detail survey of the existing
services (If any) by the side of the road or crossing the road.
o Surveyor shall make a survey report for the existing levels
prior to filling or cutting and engineer should make sure for
the same.
o All the road works and road crossings must be executed as
per the approved drawings and as per project specifications.
Road embankment:
Sub Grade:
Laying of Kerbstones
Sub-Base:
Prime Coat
Temperature:
Thickness of Cores:
o Drawing Approval
o Excavation
o Materials
Cement
Aggregates
Water
Steel
o Form Work
o Mixed Concrete
Concrete Mixing
Pouring & Compaction
o Concrete Curing
approved GA drawing
Equipments:
Hoisting / Rigging
Cutting
Machine
Personal
Fall
Arrest
System:
Safety Nets
Beamer / Glyder / Girder Grip
Retractable Lanyards
Uni Strut
Life-lines
Safety Cable (Column attached)
Approval to begin Steel Erection
Critical Lift
A lift that
Column Anchorage:
Double Connection:
Job Title: RCC Work (Drains, Culvert, Paver Page of JSA No.: Date: New Revised
Block)
Equipment: Supervisor: Analysis by:
Department: Approved by:
Required Personal Protective Equipment (PPE):
Page 32 of 45
Job Steps Potential Hazards Recommended Safe Job Procedures
Petroleum line passing through site. Consider enough space
for movement of Excavator in Horizontal and vertical
direction. Almost 1 - 2 M depth earth excavation needed.
Area fenced- only authorized and competent people to work.
Excavated earthed to be positioned at least 1 M away. Site
Engineer to consider condition of earth due to prevailing
monsoon, static load and dynamic load in surroundings,
Stability of Excavation. Assess any live service, proximate
water course or isolation failure could cause flooding of
excavation. Means of entry and exit from the excavation.
Dewatering pump. Any Mobile Plant must not be allowed
within 2 M from Electrical Cable and Pole within 5 M.
Removal of earth from site Injury Working / proper earth mover / dumper. Competent operator
/ driver. Site Engineer to direct the area of safe operation
considering Static and dynamic load on excavation.
Shoring as necessary Injury Shored, benched and or battered, as needed. Sloping of the
face prevent ground collapse. Benching and battering may
also be considered in absence of shoring.
Hard soling / PCC Injury Protection from earth collapse. Providing shield. Sloping of
the face prevent ground collapse.
Form Work Injury Protection from earth collapse. Providing shield. Sloping of
the face prevent ground collapse. PPEs (Gloves, Helmet,
Job Steps Potential Hazards Recommended Safe Job Procedures
Safety Shoe).
Installing steel Reinforcement Injury Protection from earth collapse. Providing shield. Sloping of
the face prevent ground collapse. PPEs (Gloves, Helmet,
Safety Shoe).
Positioning of aggregate, Concrete Mix Injury Demarcated area. PPEs.
Positioning of necessary equipment’s for casting Injury Demarcated area. PPEs.
Casting of Footing, RCC Wall / Flooring / Foundation Injury Protection from earth collapse. Providing shield. Sloping of
the face prevent ground collapse. PPEs (Gloves, Helmet,
Safety Shoe, Dust mask). Safety shower be provided.
Curing Injury PPEs (Gloves, Helmet, Safety Shoe)
Removal of shattering and disposal of shattering materials Injury PPEs (Gloves, Helmet, Safety Shoe)
Back Filling Injury PPEs
Retention of Embankment, as necessary (for Culvert) Injury PPEs
Job Title: Road Work (Bituminous Road) Page of JSA No.: Date: New Revised
Equipment: Supervisor: Analysis by:
Department: Approved by:
Required Personal Protective Equipment (PPE):
Page 40 of 45
Activity based Protection Equipments:
Retractable
Lanyards: 2
Lanyards
Minimum for
100% FP