level #KA Knowledge Areas (KA) #PG P mgt Process Groups (PG) #P Process Inputs Tools&Techniques Outputs

1 4 P Integration mgt A initiating PG 04.1 develop P charter Business case


1 4 P Integration mgt A initiating PG 04.1 develop P charter Contract
1 4 P Integration mgt A initiating PG 04.1 develop P charter Enterprise environmental factors
1 4 P Integration mgt A initiating PG 04.1 develop P charter Organizational process assets
1 4 P Integration mgt A initiating PG 04.1 develop P charter Project Statement of work (SOW)
1 4 P Integration mgt A initiating PG 04.1 develop P charter Project Charter
1 4 P Integration mgt A initiating PG 04.1 develop P charter Expert Judgment
0 4 P Integration mgt A initiating PG 04.1 develop P charter
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Enterprise environmental factors
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Organizational process assets
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Procurement documents
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Project charter
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Stakeholder Management Strategy
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Stakeholder Register
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Expert Judgment
1 10 P Comm mgt A initiating PG 10.1 identify stackholders Stakeholder Analysis
0 10 P Comm mgt A initiating PG 10.1 identify stackholders
1 4 P Integration mgt B1 planning PG 04.2 develop P mgt plan Enterprise environmental factors
1 4 P Integration mgt B1 planning PG 04.2 develop P mgt plan Organizational process assets
1 4 P Integration mgt B1 planning PG 04.2 develop P mgt plan Outputs from the planning processes
1 4 P Integration mgt B1 planning PG 04.2 develop P mgt plan Project charter
1 4 P Integration mgt B1 planning PG 04.2 develop P mgt plan Project Management Plan
1 4 P Integration mgt B1 planning PG 04.2 develop P mgt plan Expert Judgment
0 4 P Integration mgt B1 planning PG 04.2 develop P mgt plan
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Project Charter
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Stakeholder Register
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Requirements documentation
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Requirements management plan
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Requirements traceability matrix
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Facilitated Workshops
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Focus Groups
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Group Creativity Techniques
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Group Decision Making Techniques
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Interviews
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Observations
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Prototypes
1 5 P Scope mgt B1 planning PG 05.1 collect requirements Questionnaires and Surveys
0 5 P Scope mgt B1 planning PG 05.1 collect requirements
1 5 P Scope mgt B1 planning PG 05.2 define scope Organizational process assets
1 5 P Scope mgt B1 planning PG 05.2 define scope Project charter
1 5 P Scope mgt B1 planning PG 05.2 define scope Requirements documentation
1 5 P Scope mgt B1 planning PG 05.2 define scope Project document updates
1 5 P Scope mgt B1 planning PG 05.2 define scope Project scope statement
1 5 P Scope mgt B1 planning PG 05.2 define scope Alternatives identification
1 5 P Scope mgt B1 planning PG 05.2 define scope Expert Judgment
1 5 P Scope mgt B1 planning PG 05.2 define scope Facilitated Workshops
1 5 P Scope mgt B1 planning PG 05.2 define scope Product analysis
0 5 P Scope mgt B1 planning PG 05.2 define scope
1 5 P Scope mgt B1 planning PG 05.2 define scope
1 5 P Scope mgt B1 planning PG 05.3 create WBS Organizational process assets
1 5 P Scope mgt B1 planning PG 05.3 create WBS Project scope statement
1 5 P Scope mgt B1 planning PG 05.3 create WBS Requirements documentation
1 5 P Scope mgt B1 planning PG 05.3 create WBS Project document updates
1 5 P Scope mgt B1 planning PG 05.3 create WBS Scope baseline
1 5 P Scope mgt B1 planning PG 05.3 create WBS WBS
1 5 P Scope mgt B1 planning PG 05.3 create WBS WBS dictionary
1 5 P Scope mgt B1 planning PG 05.3 create WBS Decomposition
0 5 P Scope mgt B1 planning PG 05.3 create WBS
1 6 P Time mgt B1 planning PG 06.1 define activities Enterprise environmental factors
1 6 P Time mgt B1 planning PG 06.1 define activities Organizational process assets
1 6 P Time mgt B1 planning PG 06.1 define activities Scope baseline
1 6 P Time mgt B1 planning PG 06.1 define activities Activity attributes
1 6 P Time mgt B1 planning PG 06.1 define activities Activity list
1 6 P Time mgt B1 planning PG 06.1 define activities Milestone list
1 6 P Time mgt B1 planning PG 06.1 define activities Decomposition
1 6 P Time mgt B1 planning PG 06.1 define activities Expert Judgment
1 6 P Time mgt B1 planning PG 06.1 define activities Rolling-wave planning
1 6 P Time mgt B1 planning PG 06.1 define activities Templates
0 6 P Time mgt B1 planning PG 06.1 define activities
1 6 P Time mgt B1 planning PG 06.1 define activities
1 6 P Time mgt B1 planning PG 06.2 sequence activities Activity attributes
1 6 P Time mgt B1 planning PG 06.2 sequence activities Activity list
1 6 P Time mgt B1 planning PG 06.2 sequence activities Milestone list
1 6 P Time mgt B1 planning PG 06.2 sequence activities Organizational process assets
1 6 P Time mgt B1 planning PG 06.2 sequence activities Project scope statement
1 6 P Time mgt B1 planning PG 06.2 sequence activities Network Diagrams
1 6 P Time mgt B1 planning PG 06.2 sequence activities Project document updates
1 6 P Time mgt B1 planning PG 06.2 sequence activities Applying leads and lags
1 6 P Time mgt B1 planning PG 06.2 sequence activities Dependency determination
1 6 P Time mgt B1 planning PG 06.2 sequence activities Precedence diagramming method (PDM)
1 6 P Time mgt B1 planning PG 06.2 sequence activities Schedule network templates
0 6 P Time mgt B1 planning PG 06.2 sequence activities
1 6 P Time mgt B1 planning PG 06.2 sequence activities
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Activity attributes
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Activity list
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Enterprise environmental factors
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Organizational process assets
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Resource calendars
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Activity resource requirements
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Project document updates
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Resource breakdown structure
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Alternatives analysis
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Bottom-up estimating
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Expert Judgment
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Project management software
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources Published e stimating data
0 6 P Time mgt B1 planning PG 06.3 estimate activity resources
1 6 P Time mgt B1 planning PG 06.3 estimate activity resources
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Activity attributes
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Activity list
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Activity resource requirements
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Enterprise environmental factors
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Organizational process assets
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Project scope statement
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Resource calendars
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Duration estimates
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Project document updates
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Analogous estimating
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Expert Judgment
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Parametric estimating
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Reserve analysis
1 6 P Time mgt B1 planning PG 06.4 estimate activity durations Three-Point estimates
0 6 P Time mgt B1 planning PG 06.4 estimate activity durations
1 6 P Time mgt B1 planning PG 06.5 develop schedule Activity attributes
1 6 P Time mgt B1 planning PG 06.5 develop schedule Activity duration estimates
1 6 P Time mgt B1 planning PG 06.5 develop schedule Activity list
1 6 P Time mgt B1 planning PG 06.5 develop schedule Activity resource requirements
1 6 P Time mgt B1 planning PG 06.5 develop schedule Enterprise environmental factors
1 6 P Time mgt B1 planning PG 06.5 develop schedule Organizational process assets
1 6 P Time mgt B1 planning PG 06.5 develop schedule Project schedule network diagrams
1 6 P Time mgt B1 planning PG 06.5 develop schedule Project scope statement
1 6 P Time mgt B1 planning PG 06.5 develop schedule Resource calendars
1 6 P Time mgt B1 planning PG 06.5 develop schedule Project document updates
1 6 P Time mgt B1 planning PG 06.5 develop schedule Project schedule
1 6 P Time mgt B1 planning PG 06.5 develop schedule Schedule baseline
1 6 P Time mgt B1 planning PG 06.5 develop schedule Schedule data
1 6 P Time mgt B1 planning PG 06.5 develop schedule Applying leads and lags
1 6 P Time mgt B1 planning PG 06.5 develop schedule Critical chain method
1 6 P Time mgt B1 planning PG 06.5 develop schedule Critical path method
1 6 P Time mgt B1 planning PG 06.5 develop schedule Resource leveling
1 6 P Time mgt B1 planning PG 06.5 develop schedule Schedule compression
1 6 P Time mgt B1 planning PG 06.5 develop schedule Schedule network analysis
1 6 P Time mgt B1 planning PG 06.5 develop schedule Scheduling tool
1 6 P Time mgt B1 planning PG 06.5 develop schedule What-if scenario analysis
0 6 P Time mgt B1 planning PG 06.5 develop schedule
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Enterprise environmental factors
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Human resource plan
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Organizational process assets
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Project schedule
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Risk register
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Scope baseline
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Activity cost estimates
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Basis of estimates
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Project document updates
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Analogous estimating
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Bottom-up estimating
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Expert Judgment
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Parametric estimating
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Reserve analysis
1 7 P Cost mgt B1 planning PG 07.1 estimate costs Three-point estimates
0 7 P Cost mgt B1 planning PG 07.1 estimate costs
1 7 P Cost mgt B1 planning PG 07.2 determine budget Activity cost estimates
1 7 P Cost mgt B1 planning PG 07.2 determine budget Basis of estimates
1 7 P Cost mgt B1 planning PG 07.2 determine budget Contracts
1 7 P Cost mgt B1 planning PG 07.2 determine budget Organizational process assets
1 7 P Cost mgt B1 planning PG 07.2 determine budget Project schedule
1 7 P Cost mgt B1 planning PG 07.2 determine budget Resource calendars
1 7 P Cost mgt B1 planning PG 07.2 determine budget Scope baseline
1 7 P Cost mgt B1 planning PG 07.2 determine budget Cost performance baseline
1 7 P Cost mgt B1 planning PG 07.2 determine budget Project document updates
1 7 P Cost mgt B1 planning PG 07.2 determine budget Project funding requirements
1 7 P Cost mgt B1 planning PG 07.2 determine budget Cost aggregation
1 7 P Cost mgt B1 planning PG 07.2 determine budget Expert Judgment
1 7 P Cost mgt B1 planning PG 07.2 determine budget Funding limit reconciliation
1 7 P Cost mgt B1 planning PG 07.2 determine budget Historical relationships
1 7 P Cost mgt B1 planning PG 07.2 determine budget Reserve analysis
0 7 P Cost mgt B1 planning PG 07.2 determine budget
1 10 P Comm mgt B1 planning PG 10.2 plan communications Enterprise environmental factors
1 10 P Comm mgt B1 planning PG 10.2 plan communications Organizational process assets
1 10 P Comm mgt B1 planning PG 10.2 plan communications Stakeholder management strategy
1 10 P Comm mgt B1 planning PG 10.2 plan communications Stakeholder Register
1 10 P Comm mgt B1 planning PG 10.2 plan communications Communication management plan
1 10 P Comm mgt B1 planning PG 10.2 plan communications Project document updates
1 10 P Comm mgt B1 planning PG 10.2 plan communications Communication methods
1 10 P Comm mgt B1 planning PG 10.2 plan communications Communication models
1 10 P Comm mgt B1 planning PG 10.2 plan communications Communication technology
1 10 P Comm mgt B1 planning PG 10.2 plan communications Requirements analysis
0 10 P Comm mgt B1 planning PG 10.2 plan communications
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Communications management plan
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Cost management plan
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Enterprise environmental factors
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Organizational process assets
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Project scope statement
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Schedule management plan
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Risk Management Plan
1 11 P Risk mgt B1 planning PG 11.1 plan risk mgt Planning Meetings and Analysis
0 11 P Risk mgt B1 planning PG 11.1 plan risk mgt
1 11 P Risk mgt B1 planning PG 11.2 identify risk Activity cost estimates
1 11 P Risk mgt B1 planning PG 11.2 identify risk Activity duration estimates
1 11 P Risk mgt B1 planning PG 11.2 identify risk Cost management plan
1 11 P Risk mgt B1 planning PG 11.2 identify risk Enterprise environmental factors
1 11 P Risk mgt B1 planning PG 11.2 identify risk Organizational process assets
1 11 P Risk mgt B1 planning PG 11.2 identify risk Project documents
1 11 P Risk mgt B1 planning PG 11.2 identify risk Quality management plan
1 11 P Risk mgt B1 planning PG 11.2 identify risk Risk management plan
1 11 P Risk mgt B1 planning PG 11.2 identify risk Schedule management plan
1 11 P Risk mgt B1 planning PG 11.2 identify risk Scope baseline
1 11 P Risk mgt B1 planning PG 11.2 identify risk Stakeholder Register
1 11 P Risk mgt B1 planning PG 11.2 identify risk Risk Register
1 11 P Risk mgt B1 planning PG 11.2 identify risk Assumptions analysis
1 11 P Risk mgt B1 planning PG 11.2 identify risk Checklist analysis
1 11 P Risk mgt B1 planning PG 11.2 identify risk Diagramming techniques
1 11 P Risk mgt B1 planning PG 11.2 identify risk Documentation reviews
1 11 P Risk mgt B1 planning PG 11.2 identify risk Expert Judgment
1 11 P Risk mgt B1 planning PG 11.2 identify risk Information gathering techniques
1 11 P Risk mgt B1 planning PG 11.2 identify risk SWOT analysis
0 11 P Risk mgt B1 planning PG 11.2 identify risk
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Organizational process assets
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Project scope statement
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Risk management plan
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Risk register
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Risk Register Updates
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Expert Judgment
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Probability and impact matrix
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Risk categorization
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Risk data quality assessment
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Risk probability and impact assessment
1 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis Risk urgency assessment
0 11 P Risk mgt B1 planning PG 11.3 perform qualitative risk analysis
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Cost management plan
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Organizational process assets
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Risk management plan
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Risk register
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Schedule management plan
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Risk Register Updates
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Data gathering and representation techniques
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Expert Judgment
1 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis Quantitative risk analysis and modeling techniques
0 11 P Risk mgt B1 planning PG 11.4 perform quantitative risk analysis
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Risk management plan
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Risk register
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Project document updates
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Project management plan updates
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Risk register updates
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Risk-related contract decisions
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Contingent response strategies
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Expert Judgment
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Strategies for negative risks or threats
1 11 P Risk mgt B1 planning PG 11.5 plan risk responses Strategies for positive risks or opportunities
0 11 P Risk mgt B1 planning PG 11.5 plan risk responses
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Activity cost estimates
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Activity resource requirements
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Contract decisions
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Cost performance baseline
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Enterprise environmental factors
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Organizational process assets
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Project schedule
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Requirements documentation
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Risk register
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Scope baseline
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Teaming agreements
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Change requests
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Make-or-buy decisions
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Procurement documents
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Procurement management plan
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Procurement statements of work
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Source selection criteria
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Contract types
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Expert Judgment
1 12 P Procur mgt B1 planning PG 12.1 plan procurements Make-or-buy analysis
0 12 P Procur mgt B1 planning PG 12.1 plan procurements
1 9 P HR mgt B2 planning PG 09.1 develop hr plan Enterprise environmental factors
1 9 P HR mgt B2 planning PG 09.1 develop hr plan Organizational process assets
1 9 P HR mgt B2 planning PG 09.1 develop hr plan Resource requirements
1 9 P HR mgt B2 planning PG 09.1 develop hr plan Human Resource Plan
1 9 P HR mgt B2 planning PG 09.1 develop hr plan Networking
1 9 P HR mgt B2 planning PG 09.1 develop hr plan Organization charts and position descriptions
1 9 P HR mgt B2 planning PG 09.1 develop hr plan Organizational theory
0 9 P HR mgt B2 planning PG 09.1 develop hr plan
1 8 P Quality mgt B3 planning PG 08.1 plan quality Cost performance baseline
1 8 P Quality mgt B3 planning PG 08.1 plan quality Enterprise environmental factors
1 8 P Quality mgt B3 planning PG 08.1 plan quality Organizational process assets
1 8 P Quality mgt B3 planning PG 08.1 plan quality Risk register
1 8 P Quality mgt B3 planning PG 08.1 plan quality Schedule baseline
1 8 P Quality mgt B3 planning PG 08.1 plan quality Scope baseline
1 8 P Quality mgt B3 planning PG 08.1 plan quality Stakeholder Register
1 8 P Quality mgt B3 planning PG 08.1 plan quality Process improvement plan
1 8 P Quality mgt B3 planning PG 08.1 plan quality Project document updates
1 8 P Quality mgt B3 planning PG 08.1 plan quality Quality checklists
1 8 P Quality mgt B3 planning PG 08.1 plan quality Quality management plan
1 8 P Quality mgt B3 planning PG 08.1 plan quality Quality metrics
1 8 P Quality mgt B3 planning PG 08.1 plan quality Additional quality planning tools
1 8 P Quality mgt B3 planning PG 08.1 plan quality Benchmarking
1 8 P Quality mgt B3 planning PG 08.1 plan quality Control charts
1 8 P Quality mgt B3 planning PG 08.1 plan quality Cost of quality
1 8 P Quality mgt B3 planning PG 08.1 plan quality Cost-benefit analysis
1 8 P Quality mgt B3 planning PG 08.1 plan quality Design of experiments
1 8 P Quality mgt B3 planning PG 08.1 plan quality Flowcharting
1 8 P Quality mgt B3 planning PG 08.1 plan quality Proprietary quality management methodologies
1 8 P Quality mgt B3 planning PG 08.1 plan quality Statistical sampling
0 8 P Quality mgt B3 planning PG 08.1 plan quality
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Approved change requests
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Environmental factors
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Organizational process assets
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Project management plan
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Change requests
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Deliverables
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Project document updates
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Project management plan updates
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Work performance information
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Expert Judgment
1 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution Project management information system (PMIS)
0 4 P Integration mgt C1 executing PG 04.3 direct & manage P execution
1 9 P HR mgt C1 executing PG 09.2 acquire project team Enterprise environmental factors
1 9 P HR mgt C1 executing PG 09.2 acquire project team Organizational process assets
1 9 P HR mgt C1 executing PG 09.2 acquire project team Project management plan
1 9 P HR mgt C1 executing PG 09.2 acquire project team Project management plan updates
1 9 P HR mgt C1 executing PG 09.2 acquire project team Project staff assignments
1 9 P HR mgt C1 executing PG 09.2 acquire project team Resource calendars
1 9 P HR mgt C1 executing PG 09.2 acquire project team Acquisition
1 9 P HR mgt C1 executing PG 09.2 acquire project team Negotiation
1 9 P HR mgt C1 executing PG 09.2 acquire project team Pre-assignment
1 9 P HR mgt C1 executing PG 09.2 acquire project team Virtual teams
0 9 P HR mgt C1 executing PG 09.2 acquire project team
1 9 P HR mgt C1 executing PG 09.3 develop project team Project management plan
1 9 P HR mgt C1 executing PG 09.3 develop project team Project staff assignments
1 9 P HR mgt C1 executing PG 09.3 develop project team Resource calendars
1 9 P HR mgt C1 executing PG 09.3 develop project team Enterprise environmental factors updates
1 9 P HR mgt C1 executing PG 09.3 develop project team Team performance assessments
1 9 P HR mgt C1 executing PG 09.3 develop project team Achievement theory
1 9 P HR mgt C1 executing PG 09.3 develop project team Co-location
1 9 P HR mgt C1 executing PG 09.3 develop project team Contingency theory
1 9 P HR mgt C1 executing PG 09.3 develop project team Expectancy theory
1 9 P HR mgt C1 executing PG 09.3 develop project team Ground rules
1 9 P HR mgt C1 executing PG 09.3 develop project team Hygiene theory
1 9 P HR mgt C1 executing PG 09.3 develop project team Interpersonal skills
1 9 P HR mgt C1 executing PG 09.3 develop project team Maslow’s hierarchy of needs
1 9 P HR mgt C1 executing PG 09.3 develop project team Power of leaders
1 9 P HR mgt C1 executing PG 09.3 develop project team Recognition and rewards
1 9 P HR mgt C1 executing PG 09.3 develop project team Team-building activities
1 9 P HR mgt C1 executing PG 09.3 develop project team Theory X, Theory Y, and Theory Z
1 9 P HR mgt C1 executing PG 09.3 develop project team Training
0 9 P HR mgt C1 executing PG 09.3 develop project team
1 9 P HR mgt C1 executing PG 09.4 manage project team Project management plan
1 9 P HR mgt C1 executing PG 09.4 manage project team Project staff assignments
1 9 P HR mgt C1 executing PG 09.4 manage project team Team performance assessments
1 9 P HR mgt C1 executing PG 09.4 manage project team Change requests
1 9 P HR mgt C1 executing PG 09.4 manage project team Enterprise environmental factors updates
1 9 P HR mgt C1 executing PG 09.4 manage project team Organizational process assets updates
1 9 P HR mgt C1 executing PG 09.4 manage project team Project management plan updates
1 9 P HR mgt C1 executing PG 09.4 manage project team Conflict management
1 9 P HR mgt C1 executing PG 09.4 manage project team Interpersonal skills
1 9 P HR mgt C1 executing PG 09.4 manage project team Issue log
1 9 P HR mgt C1 executing PG 09.4 manage project team Observation and conversation
1 9 P HR mgt C1 executing PG 09.4 manage project team Project performance appraisals
0 9 P HR mgt C1 executing PG 09.4 manage project team
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Make-or-buy decisions
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Organizational process assets
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Procurement documents
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Project documents
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Project management plan
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Qualified seller list
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Seller proposals
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Source selection criteria
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Teaming agreements
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Change requests
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Procurement contract awards
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Project document updates
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Project management plan updates
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Resources calendars
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Selected sellers
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Advertising
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Bidder conferences
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Expert Judgment
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Independent estimates
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Internet search
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Procurement negotiations
1 12 P Procur mgt C2 executing PG 12.2 conduct procurements Proposal evaluation techniques
0 12 P Procur mgt C2 executing PG 12.2 conduct procurements
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Project management plan
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Quality control measurements
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Quality metrics
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Work performance information
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Change requests
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Organizational process assets updates
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Project document updates
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Project management plan updates
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Plan Quality and Perform Quality Control t ools and techniques
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Process analysis
1 8 P Quality mgt C3 executing PG 08.2 perform quality assurance Quality audits
0 8 P Quality mgt C3 executing PG 08.2 perform quality assurance
1 10 P Comm mgt C3 executing PG 10.3 distribute information Organizational process assets
1 10 P Comm mgt C3 executing PG 10.3 distribute information Performance reports
1 10 P Comm mgt C3 executing PG 10.3 distribute information Project management plan
1 10 P Comm mgt C3 executing PG 10.3 distribute information Organizational process assets updates
1 10 P Comm mgt C3 executing PG 10.3 distribute information Communication methods
1 10 P Comm mgt C3 executing PG 10.3 distribute information Information distribution tools
0 10 P Comm mgt C3 executing PG 10.3 distribute information
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Change log
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Issue log
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Organizational process assets
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Project management plan
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Stakeholder management strategy
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Stakeholder Register
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Change requests
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Organizational process assets updates
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Project document updates
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Project management plan updates
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Communication methods
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Interpersonal skills
1 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations Management skills
0 10 P Comm mgt C3 executing PG 10.4 manage stakeholders expectations
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Enterprise environmental factors
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Organizational process assets
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Performance reports
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Project management plan
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Change requests
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Project document updates
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Project management plan updates
1 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work Expert Judgment
0 4 P Integration mgt D1 monitoring&controlling PG 04.4 monitor & control P work
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Approved change requests
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Contract
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Procurement documents
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Project management plan
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Work performance information
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Change requests
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Organizational process assets updates
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Procurement documentation
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Project management plan updates
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Claims administration
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Contract change control system
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Inspections and audits
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Payment systems
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Performance reporting
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Procurement performance reviews
1 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements Records management system
0 12 P Procur mgt D1 monitoring&controlling PG 12.3 administer procurements
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Budget forecasts
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Organizational process assets
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Project management plan
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Work performance information
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Work performance measurements
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Change requests
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Organizational process assets updates
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Performance reports
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Communication methods
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Forecasting methods
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Reporting systems
1 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance Variance analysis
0 10 P Comm mgt D2 monitoring&controlling PG 10.5 report performance
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Change requests
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Enterprise environmental factors
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Organizational Process Assets
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Project management plan
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Work performance information
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Change requests status updates
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Project document updates
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Project management plan updates
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Change control meetings
1 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control Expert Judgment
0 4 P Integration mgt D3 monitoring&controlling PG 04.5 perform integrated change control
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Performance reports
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Project management plan
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Risk register
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Work performance information
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Change requests
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Organizational process assets updates
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Project document updates
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Project management plan updates
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Risk register updates
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Reserve analysis
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Risk audits
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Risk reassessment
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Status meetings
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Technical performance measurement
1 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks Variance and trend analysis
0 11 P Risk mgt D3 monitoring&controlling PG 11.6 monitor & control risks
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Organizational process assets
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Project funding requirements
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Project management plan
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Work performance information
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Budget forecasts
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Change requests
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Organizational process assets updates
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Project document updates
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Project management plan updates
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Work performance measurements
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Earned value management (EVM)
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Forecasting
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Performance reviews
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Project management software
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs To-complete performance index (TCPI)
1 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs Variance analysis
0 7 P Cost mgt D4 monitoring&controlling PG 07.3 control costs
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Organizational process assets
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Project management plan
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Project schedule
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Work performance information
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Change requests
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Organizational process assets updates
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Project document updates
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Project management plan updates
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Work performance measurements
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Adjusting leads and lags
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Performance reviews
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Project management software
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Resources leveling
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Schedule compression
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Scheduling tool
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule Variance analysis
1 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule What-if scenario analysis
0 6 P Time mgt D5 monitoring&controlling PG 06.6 control schedule
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Approved change requests
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Deliverables
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Organizational Process Assets
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Project management plan
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Quality checklists
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Quality metrics
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Work performance measurements
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Change requests
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Organizational process assets updates
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Project document updates
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Project management plan updates
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Quality control measurements
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Validated changes
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Validated deliverables
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Approved change requests review
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Cause and effect diagrams
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Control charts
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Flowcharting
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Histogram
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Inspection
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Pareto chart
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Run chart
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Scatter diagram
1 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control Statistical sampling
0 8 P Quality mgt D6 monitoring&controlling PG 08.3 perform quality control
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope Project management plan
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope Requirements documentation
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope Requirements traceability matrix
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope Validated deliverables
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope Accepted deliverables
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope Change requests
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope Project document updates
1 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope inspection
0 5 P Scope mgt D7 monitoring&controlling PG 05.4 verify scope
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Organizational Process Assets
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Project management plan
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Requirements documentation
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Requirements traceability matrix
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Work performance information
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Change requests
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Organizational process assets updates
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Project document updates
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Project management plan updates
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope Work performance measurements
1 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope variance analysis
0 5 P Scope mgt D7 monitoring&controlling PG 05.5 control scope
1 4 P Integration mgt E closing PG 04.6 close P (or phase) Accepted deliverables
1 4 P Integration mgt E closing PG 04.6 close P (or phase) Organizational process assets
1 4 P Integration mgt E closing PG 04.6 close P (or phase) Project management plan
1 4 P Integration mgt E closing PG 04.6 close P (or phase) Final product, service, or result transition
1 4 P Integration mgt E closing PG 04.6 close P (or phase) Organizational process assets updates
1 4 P Integration mgt E closing PG 04.6 close P (or phase) Administrative Closure Procedures
1 4 P Integration mgt E closing PG 04.6 close P (or phase) Expert Judgment
0 4 P Integration mgt E closing PG 04.6 close P (or phase)
1 12 P Procur mgt E closing PG 12.4 close procurements Procurement documentation
1 12 P Procur mgt E closing PG 12.4 close procurements Project management plan
1 12 P Procur mgt E closing PG 12.4 close procurements Closed procurements
1 12 P Procur mgt E closing PG 12.4 close procurements Organizational process assets updates
1 12 P Procur mgt E closing PG 12.4 close procurements Negotiated settlements
1 12 P Procur mgt E closing PG 12.4 close procurements Procurement audits
1 12 P Procur mgt E closing PG 12.4 close procurements Records management system
0 12 P Procur mgt E closing PG 12.4 close procurements