Академический Документы
Профессиональный Документы
Культура Документы
Tutorial 02
Discussion Question 1
Results from the application of problem table procedure (also known as temperature interval
analysis) of process streams in 3 different plants are summarized in Tables 1 to 3. For each of
them, study the heat cascade in column 3, provide feasible cascade in column 4, and then find
the pinch point and minimum utilities. Note that stream data are not required for this analysis.
Discussion Question 2
Refer to the heat exchanger network (shown in Figure 2-1). Pinch analysis of the given stream
system for ΔTmin = 30 °C shows that the pinch temperature for this process is 120°C (135°C for
hot streams /105°C for cold streams). Find out the hot and cold utility targets only using the
information given in the heat exchanger network below (No need to use problem table analysis
or composite curve method). Does the proposed heat exchanger network meet the targets? If not,
locate and quantify (in kW) violations of the pinch rule(s) in this network. Note: The
temperatures shown in the network are in °C.
CP (kW/°C) ∆H (kW)
350 110
H1 3.0 2 C1 720
170 kW
260 80
H2 1.2 3 C1 216
96 kW
160 90
H3 9.0 1 C1 630
405 kW
210 105
C1 12.0 H 3 1 1260
915 kW 120 kW 225 kW
140 30
C2 5.0 2 550
550 kW
H2 H1
90oC 150oC
CP
Stream
25 C o o
70 C o
100 C (kW/0C)
C2 C1 2.5
C2 3.0
73.125oC H1 2.5
H2 8.0
114o
CU C
HU
60oC
20oC
74oC 125oC
C1
60oC
The Figure 3-1 shows the heat exchanger network (HEN) for an existing pharmaceutical
process.
(a) Calculate Tpinch, QH,min and QC,min for this process for a minimum driving force (∆Tmin) of
20oC, Does the above network achieve the maximum energy recovery target for ∆Tmin =
20oC ? If not, establish the potential for hot and cold utility savings.
(This part to be completed by students based on Lecture-01/Lecture-02 discussion).
(b) Design a heat exchanger network that meets the MER target. Try to retain existing units
in their current locations as much as possible.
You are the engineer working on certain process modifications in a petrochemical plant. For this,
a contractor proposes a heat exchanger network for the following process streams, which
requires 16.4 MW and 11.8 MW of hot and cold utilities respectively.
Try to design a heat exchanger network for Discussion Question 1 from Tutorial 1. Do not worry
if you face difficulty, we will discuss this in the later chapter.