Вы находитесь на странице: 1из 46

Republic of the Philippines On December 13, 1979, the lower court rendered its

SUPREME COURT Decision 1 based on the compromise agreement submitted by the


Manila parties, the pertinent portion of which reads as follows:

SECOND DIVISION 1. Plaintiff agrees to reduce its total claim of


P117,498-95 to only P11,000 .00 and defendants
G.R. No. L-55138 September 28, 1984 agree to acknowledge the validity of such claim and
further bind themselves to initially pay out of the total
indebtedness of P10,000.00 the amount of
ERNESTO V. RONQUILLO, petitioner, 
P55,000.00 on or before December 24, 1979, the
vs.
balance of P55,000.00, defendants individually and
HONORABLE COURT OF APPEALS AND ANTONIO P.
jointly agree to pay within a period of six months
SO, respondents.
from January 1980, or before June 30, 1980;
(Emphasis supplied)
Gloria A. Fortun for petitioner.
xxx xxx xxx
Roselino Reyes Isler for respondents.
4. That both parties agree that failure on the part of
either party to comply with the foregoing terms and
conditions, the innocent party will be entitled to an
CUEVAS, J.: execution of the decision based on this compromise
agreement and the defaulting party agrees and hold
This is a petition to review the Resolution dated June 30, 1980 of the themselves to reimburse the innocent party for
then Court of Appeals (now the Intermediate Appellate Court) in CA- attorney's fees, execution fees and other fees
G.R. No. SP-10573, entitled "Ernesto V. Ronquillo versus the Hon. related with the execution.
Florellana Castro-Bartolome, etc." and the Order of said court dated
August 20, 1980, denying petitioner's motion for reconsideration of xxx xxx xxx
the above resolution.
On December 26, 1979, herein private respondent (then plaintiff filed
Petitioner Ernesto V. Ronquillo was one of four (4) defendants in a Motion for Execution on the ground that defendants failed to make
Civil Case No. 33958 of the then Court of First Instance of Rizal (now the initial payment of P55,000.00 on or before December 24, 1979
the Regional Trial Court), Branch XV filed by private respondent as provided in the Decision. Said motion for execution was opposed
Antonio P. So, on July 23, 1979, for the collection of the sum of by herein petitioner (as one of the defendants) contending that his
P17,498.98 plus attorney's fees and costs. The other defendants inability to make the payment was due to private respondent's own
were Offshore Catertrade Inc., Johnny Tan and Pilar Tan. The act of making himself scarce and inaccessible on December 24,
amount of P117,498.98 sought to be collected represents the value 1979. Petitioner then prayed that private respondent be ordered to
of the checks issued by said defendants in payment for foodstuffs accept his payment in the amount of P13,750.00. 2
delivered to and received by them. The said checks were dishonored
by the drawee bank.

1
During the hearing of the Motion for Execution and the Opposition the preliminary attachment and the execution of an
thereto on January 16, 1980, petitioner, as one of the four affidavit of desistance.
defendants, tendered the amount of P13,750.00, as his prorata
share in the P55,000.00 initial payment. Another defendant, Pilar P. WHEREFORE, let writ of execution issue as prayed
Tan, offered to pay the same amount. Because private respondent for
refused to accept their payments, demanding from them the full initial
installment of P 55,000.00, petitioner and Pilar Tan instead deposited On March 17, 1980, petitioner moved for the reconsideration of the
the said amount with the Clerk of Court. The amount deposited was above order, and the same was set for hearing on March 25,1980.
subsequently withdrawn by private respondent. 3
Meanwhile, or more specifically on March 19, 1980, a writ of
On the same day, January 16, 1980, the lower court ordered the execution was issued for the satisfaction of the sum of P82,500.00
issuance of a writ of execution for the balance of the initial amount as against the properties of the defendants (including petitioner),
payable, against the other two defendants, Offshore Catertrade Inc. "singly or jointly hable." 6
and Johnny Tan 4 who did not pay their shares.
On March 20, 1980, Special Sheriff Eulogio C. Juanson of Rizal,
On January 22, 1980, private respondent moved for the issued a notice of sheriff's sale, for the sale of certain furnitures and
reconsideration and/or modification of the aforesaid Order of appliances found in petitioner's residence to satisfy the sum of
execution and prayed instead for the "execution of the decision in its P82,500.00. The public sale was scheduled for April 2, 1980 at 10:00
entirety against all defendants, jointly and severally." 5 Petitioner a.m. 7
opposed the said motion arguing that under the decision of the lower
court being executed which has already become final, the liability of
the four (4) defendants was not expressly declared to be solidary, Petitioner's motion for reconsideration of the Order of Execution
consequently each defendant is obliged to pay only his own pro-rata dated March 17, 1980 which was set for hearing on March 25, 1980,
or 1/4 of the amount due and payable. was upon motion of private respondent reset to April 2, 1980 at 8:30
a.m. Realizing the actual threat to property rights poised by the re-
setting of the hearing of s motion for reconsideration for April 2, 1980
On March 17, 1980, the lower court issued an Order reading as at 8:30 a.m. such that if his motion for reconsideration would be
follows: denied he would have no more time to obtain a writ from the
appellate court to stop the scheduled public sale of his personal
ORDER properties at 10:00 a.m. of the same day, April 2, 1980, petitioner
filed on March 26, 1980 a petition for certiorari and prohibition with
Regardless of whatever the compromise agreement the then Court of Appeals (CA-G.R. No. SP-10573), praying at the
has intended the payment whether jointly or same time for the issuance of a restraining order to stop the public
individually, or jointly and severally, the fact is that sale. He raised the question of the validity of the order of execution,
only P27,500.00 has been paid. There appears to be the writ of execution and the notice of public sale of his properties to
a non-payment in accordance with the compromise satisfy fully the entire unpaid obligation payable by all of the four (4)
agreement of the amount of P27,500.00 on or before defendants, when the lower court's decision based on the
December 24, 1979. The parties are reminded that compromise agreement did not specifically state the liability of the
the payment is condition sine qua non to the lifting of four (4) defendants to be solidary.

2
On April 2, 1980, the lower court denied petitioner's motion for petition were already "ripe" for determination. 8 The said motion was
reconsideration but the scheduled public sale in that same day did however denied by the Court of Appeals in its Resolution dated
not proceed in view of the pendency of a certiorari proceeding before August 20, 1980.
the then Court of Appeals.
Hence, this petition for review, petitioner contending that the Court of
On June 30, 1980, the said court issued a Resolution, the pertinent Appeals erred in
portion of which reads as follows:
(a) declaring as premature, and in denying due course to the petition
This Court, however, finds the present petition to to restrain implementation of a writ of execution issued at variance
have been filed prematurely. The rule is that before with the final decision of the lower court filed barely four (4) days
a petition for certiorari can be brought against an before the scheduled public sale of the attached movable properties;
order of a lower court, all remedies available in that
court must first be exhausted. In the case at bar, (b) denying reconsideration of the Resolution of June 30, 1980,
herein petitioner filed a petition without waiting for a which declared as premature the filing of the petition, although there
resolution of the Court on the motion for is proof on record that as of April 2, 1980, the motion referred to was
reconsideration, which could have been favorable to already denied by the lower court and there was no more motion
the petitioner. The fact that the hearing of the motion pending therein;
for reconsideration had been reset on the same day
the public sale was to take place is of no moment (c) failing to resolve the legal issues raised in the petition and in not
since the motion for reconsideration of the Order of declaring the liabilities of the defendants, under the final decision of
March 17, 1980 having been seasonably filed, the the lower court, to be only joint;
scheduled public sale should be suspended.
Moreover, when the defendants, including herein
petitioner, defaulted in their obligation based on the (d) not holding the lower court's order of execution dated March 17,
compromise agreement, private respondent had 1980, the writ of execution and the notice of sheriff's sale, executing
become entitled to move for an execution of the the lower court's decision against "all defendants, singly and jointly",
decision based on the said agreement. to be at variance with the lower court's final decision which did not
provide for solidary obligation; and
WHEREFORE, the instant petition for certiorari and
prohibition with preliminary injunction is hereby (e) not declaring as invalid and unlawful the threatened execution, as
denied due course. The restraining order issued in against the properties of petitioner who had paid his pro-rata share of
our resolution dated April 9, 1980 is hereby lifted the adjudged obligation, of the total unpaid amount payable by his
without pronouncement as to costs. joint co-defendants.

SO ORDERED. The foregoing assigned errors maybe synthesized into the more
important issues of —
Petitioner moved to reconsider the aforesaid Resolution alleging that
on April 2, 1980, the lower court had already denied the motion 1. Was the filing of a petition for certiorari before the then Court of
referred to and consequently, the legal issues being raised in the Appeals against the Order of Execution issued by the lower court,

3
dated March 17, 1980, proper, despite the pendency of a motion for thereafter, the public sale scheduled that very same morning could
reconsideration of the same questioned Order? have proceeded.

2. What is the nature of the liability of the defendants (including The other issue raised refers to the nature of the liability of petitioner,
petitioner), was it merely joint, or was it several or solidary? as one of the defendants in Civil Case No. 33958, that is whether or
not he is liable jointly or solidarily.
Anent the first issue raised, suffice it to state that while as a general
rule, a motion for reconsideration should precede recourse to In this regard, Article 1207 and 1208 of the Civil Code provides —
certiorari in order to give the trial court an opportunity to correct the
error that it may have committed, the said rule is not absolutes 9 and Art. 1207. The concurrence of two or more debtors
may be dispensed with in instances where the filing of a motion for in one and the same obligation does not imply that
reconsideration would serve no useful purpose, such as when the each one of the former has a right to demand, or that
motion for reconsideration would raise the same point stated in the each one of the latter is bound to render, entire
motion 10 or where the error is patent for the order is compliance with the prestation. Then is a solidary
void 11 or where the relief is extremely urgent, as in cases where liability only when the obligation expressly so states,
execution had already been ordered 12 where the issue raised is or when the law or the nature of the obligation
one purely of law. 13 requires solidarity.

In the case at bar, the records show that not only was a writ of Art. 1208. If from the law,or the nature or the
execution issued but petitioner's properties were already scheduled wording of the obligation to which the preceding
to be sold at public auction on April 2, 1980 at 10:00 a.m. The article refers the contrary does not appear, the credit
records likewise show that petitioner's motion for reconsideration of or debt shall be presumed to be divided into as
the questioned Order of Execution was filed on March 17, 1980 and many equal shares as there are creditors and
was set for hearing on March 25, 1980 at 8:30 a.m., but upon motion debtors, the credits or debts being considered
of private respondent, the hearing was reset to April 2, 1980 at 8:30 distinct from one another, subject to the Rules of
a.m., the very same clay when petitioner's properties were to be sold Court governing the multiplicity of quits.
at public auction. Needless to state that under the circumstances,
petitioner was faced with imminent danger of his properties being The decision of the lower court based on the parties' compromise
immediately sold the moment his motion for reconsideration is agreement, provides:
denied. Plainly, urgency prompted recourse to the Court of Appeals
and the adequate and speedy remedy for petitioner under the
situation was to file a petition for certiorari with prayer for restraining 1. Plaintiff agrees to reduce its total claim of
order to stop the sale. For him to wait until after the hearing of the P117,498.95 to only P110,000.00 and defendants
motion for reconsideration on April 2, 1980 before taking recourse to agree to acknowledge the validity of such claim and
the appellate court may already be too late since without a further bind themselves to initially pay out of the total
restraining order, the public sale can proceed at 10:00 that morning. indebtedness of P110,000.00, the amount of
In fact, the said motion was already denied by the lower court in its P5,000.00 on or before December 24, 1979, the
order dated April 2, 1980 and were it not for the pendency of the balance of P55,000.00, defendants individually and
petition with the Court of Appeals and the restraining order issued jointly agree to pay within a period of six months

4
from January 1980 or before June 30, 1980. MALAYAN INSURANCE CO., INC., petitioner, 
(Emphasis supply) vs.
THE HON. COURT OF APPEALS (THIRD DIVISION) MARTIN C.
Clearly then, by the express term of the compromise agreement and VALLEJOS, SIO CHOY, SAN LEON RICE MILL, INC. and
the decision based upon it, the defendants obligated themselves to PANGASINAN TRANSPORTATION CO., INC., respondents.
pay their obligation "individually and jointly".
Freqillana Jr. for petitioner.
The term "individually" has the same meaning as "collectively",
"separately", "distinctively", respectively or "severally". An agreement B.F. Estrella & Associates for respondent Martin Vallejos.
to be "individually liable" undoubtedly creates a several
obligation, 14 and a "several obligation is one by which one Vicente Erfe Law Office for respondent Pangasinan Transportation
individual binds himself to perform the whole obligation. 15 Co., Inc.

In the case of Parot vs. Gemora 16 We therein ruled that "the Nemesio Callanta for respondent Sio Choy and San Leon Rice Mill,
phrase juntos or separadamente  or in the promissory note is an Inc.
express statement making each of the persons who signed
it individually liable for the payment of the fun amount of the
obligation contained therein." Likewise in Un Pak Leung vs.
Negorra 17 We held that "in the absence of a finding of facts that the
defendants made themselves individually hable for the debt incurred PADILLA, J.:
they are each liable only for one-half of said amount
Review on certiorari  of the judgment * of the respondent appellate
The obligation in the case at bar being described as "individually and court in CA-G.R. No. 47319-R, dated 22 February 1973, which
jointly", the same is therefore enforceable against one of the affirmed, with some modifications, the decision, ** dated 27 April
numerous obligors. 1970, rendered in Civil Case No. U-2021 of the Court of First
Instance of Pangasinan.
IN VIEW OF THE FOREGOING CONSIDERATIONS, the instant
petition is hereby DISMISSED. Cost against petitioner. The antecedent facts of the case are as follows:

SO ORDERED. On 29 March 1967, herein petitioner, Malayan Insurance Co., Inc.,


issued in favor of private respondent Sio Choy Private Car
Comprehensive Policy No. MRO/PV-15753, effective from 18 April
Republic of the Philippines 1967 to 18 April 1968, covering a Willys jeep with Motor No. ET-
SUPREME COURT 03023 Serial No. 351672, and Plate No. J-21536, Quezon City,
Manila 1967. The insurance coverage was for "own damage" not to exceed
P600.00 and "third-party liability" in the amount of P20,000.00.
SECOND DIVISION
During the effectivity of said insurance policy, and more particularly
G.R. No. L-36413 September 26, 1988 on 19 December 1967, at about 3:30 o'clock in the afternoon, the

5
insured jeep, while being driven by one Juan P. Campollo an persons arising out of any accident during the effectivity of such
employee of the respondent San Leon Rice Mill, Inc., collided with a insurance contract, which policy was in full force and effect when the
passenger bus belonging to the respondent Pangasinan vehicular accident complained of occurred. He prayed that he be
Transportation Co., Inc. (PANTRANCO, for short) at the national reimbursed by the insurance company for the amount that he may be
highway in Barrio San Pedro, Rosales, Pangasinan, causing damage ordered to pay.
to the insured vehicle and injuries to the driver, Juan P. Campollo,
and the respondent Martin C. Vallejos, who was riding in the ill-fated Also later, the herein petitioner sought, and was granted, leave to file
jeep. a third-party complaint against the San Leon Rice Mill, Inc. for the
reason that the person driving the jeep of Sio Choy, at the time of the
As a result, Martin C. Vallejos filed an action for damages against accident, was an employee of the San Leon Rice Mill, Inc.
Sio Choy, Malayan Insurance Co., Inc. and the PANTRANCO before performing his duties within the scope of his assigned task, and not
the Court of First Instance of Pangasinan, which was docketed as an employee of Sio Choy; and that, as the San Leon Rice Mill, Inc. is
Civil Case No. U-2021. He prayed therein that the defendants be the employer of the deceased driver, Juan P. Campollo, it should be
ordered to pay him, jointly and severally, the amount of P15,000.00, liable for the acts of its employee, pursuant to Art. 2180 of the Civil
as reimbursement for medical and hospital expenses; P6,000.00, for Code. The herein petitioner prayed that judgment be rendered
lost income; P51,000.00 as actual, moral and compensatory against the San Leon Rice Mill, Inc., making it liable for the amounts
damages; and P5,000.00, for attorney's fees. claimed by the plaintiff and/or ordering said San Leon Rice Mill, Inc.
to reimburse and indemnify the petitioner for any sum that it may be
Answering, PANTRANCO claimed that the jeep of Sio Choy was ordered to pay the plaintiff.
then operated at an excessive speed and bumped the PANTRANCO
bus which had moved to, and stopped at, the shoulder of the After trial, judgment was rendered as follows:
highway in order to avoid the jeep; and that it had observed the
diligence of a good father of a family to prevent damage, especially WHEREFORE, in view of the foregoing findings of
in the selection and supervision of its employees and in the this Court judgment is hereby rendered in favor of
maintenance of its motor vehicles. It prayed that it be absolved from the plaintiff and against Sio Choy and Malayan
any and all liability. Insurance Co., Inc., and third-party defendant San
Leon Rice Mill, Inc., as follows:
Defendant Sio Choy and the petitioner insurance company, in their
answer, also denied liability to the plaintiff, claiming that the fault in (a) P4,103 as actual damages;
the accident was solely imputable to the PANTRANCO.
(b) P18,000.00 representing the unearned income of
Sio Choy, however, later filed a separate answer with a cross-claim plaintiff Martin C. Vallejos for the period of three (3)
against the herein petitioner wherein he alleged that he had actually years;
paid the plaintiff, Martin C. Vallejos, the amount of P5,000.00 for
hospitalization and other expenses, and, in his cross-claim against (c) P5,000.00 as moral damages;
the herein petitioner, he alleged that the petitioner had issued in his
favor a private car comprehensive policy wherein the insurance
company obligated itself to indemnify Sio Choy, as insured, for the (d) P2,000.00 as attomey's fees or the total of
damage to his motor vehicle, as well as for any liability to third P29,103.00, plus costs.

6
The above-named parties against whom this or part of whatever the former may pay on the P20,000.00 it has
judgment is rendered are hereby held jointly and been adjudged to pay respondent Vallejos." 3
severally liable. With respect, however, to Malayan
Insurance Co., Inc., its liability will be up to only However, in order to determine the alleged liability of respondent
P20,000.00. San Leon Rice Mill, Inc. to petitioner, it is important to determine first
the nature or basis of the liability of petitioner to respondent Vallejos,
As no satisfactory proof of cost of damage to its bus as compared to that of respondents Sio Choy and San Leon Rice
was presented by defendant Pantranco, no award Mill, Inc.
should be made in its favor. Its counter-claim for
attorney's fees is also dismissed for not being Therefore, the two (2) principal issues to be resolved are (1) whether
proved. 1 the trial court, as upheld by the Court of Appeals, was correct in
holding petitioner and respondents Sio Choy and San Leon Rice Mill,
On appeal, the respondent Court of Appeals affirmed the judgment Inc. "solidarily liable" to respondent Vallejos; and (2) whether
of the trial court that Sio Choy, the San Leon Rice Mill, Inc. and the petitioner is entitled to be reimbursed by respondent San Leon Rice
Malayan Insurance Co., Inc. are jointly and severally liable for the Mill, Inc. for whatever amount petitioner has been adjudged to pay
damages awarded to the plaintiff Martin C. Vallejos. It ruled, respondent Vallejos on its insurance policy.
however, that the San Leon Rice Mill, Inc. has no obligation to
indemnify or reimburse the petitioner insurance company for As to the first issue, it is noted that the trial court found, as affirmed
whatever amount it has been ordered to pay on its policy, since the by the appellate court, that petitioner and respondents Sio Choy and
San Leon Rice Mill, Inc. is not a privy to the contract of insurance San Leon Rice Mill, Inc. are jointly and severally liable to respondent
between Sio Choy and the insurance company. 2 Vallejos.

Hence, the present recourse by petitioner insurance company. We do not agree with the aforesaid ruling. We hold instead that it is
only respondents Sio Choy and San Leon Rice Mill, Inc, (to the
The petitioner prays for the reversal of the appellate court's exclusion of the petitioner) that are solidarily liable to respondent
judgment, or, in the alternative, to order the San Leon Rice Mill, Inc. Vallejos for the damages awarded to Vallejos.
to reimburse petitioner any amount, in excess of one-half (1/2) of the
entire amount of damages, petitioner may be ordered to pay jointly It must be observed that respondent Sio Choy is made liable to said
and severally with Sio Choy. plaintiff as owner of the ill-fated Willys jeep, pursuant to Article 2184
of the Civil Code which provides:
The Court, acting upon the petition, gave due course to the same,
but "only insofar as it concerns the alleged liability of respondent San Art. 2184. In motor vehicle mishaps, the owner is
Leon Rice Mill, Inc. to petitioner, it being understood that no other solidarily liable with his driver, if the former, who was
aspect of the decision of the Court of Appeals shall be reviewed, in the vehicle, could have, by the use of due
hence, execution may already issue in favor of respondent Martin C. diligence, prevented the misfortune it is disputably
Vallejos against the respondents, without prejudice to the presumed that a driver was negligent, if he had been
determination of whether or not petitioner shall be entitled to found guilty of reckless driving or violating traffic
reimbursement by respondent San Leon Rice Mill, Inc. for the whole regulations at least twice within the next preceding
two months.

7
If the owner was not in the motor vehicle, the comprehensive policy existing between petitioner and respondent
provisions of article 2180 are applicable. Sio Choy at the time of the complained vehicular accident.

On the other hand, it is noted that the basis of liability of respondent In Guingon vs. Del Monte, 5 a passenger of a jeepney had just
San Leon Rice Mill, Inc. to plaintiff Vallejos, the former being the alighted therefrom, when he was bumped by another passenger
employer of the driver of the Willys jeep at the time of the motor jeepney. He died as a result thereof. In the damage suit filed by the
vehicle mishap, is Article 2180 of the Civil Code which reads: heirs of said passenger against the driver and owner of the jeepney
at fault as well as against the insurance company which insured the
Art. 2180. The obligation imposed by article 2176 is latter jeepney against third party liability, the trial court, affirmed by
demandable not only for one's own acts or this Court, adjudged the owner and the driver of the jeepney at fault
omissions, but also for those of persons for whom jointly and severally liable to the heirs of the victim in the total
one is responsible. amount of P9,572.95 as damages and attorney's fees; while the
insurance company was sentenced to pay the heirs the amount of
P5,500.00 which was to be applied as partial satisfaction of the
xxx xxx xxx
judgment rendered against said owner and driver of the jeepney.
Thus, in said Guingon case, it was only the owner and the driver of
Employers shall be liable for the damages caused by the jeepney at fault, not including the insurance company, who were
their employees and household helpers acting within held solidarily liable to the heirs of the victim.
the scope of their assigned tasks, even though the
former are not engaged ill any business or industry.
While it is true that where the insurance contract provides for
indemnity against liability to third persons, such third persons can
xxx xxx xxx directly sue the insurer, 6 however, the direct liability of the insurer
under indemnity contracts against third party liability does not mean
The responsibility treated in this article shall cease that the insurer can be held solidarily liable with the insured and/or
when the persons herein mentioned proved that they the other parties found at fault. The liability of the insurer is based on
observed all the diligence of a good father of a family contract; that of the insured is based on tort.
to prevent damage.
In the case at bar, petitioner as insurer of Sio Choy, is liable to
It thus appears that respondents Sio Choy and San Leon Rice Mill, respondent Vallejos, but it cannot, as incorrectly held by the trial
Inc. are the principal tortfeasors who are primarily liable to court, be made "solidarily" liable with the two principal tortfeasors
respondent Vallejos. The law states that the responsibility of two or namely respondents Sio Choy and San Leon Rice Mill, Inc. For if
more persons who are liable for a quasi-delict is solidarily.4 petitioner-insurer were solidarily liable with said two (2) respondents
by reason of the indemnity contract against third party liability-under
On the other hand, the basis of petitioner's liability is its insurance which an insurer can be directly sued by a third party — this will
contract with respondent Sio Choy. If petitioner is adjudged to pay result in a violation of the principles underlying solidary obligation
respondent Vallejos in the amount of not more than P20,000.00, this and insurance contracts.
is on account of its being the insurer of respondent Sio Choy under
the third party liability clause included in the private car In solidary obligation, the creditor may enforce the entire obligation
against one of the solidary debtors. 7 On the other hand, insurance is

8
defined as "a contract whereby one undertakes for a consideration to Standard Marine Ins. Co. vs. Scottish Metropolitan
indemnify another against loss, damage, or liability arising from an Assurance Co., 283 U.S. 284, 75 L. ed. 1037).
unknown or contingent event." 8
The right of subrogation is of the highest equity. The
In the case at bar, the trial court held petitioner together with loss in the first instance is that of the insured but
respondents Sio Choy and San Leon Rice Mills Inc. solidarily liable after reimbursement or compensation, it becomes
to respondent Vallejos for a total amount of P29,103.00, with the the loss of the insurer (44 Am. Jur. 2d, 746, note 16,
qualification that petitioner's liability is only up to P20,000.00. In the citing Newcomb vs. Cincinnati Ins. Co., 22 Ohio St.
context of a solidary obligation, petitioner may be compelled by 382).
respondent Vallejos to pay the entire obligation of P29,013.00,
notwithstanding the qualification made by the trial court. But, how Although many policies including policies in the
can petitioner be obliged to pay the entire obligation when the standard form, now provide for subrogation, and
amount stated in its insurance policy with respondent Sio Choy for thus determine the rights of the insurer in this
indemnity against third party liability is only P20,000.00? Moreover, respect, the equitable right of subrogation as the
the qualification made in the decision of the trial court to the effect legal effect of payment inures to the insurer without
that petitioner is sentenced to pay up to P20,000.00 only when the any formal assignment or any express stipulation to
obligation to pay P29,103.00 is made solidary, is an evident breach that effect in the policy" (44 Am. Jur. 2nd 746).
of the concept of a solidary obligation. Thus, We hold that the trial Stated otherwise, when the insurance company pays
court, as upheld by the Court of Appeals, erred in holding petitioner, for the loss, such payment operates as an equitable
solidarily liable with respondents Sio Choy and San Leon Rice Mill, assignment to the insurer of the property and all
Inc. to respondent Vallejos. remedies which the insured may have for the
recovery thereof. That right is not dependent upon ,
As to the second issue, the Court of Appeals, in affirming the nor does it grow out of any privity of
decision of the trial court, ruled that petitioner is not entitled to be contract (emphasis supplied) or upon written
reimbursed by respondent San Leon Rice Mill, Inc. on the ground assignment of claim, and payment to the insured
that said respondent is not privy to the contract of insurance existing makes the insurer assignee in equity (Shambley v.
between petitioner and respondent Sio Choy. We disagree. Jobe-Blackley Plumbing and Heating Co., 264 N.C.
456, 142 SE 2d 18). 9
The appellate court overlooked the principle of subrogation in
insurance contracts. Thus — It follows, therefore, that petitioner, upon paying respondent Vallejos
the amount of riot exceeding P20,000.00, shall become the subrogee
... Subrogation is a normal incident of indemnity of the insured, the respondent Sio Choy; as such, it is subrogated to
insurance (Aetna L. Ins. Co. vs. Moses, 287 U.S. whatever rights the latter has against respondent San Leon Rice Mill,
530, 77 L. ed. 477). Upon payment of the loss, the Inc. Article 1217 of the Civil Code gives to a solidary debtor who has
insurer is entitled to be subrogated pro tanto to any paid the entire obligation the right to be reimbursed by his co-debtors
right of action which the insured may have against for the share which corresponds to each.
the third person whose negligence or wrongful act
caused the loss (44 Am. Jur. 2nd 745, citing Art. 1217. Payment made by one of the solidary
debtors extinguishes the obligation. If two or more

9
solidary debtors offer to pay, the creditor may Republic of the Philippines
choose which offer to accept. SUPREME COURT
Manila
He who made the payment may claim from his co-
debtors only the share which corresponds to each, FIRST DIVISION
with the interest for the payment already made. If the
payment is made before the debt is due, no interest G.R. No. L-28046 May 16, 1983
for the intervening period may be demanded.
PHILIPPINE NATIONAL BANK, plaintiff-appellant, 
xxx xxx xxx vs.
INDEPENDENT PLANTERS ASSOCIATION, INC., ANTONIO
In accordance with Article 1217, petitioner, upon payment to DIMAYUGA, DELFIN FAJARDO, CEFERINO VALENCIA, MOISES
respondent Vallejos and thereby becoming the subrogee of solidary CARANDANG, LUCIANO CASTILLO, AURELIO VALENCIA,
debtor Sio Choy, is entitled to reimbursement from respondent San LAURO LEVISTE, GAVINO GONZALES, LOPE GEVANA and
Leon Rice Mill, Inc. BONIFACIO LAUREANA, defendants-appellees.

To recapitulate then: We hold that only respondents Sio Choy and Basa, Ilao, del Rosario Diaz for plaintiff-appellant.
San Leon Rice Mill, Inc. are solidarily liable to the respondent Martin
C. Vallejos for the amount of P29,103.00. Vallejos may enforce the Laurel Law Office for Dimayuga.
entire obligation on only one of said solidary debtors. If Sio Choy as
solidary debtor is made to pay for the entire obligation (P29,103.00) Tomas Yumol for Fajardo, defendant-appellee.
and petitioner, as insurer of Sio Choy, is compelled to pay
P20,000.00 of said entire obligation, petitioner would be entitled, as
subrogee of Sio Choy as against San Leon Rice Mills, Inc., to be
reimbursed by the latter in the amount of P14,551.50 (which is 1/2 of
P29,103.00 ) PLANA, J.:

WHEREFORE, the petition is GRANTED. The decision of the trial Appeal by the Philippine National Bank (PNB) from the Order of the
court, as affirmed by the Court of Appeals, is hereby AFFIRMED, defunct Court of First Instance of Manila (Branch XX) in its Civil Case
with the modification above-mentioned. Without pronouncement as No. 46741 dismissing PNB's complaint against several solidary
to costs. debtors for the collection of a sum of money on the ground that one
of the defendants (Ceferino Valencia) died during the pendency of
SO ORDERED. the case (i.e., after the plaintiff had presented its evidence) and
therefore the complaint, being a money claim based on contract,
should be prosecuted in the testate or intestate proceeding for the
Melencio-Herrera (Chairperson), Paras, Sarmiento and Regalado, settlement of the estate of the deceased defendant pursuant to
JJ., concur. Section 6 of Rule 86 of the Rules of Court which reads:

10
SEC. 6. Solidary obligation of decedent.— the same debt and one of them dies, the whole
obligation of the decedent is solidary with another indebtedness can be proved against the estate of
debtor, the claim shall be filed against the decedent the latter, the decedent's liability being absolute and
as if he were the only debtor, without prejudice to the primary; and if the claim is not presented within the
right of the estate to recover contribution from the time provided by the rules, the same will be
other debtor. In a joint obligation of the decedent, the barred as against the estate. It is evident from the
claim shall be confined to the portion belonging to foregoing that Section 6 of Rule 87 (now Rule 86)
him. provides the procedure should the creditor desire to
go against the deceased debtor, but there is
The appellant assails the order of dismissal, invoking its right of certainly nothing in the said provision making
recourse against one, some or all of its solidary debtors under Article compliance with such procedure a condition
1216 of the Civil Code — precedent before an ordinary action against the
surviving solidary debtors, should the creditor
choose to demand payment from the latter, could be
ART. 1216. The creditor may proceed against any
entertained to the extent that failure to observe the
one of the solidary debtors or some or all of them
same would deprive the court jurisdiction to take
simultaneously. The demand made against one of
cognizance of the action against the surviving
them shall not be an obstacle to those which may
debtors. Upon the other hand, the Civil Code
subsequently be directed against the others, so long
expressly allows the creditor to proceed against any
as the debt has not been fully collected.
one of the solidary debtors or some or all of them
simultaneously. There is, therefore, nothing improper
The sole issue thus raised is whether in an action for collection of a in the creditor's filing of an action against the
sum of money based on contract against all the solidary debtors, the surviving solidary debtors alone, instead of instituting
death of one defendant deprives the court of jurisdiction to proceed a proceeding for the settlement of the estate of the
with the case against the surviving defendants. deceased debtor wherein his claim could be filed.

It is now settled that the quoted Article 1216 grants the creditor the Similarly, in PNB vs. Asuncion, 80 SCRA 321 at 323-324, this Court,
substantive right to seek satisfaction of his credit from one, some or speaking thru Mr. Justice Makasiar, reiterated the doctrine.
all of his solidary debtors, as he deems fit or convenient for the
protection of his interests; and if, after instituting a collection suit
A cursory perusal of Section 6, Rule
based on contract against some or all of them and, during its
86 of the Revised Rules of Court
pendency, one of the defendants dies, the court retains jurisdiction to
reveals that nothing therein prevents
continue the proceedings and decide the case in respect of the
a creditor from proceeding against
surviving defendants. Thus in Manila Surety & Fidelity Co., Inc. vs.
the surviving solidary debtors. Said
Villarama et al., 107 Phil. 891 at 897, this Court ruled:
provision merely sets up the
procedure in enforcing collection in
Construing Section 698 of the Code of Civil case a creditor chooses to pursue
Procedure from whence the aforequoted provision his claim against the estate of the
(Sec. 6, Rule 86) was taken, this Court held that deceased solidary, debtor.
where two persons are bound in solidum for the

11
It is crystal clear that Article 1216 of Section 6, Rule 86 of the Revised
the New Civil Code is the applicable Rules of Court cannot be made to
provision in this matter. Said prevail over Article 1216 of the New
provision gives the creditor the right Civil Code, the former being merely
to 'proceed against anyone of the procedural, while the latter,
solidary debtors or some or all of substantive.
them simultaneously.' The choice is
undoubtedly left to the solidary, WHEREFORE the appealed order of dismissal of the court a quo in
creditor to determine against whom its Civil Case No. 46741 is hereby set aside in respect of the
he will enforce collection. In case of surviving defendants; and the case is remanded to the
the death of one of the solidary corresponding Regional Trial Court for proceedings. proceedings. No
debtors, he (the creditor) may, if he costs.
so chooses, proceed against the
surviving solidary debtors without SO ORDERED.
necessity of filing a claim in the
estate of the deceased debtors. It is
not mandatory for him to have the Teehankee (Acta. C.J.), Escolin **  Vasquez and Gutierrez, Jr., JJ.,
case dismissed against the concur.
surviving debtors and file its claim in
the estate of the deceased solidary Republic of the Philippines
debtor . . . Supreme Court
Manila
As correctly argued by petitioner, if  
Section 6, Rule 86 of the Revised  
Rules of Court were applied literally,  
Article 1216 of the New Civil Code  
would, in effect, be repealed since THIRD DIVISION
under the Rules of Court, petitioner  
has no choice but to proceed  
against the estate of Manuel ROLITO CALANG and PHILTRANCO G.R. No. 190696
Barredo only. Obviously, this SERVICE ENTERPRISES, INC.,  
provision diminishes the Bank's right Petitioners, Present:
under the New Civil, Code to    
proceed against any one, some or   CARPIO MORALES, J., Chairpers
all of the solidary debtors. Such a -         versus - BRION,
construction is not sanctioned by the   BERSAMIN,
*
principle, which is too well settled to   ABAD, and
require citation, that a substantive PEOPLE OF THE PHILIPPINES, VILLARAMA, JR., JJ.
law cannot be amended by a Respondent. -- -  
procedural rule. Otherwise stared, Promulgated:

12
 
 
August 3, 2010
x-----------------------------------------------------------------------------------------x The prosecution charged Calang with multiple homicide, multiple
 
RESOLUTION serious physical injuries and damage to property thru reckless
  imprudence before the Regional Trial Court (RTC), Branch
BRION, J.:
31, Calbayog City. The RTC, in its decision dated May 21, 2001,
 
found Calang guilty beyond reasonable doubt of reckless
We resolve the motion for reconsideration filed by the
imprudence resulting to multiple homicide, multiple physical injuries
petitioners, Philtranco Service Enterprises, Inc. (Philtranco) and
and damage to property, and sentenced him to suffer an
Rolito Calang, to challenge our Resolution of February 17, 2010. Our
indeterminate penalty of thirty days of arresto menor, as minimum, to
assailed Resolution denied the petition for review on certiorari for
four years and two months of prision correccional, as maximum. The
failure to show any reversible error sufficient to warrant the exercise
RTC ordered Calang and Philtranco, jointly and severally, to
of this Courts discretionary appellate jurisdiction.
pay P50,000.00 as death indemnity to the heirs of
 
Armando; P50,000.00 as death indemnity to the heirs of Mabansag;
Antecedent Facts
and P90,083.93 as actual damages to the private complainants.
At around 2:00 p.m. of April 22, 1989, Rolito Calang was driving
 
Philtranco Bus No. 7001, owned by Philtranco along Daang
The petitioners appealed the RTC decision to the Court of
Maharlika Highway in Barangay Lambao, Sta. Margarita, Samar
Appeals (CA), docketed as CA-G.R. CR No. 25522. The CA, in its
when its rear left side hit the front left portion of a Sarao jeep coming
decision dated November 20, 2009, affirmed the RTC
from the opposite direction. As a result of the collision, Cresencio
decision in toto. The CA ruled that petitioner Calang failed to
Pinohermoso, the jeeps driver, lost control of the vehicle, and
exercise due care and precaution in driving the Philtranco
bumped and killed Jose Mabansag, a bystander who was standing
bus. According to the CA, various eyewitnesses testified that the bus
along the highways shoulder. The jeep turned turtle three (3) times
was traveling fast and encroached into the opposite lane when it
before finally stopping at about 25 meters from the point of impact.
evaded a pushcart that was on the side of the road. In addition, he
Two of the jeeps passengers, Armando Nablo and an unidentified
failed to slacken his speed, despite admitting that he had already
woman, were instantly killed, while the other passengers sustained
seen the jeep coming from the opposite direction when it was still
serious physical injuries.
half a kilometer away. The CA further ruled that Calang

13
demonstrated a reckless attitude when he drove the bus, despite exhibits, which, if considered, would have shown that Calang was
knowing that it was suffering from loose compression, hence, not not negligent, such as the affidavit and testimony of witness
roadworthy. Celestina Cabriga; the testimony of witness Rodrigo Bocaycay; the
  traffic accident sketch and report; and the jeepneys registration
The CA added that the RTC correctly held Philtranco jointly and receipt. The petitioners also insist that the jeeps driver had the last
severally liable with petitioner Calang, for failing to prove that it had clear chance to avoid the collision.
exercised the diligence of a good father of the family to prevent the  
accident. We partly grant the motion.
   
The petitioners filed with this Court a petition for review  
on certiorari. In our Resolution dated February 17, 2010, we denied  
the petition for failure to sufficiently show any reversible error in the  
assailed decision to warrant the exercise of this Courts discretionary Liability of Calang
appellate jurisdiction.  
  We see no reason to overturn the lower courts finding on
The Motion for Reconsideration Calangs culpability. The finding of negligence on his part by the trial
  court, affirmed by the CA, is a question of fact that we cannot pass
In the present motion for reconsideration, the petitioners upon without going into factual matters touching on the finding of
claim that there was no basis to hold Philtranco jointly and severally negligence. In petitions for review on certiorari under Rule 45 of the
liable with Calang because the former was not a party in Revised Rules of Court, this Court is limited to reviewing only errors
the criminal case (for multiple homicide with multiple serious physical of law, not of fact, unless the factual findings complained of are
injuries and damage to property thru reckless imprudence) before devoid of support by the evidence on record, or the assailed
the RTC. judgment is based on a misapprehension of facts.
   
The petitioners likewise maintain that the courts below Liability of Philtranco
overlooked several relevant facts, supported by documentary  

14
deposit of such goods within the inn; and shall
We, however, hold that the RTC and the CA both erred in furthermore have followed the directions which such
holding Philtranco jointly and severally liable with Calang. We innkeeper or his representative may have given
them with respect to the care of and vigilance over
emphasize that Calang was charged criminally before the RTC. such goods. No liability shall attach in case of
Undisputedly, Philtranco was not a direct party in this case. Since the robbery with violence against or intimidation of
persons unless committed by the innkeepers
cause of action against Calang was based on delict, both the RTC employees.
and the CA erred in holding Philtranco jointly and severally liable with  
Calang, based on quasi-delict under Articles 2176 [1] and 2180[2] of the The foregoing subsidiary liability applies to employers,
Civil Code. Articles 2176 and 2180 of the Civil Code pertain to the according to Article 103 of the Revised Penal Code, which reads:
vicarious liability of an employer for quasi-delicts that an employee  
The subsidiary liability established in the
has committed. Such provision of law does not apply to civil liability next preceding article shall also apply to employers,
teachers, persons, and corporations engaged in any
arising from delict.
kind of industry for felonies committed by their
  servants, pupils, workmen, apprentices, or
employees in the discharge of their duties.
If at all, Philtrancos liability may only be subsidiary. Article
 
102 of the Revised Penal Code states the subsidiary civil liabilities of
The provisions of the Revised Penal Code on
innkeepers, tavernkeepers and proprietors of establishments, as
subsidiary liability Articles 102 and 103 are deemed written into the
follows:
judgments in cases to which they are applicable. Thus, in the
 
In default of the persons criminally liable, dispositive portion of its decision, the trial court need not expressly
innkeepers, tavernkeepers, and any other persons
pronounce the subsidiary liability of the employer.[3] Nonetheless,
or corporations shall be civilly liable for crimes
committed in their establishments, in all cases where before the employers subsidiary liability is enforced, adequate
a violation of municipal ordinances or some general
or special police regulations shall have been evidence must exist establishing that (1) they are indeed the
committed by them or their employees. employers of the convicted employees; (2) they are engaged in
 
Innkeepers are also subsidiary liable for the some kind of industry; (3) the crime was committed by the
restitution of goods taken by robbery or theft within employees in the discharge of their duties; and (4) the execution
their houses from guests lodging therein, or for the
payment of the value thereof, provided that such against the latter has not been satisfied due to insolvency. The
guests shall have notified in advance the innkeeper determination of these conditions may be done in the same criminal
himself, or the person representing him, of the

15
Assailed in this petition for review on certiorari1 are the
action in which the employees liability, criminal and civil, has been Decision2 dated November 16, 2011 and the Resolution3 dated
pronounced, in a hearing set for that precise purpose, with due December 10, 2012 of the Court of Appeals (CA) in CA-G.R. CV No.
94693 which affirmed the Decision4 dated August 25, 2009 of the
notice to the employer, as part of the proceedings for the execution Regional Trial Court of Makati City, Branch 142 (RTC) in Civil Case
of the judgment.[4] No. 03-1452 holding, inter alia, petitioner Ruks Konsult and
Construction (Ruks) and respondent Transworld Media Ads, Inc.
  (Transworld) jointly and severally liable to respondent Adworld Sign
WHEREFORE, we PARTLY GRANT the present motion. and Advertising Corporation (Adworld) for damages.cralawred

The Court of Appeals decision that affirmed in toto the RTC decision, The Facts
finding Rolito Calang guilty beyond reasonable doubt of reckless
The instant case arose from a complaint for damages filed by
imprudence resulting in multiple homicide, multiple serious physical Adworld against Transworld and Comark International Corporation
(Comark) before the RTC.5 In the complaint, Adworld alleged that it
injuries and damage to property, is AFFIRMED, with is the owner of a 75 ft. x 60 ft. billboard structure located at EDSA
the MODIFICATION that Philtrancos liability should only be Tulay, Guadalupe, Barangka Mandaluyong, which was misaligned
and its foundation impaired when, on August 11, 2003, the adjacent
subsidiary. No costs. billboard structure owned by Transworld and used by Comark
  collapsed and crashed against it. Resultantly, on August 19, 2003,
Adworld sent Transworld and Comark a letter demanding payment
SO ORDERED. for the repairs of its billboard as well as loss of rental income. On
August 29, 2003, Transworld sent its reply, admitting the damage
  caused by its billboard structure on Adworld’s billboard, but
ARTURO D. BRION nevertheless, refused and failed to pay the amounts demanded by
Associate Justice Adworld. As Adworld’s final demand letter also went unheeded, it
was constrained to file the instant complaint, praying for damages in
FIRST DIVISION the aggregate amount of P474,204.00, comprised of P281,204.00 for
materials, P72,000.00 for labor, and P121,000.00 for indemnity for
G.R. No. 204866, January 21, 2015 loss of income.6chanRoblesvirtualLawlibrary

RUKS KONSULT AND CONSTRUCTION, Petitioner, v. ADWORLD In its Answer with Counterclaim, Transworld averred that the
SIGN AND ADVERTISING CORPORATION* AND TRANSWORLD collapse of its billboard structure was due to extraordinarily strong
MEDIA ADS, INC., Respondents. winds that occurred instantly and unexpectedly, and maintained that
the damage caused to Adworld’s billboard structure was hardly
noticeable. Transworld likewise filed a Third-Party Complaint against
DECISION Ruks, the company which built the collapsed billboard structure in
the former’s favor. It was alleged therein that the structure
PERLAS-BERNABE, J.: constructed by Ruks had a weak and poor foundation not suited for
billboards, thus, prone to collapse, and as such, Ruks should

16
ultimately be held liable for the damages caused to Adworld’s cause of the damages suffered by Adworld’s
billboard structure.7chanRoblesvirtualLawlibrary billboard.14chanRoblesvirtualLawlibrary

For its part, Comark denied liability for the damages caused to Aggrieved, both Transworld and Ruks appealed to the CA. In a
Adworld’s billboard structure, maintaining that it does not have any Resolution dated February 3, 2011, the CA dismissed Transworld’s
interest on Transworld’s collapsed billboard structure as it only appeal for its failure to file an appellant’s brief on time. 15 Transworld
contracted the use of the same. In this relation, Comark prayed for elevated its case before the Court, docketed as G.R. No.
exemplary damages from Transworld for unreasonably including it as 197601.16 However, in a Resolution17 dated November 23, 2011, the
a party-defendant in the complaint.8chanRoblesvirtualLawlibrary Court declared the case closed and terminated for failure of
Transworld to file the intended petition for review on certiorari within
Lastly, Ruks admitted that it entered into a contract with Transworld the extended reglementary period. Subsequently, the Court issued
for the construction of the latter’s billboard structure, but denied an Entry of Judgment18 dated February 22, 2012 in G.R. No. 197601
liability for the damages caused by its collapse. It contended that declaring the Court’s November 23, 2011 Resolution  final and
when Transworld hired its services, there was already an existing executory.
foundation for the billboard and that it merely finished the structure
according to the terms and conditions of its contract with the The CA Ruling
latter.9chanRoblesvirtualLawlibrary
In a Decision19 dated November 16, 2011, the CA denied Ruks’s
The RTC Ruling appeal and affirmed the ruling of the RTC. It adhered to the RTC’s
finding of negligence on the part of Transworld and Ruks which
In a Decision10 dated August 25, 2009, the RTC ultimately ruled in brought about the damage to Adworld’s billboard. It found that
Adworld’s favor, and accordingly, declared, inter alia, Transworld Transworld failed to ensure that Ruks will comply with the approved
and Ruks jointly and severally liable to Adworld in the amount of plans and specifications of the structure, and that Ruks continued to
P474,204.00 as actual damages, with legal interest from the date of install and finish the billboard structure despite the knowledge that
the filing of the complaint until full payment thereof, plus attorney’s there were no adequate columns to support the
fees in the amount of P50,000.00.11chanRoblesvirtualLawlibrary same.20chanRoblesvirtualLawlibrary

The RTC found both Transworld and Ruks negligent in the Dissatisfied, Ruks moved for reconsideration,21 which was, however,
construction of the collapsed billboard as they knew that the denied in a Resolution22 dated December 10, 2012, hence, this
foundation supporting the same was weak and would pose danger to petition.
the safety of the motorists and the other adjacent properties, such as
Adworld’s billboard, and yet, they did not do anything to remedy the On the other hand, Transworld filed another appeal before the Court,
situation.12 In particular, the RTC explained that Transworld was docketed as G.R. No. 205120.23However, the Court denied outright
made aware by Ruks that the initial construction of the lower Transworld’s petition in a Resolution24 dated April 15, 2013, holding
structure of its billboard did not have the proper foundation and that the same was already bound by the dismissal of its petition filed
would require additional columns and pedestals to support the in G.R. No. 197601.
structure. Notwithstanding, however, Ruks proceeded with the
construction of the billboard’s upper structure and merely assumed The Issue Before the Court
that Transworld would reinforce its lower structure.13 The RTC then
concluded that these negligent acts were the direct and proximate The primordial issue for the Court’s resolution is whether or not the

17
CA correctly affirmed the ruling of the RTC declaring Ruks jointly and each other’s word that repairs would be done to such foundation, but
severally liable with Transworld for damages sustained by Adworld. none was done at all. Clearly, the foregoing circumstances show that
both Transworld and Ruks are guilty of negligence in the
The Court’s Ruling construction of the former’s billboard, and perforce, should be held
liable for its collapse and the resulting damage to Adworld’s billboard
The petition is without merit. structure. As joint tortfeasors, therefore, they are solidarily liable to
Adworld. Verily, “[j]oint tortfeasors are those who command,
At the outset, it must be stressed that factual findings of the RTC, instigate, promote, encourage, advise, countenance, cooperate in,
when affirmed by the CA, are entitled to great weight by the Court aid or abet the commission of a tort, or approve of it after it is done, if
and are deemed final and conclusive when supported by the done for their benefit. They are also referred to as those who act
evidence on record.25 Absent any exceptions to this rule – such as together in committing wrong or whose acts, if independent of each
when it is established that the trial court ignored, overlooked, other, unite in causing a single injury. Under Article 2194 29 of the Civil
misconstrued, or misinterpreted cogent facts and circumstances that, Code, joint tortfeasors are solidarily liable for the resulting damage.
if considered, would change the outcome of the case 26 – such In other words, joint tortfeasors are each liable as principals, to the
findings must stand. same extent and in the same manner as if they had performed the
wrongful act themselves.”30 The Court’s pronouncement in People v.
After a judicious perusal of the records, the Court sees no cogent Velasco31 is instructive on this matter, to
reason to deviate from the findings of the RTC and the CA and their wit:32chanRoblesvirtualLawlibrary
uniform conclusion that both Transworld and Ruks committed acts
resulting in the collapse of the former’s billboard, which in turn, Where several causes producing an injury are concurrent and
caused damage to the adjacent billboard of Adworld. each is an efficient cause without which the injury would not
have happened, the injury may be attributed to all or any of the
Jurisprudence defines negligence as the omission to do something causes and recovery may be had against any or all of the
which a reasonable man, guided by those considerations which responsible persons although under the circumstances of the case,
ordinarily regulate the conduct of human affairs, would do, or the it may appear that one of them was more culpable, and that the duty
doing of something which a prudent and reasonable man would not owed by them to the injured person was not same. No actor’s
do.27 It is the failure to observe for the protection of the interest of negligence ceases to be a proximate cause merely because it does
another person that degree of care, precaution, and vigilance which not exceed the negligence of other actors. Each wrongdoer is
the circumstances justly demand, whereby such other person suffers responsible for the entire result and is liable as though his acts were
injury.28chanRoblesvirtualLawlibrary the sole cause of the injury.

In this case, the CA correctly affirmed the RTC’s finding that There is no contribution between joint [tortfeasors] whose liability is
Transworld’s initial construction of its billboard’s lower structure solidary since both of them are liable for the total damage. Where
without the proper foundation, and that of Ruks’s finishing its upper the concurrent or successive negligent acts or omissions of
structure and just merely assuming that Transworld would reinforce two or more persons, although acting independently, are in
the weak foundation are the two (2) successive acts which were the combination the direct and proximate cause of a single injury to
direct and proximate cause of the damages sustained by Adworld. a third person, it is impossible to determine in what proportion
Worse, both Transworld and Ruks were fully aware that the each contributed to the injury and either of them is responsible
foundation for the former’s billboard was weak; yet, neither of them for the whole injury. x x x. (Emphases and underscoring supplied)
took any positive step to reinforce the same. They merely relied on

18
On October 7, 2000, a shipment of various electronic goods from
In conclusion, the CA correctly affirmed the ruling of the RTC Thailand and Malaysia arrived at the Port of Manila for Sony
declaring Ruks jointly and severally liable with Transworld for Philippines, Inc. (Sony). Previous to the arrival, Sony had engaged
damages sustained by Adworld.chanrobleslaw the services of TMBI to facilitate, process, withdraw, and deliver  the
shipment from the port to its warehouse in Biñan, Laguna. 2
WHEREFORE, the petition is DENIED. The Decision dated
November 16, 2011 and the Resolution dated December 10, 2012 of TMBI – who did not own any delivery trucks – subcontracted the
the Court of Appeals in CA-G.R. CV No. 94693 are services of Benjamin Manalastas’ company, BMT Trucking
hereby AFFIRMED. Services (BMT), to transport the shipment from the port to the Biñan
warehouse.3 Incidentally, TMBI notified Sony who had no objections
SO ORDERED.cralawlawlibrary to the arrangement.4

Four BMT trucks picked up the shipment from the port at about 11:00
G.R. No. 194121 a.m. of October 7, 2000. However, BMT could not immediately
undertake the delivery because of the truck ban and because the
TORRES-MADRID BROKERAGE, INC., Petitioner  following day was a Sunday. Thus, BMT scheduled the delivery on
vs. October 9, 2000.
FEB MITSUI MARINE INSURANCE CO., INC. and BENJAMIN P.
MANALAST AS, doing business under the name of BMT In the early morning of October 9, 2000, the four trucks left BMT’s
TRUCKING SERVICES, Respondents garage for Laguna.5 However, only three trucks arrived at Sony’s
Biñan warehouse.
DECISION
At around 12:00 noon, the truck driven by Rufo Reynaldo
BRION, J.: Lapesura (NSF-391)  was found abandoned along the Diversion
Road in Filinvest, Alabang, Muntinlupa City.6 Both the driver and the
We resolve the petition for review on certiorari  challenging the Court shipment were missing.
of Appeals' (CA)  October 14, 2010 decision in CA-G.R. CV No.
91829.1 Later that evening, BMT’s Operations Manager Melchor Manalastas
informed Victor Torres, TMBI’s General Manager, of the
The CA affirmed the Regional Trial Court's (RTC)  decision in Civil development.7 They went to Muntinlupa together to inspect the truck
Case No. 01-1596, and found petitioner Torres-Madrid Brokerage, and to report the matter to the police.8
Inc. (TMBI) and respondent Benjamin P. Manalastas jointly and
solidarily liable to respondent FEB Mitsui Marine Insurance Co., Victor Torres also filed a complaint with the National Bureau of
Inc. (Mitsui)  for damages from the loss of transported cargo. Investigation (NBI)  against Lapesura for "hijacking."9The complaint
resulted in a recommendation by the NBI to the Manila City
Antecedents Prosecutor’s Office to prosecute Lapesura for qualified theft. 10

TMBI notified Sony of the loss through a letter dated October 10,
2000.11 It also sent BMT a letter dated March 29, 2001, demanding

19
payment for the lost shipment. BMT refused to pay, insisting that the BMT claimed that it had exercised extraordinary diligence over the
goods were "hijacked." lost shipment, and argued as well that the loss resulted from a
fortuitous event.
In the meantime, Sony filed an insurance claim with the Mitsui, the
insurer of the goods. After evaluating the merits of the claim, Mitsui On October 14, 2010, the CA affirmed the RTC’s decision but
paid Sony PHP7,293,386.23 corresponding to the value of the lost reduced the award of attorney’s fees to PHP 200,000.
goods.12
The CA held: (1) that "hijacking" is not necessarily a fortuitous event
After being subrogated to Sony’s rights, Mitsui sent TMBI a demand because the term refers to the general stealing of cargo during
letter dated August 30, 2001 for payment of the lost goods. TMBI transit;15 (2) that TMBI is a common carrier engaged in the business
refused to pay Mitsui’s claim. As a result, Mitsui filed a complaint of transporting goods for the general public for a fee; 16 (3) even if the
against TMBI on November 6, 2001, "hijacking" were a fortuitous event, TMBI’s failure to observe
extraordinary diligence in overseeing the cargo and adopting security
TMBI, in turn, impleaded Benjamin Manalastas, the proprietor of measures rendered it liable for the loss;17 and (4) even if TMBI had
BMT, as a third-party defendant. TMBI alleged that BMT’s driver, not been negligent in the handling, transport and the delivery of the
Lapesura, was responsible for the theft/hijacking of the lost cargo shipment, TMBI still breached its contractual obligation to Sony when
and claimed BMT’s negligence as the proximate cause of the loss. it failed to deliver the shipment.18
TMBI prayed that in the event it is held liable to Mitsui for the loss, it
should be reimbursed by BMT. TMBI disagreed with the CA’s ruling and filed the present petition on
December 3, 2010.
At the trial, it was revealed that BMT and TMBI have been doing
business with each other since the early 80’s. It also came out that The Arguments
there had been a previous hijacking incident involving Sony’s cargo
in 1997, but neither Sony nor its insurer filed a complaint against TMBI’s Petition
BMT or TMBI.13
TMBI insists that the hijacking of the truck was a fortuitous event. It
On August 5, 2008, the RTC found TMBI and Benjamin Manalastas contests the CA’s finding that neither force nor intimidation was used
jointly and solidarily liable to pay Mitsui PHP 7,293,386.23 as actual in the taking of the cargo. Considering Lapesura was never found,
damages, attorney’s fees equivalent to 25% of the amount claimed, the Court should not discount the possibility that he was a victim
and the costs of the suit.14 The RTC held that TMBI and Manalastas rather than a perpetrator.19
were common carriers and had acted negligently.
TMBI denies being a common carrier because it does not own a
Both TMBI and BMT appealed the RTC’s verdict. single truck to transport its shipment and it does not offer transport
services to the public for compensation.20 It emphasizes that Sony
TMBI denied that it was a common carrier required to knew TMBI did not have its own vehicles and would subcontract the
exercise extraordinary  diligence. It maintains that it exercised the delivery to a third-party.
diligence of a good father of a family and should be absolved of
liability because the truck was "hijacked" and this was a fortuitous
event.

20
Further, TMBI now insists that the service it offered was limited to the TMBI’s brokerage service includes the eventual delivery of the cargo
processing of paperwork attendant to the entry of Sony’s goods. It to the consignee.30
denies that delivery of the shipment was a part of its obligation. 21
Mitsui invokes as well the legal presumption of negligence against
TMBI solely blames BMT as it had full control and custody of the TMBI, pointing out that TMBI simply entrusted the cargo to BMT
cargo when it was lost.22 BMT, as a common carrier, is presumed without adopting any security measures despite: (1) a previous
negligent and should be responsible for the loss. hijacking incident when TMBI lost Sony’s cargo; and (2) TMBI’s
knowledge that the cargo was worth more than 10 million pesos. 31
BMT’s Comment
Mitsui affirms that TMBI breached the contract of carriage through its
BMT insists that it observed the required standard of care. 23 Like the negligent handling of the cargo, resulting in its loss.
petitioner, BMT maintains that the hijacking was a fortuitous event –
a force majeure –  that exonerates it from liability.24 It points out that The Court’s Ruling
Lapesura has never been seen again and his fate remains a
mystery. BMT likewise argues that the loss of the cargo necessarily A brokerage may be considered a
showed that the taking was with the use of force or intimidation. 25 common carrier if it also undertakes to
deliver the goods for its customers
If there was any attendant negligence, BMT points the finger on
TMBI who failed to send a representative to accompany the Common carriers are persons, corporations, firms or associations
shipment.26 BMT further blamed TMBI for the latter’s failure to adopt engaged in the business of transporting passengers or goods or
security measures to protect Sony’s cargo.27 both, by land, water, or air, for compensation, offering their services
to the public.32 By the nature of their business and for reasons of
Mitsui’s Comment public policy, they are bound to observe extraordinary diligence in
the vigilance over the goods and in the safety of their passengers. 33
Mitsui counters that neither TMBI nor BMT alleged or proved during
the trial that the taking of the cargo was accompanied with grave or In A.F. Sanchez Brokerage Inc. v. Court of Appeals,34we held that a
irresistible threat, violence, or force.28 Hence, the incident cannot be customs broker – whose principal business is the preparation of the
considered "force majeure" and TMBI remains liable for breach of correct customs declaration and the proper shipping documents – is
contract. still considered a common carrier if it also undertakes to deliver the
goods for its customers. The law does not distinguish between one
Mitsui emphasizes that TMBI’s theory – that force or intimidation whose principal business activity is the carrying of goods and one
must have been used because Lapesura was never found – was who undertakes this task only as an ancillary activity.35 This ruling
only raised for the first time before this Court.29 It also discredits the has been reiterated in Schmitz Transport & Brokerage Corp. v.
theory as a mere conjecture for lack of supporting evidence. Transport Venture, Inc.,36Loadmasters Customs Services, Inc. v.
Glodel Brokerage Corporation,37and Westwind Shipping Corporation
v. UCPB General Insurance Co., Inc.38
Mitsui adopts the CA’s reasons to conclude that TMBI is a common
carrier. It also points out Victor Torres’ admission during the trial that
Despite TMBI’s present denials, we find that the delivery of the
goods is an integral, albeit ancillary, part of its brokerage services.

21
TMBI admitted that it was contracted to facilitate, process, and clear (4) The character of the goods or defects in the packing or in the
the shipments from the customs authorities, withdraw them from the containers;
pier, then transport and deliver them to Sony’s warehouse in
Laguna.39 (5) Order or act of competent public authority.42

Further, TMBI’s General Manager Victor Torres described the nature For all other cases - such as theft or robbery – a common carrier is
of its services as follows: presumed to have been at fault or to have acted negligently, unless it
can prove that it observed extraordinary diligence.43
ATTY. VIRTUDAZO: Could you please tell the court what is the
nature of the business of [TMBI]? Simply put, the theft or the robbery of the goods is not considered a
fortuitous event or a force majeure. Nevertheless, a common carrier
Witness MR. Victor Torres of Torres Madrid: We are engaged in may absolve itself of liability for a resulting loss: (1) if it proves that it
customs brokerage business. We acquire the release documents exercised extraordinary diligence in transporting and safekeeping
from the Bureau of Customs and eventually deliver the cargoes to the goods;44 or (2) if it stipulated with the shipper/owner of the goods
the consignee’s warehouse and we are engaged in that kind of to limit its liability for the loss, destruction, or deterioration of the
business, sir.40 goods to a degree less than extraordinary diligence.45

That TMBI does not own trucks and has to subcontract the delivery However, a stipulation diminishing or dispensing with the common
of its clients’ goods, is immaterial. As long as an entity holds itself to carrier’s liability for acts committed by thieves or robbers who do not
the public for the transport of goods as a business, it is considered a act with grave or irresistible threat, violence, or force is void under
common carrier regardless of whether it owns the vehicle used or Article 1745 of the Civil Code for being contrary to public
has to actually hire one.41 policy.46 Jurisprudence, too, has expanded Article 1734’s five
exemptions. De Guzman v. Court of Appeals47 interpreted Article
Lastly, TMBI’s customs brokerage services – including the 1745 to mean that a robbery attended by "grave or irresistible threat,
transport/delivery of the cargo – are available to anyone willing to violence or force" is a fortuitous event that absolves the common
pay its fees. Given these circumstances, we find it undeniable that carrier from liability.
TMBI is a common carrier.
In the present case, the shipper, Sony, engaged the services of
Consequently, TMBI should be held responsible for the loss, TMBI, a common carrier, to facilitate the release of its shipment and
destruction, or deterioration of the goods it transports unless it deliver the goods to its warehouse. In turn, TMBI subcontracted a
results from: portion of its obligation – the delivery of the cargo – to another
common carrier, BMT.
(1) Flood, storm, earthquake, lightning, or other natural disaster or
calamity; Despite the subcontract, TMBI remained responsible for the cargo.
Under Article 1736, a common carrier’s extraordinary responsibility
over the shipper’s goods lasts from the time these goods are
(2) Act of the public enemy in war, whether international or civil;
unconditionally placed in the possession of, and received by, the
carrier for transportation, until they are delivered, actually or
(3) Act of omission of the shipper or owner of the goods; constructively, by the carrier to the consignee.48

22
That the cargo disappeared during transit while under the custody of Notably, TMBI’s liability to Mitsui does not stem from a quasi-delict
BMT – TMBI’s subcontractor – did not diminish nor terminate TMBI’s (culpa aquiliana) but from its breach of contract (culpa contractual).
responsibility over the cargo. Article 1735 of the Civil Code presumes The tie that binds TMBI with Mitsui is contractual, albeit one that
that it was at fault. passed on to Mitsui as a result of TMBI’s contract of carriage with
Sony to which Mitsui had been subrogated as an insurer who had
Instead of showing that it had acted with extraordinary paid Sony’s insurance claim. The legal reality that results from this
diligence, TMBI simply argued that it was not a common carrier contractual tie precludes the application of quasi-delict based Article
bound to observe extraordinary diligence. Its failure to successfully 2194.
establish this premise carries with it the presumption of fault or
negligence, thus rendering it liable to Sony/Mitsui for breach of A third party may recover from a
contract. common carrier for quasi-delict but must
prove actual negligence
Specifically, TMBI’s current theory – that the hijacking was attended
by force or intimidation – is untenable. We likewise disagree with the finding that BMT is directly liable to
Sony/Mitsui for the loss of the cargo. While it is undisputed that the
First, TMBI alleged in its Third Party Complaint against BMT that cargo was lost under the actual custody of BMT (whose employee is
Lapesura was responsible for hijacking the shipment.49 Further, the primary suspect in the hijacking or robbery of the shipment), no
Victor Torres filed a criminal complaint against Lapesura with the direct contractual relationship existed between Sony/Mitsui and BMT.
NBI.50 These actions constitute direct and binding admissions that If at all, Sony/Mitsui’s cause of action against BMT could only arise
Lapesura stole the cargo. Justice and fair play dictate that TMBI from quasi-delict, as a third party suffering damage from the action of
should not be allowed to change its legal theory on appeal. another due to the latter’s fault or negligence, pursuant to Article
2176 of the Civil Code.51
Second, neither TMBI nor BMT succeeded in substantiating this
theory through evidence. Thus, the theory remained an unsupported We have repeatedly distinguished between an action for breach of
allegation no better than speculations and conjectures. The CA contract (culpa contractual) and an action for quasi-delict (culpa
therefore correctly disregarded the defense of force majeure. aquiliana).

TMBI and BMT are not solidarily liable In culpa contractual,  the plaintiff only needs to establish the
to Mitsui existence of the contract and the obligor’s failure to perform his
obligation. It is not necessary for the plaintiff to prove or even allege
that the obligor’s non-compliance was due to fault or negligence
We disagree with the lower courts’ ruling that TMBI and BMT are
because Article 1735 already presumes that the common carrier is
solidarily liable to Mitsui for the loss as joint tortfeasors. The ruling
negligent. The common carrier can only free itself from liability by
was based on Article 2194 of the Civil Code:
proving that it observed extraordinary diligence. It cannot discharge
this liability by shifting the blame on its agents or servants. 52
Art. 2194. The responsibility of two or more persons who are liable
for quasi-delict is solidary.
On the other hand, the plaintiff in culpa aquiliana  must clearly
establish the defendant’s fault or negligence because this is the very
basis of the action.53 Moreover, if the injury to the plaintiff resulted

23
from the act or omission of the defendant’s employee or servant, the b. Attorney's foes in the amount of PHP 200,000.00; and
defendant may absolve himself by proving that he observed the
diligence of a good father of a family to prevent the damage. 54 c. Costs of suit.

In the present case, Mitsui’s action is solely premised on TMBI’s Respondent Benjamin P. Manalastas is in
breach of contract. Mitsui did not even sue BMT, much less prove turn ORDERED to REIMBURSE Torres-Madrid Brokerage, Inc. of
any negligence on its part. If BMT has entered the picture at all, it is the above-mentioned amounts.
because TMBI sued it for reimbursement for the liability that TMBI
might incur from its contract of carriage with Sony/Mitsui. SO ORDERED.
Accordingly, there is no basis to directly hold BMT liable to Mitsui for
quasi-delict.
ARTURO D. BRION
Associate Justice
BMT is liable to TMBI for breach of their
contract of carriage
January 11, 2016
We do not hereby say that TMBI must absorb the loss. By
subcontracting the cargo delivery to BMT, TMBI entered into its own G.R. No. 167615
contract of carriage with a fellow common carrier.
SPOUSES ALEXANDER AND JULIE LAM, Doing Business
The cargo was lost after its transfer to BMT' s custody based on its Under the Name and Style "COLORKWIK LABORATORIES"
contract of carriage with TMBI. Following Article 1735, BMT is AND "COLORKWIK PHOTO SUPPLY", Petitioners, 
presumed to be at fault. Since BMT failed to prove that it vs.
observed extraordinary diligence in the performance of its obligation KODAK PHILIPPINES, LTD., Respondent.
to TMBI, it is liable to TMBI for breach of their contract of carriage.
DECISION
In these lights, TMBI is liable to Sony (subrogated by Mitsui) for
breaching the contract of carriage. In tum, TMBI is entitled to LEONEN, J.:
reimbursement from BMT due to the latter's own breach of its
contract of carriage with TMBI. The proverbial buck stops with BMT This is a Petition for Review on Certiorari filed on April 20, 2005
who may either: (a) absorb the loss, or (b) proceed after its missing assailing the March 30, 2005 Decision1 and September 9, 2005
driver, the suspected culprit, pursuant to Article 2181. 55 Amended Decision2 of the Court of Appeals, which modified the
February 26, 1999 Decision3 of the Regional Trial Court by reducing
WHEREFORE, the Court hereby ORDERS petitioner TorresMadrid the amount of damages awarded to petitioners Spouses Alexander
Brokerage, Inc. to pay the respondent FEB Mitsui Marine Insurance and Julie Lam (Lam Spouses).4 The Lam Spouses argue that
Co", Inc. the following: respondent Kodak Philippines, Ltd.’s breach of their contract of sale
entitles them to damages more than the amount awarded by the
a. Actual damages in the amount of PHP 7,293,386.23 plus legal Court of Appeals.5
interest from the time the complaint was filed until it is fully paid;
I

24
On January 8, 1992, the Lam Spouses and Kodak Philippines, Ltd. On January 15, 1992, Kodak Philippines, Ltd. delivered one (1) unit
entered into an agreement (Letter Agreement) for the sale of three of the Minilab Equipment in Tagum, Davao Province. 9 The delivered
(3) units of the Kodak Minilab System 22XL6 (Minilab Equipment) in unit was installed by Noritsu representatives on March 9, 1992. 10 The
the amount of ₱1,796,000.00 per unit,7 with the following terms: Lam Spouses issued postdated checks amounting to ₱35,000.00
each for 12 months as payment for the first delivered unit, with the
This confirms our verbal agreement for Kodak Phils., Ltd. To provide first check due on March 31, 1992.11
Colorkwik Laboratories, Inc. with three (3) units Kodak Minilab
System 22XL . . . for your proposed outlets in Rizal Avenue (Manila), The Lam Spouses requested that Kodak Philippines, Ltd. not
Tagum (Davao del Norte), and your existing Multicolor photo counter negotiate the check dated March 31, 1992 allegedly due to
in Cotabato City under the following terms and conditions: insufficiency of funds.12 The same request was made for the check
due on April 30, 1992. However, both checks were negotiated by
1. Said Minilab Equipment packages will avail a total of 19% Kodak Philippines, Ltd. and were honored by the depository
multiple order discount based on prevailing equipment price bank.13 The 10 other checks were subsequently dishonored after the
provided said equipment packages will be purchased not Lam Spouses ordered the depository bank to stop payment. 14
later than June 30, 1992.
Kodak Philippines, Ltd. canceled the sale and demanded that the
2. 19% Multiple Order Discount shall be applied in the form Lam Spouses return the unit it delivered together with its
of merchandise and delivered in advance immediately after accessories.15 The Lam Spouses ignored the demand but also
signing of the contract. rescinded the contract through the letter dated November 18, 1992
on account of Kodak Philippines, Ltd.’s failure to deliver the two (2)
remaining Minilab Equipment units.16
* Also includes start-up packages worth P61,000.00.

On November 25, 1992, Kodak Philippines, Ltd. filed a Complaint for


3. NO DOWNPAYMENT.
replevin and/or recovery of sum of money. The case was raffled to
Branch 61 of the Regional Trial Court, Makati City.17 The Summons
4. Minilab Equipment Package shall be payable in 48 and a copy of Kodak Philippines, Ltd.’s Complaint was personally
monthly installments at THIRTY FIVE THOUSAND PESOS served on the Lam Spouses.18
(P35,000.00) inclusive of 24% interest rate for the first 12
months; the balance shall be re-amortized for the remaining
The Lam Spouses failed to appear during the pre-trial conference
36 months and the prevailing interest shall be applied.
and submit their pre-trial brief despite being given
extensions.19 Thus, on July 30, 1993, they were declared in
5. Prevailing price of Kodak Minilab System 22XL as of default.20 Kodak Philippines, Ltd. presented evidence ex-parte.21 The
January 8, 1992 is at ONE MILLION SEVEN HUNDRED trial court issued the Decision in favor of Kodak Philippines, Ltd.
NINETY SIX THOUSAND PESOS. ordering the seizure of the Minilab Equipment, which included the
lone delivered unit, its standard accessories, and a separate
6. Price is subject to change without prior notice. generator set.22 Based on this Decision, Kodak Philippines, Ltd. was
able to obtain a writ of seizure on December 16, 1992 for the Minilab
*Secured with PDCs; 1st monthly amortization due 45 days Equipment installed at the Lam Spouses’ outlet in Tagum, Davao
after installation[.]8 Province.23 The writ was enforced on December 21, 1992, and

25
Kodak Philippines, Ltd. gained possession of the Minilab Equipment Kodak Philippines, Ltd. failed to give a sufficient explanation for its
unit, accessories, and the generator set.24 failure to deliver all three (3) purchased units within a reasonable
time.32
The Lam Spouses then filed before the Court of Appeals a Petition to
Set Aside the Orders issued by the trial court dated July 30, 1993 The trial court found:
and August 13, 1993. These Orders were subsequently set aside by
the Court of Appeals Ninth Division, and the case was remanded to Kodak would have the court believe that it did not deliver the other
the trial court for pre-trial.25 two (2) units due to the failure of defendants to make good the
installments subsequent to the second. The court is not convinced.
On September 12, 1995, an Urgent Motion for Inhibition was filed First of all, there should have been simultaneous delivery on account
against Judge Fernando V. Gorospe, Jr.,26 who had issued the writ of of the circumstances surrounding the transaction. . . . Even after the
seizure.27 The ground for the motion for inhibition was not provided. first delivery . . . no delivery was made despite repeated demands
Nevertheless, Judge Fernando V. Gorospe Jr. inhibited himself, and from the defendants and despite the fact no installments were due.
the case was reassigned to Branch 65 of the Regional Trial Court, Then in March and in April (three and four months respectively from
Makati City on October 3, 1995.28 the date of the agreement and the first delivery) when the
installments due were both honored, still no delivery was made.
In the Decision dated February 26, 1999, the Regional Trial Court
found that Kodak Philippines, Ltd. defaulted in the performance of its Second, although it might be said that Kodak was testing the waters
obligation under its Letter Agreement with the Lam Spouses. 29 It held with just one delivery - determining first defendants’ capacity to pay -
that Kodak Philippines, Ltd.’s failure to deliver two (2) out of the three it was not at liberty to do so. It is implicit in the letter agreement that
(3) units of the Minilab Equipment caused the Lam Spouses to stop delivery within a reasonable time was of the essence and failure to
paying for the rest of the installments.30 The trial court noted that so deliver within a reasonable time and despite demand would
while the Letter Agreement did not specify a period within which the render the vendor in default.
delivery of all units was to be made, the Civil Code provides
"reasonable time" as the standard period for compliance: ....

The second paragraph of Article 1521 of the Civil Code provides: Third, at least two (2) checks were honored. If indeed Kodak refused
delivery on account of defendants’ inability to pay, non-delivery
Where by a contract of sale the seller is bound to send the goods to during the two (2) months that payments were honored is
the buyer, but no time for sending them is fixed, the seller is bound to unjustified.33
send them within a reasonable time.
Nevertheless, the trial court also ruled that when the Lam Spouses
What constitutes reasonable time is dependent on the circumstances accepted delivery of the first unit, they became liable for the fair
availing both on the part of the seller and the buyer. In this case, value of the goods received:
delivery of the first unit was made five (5) days after the date of the
agreement. Delivery of the other two (2) units, however, was never On the other hand, defendants accepted delivery of one (1) unit.
made despite the lapse of at least three (3) months. 31 Under Article 1522 of the Civil Code, in the event the buyer accepts
incomplete delivery and uses the goods so delivered, not then
knowing that there would not be any further delivery by the seller, the

26
buyer shall be liable only for the fair value to him of the goods 2) PHP 1,300,000.00 as actual expenses in the renovation of
received. In other words, the buyer is still liable for the value of the the Tagum, Davao and Rizal Ave., Manila outlets.
property received. Defendants were under obligation to pay the
amount of the unit. Failure of delivery of the other units did not SO ORDERED.39
thereby give unto them the right to suspend payment on the unit
delivered. Indeed, in incomplete deliveries, the buyer has the remedy On March 31, 1999, the Lam Spouses filed their Notice of Partial
of refusing payment unless delivery is first made. In this case though, Appeal, raising as an issue the Regional Trial Court’s failure to order
payment for the two undelivered units have not even commenced; Kodak Philippines, Ltd. to pay: (1) ₱2,040,000 in actual damages; (2)
the installments made were for only one (1) unit. ₱50,000,000 in moral damages; (3) ₱20,000,000 in exemplary
damages; (4) ₱353,000 in attorney’s fees; and (5) ₱300,000 as
Hence, Kodak is right to retrieve the unit delivered. 34 litigation expenses.40 The Lam Spouses did not appeal the Regional
Trial Court’s award for the generator set and the renovation
The Lam Spouses were under obligation to pay for the amount of expenses.41
one unit, and the failure to deliver the remaining units did not give
them the right to suspend payment for the unit already Kodak Philippines, Ltd. also filed an appeal. However, the Court of
delivered.35 However, the trial court held that since Kodak Appeals42 dismissed it on December 16, 2002 for Kodak Philippines,
Philippines, Ltd. had elected to cancel the sale and retrieve the Ltd.’s failure to file its appellant’s brief, without prejudice to the
delivered unit, it could no longer seek payment for any deterioration continuation of the Lam Spouses’ appeal.43 The Court of Appeals’
that the unit may have suffered while under the custody of the Lam December 16, 2002 Resolution denying Kodak Philippines, Ltd.’s
Spouses.36 appeal became final and executory on January 4, 2003. 44

As to the generator set, the trial court ruled that Kodak Philippines, In the Decision45 dated March 30, 2005, the Court of Appeals Special
Ltd. attempted to mislead the court by claiming that it had delivered Fourteenth Division modified the February 26, 1999 Decision of the
the generator set with its accessories to the Lam Spouses, when the Regional Trial Court:
evidence showed that the Lam Spouses had purchased it from
Davao Ken Trading, not from Kodak Philippines, Ltd. 37 Thus, the WHEREFORE, PREMISES CONSIDERED, the Assailed Decision
generator set that Kodak Philippines, Ltd. wrongfully took from the dated 26 February 1999 of the Regional Trial Court, Branch 65 in
Lam Spouses should be replaced.38 Civil Case No. 92-3442 is hereby MODIFIED. Plaintiff-appellant is
ordered to pay the following:
The dispositive portion of the Regional Trial Court Decision reads:
1. P130,000.00 representing the amount of the generator
PREMISES CONSIDERED, the case is hereby dismissed. Plaintiff is set, plus legal interest at 12% per annum from December
ordered to pay the following: 1992 until fully paid; and

1) PHP 130,000.00 representing the amount of the generator 2. P440,000.00 as actual damages;
set, plus legal interest at 12% per annum from December
1992 until fully paid; and 3. P25,000.00 as moral damages; and

27
4. P50,000.00 as exemplary damages. the other two (2) equipment cannot bar its recovery for the full
payment of the equipment already delivered. As far as Kodak is
SO ORDERED.46 (Emphasis supplied) concerned, it had already fully complied with its separable obligation
to deliver the first unit of Minilab Equipment.47 (Emphasis supplied)
The Court of Appeals agreed with the trial court’s Decision, but
extensively discussed the basis for the modification of the dispositive The Court of Appeals held that the issuance of a writ of replevin is
portion. proper insofar as the delivered Minilab Equipment unit and its
standard accessories are concerned, since Kodak Philippines, Ltd.
had the right to possess it:48
The Court of Appeals ruled that the Letter Agreement executed by
the parties showed that their obligations were susceptible of partial
performance. Under Article 1225 of the New Civil Code, their The purchase price of said equipment is P1,796,000.00 which, under
obligations are divisible: the agreement is payable with forty eight (48) monthly amortization.
It is undisputed that Sps. Lam made payments which amounted to
Two Hundred Seventy Thousand Pesos (P270,000.00) through the
In determining the divisibility of an obligation, the following factors
following checks: Metrobank Check Nos. 00892620 and 00892621
may be considered, to wit: (1) the will or intention of the parties,
dated 31 March 1992 and 30 April 1992 respectively in the amount of
which may be expressed or presumed; (2) the objective or purpose
Thirty Five Thousand Pesos (P35,000.00) each, and BPI Family
of the stipulated prestation; (3) the nature of the thing; and (4)
Check dated 31 July 1992 amounting to Two Hundred Thousand
provisions of law affecting the prestation.
Pesos (P200,000.00). This being the case, Sps. Lam are still liable to
Kodak in the amount of One Million Five Hundred Twenty Six
Applying the foregoing factors to this case, We found that the Thousand Pesos (P1,526,000.00), which is payable in several
intention of the parties is to be bound separately for each Minilab monthly amortization, pursuant to the Letter Agreement. However,
Equipment to be delivered as shown by the separate purchase price Sps. Lam admitted that sometime in May 1992, they had already
for each of the item, by the acceptance of Sps. Lam of separate ordered their drawee bank to stop the payment on all the other
deliveries for the first Minilab Equipment and for those of the checks they had issued to Kodak as payment for the Minilab
remaining two and the separate payment arrangements for each of Equipment delivered to them. Clearly then, Kodak ha[d] the right to
the equipment. Under this premise, Sps. Lam shall be liable for the repossess the said equipment, through this replevin suit. Sps. Lam
entire amount of the purchase price of the Minilab cannot excuse themselves from paying in full the purchase price of
the equipment delivered to them on account of Kodak’s breach of the
Equipment delivered considering that Kodak had already completely contract to deliver the other two (2) Minilab Equipment, as
fulfilled its obligation to deliver the same. . . . contemplated in the Letter Agreement.49(Emphasis supplied)

Third, it is also evident that the contract is one that is severable in Echoing the ruling of the trial court, the Court of Appeals held that
character as demonstrated by the separate purchase price for each the liability of the Lam Spouses to pay the remaining balance for the
of the minilab equipment.  "If the part to be performed by one party first delivered unit is based on the second sentence of Article 1592 of
consists in several distinct and separate items and the price is the New Civil Code.50 The Lam Spouses’ receipt and use of the
apportioned to each of them, the contract will generally be held to be Minilab Equipment before they knew that Kodak Philippines, Ltd.
severable. In such case, each distinct stipulation relating to a would not deliver the two (2) remaining units has made them liable
separate subject matter will be treated as a separate for the unpaid portion of the purchase price.51
contract." Considering this, Kodak's breach of its obligation to deliver

28
The Court of Appeals noted that Kodak Philippines, Ltd. sought the lastly, the payment of P300,000.00, as compromise agreement for
rescission of its contract with the Lam Spouses in the letter dated the pre-termination of the contract of lease with Ruales. 60
October 14, 1992.52 The rescission was based on Article 1191 of the
New Civil Code, which provides: "The power to rescind obligations is The total amount is ₱440,000.00. The Court of Appeals found that all
implied in reciprocal ones, in case one of the obligors should not other claims made by the Lam Spouses were not supported by
comply with what is incumbent upon him."53 In its letter, Kodak evidence, either through official receipts or check payments. 61
Philippines, Ltd. demanded that the Lam Spouses surrender the lone
delivered unit of Minilab Equipment along with its standard As regards the generator set improperly seized from Kodak
accessories.54 Philippines, Ltd. on the basis of the writ of replevin, the Court of
Appeals found that there was no basis for the Lam Spouses’ claim
The Court of Appeals likewise noted that the Lam Spouses for reasonable rental of ₱5,000.00. It held that the trial court’s award
rescinded the contract through its letter dated November 18, 1992 on of 12% interest, in addition to the cost of the generator set in the
account of Kodak Philippines, Inc.’s breach of the parties’ agreement amount of ₱130,000.00, is sufficient compensation for whatever
to deliver the two (2) remaining units.55 damage the Lam Spouses suffered on account of its improper
seizure.62
As a result of this rescission under Article 1191, the Court of Appeals
ruled that "both parties must be restored to their original situation, as The Court of Appeals also ruled on the Lam Spouses’ entitlement to
far as practicable, as if the contract was never entered into." 56 The moral and exemplary damages, as well as attorney’s fees and
Court of Appeals ratiocinated that Article 1191 had the effect of litigation expenses:
extinguishing the obligatory relation as if one was never created: 57
In seeking recovery of the Minilab Equipment, Kodak cannot be
To rescind is to declare a contract void in its inception and to put an considered to have manifested bad faith and malevolence because
end to it as though it never were. It is not merely to terminate it and as earlier ruled upon, it was well within its right to do the same.
to release parties from further obligations to each other but abrogate However, with respect to the seizure of the generator set, where
it from the beginning and restore parties to relative positions which Kodak misrepresented to the court a quo  its alleged right over the
they would have occupied had no contract been made. 58 said item, Kodak’s bad faith and abuse of judicial processes become
self-evident. Considering the off-setting circumstances attendant, the
The Lam Spouses were ordered to relinquish possession of the amount of P25,000.00 by way of moral damages is considered
Minilab Equipment unit and its standard accessories, while Kodak sufficient.
Philippines, Ltd. was ordered to return the amount of ₱270,000.00,
tendered by the Lam Spouses as partial payment.59 In addition, so as to serve as an example to the public that an
application for replevin should not be accompanied by any false
As to the actual damages sought by the parties, the Court of Appeals claims and misrepresentation, the amount of P50,000.00 by way of
found that the Lam Spouses were able to substantiate the following: exemplary damages should be pegged against Kodak.

Incentive fee paid to Mr. Ruales in the amount of P100,000.00; the With respect to the attorney’s fees and litigation expenses, We find
rider to the contract of lease which made the Sps. Lam liable, by way that there is no basis to award Sps. Lam the amount sought for. 63
of advance payment, in the amount of P40,000.00, the same being
intended for the repair of the flooring of the leased premises; and

29
Kodak Philippines, Ltd. moved for reconsideration of the Court of a. P270,000.00 representing the partial payment made on
Appeals Decision, but it was denied for lack of merit.64 However, the the Minilab equipment.
Court of Appeals noted that the Lam Spouses’ Opposition correctly
pointed out that the additional award of ₱270,000.00 made by the b. P130,000.00 representing the amount of the generator
trial court was not mentioned in the decretal portion of the March 30, set, plus legal interest at 12% per annum from December
2005 Decision: 1992 until fully paid;

Going over the Decision, specifically page 12 thereof, the Court c. P440,000.00 as actual damages;
noted that, in addition to the amount of Two Hundred Seventy
Thousand (P270,000.00) which plaintiff-appellant should return to d. P25,000.00 as moral damages; and
the defendantsappellants, the Court also ruled that defendants-
appellants should, in turn, relinquish possession of the Minilab
Equipment and the standard accessories to plaintiff-appellant. e. P50,000.00 as exemplary damages.
Inadvertently, these material items were not mentioned in the
decretal portion of the Decision. Hence, the proper correction should Upon the other hand, defendants-appellants are hereby ordered to
herein be made.65 return to plaintiff-appellant the Minilab equipment and the standard
accessories delivered by plaintiff-appellant.
The Lam Spouses filed this Petition for Review on April 14, 2005. On
the other hand, Kodak Philippines, Ltd. filed its Motion for SO ORDERED."
Reconsideration66 before the Court of Appeals on April 22, 2005.
SO ORDERED.68 (Emphasis in the original)
While the Petition for Review on Certiorari filed by the Lam Spouses
was pending before this court, the Court of Appeals Special Upon receiving the Amended Decision of the Court of Appeals,
Fourteenth Division, acting on Kodak Philippines, Ltd.’s Motion for Kodak Philippines, Ltd. filed a Motion for Extension of Time to File an
Reconsideration, issued the Amended Decision67 dated September Appeal by Certiorari under Rule 45 of the 1997 Rules of Civil
9, 2005. The dispositive portion of the Decision reads: Procedure before this court.69

WHEREFORE, premises considered, this Court resolved that: This was docketed as G.R. No. 169639. In the Motion for
Consolidation dated November 2, 2005, the Lam Spouses moved
A. Plaintiff-appellant’s Motion for Reconsideration is that G.R. No. 167615 and G.R. No. 169639 be consolidated since
hereby DENIED for lack of merit. both involved the same parties, issues, transactions, and essential
facts and circumstances.70
B. The decretal portion of the 30 March 2005 Decision
should now read as follows: In the Resolution dated November 16, 2005, this court noted the
Lam Spouses’ September 23 and September 30, 2005
"WHEREFORE, PREMISES CONSIDERED, the Assailed Decision Manifestations praying that the Court of Appeals’ September 9, 2005
dated 26 February 1999 of the Regional Trial Court, Branch 65 in Amended Decision be considered in the resolution of the Petition for
Civil Cases No. 92-3442 is hereby MODIFIED. Plaintiff-appellant is Review on Certiorari.71 It also granted the Lam Spouses’ Motion for
ordered to pay the following: Consolidation.72

30
In the Resolution73 dated September 20, 2006, this court to respondent were intended to be applied to the whole package of
deconsolidated G.R No. 167615 from G.R. No. 169639 and declared three units.80 The postdated checks were also intended as initial
G.R. No. 169639 closed and terminated since Kodak Philippines, payment for the whole package.81 The separate purchase price for
Ltd. failed to file its Petition for Review. each item was merely intended to particularize the unit prices, not to
negate the indivisible nature of their transaction.82 As to the issue of
II delivery, petitioners claim that their acceptance of separate deliveries
of the units was solely due to the constraints faced by respondent,
who had sole control over delivery matters.83
We resolve the following issues:

With the obligation being indivisible, petitioners argue that


First, whether the contract between petitioners Spouses Alexander
respondent’s failure to comply with its obligation to deliver the two (2)
and Julie Lam and respondent Kodak Philippines, Ltd. pertained to
remaining Minilab Equipment units amounted to a breach. Petitioners
obligations that are severable, divisible, and susceptible of partial
claim that the breach entitled them to the remedy of rescission and
performance under Article 1225 of the New Civil Code; and
damages under Article 1191 of the New Civil Code.84
Second, upon rescission of the contract, what the parties are entitled
Petitioners also argue that they are entitled to moral damages more
to under Article 1190 and Article 1522 of the New Civil Code.
than the ₱50,000.00 awarded by the Court of Appeals since
respondent’s wrongful act of accusing them of non-payment of their
Petitioners argue that the Letter Agreement it executed with obligations caused them sleepless nights, mental anguish, and
respondent for three (3) Minilab Equipment units was not severable, wounded feelings.85 They further claim that, to serve as an example
divisible, and susceptible of partial performance. Respondent’s for the public good, they are entitled to exemplary damages as
recovery of the delivered unit was unjustified.74 respondent, in making false allegations, acted in evident bad faith
and in a wanton, oppressive, capricious, and malevolent manner. 86
Petitioners assert that the obligations of the parties were not
susceptible of partial performance since the Letter Agreement was Petitioners also assert that they are entitled to attorney’s fees and
for a package deal consisting of three (3) units.75 For the delivery of litigation expenses under Article 2208 of the New Civil Code since
these units, petitioners were obliged to pay 48 monthly payments, respondent’s act of bringing a suit against them was baseless and
the total of which constituted one debt.76 Having relied on malicious. This prompted them to engage the services of a lawyer. 87
respondent’s assurance that the three units would be delivered at the
same time, petitioners simultaneously rented and renovated three
Respondent argues that the parties’ Letter Agreement contained
stores in anticipation of simultaneous operations.77 Petitioners argue
divisible obligations susceptible of partial performance as defined by
that the divisibility of the object does not necessarily determine the
Article 1225 of the New Civil Code.88 In respondent’s view, it was the
divisibility of the obligation since the latter is tested against its
intention of the parties to be bound separately for each individually
susceptibility to a partial performance.78 They argue that even if the
priced Minilab Equipment unit to be delivered to different outlets: 89
object is susceptible of separate deliveries, the transaction is
indivisible if the parties intended the realization of all parts of the
agreed obligation.79 The three (3) Minilab Equipment are intended by petitioners LAM for
install[a]tion at their Tagum, Davao del Norte, Sta. Cruz, Manila and
Cotabato City outlets. Each of these units [is] independent from one
Petitioners support the claim that it was the parties’ intention to have
another, as many of them may perform its own job without the other.
an indivisible agreement by asserting that the payments they made

31
Clearly the objective or purpose of the prestation, the obligation is This confirms our verbal agreement for Kodak Phils., Ltd. to provide
divisible. Colorkwik Laboratories, Inc. with three (3) units Kodak Minilab
System 22XL . . . for your proposed outlets in Rizal Avenue (Manila),
The nature of each unit of the three (3) Minilab Equipment is such Tagum (Davao del Norte), and your existing Multicolor photo counter
that one can perform its own functions, without awaiting for the other in Cotabato City under the following terms and conditions:
units to perform and complete its job. So much so, the nature of the
object of the Letter Agreement is susceptible of partial performance, 1. Said Minilab Equipment packages will avail a total of 19%
thus the obligation is divisible.90 multiple order discount based on prevailing equipment price
provided said equipment packages will be purchased not
With the contract being severable in character, respondent argues later than June 30, 1992.
that it performed its obligation when it delivered one unit of the
Minilab Equipment.91 Since each unit could perform on its own, there 2. 19% Multiple Order Discount shall be applied in the form
was no need to await the delivery of the other units to complete its of merchandise and delivered in advance immediately after
job.92 Respondent then is of the view that when petitioners ordered signing of the contract.
the depository bank to stop payment of the issued checks covering
the first delivered unit, they violated their obligations under the Letter * Also includes start-up packages worth P61,000.00.
Agreement since respondent was already entitled to full payment. 93
3. NO DOWNPAYMENT.
Respondent also argues that petitioners benefited from the use of
the Minilab Equipment for 10 months—from March to December 4. Minilab Equipment Package shall be payable in 48
1992— despite having paid only two (2) monthly monthly installments at THIRTY FIVE THOUSAND PESOS
installments.94 Respondent avers that the two monthly installments (P35,000.00) inclusive of 24% interest rate for the first 12
amounting to ₱70,000.00 should be the subject of an offset against months; the balance shall be re-amortized for the remaining
the amount the Court of Appeals awarded to petitioners. 95 36 months and the prevailing interest shall be applied.

Respondent further avers that petitioners have no basis for claiming 5. Prevailing price of Kodak Minilab System 22XL as of
damages since the seizure and recovery of the Minilab Equipment January 8, 1992 is at ONE MILLION SEVEN HUNDRED
was not in bad faith and respondent was well within its right. 96 NINETY SIX THOUSAND PESOS.

III 6. Price is subject to change without prior notice.

The Letter Agreement contained an indivisible obligation. *Secured with PDCs; 1st monthly amortization due 45 days
after installation[.]98
Both parties rely on the Letter Agreement97 as basis of their
respective obligations. Written by respondent’s Jeffrey T. Go and Based on the foregoing, the intention of the parties is for there to be
Antonio V. Mines and addressed to petitioner Alexander Lam, the a single transaction covering all three (3) units of the Minilab
Letter Agreement contemplated a "package deal" involving three (3) Equipment. Respondent’s obligation was to deliver all products
units of the Kodak Minilab System 22XL, with the following terms and
conditions:

32
purchased under a "package," and, in turn, petitioners’ obligation However, even though the object or service may be physically
was to pay for the total purchase price, payable in installments. divisible, an obligation is indivisible if so provided by law or intended
by the parties.  (Emphasis supplied)
The intention of the parties to bind themselves to an indivisible
obligation can be further discerned through their direct acts in In Nazareno v. Court of Appeals,101 the indivisibility of an obligation is
relation to the package deal. There was only one agreement tested against whether it can be the subject of partial performance:
covering all three (3) units of the Minilab Equipment and their
accessories. The Letter Agreement specified only one purpose for An obligation is indivisible when it cannot be validly performed in
the buyer, which was to obtain these units for three different outlets. parts, whatever may be the nature of the thing which is the object
If the intention of the parties were to have a divisible contract, then thereof. The indivisibility refers to the prestation and not to the object
separate agreements could have been made for each Minilab thereof.  In the present case, the Deed of Sale of January 29, 1970
Equipment unit instead of covering all three in one package deal. supposedly conveyed the six lots to Natividad. The obligation is
Furthermore, the 19% multiple order discount as contained in the clearly indivisible because the performance of the contract cannot be
Letter Agreement was applied to all three acquired units. 99 The "no done in parts, otherwise the value of what is transferred is
downpayment" term contained in the Letter Agreement was also diminished. Petitioners are therefore mistaken in basing the
applicable to all the Minilab Equipment units. Lastly, the fourth clause indivisibility of a contract on the number of obligors. 102 (Emphasis
of the Letter Agreement clearly referred to the object of the contract supplied, citation omitted)
as "Minilab Equipment Package."
There is no indication in the Letter Agreement that the units
In ruling that the contract between the parties intended to cover petitioners ordered were covered by three (3) separate transactions.
divisible obligations, the Court of Appeals highlighted: (a) the The factors considered by the Court of Appeals are mere incidents of
separate purchase price of each item; (b) petitioners’ acceptance of the execution of the obligation, which is to deliver three units of the
separate deliveries of the units; and (c) the separate payment Minilab Equipment on the part of respondent and payment for all
arrangements for each unit.100 However, through the specified terms three on the part of petitioners. The intention to create an indivisible
and conditions, the tenor of the Letter Agreement indicated an contract is apparent from the benefits that the Letter Agreement
intention for a single transaction. This intent must prevail even afforded to both parties. Petitioners were given the 19% discount on
though the articles involved are physically separable and capable of account of a multiple order, with the discount being equally
being paid for and delivered individually, consistent with the New applicable to all units that they sought to acquire. The provision on
Civil Code: "no downpayment" was also applicable to all units. Respondent, in
turn, was entitled to payment of all three Minilab Equipment units,
Article 1225. For the purposes of the preceding articles, obligations payable by installments.
to give definite things and those which are not susceptible of partial
performance shall be deemed to be indivisible. IV

When the obligation has for its object the execution of a certain With both parties opting for rescission of the contract under Article
number of days of work, the accomplishment of work by metrical 1191, the Court of Appeals correctly ordered for restitution.
units, or analogous things which by their nature are susceptible of
partial performance, it shall be divisible. The contract between the parties is one of sale, where one party
obligates himself or herself to transfer the ownership and deliver a

33
determinate thing, while the other pays a certain price in money or its the beginning and restore the parties to their relative positions as if
equivalent.103 A contract of sale is perfected upon the meeting of no contract has been made.109 (Emphasis supplied, citations omitted)
minds as to the object and the price, and the parties may reciprocally
demand the performance of their respective obligations from that The Court of Appeals correctly ruled that both parties must be
point on.104 restored to their original situation as far as practicable, as if the
contract was never entered into. Petitioners must relinquish
The Court of Appeals correctly noted that respondent had rescinded possession of the delivered Minilab Equipment unit and accessories,
the parties’ Letter Agreement through the letter dated October 14, while respondent must return the amount tendered by petitioners as
1992.105 It likewise noted petitioners’ rescission through the letter partial payment for the unit received. Further, respondent cannot
dated November 18, 1992.106This rescission from both parties is claim that the two (2) monthly installments should be offset against
founded on Article 1191 of the New Civil Code: the amount awarded by the Court of Appeals to petitioners because
the effect of rescission under Article 1191 is to bring the parties back
The power to rescind obligations is implied in reciprocal ones, in to their original positions before the contract was entered into. Also
case one of the obligors should not comply with what is incumbent in Velarde:
upon him.
As discussed earlier, the breach committed by petitioners was the
The injured party may choose between the fulfilment and the nonperformance of a reciprocal obligation, not a violation of the
rescission of the obligation, with the payment of damages in either terms and conditions of the mortgage contract. Therefore, the
case. He may also seek rescission, even after he has chosen automatic rescission and forfeiture of payment clauses stipulated in
fulfilment, if the latter should become impossible. the contract does not apply. Instead, Civil Code provisions shall
govern and regulate the resolution of this controversy.
The court shall decree the rescission claimed, unless there be just
cause authorizing the fixing of a period. Considering that the rescission of the contract is based on Article
1191 of the Civil Code, mutual restitution is required to bring back
the parties to their original situation prior to the inception of the
Rescission under Article 1191 has the effect of mutual
contract. Accordingly, the initial payment of ₱800,000 and the
restitution.107 In Velarde v. Court of Appeals:108
corresponding mortgage payments in the amounts of ₱27,225,
₱23,000 and ₱23,925 (totaling ₱874,150.00) advanced by
Rescission abrogates the contract from its inception and requires a petitioners should be returned by private respondents, lest the latter
mutual restitution of benefits received. unjustly enrich themselves at the expense of the
former.110 (Emphasis supplied)
....
When rescission is sought under Article 1191 of the Civil Code, it
Rescission creates the obligation to return the object of the contract. need not be judicially invoked because the power to resolve is
It can be carried out only when the one who demands rescission can implied in reciprocal obligations.111 The right to resolve allows an
return whatever he may be obliged to restore. To rescind is to injured party to minimize the damages he or she may suffer on
declare a contract void at its inception and to put an end to it as account of the other party’s failure to perform what is incumbent
though it never was. It is not merely to terminate it and release the upon him or her.112 When a party fails to comply with his or her
parties from further obligations to each other, but to abrogate it from obligation, the other party’s right to resolve the contract is

34
triggered.113 The resolution immediately produces legal effects if the analysis, the question of whether the said award is fully supported by
non-performing party does not question the resolution. 114 Court evidence is a factual question as it would necessitate whether the
intervention only becomes necessary when the party who allegedly evidence adduced in support of the same has any probative value.
failed to comply with his or her obligation disputes the resolution of For a question to be one of law, it must involve no examination of the
the contract.115 Since both parties in this case have exercised their probative value of the evidence presented by the litigants or any of
right to resolve under Article 1191, there is no need for a judicial them.120 (Emphasis supplied, citations omitted)
decree before the resolution produces effects.
The damages awarded by the Court of Appeals were supported by
V documentary evidence.121 Petitioners failed to show any reason why
the factual determination of the Court of Appeals must be reviewed,
The issue of damages is a factual one. A petition for review on especially in light of their failure to produce receipts or check
certiorari under Rule 45 shall only pertain to questions of law. 116 It is payments to support their other claim for actual damages. 122
not the duty of this court to re-evaluate the evidence adduced before
the lower courts.117Furthermore, unless the petition clearly shows Furthermore, the actual damages amounting to ₱2,040,000.00 being
that there is grave abuse of discretion, the findings of fact of the trial sought by petitioners123 must be tempered on account of their own
court as affirmed by the Court of Appeals are conclusive upon this failure to pay the rest of the installments for the delivered unit. This
court.118 In Lorzano v. Tabayag, Jr.:119 failure on their part is a breach of their obligation, for which the
liability of respondent, for its failure to deliver the remaining units,
For a question to be one of law, the same must not involve an shall be equitably tempered on account of Article 1192 of the New
examination of the probative value of the evidence presented by the Civil Code.124 In Central Bank of the Philippines v. Court of
litigants or any of them. The resolution of the issue must rest solely Appeals:125
on what the law provides on the given set of circumstances. Once it
is clear that the issue invites a review of the evidence presented, the Since both parties were in default in the performance of their
question posed is one of fact. respective reciprocal obligations, that is, Island Savings Bank failed
to comply with its obligation to furnish the entire loan and Sulpicio M.
.... Tolentino failed to comply with his obligation to pay his ₱17,000.00
debt within 3 years as stipulated, they are both liable for damages.
For the same reason, we would ordinarily disregard the petitioner’s
allegation as to the propriety of the award of moral damages and Article 1192 of the Civil Code provides that in case both parties have
attorney’s fees in favor of the respondent as it is a question of fact. committed a breach of their reciprocal obligations, the liability of the
Thus, questions on whether or not there was a preponderance of first infractor shall be equitably tempered by the courts. WE rule that
evidence to justify the award of damages or whether or not there the liability of Island Savings Bank for damages in not furnishing the
was a causal connection between the given set of facts and the entire loan is offset by the liability of Sulpicio M. Tolentino for
damage suffered by the private complainant or whether or not the damages, in the form of penalties and surcharges, for not paying his
act from which civil liability might arise exists are questions of fact. overdue ₱17,000.00 debt. The liability of Sulpicio M. Tolentino for
interest on his ₱17,000.00 debt shall not be included in offsetting the
liabilities of both parties. Since Sulpicio M. Tolentino derived some
Essentially, the petitioner is questioning the award of moral damages
benefit for his use of the ₱17,000.00, it is just that he should account
and attorney’s fees in favor of the respondent as the same is
for the interest thereon.126 (Emphasis supplied)
supposedly not fully supported by evidence. However, in the final

35
The award for moral and exemplary damages also appears to be (b) P130,000.00, representing the amount of the generator
sufficient. Moral damages are granted to alleviate the moral suffering set, plus legal interest at 12% .per annum from December
suffered by a party due to an act of another, but it is not intended to 1992 until fully paid;
enrich the victim at the defendant’s expense.127 It is not meant to
punish the culpable party and, therefore, must always be reasonable (c) P440,000.00 as actual damages;
vis-a-vis the injury caused.128 Exemplary damages, on the other
hand, are awarded when the injurious act is attended by bad (d) P25,000.00 as moral damages;
faith.129 In this case, respondent was found to have misrepresented
its right over the generator set that was seized. As such, it is properly
liable for exemplary damages as an example to the public. 130 (e) P50,000.00 as exemplary damages; and

However, the dispositive portion of the Court of Appeals Amended (f) P20,000.00 as attorney's fees.
Decision dated September 9, 2005 must be modified to include the
recovery of attorney’s fees and costs of suit in favor of petitioners. Petitioners are ordered to return the Kodak Minilab System 22XL unit
In Sunbanun v. Go:131 and its standard accessories to respondent.

Furthermore, we affirm the award of exemplary damages and SO ORDERED.


attorney’s fees. Exemplary damages may be awarded when a
wrongful act is accompanied by bad faith or when the defendant MARVIC M.V.F. LEONEN
acted in a wanton, fraudulent, reckless, oppressive, or malevolent Associate Justice
manner which would justify an award of exemplary damages under
Article 2232 of the Civil Code. Since the award of exemplary Republic of the Philippines
damages is proper in this case, attorney’s fees and cost of the suit SUPREME COURT
may also be recovered as provided under Article 2208 of the Civil Manila
Code.132 (Emphasis supplied, citation omitted)
EN BANC
Based on the amount awarded for moral and exemplary damages, it
is reasonable to award petitioners ₱20,000.00 as attorney’s fees.
G.R. No. L-28497             November 6, 1928
WHEREFORE, the Petition is DENIED. The Amended Decision
THE BACHRACH MOTOR CO., INC., plaintiff-appellee, 
dated September 9, 2005 is AFFIRMED with
vs.
MODIFICATION. Respondent Kodak Philippines, Ltd. is ordered to
FAUSTINO ESPIRITU, defendant-appellant.
pay petitioners Alexander and Julie Lam:

------------------------------
(a) P270,000.00, representing the partial payment made on
the Minilab Equipment;
G.R. No. L-28498             November 6, 1928

36
THE BACHRACH MOTOR CO., INC., plaintiff-appellee,  In both sales it was agreed that 12 per cent interest would be paid
vs. upon the unpaid portion of the price at the executon of the contracts,
FAUSTINO ESPIRITU, defendant-appellant, and  and in case of non-payment of the total debt upon its maturity, 25 per
ROSARIO ESPIRITU, intervenor-appellant. cent thereon, as penalty.

Ernesto Zaragoza and Simeon Ramos for defendant-appellant.  In addition to the mortagage deeds referred to, which the defendant
Benito Soliven and Jose Varela Calderon for intervenor-appellant.  executed in favor of the plaintiff, the defendant at the same time also
B. Francisco for appellee. signed a promissory note solidarily with his brother Rosario Espiritu
for the several sums secured by the two mortgages (Exhibits B and
D).

Rosario Espiritu appeared in these two cases as intervenor, alleging


AVANCEÑA, C. J.: to be the exclusive owner of the two White trucks Nos. 77197 and
92744, which appear to have been mortgaged by the defendants to
the plaintiff. lawphi1.net
These two cases, Nos. 28497 and 28948, were tried together.
While these two cases were pending in the lower court the
It appears, in connection with case 28497; that on July 28, 1925 the mortgaged trucks were sold by virtue of the mortgage, all of them
defendant Faustino Espiritu purchased of the plaintiff corporation a together bringing in, after deducting the sheriff's fees and
two-ton White truck for P11,983.50, paying P1,000 down to apply on transportation charges to Manila, the net sum of P3,269.58.
account of this price, and obligating himself to pay the remaining
P10,983.50 within the periods agreed upon. To secure the payment
of this sum, the defendants mortgaged the said truck purchased and, The judgment appealed from ordered the defendants and the
besides, three others, two of which are numbered 77197 and 92744 intervenor to pay plaintiff in case 28497 the sum of P7,732.09 with
respectively, and all of the White make (Exhibit A). These two trucks interest at the rate of 12 per cent per annum from May 1, 1926 until
had been purchased from the same plaintiff and were fully paid for fully paid, and 25 per cent thereof in addition as penalty. In case
by the defendant and his brother Rosario Espiritu. The defendant 28498, the trial court ordered the defendant and the intervenor to pay
failed to pay P10,477.82 of the price secured by this mortgage. plaintiff the sum of P4,208.28 with interest at 12 per cent per annum
from December 1, 1925 until fully paid, and 25 per cent thereon as
penalty.
In connection with case 28498, it appears that on February 18, 1925
the defendant bought a one-ton White truck of the plaintiff
corporation for the sum of P7,136.50, and after having deducted the The appellants contend that trucks 77197 and 92744 were not
P500 cash payment and the 12 per cent annual interest on the mortgaged, because, when the defendant signed the mortgage
unpaid principal, obligated himself to make payment of this sum deeds these trucks were not included in those documents, and were
within the periods agreed upon. To secure this payment the only put in later, without defendant's knowledge. But there is positive
defendant mortgaged to the plaintiff corporation the said truck proof that they were included at the time the defendant signed these
purchased and two others, numbered 77197 and 92744, documents. Besides, there were presented two of defendant's letters
respectively, the same that were mortgaged in the purchase of the to Hidalgo, an employee of the plaintiff's written a few days before
other truck referred to in the other case. The defendant failed to pay the transaction, acquiescing in the inclusion of all his White trucks
P4,208.28 of this sum. already paid for, in the mortgage (Exhibit H-I).

37
Appellants also alleged that on February 4, 1925, the defendant sold include the interest, and which may be demamded separetely.
his rights in said trucks Nos. 77197 and 92744 to the intervenor, and According to this, the penalty is not to be added to the interest for the
that as the latter did not sign the mortgage deeds, such trucks determination of whether the interest exceeds the rate fixed by the
cannot be considered as mortgaged. But the evidence shows that law, since said rate was fixed only for the interest. But considering
while the intervenor Rosario Espiritu did not sign the two mortgage that the obligation was partly performed, and making use of the
deeds (Exhibits A and C), yet, together with the defendants Faustino power given to the court by article 1154 of the Civil Code, this
Espiritu, he signed the two promissory notes (Exhibits B and D) penalty is reduced to 10 per cent of the unpaid debt.
secured by these two mortgages. All these instruments were
executed at the same time, and when the trucks 77197 and 92744 With the sole modification that instead of 25 per cent upon the sum
were included in the mortgages, the intervenor Rosario Espiritu was owed, the defendants need pay only 10 per cent thereon as penalty,
aware of it and consented to such inclusion. These facts are the judgment appealed from is affired in all other respects without
supported by the testimony of Bachrach, manager of the plaintiff special pronouncement as to costs. So ordered.
corporation, of Agustin Ramirez, who witnessed the execution of all
these documents, and of Angel Hidalgo, who witnessed the Malcolm, Villamor, Ostrand, Romualdez and Villa-Real, JJ., concur.
execution of Exhibits B and D.
epublic of the Philippines
We do not find the statement of the intervenor Rosario Espiritu that SUPREME COURT
he did not sign promissory notes Exhibits B and C to be sufficient to Manila
overthrow this evidence. A comparison of his genuine signature on
Exhibit AA with those appearing on promissory notes B and C,
convinces us that the latter are his signatures. And such is our FIRST DIVISION
conclusion, notwithstanding the evidence presented to establish that
on the date when Exhibits B appears to have been signed, that is G.R. No. L-41093 October 30, 1978
July 25, 1925, the intervenor was in Batac, Ilocos Norte, many miles
away from Manila. And the fact that on the 24th of said month of ROBES-FRANCISCO REALTY & DEVELOPMENT
July, the plaintiff sent some truck accessory parts by rail to Ilocos for CORPORATION, petitioner, 
the intervenor does not necessarily prove that the latter could not vs.
have been in Manila on the 25th of that month. COURT OF FIRST INSTANCE OF RIZAL (BRANCH XXXIV), and
LOLITA MILLAN, respondents.
In view of his conclusion that the intervenor signed the promissory
notes secured by trucks 77197 and 92744 and consented to the Purugganan & Bersamin for petitioner.
mortgage of the same, it is immaterial whether he was or was not the
exclusive owner thereof. Salvador N. Beltran for respondent.

It is finally contended that the 25 per cent penalty upon the debt, in
addition to the interest of 12 per cent per annum, makes the contract
usurious. Such a contention is not well founded. Article 1152 of the
MUÑOZ PALMA, J.:
Civil Code permits the agreement upon a penalty apart from the
interest. Should there be such an agreemnet, the penalty, as was
held in the case of Lopez vs. Hernaez (32 Phil., 631), does not

38
This is a direct appeal on questions of law from a decision of the 276 square meters, situated in Barrio Camarin, Caloocan City,
Court of First Instance of Rizal, Branch XXXIV, presided by the known as Lot No. 20, Block No. 11 of its Franville Subdivision. 2
Honorable Bernardo P. Pardo, the dispositive portion of which reads:
Millan complied with her obligation under the contract and paid the
WHEREFORE, judgment is hereby rendered installments stipulated therein, the final payment having been made
commanding the defendant to register the deed of on December 22, 1971. The vendee made a total payment of
absolute sale it had executed in favor of plaintiff with P5,193.63 including interests and expenses for registration of title. 3
the Register of Deeds of Caloocan City and secure
the corresponding title in the name of plaintiff within Thereafter, Lolita Millan made repeated demands upon the
ten (10) days after finality of this decision; if, for any corporation for the execution of the final deed of sale and the
reason, this not possible, defendant is hereby issuance to her of the transfer certificate of title over the lot. On
sentenced to pay plaintiff the sum of P5,193.63 with March 2, 1973, the parties executed a deed of absolute sale of the
interest at 4% per annum from June 22, 1972 until aforementioned parcel of land. The deed of absolute sale contained,
fully paid. among others, this particular provision:

In either case, defendant is sentenced to pay plaintiff That the VENDOR further warrants that the transfer
nominal damages in the amount of P20,000.00 plus certificate of title of the above-described parcel of
attorney's fee in the amount of P5,000.00 and costs. land shall be transferred in the name of the VENDEE
within the period of six (6) months from the date of
SO ORDERED. full payment and in case the VENDOR fails to issue
said transfer certificate of title, it shall bear the
Caloocan City, February 11, 1975. (rollo, p. 21) obligation to refund to the VENDEE the total amount
already paid for, plus an interest at the rate of 4%
per annum. (record on appeal, p. 9)
Petitioner corporation questions the award for nominal damages of
P20,000.00 and attorney's fee of P5,000.00 which are allegedly
excessive and unjustified. Notwithstanding the lapse of the above-mentioned stipulated period
of six (6) months, the corporation failed to cause the issuance of the
corresponding transfer certificate of title over the lot sold to Millan,
In the Court's resolution of October 20, 1975, We gave due course to
hence, the latter filed on August 14, 1974 a complaint for specific
the Petition only as regards the portion of the decision awarding
performance and damages against Robes-Francisco Realty &
nominal damages. 1
Development Corporation in the Court of First Instance of Rizal,
Branch XXXIV, Caloocan City, docketed therein as Civil Case No. C-
The following incidents are not in dispute: 3268. 4

In May 1962 Robes-Francisco Realty & Development Corporation, The complaint prayed for judgment (1) ordering the reformation of
now petitioner, agreed to sell to private respondent Lolita Millan for the deed of absolute sale; (2) ordering the defendant to deliver to
and in consideration of the sum of P3,864.00, payable in plaintiff the certificate of title over the lot free from any lien or
installments, a parcel of land containing an area of approximately encumbrance; or, should this be not possible, to pay plaintiff the
value of the lot which should not be less than P27,600.00 (allegedly

39
the present estimated value of the lot); and (3) ordering the certificate of title within six months from the date of full payment, it
defendant to pay plaintiff damages, corrective and actual in the sum shall refund to the vendee the total amount paid for with interest at
of P15 000.00. 5 the rate of 4% per annum, hence, the vendee is bound by the terms
of the provision and cannot recover more than what is agreed upon.
The corporation in its answer prayed that the complaint be dismissed Presumably, petitioner in invoking Article 1226 of the Civil Code
alleging that the deed of absolute sale was voluntarily executed which provides that in obligations with a penal clause, the penalty
between the parties and the interest of the plaintiff was amply shall substitute the indemnity for damages and the payment of
protected by the provision in said contract for payment of interest at interests in case of noncompliance, if there is no stipulation to the
4% per annum of the total amount paid, for the delay in the issuance contrary.
of the title. 6
The foregoing argument of petitioner is totally devoid of merit. We
At the pretrial conference the parties agreed to submit the case for would agree with petitioner if the clause in question were to be
decision on the pleadings after defendant further made certain considered as a penal clause. Nevertheless, for very obvious
admissions of facts not contained in its answer. 7 reasons, said clause does not convey any penalty, for even without
it, pursuant to Article 2209 of the Civil Code, the vendee would be
entitled to recover the amount paid by her with legal rate of interest
Finding that the realty corporation failed to cause the issuance of the
which is even more than the 4% provided for in the clause. 7-A
corresponding transfer certificate of title because the parcel of land
conveyed to Millan was included among other properties of the
corporation mortgaged to the GSIS to secure an obligation of P10 It is therefore inconceivable that the aforecited provision in the deed
million and that the owner's duplicate certificate of title of the of sale is a penal clause which will preclude an award of damages to
subdivision was in the possession of the Government Service the vendee Millan. In fact the clause is so worded as to work to the
Insurance System (GSIS), the trial court, on February 11, 1975, advantage of petitioner corporation.
rendered judgment the dispositive portion of which is quoted in
pages 1 and 2 of this Decision. We hold that the trial court did not err Unfortunately, the vendee, now private respondent, submitted her
in awarding nominal damages; however, the circumstances of the case below without presenting evidence on the actual damages
case warrant a reduction of the amount of P20,000.00 granted to suffered by her as a result of the nonperformance of petitioner's
private respondent Millan. obligation under the deed of sale. Nonetheless, the facts show that
the right of the vendee to acquire title to the lot bought by her was
There can be no dispute in this case under the pleadings and the violated by petitioner and this entitles her at the very least to nominal
admitted facts that petitioner corporation was guilty of delay, damages.
amounting to nonperformance of its obligation, in issuing the transfer
certificate of title to vendee Millan who had fully paid up her The pertinent provisions of our Civil Code follow:
installments on the lot bought by her. Article 170 of the Civil Code
expressly provides that those who in the performance of their Art. 2221. Nominal damages are adjudicated in
obligations are guilty of fraud, negligence, or delay, and those who in order that a right of the plaintiff, which has been
any manner contravene the tenor thereof, are liable for damages. violated or invaded by the defendant, may be
vindicated or recognized, and not for the purpose of
Petitioner contends that the deed of absolute sale executed between indemnifying the plaintiff for any loss suffered by
the parties stipulates that should the vendor fail to issue the transfer him.

40
Art. 2222. The court may award nominal damages in Cuenca. The Court there found special reasons for considering
every obligation arising from any source enumerated P20,000.00 as "nominal". Cuenca who was the holder of a first class
in article 1157, or in every case where any property ticket from Manila to Tokyo was rudely compelled by an agent of
right has been invaded. petitioner Airlines to move to the tourist class notwithstanding its
knowledge that Cuenca as Commissioner of Public Highways of the
Under the foregoing provisions nominal damages are not intended Republic of the Philippines was travelling in his official capacity as a
for indemnification of loss suffered but for the vindication or delegate of the country to a conference in Tokyo." 11
recognition of a right violated or invaded. They are recoverable
where some injury has been done the amount of which the evidence Actually, as explained in the Court's decision in Northwest Airlines,
fails to show, the assessment of damages being left to the discretion there is no conflict between that case and Medina, for in the latter,
of the court according to the circumstances of the case. 8 the P10,000.00 award for nominal damages was eliminated
principally because the aggrieved party had already been awarded
It is true as petitioner claims that under American jurisprudence P6,000.00 as compensatory damages, P30,000.00 as moral
nominal damages by their very nature are small sums fixed by the damages and P10,000.00 as exemplary damages, and "nominal
court without regard to the extent of the harm done to the injured damages cannot coexist with compensatory damages," while in the
party. case of Commissioner Cuenca, no such compensatory, moral, or
exemplary damages were granted to the latter. 12
It is generally held that a nominal damage is a
substantial claim, if based upon the violation of a At any rate, the circumstances of a particular case will determine
legal right; in such case, the law presumes a whether or not the amount assessed as nominal damages is within
damage, although actual or compensatory damages the scope or intent of the law, more particularly, Article 2221 of the
are not proven; in truth nominal damages are Civil Code.
damages in name only and not in fact, and are
allowed, not as an equivalent of a wrong inflicted, In the situation now before Us, We are of the view that the  amount of
but simply in recogniton of the existence of a P20,000.00 is excessive. The admitted fact that petitioner
technical injury. (Fouraker v. Kidd Springs Boating corporation failed to convey a transfer certificate of title to
and Fishing Club, 65 S. W. 2d 796-797, citing 17 respondent Millan because the subdivision property was mortgaged
C.J. 720, and a number of authorities).9 to the GSIS does not in itself show that there was bad faith or fraud.
Bad faith is not to be presumed. Moreover, there was the expectation
In this jurisdiction, in Vda. de Medina, et al. v. Cresencia, et al. 1956, of the vendor that arrangements were possible for the GSIS to make
which was an action for damages arising out of a vehicular accident, partial releases of the subdivision lots from the overall real estate
this Court had occasion to eliminate an award of P10,000.00 mortgage. It was simply unfortunate that petitioner did not succeed in
imposed by way of nominal damages, the Court stating inter alia that that regard.
the amount cannot, in common sense, be demeed "nominal". 10
For that reason We cannot agree with respondent Millan Chat the
In a subsequent case, viz: Northwest Airlines, Inc. v. Nicolas L. P20,000.00 award may be considered in the nature of exemplary
Cuenca, 1965, this Court, however, through then Justice Roberto damages.
Concepcion who later became Chief Justice of this Court, sustained
an award of P20,000.00 as nominal damages in favor of respnodent

41
In case of breach of contract, exemplary damages may be awarded G.R. No. L-26339 December 14, 1979
if the guilty party acted in wanton, fraudulent, reckless, oppressive or
malevolent manner. 13 Furthermore, exemplary or corrective MARIANO C. PAMINTUAN, petitioner-appellant, 
damages are to be imposed by way of example or correction for the vs.
public good, only if the injured party has shown that he is entitled to COURT OF APPEALS and YU PING KUN CO., INC., respondent-
recover moral, temperate or compensatory damages." appellees.

Here, respondent Millan did not submit below any evidence to prove V. E. del Rosario & Associates for appellant.
that she suffered actual or compensatory damages. 14
Sangco & Sangalang for private respondent.
To conclude, We hold that the sum of Ten Thousand Pesos
(P10,000.00) by way of nominal damages is fair and just under the
following circumstances, viz: respondent Millan bought the lot from
petitioner in May, 1962, and paid in full her installments on
December 22, 1971, but it was only on March 2, 1973, that a deed of AQUINO, J.:
absolute sale was executed in her favor, and notwithstanding the
lapse of almost three years since she made her last payment, This case is about the recovery compensatory, damages for breach
petitioner still failed to convey the corresponding transfer certificate of a contract of sale in addition to liquidated damages.
of title to Millan who accordingly was compelled to file the instant
complaint in August of 1974. Mariano C. Pamintuan appealed from the judgment of the Court of
Appeals wherein he was ordered to deliver to Yu Ping Kun Co., Inc.
PREMISES CONSIDERED, We modify the decision of the trial court certain plastic sheetings and, if he could not do so, to pay the latter
and reduce the nominal damages to Ten Thousand Pesos P100,559.28 as damages with six percent interest from the date of
(P10,000.00). In all other respects the aforesaid decision stands. the filing of the complaint. The facts and the findings of the Court of
Appeals are as follows:
Without pronouncement as to costs.
In 1960, Pamintuan was the holder of a barter license wherein he
SO ORDERED. was authorized to export to Japan one thousand metric tons of white
flint corn valued at forty-seven thousand United States dollars in
exchange for a collateral importation of plastic sheetings of an
Teehankee (Chairman), Makasiar, Fernandez and Guerrero, JJ., equivalent value.
concur.
By virtue of that license, he entered into an agreement to ship his
Republic of the Philippines corn to Tokyo Menka Kaisha, Ltd. of Osaka, Japan in exchange for
SUPREME COURT plastic sheetings. He contracted to sell the plastic sheetings to Yu
Manila Ping Kun Co., Inc. for two hundred sixty-five thousand five hundred
fifty pesos. The company undertook to open an irrevocable domestic
SECOND DIVISION letter of credit for that amount in favor of Pamintuan.

42
It was further agreed that Pamintuan would deliver the plastic 100 cases. November 15, 1960 — 30 cases out of
sheetings to the company at its bodegas in Manila or suburbs 100 cases.
directly from the piers "within one month upon arrival of" the carrying
vessels. Any violation of the contract of sale would entitle the Pamintuan withheld delivery of (1) 50 cases of plastic sheetings
aggreived party to collect from the offending party liquidated containing 26,000 yards valued at $5,200; (2) 37 cases containing
damages in the sum of ten thousand pesos (Exh. A). 18,440 yards valued at $2,305; (3) 60 cases containing 30,000 yards
valued at $5,400 and (4) 83 cases containing 40,850 yards valued at
On July 28, 1960, the company received a copy of the letter from the $5,236.97. While the plastic sheetings were arriving in Manila,
Manila branch of Toyo Menka Kaisha, Ltd. confirming the Pamintuan informed the president of Yu Ping Kun Co., Inc. that he
acceptance by Japanese suppliers of firm offers for the consignment was in dire need of cash with which to pay his obligations to the
to Pamintuan of plastic sheetings valued at forty-seven thousand Philippine National Bank. Inasmuch as the computation of the prices
dollars. Acting on that information, the company lost no time in of each delivery would allegedly be a long process, Pamintuan
securing in favor of Pamintuan an irrevocable letter of credit for two requested that he be paid immediately.
hundred sixty-five thousand five hundred fifty pesos.
Consequently, Pamintuan and the president of the company, Benito
Pamintuan was apprised by the bank on August 1, 1960 of that letter Y.C. Espiritu, agreed to fix the price of the plastic sheetings at
of credit which made reference to the delivery to Yu Ping Kun Co., P0.782 a yard, regardless of the kind, quality or actual invoice value
Inc. on or before October 31, 1960 of 336, 360 yards of plastic thereof. The parties arrived at that figure by dividing the total price of
sheetings (p. 21, Record on Appeal). P265,550 by 339,440 yards, the aggregate quantity of the
shipments.
On September 27 and 30 and October 4, 1960, the Japanese
suppliers shipped to Pamintuan, through Toyo Menka Kaisha, Ltd., After Pamintuan had delivered 224,150 yards of sheetings of interior
the plastic sheetings in four shipments to wit: (1) Firm Offer No. 327 quality valued at P163,.047.87, he refused to deliver the remainder
for 50,000 yards valued at $9,000; (2) Firm Offer No. 328 for 70,000 of the shipments with a total value of P102,502.13 which were
yards valued at $8,050; (3) Firm Offers Nos. 329 and 343 for covered by (i) Firm Offer No. 330, containing 26,000 yards valued at
175,000 and 18,440 yards valued at $22,445 and $2,305, P29,380; (2) Firm Offer No. 343, containing 18,440 yards valued at
respectively, and (4) Firm Offer No. 330 for 26,000 yards valued at P13,023.25; (3) Firm Offer No. 217, containing 30,000 yards valued
$5,200, or a total of 339,440 yards with an aggregate value of at P30,510 and (4) Firm Offer No. 329 containing 40,850 yards
$47,000 (pp. 4-5 and 239-40, Record on Appeal). valued at P29,588.88 (See pp. 243-2, Record on Appeal).

The plastic sheetings arrived in Manila and were received by As justification for his refusal, Pamintuan said that the company
Pamintuan. Out of the shipments, Pamintuan delivered to the failed to comply with the conditions of the contract and that it was
company's warehouse only the following quantities of plastic novated with respect to the price.
sheetings:
On December 2, 1960, the company filed its amended complaint for
November 11, 1960 — 140 cases, size 48 inches by damages against Pamintuan. After trial, the lower court rendered the
50 yards. November 14, 1960 — 258 cases out of judgment mentioned above but including moral damages.
352 cases. November 15, 1960 — 11 cases out of
352 cases. November 15, 1960 — 10 cases out of

43
The unrealized profits awarded as damages in the trial court's as stipulated liquidated damages, (b) P10,000 as moral damages, (c)
decision were computed as follows (pp. 248-9, Record on Appeal): Pl,102.85 as premium paid by the company on the bond of
P102,502.13 for the issuance of the writ of preliminary attachment
(1) 26,000 yards with a contract price of Pl.13 per and (d) P10,000 as attorney's fees, or total damages of
yard and a selling price at the time of delivery of P110,559.28) p. 250, Record on Appeal). The Court of Appeals
Pl.75 a yard........................................................... affirmed that judgment with the modification that the moral damages
P16,120.00 were disallowed (Resolution of June 29, 1966).

(2) 18,000 yards with a contract price of P0.7062 per Pamintuan appealed. The Court of Appeals in its decision of March
yard and selling price of Pl.20 per yard at the time of 18, 1966 found that the contract of sale between Pamintuan and the
delivery......................................... 9,105.67 company was partly consummated. The company fulfilled its
obligation to obtain the Japanese suppliers' confirmation of their
acceptance of firm offers totalling $47,000. Pamintuan reaped certain
(3) 30,000 yards with a contract price of Pl.017 per
benefits from the contract. Hence, he is estopped to repudiate it;
yard and a selling price of Pl.70 per yard. 20,490.00
otherwise, he would unjustly enrich himself at the expense of the
company.
(4) 40,850 yards with a contract price of P0.7247 per
yard and a selling price of P1.25 a yard at the time of
The Court of Appeals found that the writ of attachment was properly
delivery.............................................. 21,458.50 Tota
issued. It also found that Pamintuan was guilty of fraud because (1)
l unrealized profits....................... P67,174.17
he was able to make the company agree to change the manner of
paying the price by falsely alleging that there was a delay in
The overpayment of P12,282.26 made to Pamintuan by Yu Ping Kun obtaining confirmation of the suppliers' acceptance of the offer to
Co., Inc. for the 224,150 yards, which the trial court regarded as an buy; (2) he caused the plastic sheetings to be deposited in the
item of damages suffered by the company, was computed as follows bonded warehouse of his brother and then required his brother to
(p. 71, Record on Appeal): make him Pamintuan), his attorney-in-fact so that he could control
the disposal of the goods; (3) Pamintuan, as attorney-in-fact of the
Liquidation value of 224,150 yards at P0.7822 a yard warehouseman, endorsed to the customs broker the warehouse
.............................................................................. receipts covering the plastic sheetings withheld by him and (4) he
P175,330.13 overpriced the plastic sheetings which he delivered to the company.

Actual peso value of 224,150 yards as per firm offers The Court of Appeals described Pamintuan as a man "who, after
or as per having succeeded in getting another to accommodate him by
contract............................................163,047.87 agreeing to liquidate his deliveries on the basis of P0.7822 per yard,
irrespective of invoice value, on the pretense that he would deliver
Overpayment.............................................................. what in the first place he ought to deliver anyway, when he knew all
.. P 12,282.26 the while that he had no such intention, and in the process delivered
only the poorer or cheaper kind or those which he had
To these two items of damages (P67,174.17 as unrealized profits predetermined to deliver and did not conceal in his brother's name
and P12,282.26 as overpayment), the trial court added (a) P10,000 and thus deceived the unwary party into overpaying him the sum of
P 1 2,282.26 for the said deliveries, and would thereafter refuse to

44
make any further delivery in flagrant violation of his plighted word, damages and both may be reduced when proper (Arts. 1229, 2216
would now ask us to sanction his actuation" (pp. 61-62, Rollo). and 2227, Civil Code. See observations of Justice J.B.L. Reyes,
cited in 4 Tolentino's Civil Code, p. 251).
The main contention of appellant Pamintuan is that the buyer, Yu
Ping Kun Co., Inc., is entitled to recover only liquidated damages. Castan Tobeñas notes that the penal clause in an obligation has
That contention is based on the stipulation "that any violation of the three functions: "1. Una funcion coercitiva o de garantia, consistente
provisions of this contract (of sale) shall entitle the aggrieved party to en estimular al deudor al complimiento de la obligacion principal,
collect from the offending party liquidated damages in the sum of ante la amenaza de tener que pagar la pena. 2. Una
P10,000 ". funcion liquidadora del daño, o sea la de evaluar por anticipado los
perjuicios que habria de ocasionar al acreedor el incumplimiento o
Pamintuan relies on the rule that a penalty and liquidated damages cumplimiento inadecuado de la obligacion. 3. Una
are the same (Lambert vs. Fox 26 Phil. 588); that "in obligations with funcion estrictamente penal, consistente en sancionar o castigar
a penal clause, the penalty shall substitute the indemnity for dicho incumplimiento o cumplimiento inadecuado, atribuyendole
damages and the payment of interests in case of non-compliance, if consecuencias mas onerosas para el deudor que las que
there is no stipulation to the contrary " (1st sentence of Art. 1226, normalmente lleva aparejadas la infraccion contractual. " (3 Derecho
Civil Code) and, it is argued, there is no such stipulation to the Civil Espanol, 9th Ed., p. 128).
contrary in this case and that "liquidated damages are those agreed
upon by the parties to a contract, to be paid in case of breach The penalty clause is strictly penal or cumulative in character and
thereof" (Art. 2226, Civil Code). does not partake of the nature of liquidated damages (pena
sustitutiva) when the parties agree "que el acreedor podra pedir, en
We hold that appellant's contention cannot be sustained because the el supuesto incumplimiento o mero retardo de la obligacion principal,
second sentence of article 1226 itself provides that I nevertheless, ademas de la pena, los danos y perjuicios. Se habla en este caso
damages shall be paid if the obligor ... is guilty of fraud in the de pena cumulativa, a differencia de aquellos otros ordinarios, en
fulfillment of the obligation". "Responsibility arising from fraud is que la pena es sustitutiva de la reparacion ordinaria." (Ibid, Castan
demandable in all obligations" (Art. 1171, Civil Code). "In case of Tobenas, p. 130).
fraud, bad faith, malice or wanton attitude, the obligor shall be
responsible for an damages which may be reasonably attributed to After a conscientious consideration of the facts of the case, as found
the non-performance of the obligation" (Ibid, art. 2201). by Court of Appeals and the trial court, and after reflecting on
the/tenor of the stipulation for liquidated damages herein, the true
The trial court and the Court of Appeals found that Pamintuan was nature of which is not easy to categorize, we further hold that justice
guilty of fraud because he did not make a complete delivery of the would be adequately done in this case by allowing Yu Ping Kun Co.,
plastic sheetings and he overpriced the same. That factual finding is Inc. to recover only the actual damages proven and not to award to it
conclusive upon this Court. the stipulated liquidated damages of ten thousand pesos for any
breach of the contract. The proven damages supersede the
stipulated liquidated damages.
There is no justification for the Civil Code to make an apparent
distinction between penalty and liquidated damages because the
settled rule is that there is no difference between penalty and This view finds support in the opinion of Manresa (whose comments
liquidated damages insofar as legal results are concerned and that were the bases of the new matter found in article 1226, not found in
either may be recovered without the necessity of proving actual article 1152 of the old Civil Code) that in case of fraud the difference

45
between the proven damages and the stipulated penalty may be
recovered (Vol. 8, part. 1, Codigo Civil, 5th Ed., 1950, p. 483).

Hence, the damages recoverable by the firm would amount to ninety


thousand five hundred fifty-nine pesos and twenty-eight centavos
(P90,559.28), with six percent interest a year from the filing of the
complaint.

With that modification the judgment of the Court of Appeals is


affirmed in all respects. No costs in this instance.

SO ORDERED.

Barredo, Concepcion, Jr., and Santos, JJ., concur.

Abad Santos, J., concur in the result.

46

Вам также может понравиться