REPORT FY 2018
Development and Rehabilitation of Irrigation Systems is one of the priority Programs of the
Department of Agriculture as well as the Provincial Government of Sorsogon to improve the quality
of farming industry and to have a sufficient irrigation water to sustain the needs of the farmers
throughout the whole cropping season. The Engineering Team were conducted a regular monitoring
of the existing, newly constructed and ongoing construction of SSIP sites under DA PAMANA
Projects and DA Rice Program . Also, conducted site validation and geotagging of proposed SSIPs
sites and has a potential to construct an irrigation facilities. These SSIPs shall be implemented
outside the service area of NIA systems. The SSIPs were categorized below:
D. Spring Development
Consists of concrete storage tank or intake structure and Polyethylene (PE) pipes or
concrete canals for distribution by gravity.
Abuyog Small Water Impounding Project (2017), Brgy. Abuyog, Sorsogon City, Sorsogon
Biyong San Isidro Diversion Dam (2017), Sitio Bitong, Brgy. San Isidro, Bacon District, Sorsogon City
Sta. Lourdes Diversion Dam (2014), Brgy. Sta. Lourdes, Barcelona, Sorsogon
Butag Diversion Dam (1998), Sitio Lumacao, Brgy. Butag, Bulan, Sorsogon
San Isidro Earth Impounding Dam (1998), Brgy. San Isidro, Donsol, Sorsogon
NEWLY CONSTRUCTED SSIP IN THE PROVINCE OF SORSOGON under DA Regular Project under Rice
Program 2018
PHOTO DOCUMENTATION
PROVINCIAL AGRICULTURAL ENGINEERING GROUP –
SORSOGON
53
ANNUAL ACCOMPLISHMENT REPORT 2018
Completed Burad Diversion Dam (2018), Sitio Burad, San Isidro, Bacon District, Sorsogon City,
Sorsogon
On going construction of Sitio Burad DD Lined Canal as of June 19,2018 in Sitio Burad, Brgy. San
Isidro, Bacon District, Sorsogon City, Sorsogo
PROPOSED SMALL SCALE IRRIGATION PROJECTS for 2018 under PAMANA 2019
& DA REGULAR FUND
FARMER
NAME OF SERVICE TYPE OF PROPOSED
LOCATION S REMARKS
ASSOCIATION AREA (ha) PROJECT TOTAL COST
SERVED
Sta. Lourdes Ulag Sta. Lourdes, Pto. 48 70 Const. of DD and 4.5 M COMPLETED
Irrigators Association Diaz, Sorsogon Lined Canal
Buenavista Farmers and Macawayan, 13 15 Const. of DD and 3.5M The proposed length of
Fishermen Association Buenavista, Bacon Lined Canal dam is 8 meters and
District, Sor. City height of 2.5 meters.
The proposed length of
Lined Canal is 650 m
Samahang Magsasaka San Isidro, Bacon 13 15 Lined Canal 3M Proposed length of
at Magbubukid ng District, Sorsogon Construction Lined Canal is 1,200 lm
Bacon including all lateral
Union Cadac an Union, Gubat, 35 27 Improvement of DD 2.5 M The proposed width of
Farmers Association Sorsogon and Lined Canal dam is 4 meters and
Extension height is 1.5 meters.
The proposed length of
lined canal is 350 lm.
Gabao Samahang Palanka, Gabao, 43 65 Construction of DD 3.2M The proposed length of
Nayon Multi Purpose Irosin, Sorsogon and Lined Canal dam is 23 meters and
Development height is 2.5 meters.
Cooperative The proposed length of
lined canal is 650 lm
including its lateral.
Del Rosario Bacon Del Rosario Bacon 52 40 Construction of Lined 2.5M The proposed length of
Farmers and Fisherfolks District, Sorsogon Canal lined canal is 1000 lm
Association including its lateral.
Bagacay Cabungahan Bagacay, Gubat, 30 25 Construction of Lined 3M The proposed length of
Farmers Association Sorsogon Canal lined canal is 1200 lm
including its lateral
Ogao Paco Farmers Ogao, Gubat, 40 18 Extension of Lined 2.5 M The proposed length of
Irrigators Association Sorsogon Canal lined canal is 800 lm
including its lateral
Sta. Lourdes San San Antonio, 42 25 Extension of Lined 6.3 M The proposed length of
Antonio Irrigators Barcelona Canal lined canal is 2500 lm
Association including its lateral
Catanusan Irrigators Catanusan, Juban 72 56 Construction of Lined 4.5 M The target length of
Association Canal lined canal is 1800 lm
including its lateral
Alulukdo Barayong Carriedo, Gubat 51 33 Construction of Canal 5.1 M The target length of
Irrigators Association lined canal is 2000 lm
including its lateral
Aroroy Farmers Aroroy, Juban 20 70 Construction of Lined 3.8 M The target length of
Association Canal lined canal is 1500 lm
including its lateral
Sitio Burad Diversion Dam, Sitio Burad, San Isidro, Bacon District, Sorsogon City, Sorsogon
Sitio Burad Lined Canal, Sitio Burad, San Isidro, Bacon District, Sorsogon City, Sorsogon
SHALLOW TUBE WELL (STW) AND PUMP IRRIGATION SYSTEM FOR OPEN
SOURCE (PISOS) PROJECT
PROVINCIAL AGRICULTURAL ENGINEERING GROUP –
SORSOGON
53
ANNUAL ACCOMPLISHMENT REPORT 2018
The Rice Program is one of the banner components of the Department of Agriculture mainly
concerned in rice farming and uplifting the lives of Filipino farmers. The National Rice Program integrates
government initiatives and interventions for the agriculture sector, namely: food security and self-sufficiency,
sustainable resource management, support services from farm to table, and broad – based local partnerships.
Some of its key strategies is the provision of Shallow Tube Well (STW) that consists of a tube or pipe vertically
set into the ground at a depth of 6 to 20 meters designed to lift water from shallow aquifer for irrigation using
pump and engine set; and the provision of Pump Irrigation Systems for Open Source (PISOS) that consists of
pump and engine sets, suction and discharge pipes to lift water from the surface water and deliver it to point
of use. Table 1.0 shows the requirements and additional information required to avail the said projects.
Validation and geo-tagging which is one of the requirements for the endorsement of the Office of the
Provincial Agriculturist was conducted thru its Agricultural Engineering Section. Table 2.0 shows the list of
individual farmers and Farmer Associations already validated and endorsed to DA-RFU 5.
TABLE 2.0 LIST OF INDIVIDUAL FARMERS AND FARMER ASSOCIATIONS ALREADY VALIDATED AND ENDORSED TO DA-
RFU 5
Most of the problems in agriculture industry are on the production, postharvest, marketing and
processing aspect. There is much work to be done to increase food production and alleviate the living
condition of subsistence farmers in the province. The postharvest development programs, projects, activities
and interventions are vital inputs in attaining profitable and sustainable agribusiness ventures leading to
improved socio-economic well- being of the country’s farmers.
The lack of postproduction/processing facilities especially for small farmers has been one of the most
serious problems plaguing the grains industry of the country. Even with the increased yields, small rice/corn
farmers remain in poverty because they are forced to sell their poorly processed produce at low prices to
traders and millers. One of the key strategies of the Department of Agriculture is the Postharvest
Mechanization Program that includes provision of appropriate drying facilities such as Flat Bed Dryer and Multi-
Purpose Drying Pavement (MPDP); and provision of postharvest facilities/ equipment to Framers
Associations/Irrigators’ Association within rice production areas. Table 1.0 shows the requirements and
additional information required to avail the said projects.
Monitoring of Alinao Bibincahan Flat Bed Dryer in Brgy. Bibincahan, Sorsogon City, Sorsogon
Monitoring of the two (2) Units SAADECO Flat Bed Dryer in Brgy. Gimaloto, Sorsogon City, Sorsogon
Validation of Proposed Rehabilitation of SAADECO Flat Bed Dryer in Brgy. Gimaloto, Sorsogon City, Sorsogon
Validation of the Proposed Relocation Site for Flat Bed Dryer in Brgy. Carriedo, Irosin, Sorsogon
Validation of the Proposed Site for Flat Bed Dryer in Brgy. San Pascual, Bacon District, Sorsogon City, Sorsogon
Monitoring of the On Going Construction of SAADECO Multi-Purpose Drying Pavement in Gimaloto, Sorsogon
City, Sorsogon as of August 15, 2018
Monitoring and Inspection of the On Going Repair of Flat Bed Dryer in Brgy. Macawayan, Irosin, Sorsogon as of
July 19,2018
Monitoring and Inspection of the On Going Repair of Flat Bed Dryer in Brgy. Poblacion, Irosin, Sorsogon as of
July 19,2018
Monitoring and Inspection of the Completed SAADECO Multi-Purpose Drying Pavement in Brgy. Gimaloto,
Sorsogon City
Monitoring and Inspection of the Completed of Alinao Bibincahan Multi-Purpose Drying Pavement in Brgy.
Bibincahan, Sorsogon City, Sorsogon
Under the banner program of Department of Agriculture is the Rice Program which mainly
concern is to uplift the rice farming industry of Filipino farmers. The ultimate goal of this program is
to provide farm/Agri Machineries to enable small farmers, Farmers Association and Cooperatives
awareness and to access them with the new technology and improve their farming industry through
Mechanization. The Provincial Government of Sorsogon and the Department of Agriculture through
the DA Regional Field Office 5 have partnered to provide postharvest and farm machineries to the
different qualified and active Irrigator’s Association.
EQUIPMENT REQUIREMENTS
Hand Tractor Letter of Intent from the Farmers Association and a board resolution stating
Rice Thresher its need of the technologies and the capacity to manage the project.
Floating Tiller
SEC/CDA/DOLE latest certificate of registration for IAs/FCs and other Fas
Reaper
Drum Seeder MAO/CAO/PAO endorsements
Seed Cleaner Fill up pro-forma of the project proposal to be provided by the DA RFO5
Seed Spreader Latest Audited Financial Statement – Additional requirement for Combine
Combine Harvester Harvester, Mini Combine Harvester & 4WD Mini Tractor
Mini Combine MAFC/PAFC/CAFC Endorsement
Harvester
4WD Mini Tractor
Rice Cutter
Combine Harvester Must have at least a cluster of Qualified Cooperator include: LGUs, NGOs,
100 hectares (with names of and Farmers Cooperative/ Farmers
farmers who intend to use the Associations engaged in rice farming duly
machine, duly certified by the registered with Securities and Exchange
Municipal/City Agriculturist of Commission (SEC) and Cooperative (CDA)
existing or potential areas duly The Cooperator shall make the unit available
validated by DA RFO5 for custom services to maximize its utilization
thereby making it economically profitable.
Mini Combine Must have at least a cluster of The cooperator shall enter into a MOA under a
Alinao Irrigators Association Bibincahan, Sorsogon City Geofrey Gigantoca Hand Tractor RECEIVED
Rizal Quidolog Irrigators Association Rizal, Pto. Diaz Jose Domalaon Hand Tractor RECEIVED
Bagacay Kabungahan Farmers Association Bagacay, Gubat Celso Espinola Hand Tractor a
Combine Harvester
Adgao Irrigators Association Sn. Roque, Sta. Magdalena Pedro Formento Hand Tractor RECEIVED
Sorsogon Agro Aquatic Development Cooperative Gimaloto, Sorsogon City Floribe Macapagal Hand Tractor RECEIVED
Seed Spreader
Malayang Ugnayan ng Magsasaka Magsaysay, Bulan Clifford Bueno Hand Tractor For pick up
Del Pilar Farmers Association Del Pilar, Bulan Salve Gino Thresher RECEIVED
Gabao Samahang Nayon Multi-Purpose Gabao, Irosin Reil Palencia Rice Transplanter RECEIVED
Development Cooperative Seed Spreader
Combine Harvester
Alulukdo Barayong Irrigators Association Carriedo, Gubat Jose Enaje Rice Transplanter
Ulag Prieto Diaz Farmers Association Ulag, Pto. Diaz Domingo Bayle Rice Transplanter
Pitigawan Irrigators Association Gogon, Pto. Diaz Jaime Domasig Thresher RECEIVED
FOR PICK UP FARM MACHINERY &EQUIPMENT TO THE QUALIFIED RECIPIENTS at Sorsogon Dairy Farm
FOR PICK UP AGRI MACHINERY UNDER RICE PROGRAM 2018 AT SORSOGON DAIRY FARM, SOR. CITY
PHOTO DOCUMENTATION
Proposed Site and Garage of 1 unit Rice Reaper and 1 unit Seed Spreader of SAADECO
Proposed site and Garage for 1 unit HandTractor, 1 unit Thresher and a Mechanical Dryer of San Jose,
Maricrum Farmers Association
Proposed Site and Garage of 2 units Grass Cutters, 1 unit HandTractor, 1 unit thresher and 1 unit 4WD
Tractor of Abuyog Farmers Association
San Pascual Irrigators Association at Brgy. Sn. Pascual, Bacon District, Sorsogon City
53
ANNUAL ACCOMPLISHMENT REPORT 2018
1 Unit of handtractor and 1 unit of rice tresher was monitored under BUB project of
LGU-Juban, Sorsogon.
Buenavista Farmers Association represented by its President Mr. Calixto Anzano from Brgy.
Buenavista, Castilla. Recipient of 2017 Agri Machinery & Equipment allocation
Program
Gabao Samahang Nayon Multi Development Cooperative represented by its President Mr.
Reil Palencia from Brgy. Gabao, Irosin. Monitor the Agri Machinery & Equipment.
Program
Bagacay Kabungahan Farmers Association represented by its President Mr. Celso Espinola
53
ANNUAL ACCOMPLISHMENT REPORT 2018
Gabao Samahang Nayon Multi Development Cooperative represented by its President Mr.
Reil Palencia from Brgy. Gabao, Irosin. Monitor the Agri Machinery & Equipment.
Program
TRAINING(S) CONDUCTED
1. Conducted 2 daysTraining on Operation and Maintenance of DC-35 Combine Harvester in
Brgy. Gabao, Irosin, Participated by GASANAMUDECO members and Municipal Agriculture
Office-Irosin staffs headed by Mrs. Nimfa Ferolino.
The Department of Agriculture Regional Field Unit 5 has allocated one (1) unit of DC 60 Rice Combine
Harvester in the Province of Sorsogon and one (1) unit was availed by the Provincial Local
Government Unit of Sorsogon in 90-10% scheme, the PLGU was gave its counterpart to avail the said
equipment. The two (2) units of Harvester was located at the Office of the Provincial Agriculturist
under the overseeing of the Provincial Agricultural Engineering Group. The said harvester was
operational and it was utilized upon the request of the farmers/clients.
Date of Harvest Place of Harvest Name of Owner No. Harvested Hectare No. of Bags
April 2018 Tabi, Gubat Ronaldo Embile 1 ha 115
April 12-14, 2018 Gabao, Irosin Teresita Futalan 5 568
March 28, 2018 Bibincahan, Sor. City Evelyn Broqueza 1
Oct. 15-16, 2018 Abuyog, Sorsogon City Jimmy Timajo 3
April 19-20, 2018 Abuyog, Sorsogon City Jimmy Timajo 4
Sept. 27-28, 2018 Abuyog, Sorsogon City Jimmy Timajo 1
Oct. 2018 Guruyan, Juban Dra. Josefina Valer
Oct. 2018 Guruyan, Juban Cesar Olondriz 3
Oct. 2018 Guruyan, Juban Atty. Merl Margaret Gratela 4 ha
Oct. 25, 2018 Guruyan, Juban Jesus Guamos 5.5
Sept. 18, 2018 Sn. Isidro, Bacon District Geronimo Divina 1.6
Nov. 27-30, 2018 Gabao, Irosin Teresita Futalan 5
PHOTO DOCUMENTATION
PROVINCIAL AGRICULTURAL
At Brgy.ENGINEERING GROUP
Gabao. Irosin, Sorsogon – Field of
at the Rice
SORSOGON Hon. Tess Futalan with 5hectares rice area.
53
ANNUAL ACCOMPLISHMENT REPORT 2018
The Bureau of Soil and Water Management has coordinated with the Office of the Provincial
Agriculturist thru the Agricultural Engineering Division in the conduct of monitoring of installed Solar
Powered Water Pumps and Ram Pump in the Province of Sorsogon. One unit was installed in
Sorsogon Dairy Farm to be used for irrigation of Vegetables & Rice and the other one was installed in
Brgy. Escuala Casiguran Sorsogon to irrigate high value commercial crops.
PHOTO DOCUMENTATION
At Brgy. Sn. Roque, Bacon District, Sorsogon City at the Rice Field
of Mr. Divina with 2hectares rice area.
Monitoring of the Installed Solar Water Pump under HVCDP Program of BSWM installed at Brgy.
Escuala, Casiguran, Sorsogon. The Solar Water Pump was no longer utilized that time during site
inspection.
Site Inspection of the Proposed Site Solar Water Pump under HVCDP Program of BSWM at Brgy.
Macawayan, Irosin, Sorsogon together with the Staff of the winning contractor (One Renewable
Energy) & Staff from MAO Office headed by MA Nimfa Ferolino and the Farmers Association
Recipient..
Monitoring and Site Inspection of the Installed Ram Pump Irrigation System under HVCDP
Program of BSWM at Brgy. Escuala, Casiguran, Sorsogon. Together with the Representative from
MAO Office and Engr. Eddie Martinez from BSWM Central Office.
The objectives of PAMANA are the following: 1.) To Improve Governance through partnerships with
national and local institution, building capacities or governance, and enhancement of transparent
and accountability mechanisms. 2.) To Reduce Poverty and vulnerability in conflict-affected areas
through sustainable rural development, community infrastructure and focused delivery of social
services and 3.) To Empower Communities and strengthen their capacity to address issues of conflict
and peace through activities that promote social cohesion.
Sorsogon has seven (7) identified PAMANA areas, the municipalities of Magallanes, Pto. Diaz, Irosin,
Juban, Barcelona, Bulusan and Gubat. Rehabilitation and Development of Irrigation facilities and
Construction/Fabrication of Postharvest Facilities (Mechanical Flatbed Dryer) are some of the
projects implemented in the province.
Monitored the Newly Constructed SSIPs Site in the Province of Sorsogon under DA PAMANA
PROGRAM.
Implemented SSIPs Site in the Province of Sorsogon under OPAPP PAMANA 2017 FUND
NAME OF PROJECT LOCATION PROJECT STATUS AS OF December, 2018
COST
Construction of Brgy. Incarizan, Php 4, 500, 000.00 The Project is still ON-GOING as to this date.
1 Incarizan Diversion Dam Magallanes, Sorsogon
2 Extension of Rangas Brgy. Rangas, Juban, Php 1, 500, 000.00 The Project was already COMPLETED.
Lined Canal Sorsogon
3 Extension of Pange Brgy. Payawin, Gubat, Php 2, 000, 000.00 The Project is now Completed as to this date.
Lined Canal Sorsogon
4 Extension of Jupi Lined Brgy. Jupi, Gubat, Php 2, 000, 000.00 The Project is now Completed as to this date.
Canal Sorsogon
5 Extension of Patong Brgy. Naagtan, Gubat, Php 2, 000, 000.00 Awaits to finish the 1st tranche Project since it is
Lined Canal Sorsogon a 2nd tranche Project
6 Provision of Twenty 4 sites – Pto. Diaz Php 3, 500, 000.00 Awaits to finish the 1st tranche Project since it is
(20) units of Shallow 8 sites – Juban (P175,000.00/site) a 2nd tranche Project
Tube Well (STW) 4 sites – Irosin
Project (Drilled and 4 sites - Casiguran
Installation Works)
PHOTO DOCUMENTATION
Monitoring of the recently completion of Construction of Patong Diversion Dam & Irrigation Lined
Canal at Brgy. Naagtan, Gubat, Sorsogon
Monitoring of the recently completed of Saline Tilapia Hatchery Pond RC Entrance Gate at Brgy.
Tughan, Juban, Sorsogon
The Philippine Rice Research Institute (PhilRice) is spearheading a campaign called “Be Riceponsible”
to prevent rice wastage and consumption of healthier rice and is urging Government Organization
(GOs), Local Government Units (LGUs) and Higher Education Institutions (HEIs) to support the
campaign in their own areas. The Office of the Provincial Agriculturist (OPAg) – Sorsogon has joined
this search. In so doing, activities for the campaign have been lined up. One of these is the
coordination with other agencies and organizations to drum up support in getting across the four (4)
Ks, basic messages espoused by the Be Riceponsible campaign, which are: 1. Konti konting kanin
muna para walang tira; 2. Kumain ng Brown (unpolished) rice; 3. Kakaibang kanin naman
(consumption of rice mixed with other staples); 4. Kilalanin at pasalamatan ang mga magsasaka sa
pamamagitan ng pagpapahalaga sa bawat butil ng kanin.
Distribution of Brown Rice to the selected school & in the Office of the Senior Citizen in the Province
of Sorsogon were done.
Training on Skills Training Course on the Performance Testing and Evaluation of PHilMech
Corn and Cassava Technologies
PHilMech, CLSU Compound, Science City of Muñoz, Nueva Ecija
April 8-14, 2018
Training Course on Agro - Hrdrology and Dam Design for SWIP and Diversion Dam (DD)
Legaspi City, Albay
July 23, 2018 to August 5, 2018
Training of Trainers on Climate Smart Farm Business School for Agricultural Extension
Workers
Macagang Business Center, Nabua, Camarines Sur
September 3 - 14, 2018
Implementation Meeting cum Workshop with the Contractors and Recipients of CY 2018
Small Scale Irrigation Projects
Naga Pilgrims Hotel, Naga City
November 7-8, 2018
Luzon-wide Local Government Unit (LGU) Summit: Roles, Duties and Responsibilities of the
LGUs on Agricultural Mechanization Programs
Rembrandt Hotel, Visayas Avenue, Quezon City, Manila
November 25-27, 2018
TIER II Meeting
SLMCS, Brgy. Talisay, Sorsogon City
December 2018
HIROSHI G. DE VERA
Engineer II, Head, PAEG & Soils Section
In Charge - Farm Mechanization
Technical Staff, PAMANA Projects
Member, TIER II Projects
Member, BE RICEponsible Team
Provincial Agricultural Engineering and Soils Section
Office of the Provincial Agriculturist