Saudi Aramco 2616-ENG (03/99)

PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
ARM
ENGG CERT

ISSUED FOR REVEIW AND APPROVAL


DESCRIPTION

6600031345

CONSTRUCTION OF LOADING RACK


FACILITIES AT THE RT DISTRIBUTION
JO/EWO

31345 6Mar2014
DATE

Method Statement
NO.
REV

DISCIPLINE

Concrete Surface Preparation &


ENGINEER

DATE:
PROJECT
ENGINEER Coating Application
DATE:
CERTIFIED

DATE:
CONSTRUCTION
AGENCY

DATE: PREPARED BY:


OPERATIONS

DATE:
CONTROL NUMBER
VERIFICATION
EDSD

DATE:
BY:
REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


(DCC) NO. _____________________

pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.


REVISION

MS for Concrete Curface Preparation & Coating Application DOC


1
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
ARM
ENGG CERT

TABLE OF CONTENTS
A. PURPOSE 3
B. SCOPE...........................................................................................................................3
ISSUED FOR REVEIW AND APPROVAL

C. REFERENCES 3
D. DEFINITIONS 4
DESCRIPTION

E. RESPONSIBILITIES 4
F. RESOURCES 4
G. METHODOLOGY 5
H. QUALITY ASSURANCE AND QUALITY CONTROL 6
I. HEALTH, SAFETY AND ENVIRONMENT 6
J. RISK ASSESSMENT AND SAFETY MEASURE 7
JO/EWO

31345 6Mar2014
DATE

K. ATTACHMENTS 8
NO.
REV

DISCIPLINE
ENGINEER

DATE:
PROJECT
ENGINEER

DATE:
CERTIFIED

DATE:
CONSTRUCTION
AGENCY

DATE:
OPERATIONS

DATE:
CONTROL NUMBER
VERIFICATION
EDSD

DATE:
BY:
REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


(DCC) NO. _____________________

pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.


REVISION

MS for Concrete Curface Preparation & Coating Application DOC


2
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
A. PURPOSE
ARM
ENGG CERT

Define a procedure to provide a proper and efficient sequence of works shall be performed
in safety manner & good working practice in accordance with the project specifications,
Saudi Aramco, relevant industry codes & standards, IFC drawings and approved
methodology.
ISSUED FOR REVEIW AND APPROVAL

B. SCOPE
This covers the necessary surface preparation of concrete structure prior to application of
DESCRIPTION

protective coating. This shall be read in conjunction with other approved method statements
& project specifications. In the event of conflict with the others, the most stringent shall
govern.

C. REFERENCES
(As stipulated in the Contract & weekly MOM between Subcontractor, DGC & SAPMT, the
Saudi Aramco Desktop Standards as of 31 December 2012 shall be used for this project)
JO/EWO

31345

Saudi Aramco Engineering Standards


SAES-H-001 Coating Selection and Application Requirements for Industrial Plants…
6Mar2014
DATE

SAES-H-003 Protective Coating for Industrial Concrete Structures


2

SAES-H-101V Approve SA Data Sheet Paints & Coating


NO.
REV

DISCIPLINE SAES-H-102 Safety Requirements for Coating Application


ENGINEER
SAES-Q-001 Criteria for Design & Construction of Concrete Structures
DATE:
PROJECT SAES-Q-005 Concrete Foundations
ENGINEER

SAES-Q-007 Foundations & Supporting Structures for Heavy Machinery


DATE:
CERTIFIED SAES-S-020 Industrial Drainage & Sewers
Saudi Aramco Engineering Procedure
DATE:
CONSTRUCTION SAEP-316 Performance Qualification of Coating Personnel
AGENCY
Saudi Aramco Typical Inspection Plan
DATE:
OPERATIONS SATIP-H-003-01 Coating Application on Concrete Structures
Saudi Aramco Inspection Checklist
DATE:
SAIC-H-1002 Concrete Coatings & Repair Materials Receiving, Storage & Preservation
CONTROL NUMBER
VERIFICATION

SAIC-H-1003 Concrete Coatings Pre-Installation Inspection


EDSD

SAIC-H-1004 Coating & Final Inspection


DATE:
BY:

Saudi Aramco Material System Specifications


REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,

09-SAMSS-067 Qualification Requirements for Epoxy Coatings for Immersion Services


THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE

09-SAMSS-068 Qualification Requirements for Coal Tar Epoxy Coatings for Immersion
(DCC) NO. _____________________

Services (APCS-3)

pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.


REVISION

MS for Concrete Curface Preparation & Coating Application DOC


3
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
09-SAMSS-069 Qualification Requirements for Epoxy Coatings for Atmospheric Service
ARM
ENGG CERT

Saudi Aramco Construction Safety Manual


Saudi Aramco HSE
GI-0002.100 Work Permit System
American Concrete Institute
ISSUED FOR REVEIW AND APPROVAL

ACI 201.1R Guide for making a Condition Survey of Concrete


ACI 228.1R Manual of Concrete Inspection
DESCRIPTION

ACI 308R Guide to Concrete Inspection


American Society for Testing & Materials
ASTM D3363 Test Method for Film Hardness by Pencil Test
ASTM D4138 Test Method for Measurement of Dry Film Thickness of Protective Coating
Systems by Destructive Means
ASTM D4541 Test Method for Pull-Off Strength of Coating using Portable Adhesion
Tester
JO/EWO

31345

D. DEFINITIONS
6Mar2014
DATE

All terms used in the development of this procedure are defined as follows:
2
NO.
REV

 CLIENT - Saudi Arabian Oil Co. (Saudi Aramco)


A

DISCIPLINE
ENGINEER  CONTRACTOR - Dragados Gulf Const. Co. Ltd. (Dragados)
 SUBCONTRACTOR - Eastern Trading & Cont. Est. (ETE)
DATE:
PROJECT
ENGINEER E. RESPONSIBILITIES
Construction Manager shall ensure that all operations have been risk assessed and
DATE:
CERTIFIED
necessary control measures have been implemented to carry out the task in a safely
manner. He shall strictly implement and monitor the methodology of works as per project
specifications & IFC drawings compliance with quality, schedule & safety requirements.
DATE:
CONSTRUCTION
AGENCY Civil Supervisor at site shall ensure compliance by all labour and equipment operators and
other associated craftsmen to the requirements of this procedure, Project Quality Plan,
DATE: relevant IFC drawings, HSE requirements as well as the project specifications. Secure all
OPERATIONS necessary Work Permits.
QC-Civil Inspector shall monitor the daily activities and verifies its compliance to project
DATE:
specifications. Conduct activities in accordance with the Project QA Manual and Quality
CONTROL NUMBER

Inspection Plan.
VERIFICATION
EDSD

Engineering department shall provide technical assistance to construction operation. Ensure


that IFC drawings at site shall be in its most recent revision together with the relevant
DATE:
BY:

shopdrawings shall be provided at site.


REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,

HSE officer shall control, supervise and record toolbox meetings. Inspect, approve or reject
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE

engaged resources. Ensure that all HSE requirements are met and implemented while
(DCC) NO. _____________________

executing the works. Notify the person in charge on site if any deviation and/or corrective
remedy action to be applied before and while executing the works. Ensure that
pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
REVISION

MS for Concrete Curface Preparation & Coating Application DOC


4
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
recommendation of work place precaution followed up strictly. Stop any/or all works in case
ARM
ENGG CERT

specified recommendation/ observations were not followed up by construction management


team.

F. RESOURCES
Contractor shall deploy adequate number of resources but not limited to the following as the
ISSUED FOR REVEIW AND APPROVAL

Works may requires complying with the approved schedule and resource histograms:

Equipments/ Tools
DESCRIPTION

 Paint/ Wire Brush


 Air Compressor/Blower
 Chipping Bit with Hammer & Chisel
 Other necessary hand tools
 PPE’s
Manpower
 Project Engineer
JO/EWO

31345

 Civil Supervisor
 Contractor QC Inspector-Civil

6Mar2014

Approved 3rd Party Laboratory Technician


DATE

 Safety Supervisor
2

 Foreman
NO.
REV

DISCIPLINE
 Coating Personnel (Crew Supervisor & Applicators - Aramco Approved)
ENGINEER  Skilled Personnel (Mason, Carpenter, Electrician etc.)
 Labour Crew
DATE:
PROJECT
ENGINEER Safety Equipment
 First-Aid Kit
DATE:
CERTIFIED  Fire Extinguishers
 Warning Signage
DATE:  Barricades/Jersey Barriers/Fences
CONSTRUCTION
AGENCY
 Signage for Traffic Control & Detours

DATE:
OPERATIONS
G. METHODOLOGY
Overview
DATE: The purpose of surface preparation is to remove laitance, contaminants and other
CONTROL NUMBER

unsuitable compounds on the concrete like oil, dust, etc. to ensure the good bond of
VERIFICATION

coating to the concrete. Concrete surface shall be prepared for coating after it is
EDSD

adequately cured. The preparation works shall includes but not limited to: repair of
DATE:

cracks, spalls, pop outs and other irregularities, removal of surface contaminants that
BY:

induces early coating deterioration, roughen the smooth surfaces to improved coating
REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,

adhesión.
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE

Surface Preparation
(DCC) NO. _____________________

pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.


REVISION

MS for Concrete Curface Preparation & Coating Application DOC


5
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
1. Any concrete defects and unsound concrete shall be repaired immediately prior
ARM
ENGG CERT

to surface preparation and coating.


2. Roughen the surface and remove any protrusions and sharp edges by using a
grinding tools and wire brush.
3. Remove any surface contaminants such as laitance by wire brushing; form oils,
grease, etc. shall be removed by steam cleaning added with a water
ISSUED FOR REVEIW AND APPROVAL

emulsifying detergent.
4. Clean the surface using air compressor to remove the dust and other debris
and prepare for application of coating.
DESCRIPTION

Concrete Coating Application


1. Conduct moisture content determination per ASTM D4263 prior to application
of coating. No coating shall be applied until the moisture content determination
is passed, i.e. 4% or less.
2. Coating works shall be carried out in accordance with the manufacturer’s data
sheet & SAES-H-101V.
3. Use APCS-3 “Bitumastic 300M-Coal Tar Epoxy” for below ground concrete
JO/EWO

31345

structures, such as manholes, sleepers, foundation, etc. For other


areas/structure, refer to SAES-H-001 for coating selection and applications
requirements.
6Mar2014
DATE

4. Coating shall be applied at temperature from 10-60°C. Never apply paint under
2

adverse weather condition and if the substrate contains oil, grease & other
NO.
REV

DISCIPLINE surface contaminants and if less than 3°C (5°F) above the dew point.
ENGINEER
5. All coating personnel or crew shall be Aramco Approved Coating Applicators
DATE: prior to commence with the work.
PROJECT
ENGINEER
6. Conduct the typical coating inspection as per SAIC requirements.
DATE: 7. Clean the area afterwards prior to proceed with the next activity.
CERTIFIED
8. End of procedure.
DATE:
CONSTRUCTION
AGENCY

DATE: H. QUALITY ASSURANCE AND QUALITY CONTROL


OPERATIONS
The quality of the works shall be performed in line with the SA Quality Standards. Relevant
Inspections shall be made at stages as per the approved ITP’s.
DATE:
Contractor QA/QC Inspectors shall closely monitor and assure all general materials are
CONTROL NUMBER
VERIFICATION

complying with the project specifications. Frequent inspections shall be conducted and all
EDSD

records shall be maintained as required by project QA/QC Program in accordance with


approved Project Quality Plan & ITP’s.
DATE:
BY:

All the tests to be performed shall be in conformance with the project standards. Only
REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,

approved third party testing laboratory technician(s) shall be responsible for performing all
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE

related civil tests. Any materials and works not conforming to the project specifications shall
(DCC) NO. _____________________

be rejected by the relevant discipline approved QC Inspector(s).

pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.


REVISION

MS for Concrete Curface Preparation & Coating Application DOC


6
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
I. HEALTH, SAFETY AND ENVIRONMENT
ARM
ENGG CERT

The health and safety shall perform a splendid role in all construction activities to ensure that
all the works are being carried out in a safe manner and creating a healthy environment at
site. All activities shall be carried out safely in accordance with ETE-HSE plan approved by
Client and related SACSM.
Contractor's site supervisor shall conduct daily toolbox meetings and discuss the
ISSUED FOR REVEIW AND APPROVAL

requirements of the project and other special needs to create a safe working environment.
He is responsible for achieving the target and the project milestones.
Appropriate work permits shall be applied in accordance to the requirements of SACSM.
DESCRIPTION

Necessary checklists for the specific job shall be properly completed, approved and be
always made available at the job site.
Safety Inspector (ETE) shall closely monitor and assure that all works are carried out in
highly safe manner, gearing the workers with full strength of safety protective equipment,
preparation of safety barricading and dust control screening wherever applicable in safe
manner, safe workability of equipment to be used and fulfilling any other additional safety
needs as required during work executions. He shall also check and ensure that only qualified
personnel are carrying out the equipment & machinery related works.
JO/EWO

31345

ETE/DGC-HSE Manager & personnel shall conduct a safety walk in regular basis, around
the site (e.g. weekly). This shall be reported and submitted to the Client. Any accidents or
6Mar2014
DATE

incidents that occurred shall be informed immediately to the client and recorded accordingly.
2

All works shall be done safely in accordance to the requirements of SACSM, highlighted as
NO.
REV

follows:
A

DISCIPLINE
ENGINEER
 A safety officer shall be at site during the execution of works.
DATE:
 Daily toolbox meetings shall be conducted as mandatory. Educate skilled personnel &
PROJECT labors about evacuation drills, motivates them to use proper PPE at all times.
ENGINEER
 All workers shall be provided with job specific PPE’s.
DATE:
 Following safety requirements shall be fulfilled
CERTIFIED  Proper housekeeping at site to be carried out in daily basis
 Information for “EMERGENCY CONTACT NUMBERS” posted in conspicuous place
DATE:  Providing First-Aid kit at site
CONSTRUCTION
AGENCY  Safety barricade shall be provided wherever necessary
 Necessary safety signboards shall be displayed as required.
DATE:
 Road areas shall be illuminated; use of reflective signs or flags, flagmen shall wear highly
OPERATIONS
visible PPE’s.
 Safety flickering lights shall be provided for vehicles working on longtime hours.
DATE:
 The approving authority prior to start of the work shall inspect all equipment.
CONTROL NUMBER


VERIFICATION

Working equipment shall be equipped with amber lights, horns, safety guards, backup
alarms’ etc. as required per safety provisions.
EDSD

 Inspection & maintenance of vehicles & equipments shall be conducted in regular basis.
DATE:

 Any incident at site shall be immediately reported to client and recorded.


BY:

 Weekly safety statistics reports and safety performance reports etc. shall be prepared
REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

and recorded.
OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE

 Daily safety task assignment to be prepared


(DCC) NO. _____________________

pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.


REVISION

MS for Concrete Curface Preparation & Coating Application DOC


7
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
 Man shelters shall be provided to protect the workers from adverse climatic condition, i.e.
ARM
ENGG CERT

sand storm, high temperature, etc.


 Potable water source shall be located within 100m walking distance and in all designated
break/rest areas.
 Toilet and eating area shall be provided for adequate number of workers.
 Holiday & Friday works shall be inform to PMT in advance on monthly basis
 Conducts Internal Safety Audits in weekly basis with PMT presence (for occasional
ISSUED FOR REVEIW AND APPROVAL

auditing) to close the project with ZERO ACCIDENTS.


DESCRIPTION

J. RISK ASSESSMENT AND SAFETY MEASURE

Work Activity Job Hazards Control Measures

PPE including mask and proper


Handling of chemicals and Suffocation, eyes orientation to workers shall be given
raw materials and skin irritation Store chemicals away from flammable
items with proper label for identification
JO/EWO

31345

Only skilled worker shall operate the


6Mar2014
DATE

Operating equipments equipments.


Self-injuries and
such as concrete chipping, Full PPE must be worn when working.
2

property damage
cutting, grinding, etc. Calibration of required equipments must
NO.
REV

DISCIPLINE be updated.
ENGINEER

DATE:
PROJECT
ENGINEER K. ATTACHMENTS
MSDS of Approved Coating Material
DATE:
CERTIFIED Bitumastic 300M – Carboline

DATE:
Saudi Aramco Typical Inspection Plan
CONSTRUCTION
AGENCY SATIP-H-003-01 Coating Application on Concrete Structures
Saudi Aramco Inspection Checklist
DATE:
OPERATIONS SAIC-H-1002 Concrete Coatings & Repair Materials Receiving, Storage &
Preservation
DATE:
SAIC-H-1003 Concrete Coatings Pre-Installation Inspection
CONTROL NUMBER
VERIFICATION

SAIC-H-1004 Coating & Final Inspection


EDSD

DATE:
BY:
REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


(DCC) NO. _____________________

pr DWG.TYPE PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.


REVISION

MS for Concrete Curface Preparation & Coating Application DOC


8
GEN A RTLRF-ETE-DGC-MS-008
Construction of Loading Rack Facilities at the RT Distribution of B
Ras Tanura Saudi Arabia
RJO / EWO: BI-10-00914 8
EDSD/2616-0399.doc