Вы находитесь на странице: 1из 19

education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

Contents lists available at SciVerse ScienceDirect

Education for Chemical Engineers

journal homepage: www.elsevier.com/locate/ece

Safety education through case study presentations

David C. Shallcross ∗
Department of Chemical and Biomolecular Engineering, University of Melbourne, Melbourne, Victoria 3010, Australia

a b s t r a c t

Process safety was introduced into the curriculum of two second year undergraduate subjects in the chemical engi-
neering programs at the University of Melbourne in 2009. As part of the student learning, groups of three to four
students were each given a safety case study to investigate and report on to the rest of the class. The case studies
include well known process incidents including Bhopal, Buncefield, Longford, Flixborough and Piper Alpha. Also
included were incidents drawn from other industries still with valuable lessons to be learnt regarding procedure
and failure modes. Each student in the group was expected to talk for 4–5 min on an aspect of the safety incident
but within a seamless presentation that was well constructed. Each student was also assigned another student for
whose presentation they were to provide a written critique. Students presenting in the second week were required
to critique the presentation of a student presenting in the first week. Both the student’s presentation and the written
critique were marked by the lecturer-in-charge. Feedback from students was very positive to the use of presentations
to study safety case studies. This paper describes how the case studies have been successfully used in the class room
and presents information on 27 case studies.
© 2012 The Institution of Chemical Engineers. Published by Elsevier B.V. All rights reserved.

Keywords: Safety; Case studies; Education; Chemical engineering; Pedagogy

1. Introduction killed four people at the T2 Laboratories chemical manufac-


turing facility in Florida in 2007 (USCSHIB, 2009aU.S. Chemical
The teaching of process safety is critical to any undergraduate Safety and Hazard Investigation Board, 2009a). An investiga-
chemical engineering program. Students need to understand tion by the U.S. Chemical Safety and Hazard Investigation
their responsibilities to themselves, their work colleagues and Board found that none of the operations staff involved at the
the wider community. They need to be aware of safe prac- site, including the owner, a trained chemical engineer, had any
tices and also the consequences that may arise when those appreciation for the hazards associated with reactive chemi-
safe practices are not followed. The teaching of safety is also cal processes. In their recommendations in the incident report
an accreditation requirement specified by international bodies they strongly recommended that reactive chemical process
such as the Institution of Chemical Engineers (2012) and the awareness be incorporated into all undergraduate chemical
International Engineering Alliance (2009) as well as national engineering programs in the US. Subsequently Willey et al.
accrediting bodies such as ABET (2011) in the US and Engineers (2011) developed an activity for use in an undergraduate reac-
Australia (2008). More recently the European Federation of tion engineering subject based around this very incident.
Chemical Engineering Working Party on Education (EFCE-WPE) In reviewing the important safety topics that all engineer-
released guidelines on chemical engineering curricula within ing students should be aware of Bryan (1999) developed a
Europe which includes a significant safety element (Gillett, comprehensive list that included:
2001; EFCE, 2010European Federation of Chemical Engineer-
ing, 2010). This supports the central contention of Hendershot • where practicing engineers would be able to find informa-
and Smades (2007) that “. . .the foundation of a great safety tion on safety and health rules, regulations and standards;
culture in the process industries begins in the classroom. . .”. • employer and employee rights and responsibilities under
The importance of teaching safety was confirmed following the law where they are practicing;
the investigation into the explosion and subsequent fires that • record keeping and reporting requirements;


Tel.: +61 3 8344 6614; fax: +61 3 8344 4153.
E-mail address: dcshal@unimelb.edu.au
Received 15 September 2012; Accepted 23 October 2012
1749-7728/$ – see front matter © 2012 The Institution of Chemical Engineers. Published by Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.ece.2012.10.002
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e13

• fire prevention and protection; 2. Background


• the hazards of dealing with chemicals, toxic material and
hazardous wastes; Safety case studies are included in the two second year
• biomedical hazards; subjects taught in the undergraduate chemical engineering
• permit-to-work systems relating to procedures including programs at the University of Melbourne. These subjects,
confined space entry; Chemical Process Analysis 1 and 2, are taught in the first and
• safety management systems; second semesters respectively of the second year of the Bach-
• responding to site emergencies such as hazardous material elor of Science (Chemical Systems) program. At Melbourne
emergencies; chemical engineering is taught in a 3-year Bachelor of Science
• environmental protection requirements. degree which is followed by a second-cycle 2-year Master of
Engineering (Chemical) degree. Melbourne ceased intake into
its more traditional 4-year Bachelor of Engineering programs
To this list the author could have added in 2010.
The two subjects were taught for the first time in 2009. The
syllabus for Chemical Process Analysis 1 includes an introduc-
• human factors and safety; tion to process operations, compositions of mixtures, material
• hazards associated with maintenance procedures and balances, real gas behaviour, humidity, process control and
recovering from process upsets; process safety. Chemical Process Analysis 2 covers introduc-
• process control; tory thermodynamics, concepts of energy, enthalpy and heat
• hazard identification and strategies for minimization of capacity, energy balances involving reacting and non-reacting
risk; systems, manufacturing processes and process safety. Both
• the hazards associated with reactive systems; and subjects have three lectures per week, a weekly 2-h workshop
• inherently safe design. class and two laboratory classes during the semester. Each
semester includes 12 teaching weeks.
Since 2009 the class size for both subjects has ranged
As British philosopher and statesman Edmund Burke said between 70 and 140 students averaging around 100. The safety
in the 18th century, “Those who do not learn from history are case study presentation activities were conducted during the
destined to repeat it”. Many workers have suggested that the weekly 2-h workshops towards the end of each semester. The
use of case studies is an effective method to address some class was divided into separate workshops each of between 32
aspects of chemical engineering safety education. Saleh and and 38 students. Students within each workshop were then
Pendley (2012) propose an entire subject on chemical engineer- further divided into groups of three or four. The groups were
ing safety that relies in part on the use of case studies. Cortés not self-selected being assigned by the lecturer-in-charge.
et al. (2012) conducted a survey of Spanish safety engineering In Semester 1 half the groups were randomly assigned to
professionals and concluded that the best way to teach safety present on either a safety case study selected from the list of
in an undergraduate engineering course is via a standalone case studies in the next section of this paper, or on the man-
subject. None of the engineers surveyed however in that study ufacturing process of common products such as shampoo,
were chemical engineers. Ferjencik (2007) describe a subject transdermal patches or paints. In the next semester stu-
that has been successfully taught in the Czech Republic for dents were assigned to different groups with half the groups
many years that covers safety using case studies. assigned to either further safety case studies or a manu-
An equally strong argument can be made for integrating facturing process for the production of chemicals such as
chemical engineering safety across the chemical engineering benzene, formaldehyde or acetone. The students were typi-
curriculum. Rather than addressing safety in a single subject cally assigned their groups and topic in Weeks 7 or 8 of the
which is usually taught in either of the last 2 years of an under- 12-week semester with presentations occurring over a 2-week
graduate degree the safety topics can be covered in subjects period in during Weeks 10–12.
from the first to the final semester. While a core of safety Each student in the group was expected to talk for 4–5 min
material can be taught in a single subject together with other on an aspect of the safety incident within a seamless presen-
material relating to sustainability, ethics and other profes- tation that was well constructed. The groups were asked to
sional issues the use of carefully selected case studies allows answer three main questions:
many of the topics to be addressed in other units.
Safety case studies that present students with the real sit-
uations that have occurred that have resulted in either death, 1. “What happened? – Describe the nature of the accident
injury or at least property loss, are an excellent way to engage and the consequences in terms of fatalities, injuries and/or
students in learning. Case studies include well known inci- property loss”,
dents that occurred in Bhopal, Flixborough, Longford, Piper 2. “What was the cause of the accident? – Describe the failure
Alpha and Texas City. in either equipment, procedure or personnel that led to the
One method of using case studies in student learning is accident”, and
to present selected case studies in lectures taking time to 3. “What technical improvements are required to ensure that
highlight key points and the chain of events that led to the a similar accident will not occur again?”
disasters. This paper describes an alternative approach in
which groups of students prepare presentations for delivery The students made their presentation to the entire work-
to the class, each group looking at a different case study. This shop so that in any one 2-h session up to six groups could
approach not only allows students to learn more deeply about present their work. Students were assessed individually on the
one specific case study but it also helps to improve their com- content of their presentations as well as on their presentation
munication skills. skills.
e14 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

Students were also assigned a class mate for whom they • poor control room display
had to prepare a written critique of their presentation. The • poor maintenance procedures
critiques were to be 200–300 words. Students were given • poor general procedures
guidelines as to what to include in their critiques. Students • single point failure.
presenting in the first week of presentations were required
to critique students presenting in the second week and vice Six of the case studies relate to incidents that occurred
versa. While the critiques were not used to assess the stu- recovering from a process upset while eight occurred during
dents for whom they were written, they formed part of the or immediately after maintenance procedures (Table 1).
assessment for the students who prepared them. Several of the later case studies suggest that lessons from
Every student received feedback from the lecturer-in- early incidents have not been learned or remembered. These
charge via private e-mail and all presentations were recorded points can be made to the presenting students. As an example,
on video, allowing students to later download a record of their the control room at the Hypro plant in Flixborough was located
group’s presentation so that they might gain further feedback. in the middle of the process area. The control room was not
One of the teaching staff who was familiar with all the designed to withstand blast pressures and was destroyed in
case studies was always present when the presentations are the explosion killing everyone inside. Over 30 years later engi-
made by the student groups. Each group was given immedi- neers at BP’s refinery at Texas City located the portable office
ate feedback at the end of their presentation and any errors close to the process area. When an explosion occurred follow-
of fact were corrected to avoid the spreading of misinforma- ing a leak for the raffinate splitter tower 15 people working in
tion. Occasionally students missed some of the key points the potable offices were killed. The offices should never have
that should have been made out of the case studies and the been located so close to the process area, a lesson that should
opportunity was taken by the teaching staff to ensure that the have been learnt from the Flixborough lesson. By having the
key lessons that should be learnt from the case studies were student groups present these two case studies one after the
addressed. No attempt was made to assess student learning of other, similarities between the two events can be drawn to
the presentations in other elements of the subject assessment the class’ attention.
such as in the final end-of-semester exam. Included in the list of case studies are examples from
The topic of safety is integrated throughout the chemical other industries. The collapse of the walkway in the Kansas
engineering programs at Melbourne. This paper describes how City Hyatt Regency resulted from an ill-considered change to
it is assessed at the second year of the first cycle program. the confirmed construction plans. The capsize of the English
Channel Ferry, Herald of Free Enterprise, occurred because of
3. The case studies poor procedures and a lack of a safety culture within the ship’s
company. The crash of a passenger airliner in Canada in 1989
A good case study is one which has sufficient detail readily arose from allowing an aircraft to fly with one critical piece of
available to allow the students to understand the nature, equipment inoperable. The design of the wheels on Germany’s
causes and consequences of the incident. Also, there should fast trains was not fit-for-purpose and led to the derailment at
be little uncertainty or debate around the circumstances of the Eschede in 1998. Finally, the loss of the Russian Navy subma-
event. The case studies have been chosen so that students are rine Kursk occurred primarily because of the failure to carry
able to learn important lessons from the incident. The 27 case out the most basic of maintenance procedures on practice tor-
studies are summarized in Table 1. As well as drawing exam- pedoes – torpedoes that had not been checked in the 10 years
ples from the process industries the list also includes case since they were manufactured.
studies from the construction, maritime and transportation The case studies that follow are presented in chronological
industries. order.
The class is directed to important sources on information
on process safety incidents. These sources include: 3.1. Feyzin LPG explosion (January 1966)

A massive leakage of liquefied petroleum gas occurred during


• “Lees’ Loss Prevention in the Process Industries”, 3rd edi-
a non-routine operation to obtain a sample from a 1200 m3
tion published by Elsevier and available on-line through the
pressurised propane sphere (Kletz, 1999). The sphere was
Knovel resource
one of eight on the site in Feyzin, France used to store liq-
• Health and Safety Executive of the United Kingdom, the
uefied flammable gas. Operators needed to obtain a liquid
government agency that investigates industry mishaps –
sample from the storage tank as there was concern that the
www.hse.gov.uk
ethane content of the hydrocarbon mixture was too high. The
• U.S. Chemical Safety and Hazard Investigation Board, the
sampling points provided on the tank were inoperable so an
US federal government agency charged with investigating
unofficial but common practice was used in which the sam-
industrial chemical accidents – www.csb.gov
ples were collected through two drainage valves at the base of
the tank (Atheron and Gill, 2008a).
The underlying causes of the incidents covered in the
The liquid sample was to be drained from the base of the
selected case studies include:
sphere through two valves connected in series with the upper
valve connected to the sphere and the lower valve open to
• design not fit-for-purpose the atmosphere. When the sampling operation was nearly
• human factors complete the upper valve was closed and then cracked open
• lack of safety adequate training again. When no flow emerged from the cracked valve, probably
• lack of safety culture because of a blockage caused by ice, the upper valve was fully
• lack of understanding of hazards opened. The blockage immediately cleared and the propane
• lack of understanding of underlying process principles gushed out. The operator was unable to close either valve – the
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e15

Table 1 – Summary of safety case studies.


Incident Date Location Fatalities Following During/after
process maintenance
upset

LPG explosion 01/66 Feyzin, France 18


Hydrocarbon explosion 06/74 Flixborough, UK 28
Runaway reaction and gas release 07/76 Seveso, Italy 0
Road tanker crash and explosion 07/78 San Carlos de la Rapito, Spain 215
Radioactive gas release 03/79 Three Mile Island, US 0 X
Hyatt Regency walkway collapse 07/81 Kansas City, UK 114
Toxic gas release 12/84 Bhopal, India 4000+
Radioactive gas release 04/86 Chernobyl, Ukraine 31+ X
Ship capsize 03/87 Zeebrugge, Belgium 193
Refinery fire 03/87 Grangemouth, UK 2 X
Refinery explosion 03/87 Grangemouth, UK 1 X
Tank fire 03/87 Dalmeny, UK 1 X
Offshore platform fire and explosions 07/88 North Sea, UK 167 X
Jet airliner crash 03/89 Dryden, Canada 24
Refinery explosion 10/89 Pasadena, US 23 X
Runaway reaction and explosion 03/90 Stanslow, UK 1
Chemical store fire 07/92 Bradford, UK 0
Chemical storage tank fire 09/92 Castleford, UK 5 X
Refinery explosion and fire 07/94 Milford Haven, UK 0 X
Train derailment 06/98 Eschede, Germany 101
Gas plant explosion 09/98 Longford, Australia 2 X
Loss of nuclear submarine 04/00 Russia 118
Thermal decomposition 03/01 Augusta, US 3 X X
Refinery explosion 03/05 Texas City, US 15 X
Storage tank explosion 12/05 Buncefield, UK 0
Dust explosion 02/08 Port Wentworth, US 13
Heat exchanger rupture 06/08 Houston, US 1 X

handle came off the upper valve and the lower valve became 3.2. Flixborough explosion (June 1974)
frozen. A massive leak of LPG ensued with a vapour cloud 1 m
deep spreading over 150 m from the tank. The operators man- The caprolactam plant located in Flixborough, England, used
aged to leave the immediate vicinity of the tanks and to stop a process of the partial oxidation of cyclohexane to produce
traffic on a nearby road however the gas ignited and the stor- cyclohexanol and cyclohexanone as an intermediate product.
age sphere was engulfed in the fire that followed. The tank The cyclohexane was recirculated through six reactors linked
was on flat ground so that any propane that leaked from the in series. The six reactors were arranged so that each succes-
tank and that was not consumed immediately collected under sive reactor was at a lower height that the one before it. Thus
the tank to burn later. there was a considerable difference in height between the first
The fire fighters who arrived at the site were untrained and last reactors. Two months before the explosion a vertical
in dealing with LPG fires and they failed to cool the leaking crack was found in the fifth reactor.
sphere, instead concentrating their efforts on cooling the other The decision was taken to remove the reactor and to con-
seven sphere. The sphere was fitted with a full water deluge nect a replacement bypass line between the fourth and sixth
system but it was capable of delivering only half the amount of reactors that spanned the gap between the missing reactor.
water that was actually required. Ten fire fighters were killed Because the inlet and outlet points of this bypass line were
in the fire that ensued when the first tank failed. As the inci- at different heights the final bypass assembly contained two
dent ran its course four additional spheres failed and 18 people 90◦ bends in the pipe in close proximity to one another. The
were killed with 81 others injured (Mannan, 2005a; HSE, 2010a). bypass line also included two bellows sections. The bypass
The accident occurred because an operator allowed the pipe assembly was supported on temporary scaffolding. The
two discharge valves to be open simultaneously. The conse- bypass line ruptured releasing cyclohexane which formed a
quences of these actions were foreseeable. vapour cloud low to the ground. When the flammable mixture
Important lessons that may be learned from the Feyzin encountered an ignition source a massive explosion followed
disaster include: killing 28 workers and injuring 36. It has been suggested that
the leak may have been caused in some way by a fire on a
• all procedures need to be carefully planned and the subject nearby pipe which had been burning for some time prior to
of safety analyses; the explosion others (Mannan, 2005b; Khan and Abbasi, 1999;
• remotely controlled isolation valves need to be fitted to all Venart, 2007).
such storage tanks; All 18 workers present within the control room at the
• provide an adequate water deluge system; time of the explosion were killed when the room collapsed.
• the ground should slope away from storage tanks to prevent The control room had been located within the process area
the collection of spilled liquids under and around the tanks; of the plant and had not been designed to withstand the
• insulate the tanks with some form of fire-resistant insula- overpressure which accompanied the explosion. The main
tion to help prevent tanks from heating rapidly in the event administration building was also destroyed but because the
of a nearby fire. incident occurred on a Saturday the building was empty.
e16 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

Indeed the loss of life could have been much higher if the Several lessons can be learnt from the Seveso disaster
explosion had not have occurred during the weekend. (Mannan, 2005c):
An inquiry held to investigate the incident found that insuf-
ficient design calculations had been performed for the bypass • accepted operating procedures should never be modified
line (Parker, 1975). The works engineer had left the company without careful consideration of all the consequences;
earlier in the year before the bypass line had been installed • chemical reaction vessels should be designed to vent safely
and there was no engineer left on site who had the neces- to a flare rather than directly to the environment;
sary mechanical engineering design skills to properly design • companies and local governmental authorities should be
the bypass line. In the event the bypass line was designed by ready to respond to emergencies such as the accidental gas
chemical engineers working outside their area of competence. leak as occurred at Seveso.
The limited calculations that were made in designing the
bypass did not account for the stresses or bending moments 3.4. Road tanker explosion at San Carlos de la Rapita,
that would be present within the two 90◦ bends. The enquiry Spain (July 1978)
also noted that after a crack had been found in the fifth reac-
tor no inspections were ever made on the other five reactors A road tanker was filled with a load of liquid propylene for the
to determine whether similar cracks existed in those reactors journey from a refinery in Tarragona on the Spanish coast to
(Parker, 1975). a customer in the centre of Spain. While travelling through
Key lessons learned from the Flixborough disaster include: the coastal town of San Carlos de la Rapita between Valencia
and Barcelona the tanker ruptured beside a popular camp-
ing ground releasing the propylene into the atmosphere. The
• locating control rooms away from the process areas and
hydrocarbon cloud ignited and the resulting explosion killed
designing them to withstand explosion overpressures – this
215 people including the driver (Mannan, 2005d).
also included the elimination of windows from control room
No facility was available at the refinery where the tanker
design;
was filled to measure the actual tanker load. It was only once
• engineers should only work and sign off on design in their
the tanker had left the filling station that the load could actu-
area of competence.
ally be measured. On occasions when the tanker was overfilled
the excess could be burnt off. On the day of the accident the
3.3. Seveso gas release (July 1976) road tanker was overfilled to 23½ tonnes even though it had a
maximum rated capacity of only 19 tonnes. Neither the driver
A toxic gas release near the town of Seveso in Italy in 1976 nor any of the refinery workers aware of this situation took
precipitated a Europe-wide directive aimed at improving the any action. The driver then departed on his trip.
safety of sites holding large quantities of dangerous chemi- The driver had been instructed to take a tolled dual car-
cals. While no deaths could be directly and conclusively linked riageway which would keep the tanker away from more
to the release of the gas many suffered from ill-effects includ- populated areas and which was a relatively safer route to take.
ing sever chloracne (Mannan, 2005c). However on his way to his destination the driver decided to
The production of 2,4,5-trichlorophenol (TCP) at the Icmesa take a coastal road which wound through the middle of sev-
Chemical Company facility near Seveso was a two-stage eral towns. As he had been given the money for the tolls this
batch process. In the first stage 1,2,4,5-tetrachlorobenzene allowed him to pocket the unspent toll charges.
was reacted with sodium hydroxide in the presence of eth- While it remains unclear what the exact mechanism was
ylene glycol at a temperature of between 170 and 180 ◦ C to for the rupturing of the tank what is clear was that the tanker
produce 2,4,5-sodium trichlorophenate. Approximately half was overloaded and unsafe. Key lessons that may be learnt
of the ethylene glycol was then drained off before the sec- from this incident include (Mannan, 2005d):
ond stage commenced in which the phenate was reacted with
hydrochloric acid to produce TCP. • the importance of equipment, procedures and training to
At the time of the accident Italian law required that the prevent overfilling of tankers;
plant be closed over the weekends requiring all the processes • the need for pressure relief systems on vehicles carrying
within the facility to be shutdown before Friday evening. On flammable materials;
Friday July 8, 1976 as the plant was being shutdown for the • the importance of keeping tankers away from populated
weekend the first stage of batch process had just concluded. areas;
The operators drained off some 15% of the ethylene glycol in • the importance of human factors in the operation of any
the reactor and then secured the process. This was counter to procedure.
the company guidelines which required at least 50% of the gly-
col solution to be drained off before the contents of the reactor 3.5. Radioactive release at Three Mile Island (March
could be considered stable. Power to the reactor was switched 1979)
off and with the facility shutdown, the facility was left unat-
tended. Over the Friday night the temperature in the reactor The Three Mile Island nuclear power plant consisted of two
rose to around 300 ◦ C (Kletz, 2009). Just after noon on the Satur- pressurised water reactors. When a turbine tripped out, opera-
day bursting disk on the reactor failed releasing a cloud of toxic tors monitoring the system became confused by contradictory
gas containing dioxins into the environment. The response information that was erroneously displayed in the control
of local authorities was slow and subject to much criticism room. In seeking to recover from the process upset they took
following the incident. incorrect action which resulted in loss of water within the core.
At the time the facility had been built the site was away This in turn caused a partial meltdown of core and a hydro-
from populated areas but over time houses began to encroach gen explosion that released reactivity into the main building
into the vicinity of the facility. (Mannan, 2005e).
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e17

Some time before the actual incident, in an effort to clear crowded with people. Both walkways fell to the ground killing
a blockage in a process air line operators connected up the 114 and injuring more than 200 others. At the time of the
process air line to an instrument air line. Because the pres- accident the hotel had only been open for a year (Petroski,
sure in the process air line was significantly higher than the 1992).
instrument air line, air with some condensed water entered Plans called for the atrium at the new Kansas City Hyatt
the instrument air line despite the presence of a non-return Regency Hotel to be spanned by three walkways. Each walkway
valve on that line. Some hours later the water that had passed was to be suspended from the ceiling by long bolts that would
into the instrument air line system caused isolation valves on take the weight of the walkway. Because two of the walkways
the condensate polishing system to close. Within seconds a were to be located so that one would be directly above the
series of other equipment tripped until finally the main tur- other the engineers decided to use the same very long bolts
bine tripped out. The reactor began to shutdown however one to support both of the walkways. Each threaded bolt was to be
critical valve did not shut despite being sent the proper com- over 5 m in length. Nuts would be screwed onto the bolts and
mand to shut. Unfortunately, displayed to the operators was then the walkways would essentially be supported by resting
not the actual state of the valve but instead the instruction on the nuts. Calculations showed that the correctly positioned
that had been sent to the valve. Thus, although the valve was nuts would be more than able to support the weight of each
still wide open, the display in the control room indicated that of the walkways.
the valve was shut because this was the instruction that had Just before the walkways were to be installed the builder
been sent to it. Another key parameter displayed on one of approached the engineers with a request for the bolts to be
the panels in the control room was the height of water within re-designed. Rather than use the series of long bolts they pro-
the reactor cooling system. However it was the mass of water posed that two series of bolts be used. The higher of the two
present in the cooling system that was the critical parameter walkways would be suspended from the ceiling using one set
to monitor, not the water level. Because the water contained of bolts while the lower walkway would be suspended from
steam bubbles the fluid was less dense meaning that the liq- the upper walkway above it using a second series of long bolts.
uid level over-indicated the mass of liquid water available for Again, nuts correctly positions on each series of bolts would
cooling. take the weight of the walkways.
As well as being misinformed about the state of two criti- The engineer-in-charge of the walkway approved this, what
cal parameters at one point the operators had over 100 alarms appeared to be minor, amendment and construction started.
sounding on a system which did not prioritise the importance In giving his approval the engineer conducted no calculations
of the many alarms. The operators on duty in the control on the new design, assuming that the change was so minor
room were overwhelmed by the many alarms and were tricked that the design had not changed in any significant manner.
into incorrectly responding to the situation by the two incor- What the engineer failed to appreciate was that the bolts
rect pieces of information displayed in the control room. They supporting the upper walkway from the upper series of bolts
allowed the water levels within the reactor to fall to an unsafe suspended from the ceiling were also supporting the weight of
level, exposing part of the core. A steam-zirconium reaction the lower walkway as well. These bolts and the walkway struc-
then occurred which generated hydrogen which later was ture where they were attached were not designed to support
vented into the containment building. This hydrogen later what was essentially a double load. Under the stress of two
exploded within the building. fully loaded walkways the nuts failed causing the walkways
Some of the key lessons that may be learned from the Three to collapse.
Mile Island incident include: During construction of the walkways the labourers on the
site had noted excessive movement of these two walkways
• the importance of showing in the control room the key compared to the properly installed single walkway but no one
parameters that have been measured directed and which thought to draw the movement to the attention of any of the
are only inferred; engineers. The engineer who signed off on the design change
• the importance of displaying information in a logical and without adequate checking of the new designs lost his licence
clear manner which does not overwhelm the operators to practice as an engineer.
particular in an emergency when multiple alarms may be Lessons that may be learnt from this example from civil
sounding; engineering include:
• emergency training had centred around the failure of major
components of items of equipment rather than in consid- • the importance of checking all design calculations when-
ering how to respond to the more-likely failure of minor ever any design change is made, even if it appears to be
equipment items; minor;
• the need to learn from past mistakes which had not previ- • the need to encourage all staff to report any incident or
ously occurred at Three Mile Island; occurrence that appears out of the ordinary.
• an appreciation that non-return valves are not designed to
be completely watertight but rather to stop the bulk flow of 3.7. Bhopal toxic gas release (December 1984)
liquid in the undesired direction;
• instrument air should never be interconnected with process In the early 1980s Union Carbide began producing pesticides
air (Mannan, 2005e). for the Indian market in a plant in Bhopal. Monomethylamine
was reacted with phosgene to produce methylisocyanate (MIC)
3.6. Kansas City Hyatt Regency walkway collapse (July as an intermediate which was then in turn used to produce
1981) the carbonate pesticides. Initially the MIC was imported from
the US so three 57 cubic metre tanks were used to store the
A crowded elevated walkway spanning a hotel atrium in MIC until required. Later MIC was manufactured on the site
Kansas City collapsed onto another lower walkway also and the need for the tanks disappeared. They remained in
e18 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

service however. Since methylisocyanate is highly toxic the place that would cause the reactor to shutdown immediately
plant included a vent gas scrubber and a flare so that in an should any one of a range of different conditions exist.
emergency the MIC would be safely destroyed (Mannan, 2005f). The power station control systems drew their power from
Early is the morning on December 3, 1984 some 500–800 L the external power grid. In the event of an outage back-up
of water invaded one of the tanks storing the MIC. The water diesel-powered generators were available as a back-up power
reacted with the MIC exothermically to produce elevated tem- supply but at that time in the Soviet Union the only gen-
peratures and increased pressures due to the production of erators available would take at least a minute to start-up in
carbon dioxide. Chloroform that was also present attacked the an emergency. The engineers of the power station therefore
iron in the structure which in turn catalysed the trimerization decided to test whether the turbines that were spinning down
of the MIC leading to the further release of heat. The pres- in response to an emergency shutdown might still provide suf-
sure relief valve finally lifted venting the MIC from the tank. ficient power to safely control the reactors and their associated
The vent gas scrubber had been decommissioned sometime systems. The engineers and operators carefully prepared a test
before the incident and the flare stack was out of service due that would simulate an emergency shutdown. As part of the
to a maintenance issue. As a result the MIC, a toxic gas that approved sequence of events that had been agreed by all par-
causes asphyxiation within the lungs, was released directly ticipants part of the reactor’s safety systems would be disabled
into the atmosphere. For over 2 h the gas was vented and so that the reactor would not shutdown automatically.
drifted over the shanty town that had grown up around the While the test was planned for the middle of the day it
plant over the previous decade. Thousands died that morning was delayed until after midnight so that the reactor could be
and many more died over the next decade. taken off-line during a period of low load. Most of the senior
The exact cause of the water entering the MIC tank has engineers had gone home leaving the test to be conducted by
never been established beyond doubt. Two theories have the most junior engineers. As the test progressed the engi-
emerged: neers found that they had to take action disabling more of the
reactor’s safety system than was included in the agreed test
1) water that was being used to flush some of the process lines procedure. This was done in order to ensure that the reactor
leaked into the wrong area of the plant and then made its did not shutdown prematurely.
way into the tank; or, In the early morning of April 26, 1986 the engineers oper-
2) a disgruntled employee may have admitted some water ating the reactor lost control of it. Power output dropped to as
into the tank not fully realizing the consequences of their low as 3% of rated output and then spiked at around 100 times
actions. the rated output. Water in the reactor quickly flashed into
steam which caused the pressure tubes to fail catastrophically.
The exposed zirconium reacted with the steam to produce
The entire process for the production of the pesticides was
hydrogen which accumulated within the containing building.
not inherently safe. Other processing routes were available
When the hydrogen exploded debris was injected into the air
that could have been used to produce the pesticides without
as the containment building failed. In the aftermath at least
using MIC as an intermediate. Moreover, there was no need
31 people died as a release of the radiation but many more
to store as much MIC on the site as was present that early
may have died.
morning in December, 1984.
Key lessons learned from the Chernobyl explosions and
Key lessons learned from Bhopal include (Mannan, 2005f):
fires include (Mannan, 2005g):

• the need to consider the continued operation of a processing • the power station had a poor safety culture as evidenced by
facility which is surrounded by a shanty town with a popu- the decision to run a dangerous test on an operating reactor;
lation of many thousands; • it should have been impossible for the engineers to disable
• the need to shutdown a process when key safety equipment the reactor’s safety features both physically and psycholog-
is taken off-line for maintenance; ically;
• the importance of considering whether dangerous or toxic • a procedure that had been agreed to by all the key
chemicals may be substituted by less harmful substances stakeholders was changed without proper thought to the
within a process; consequences;
• the need to keep inventories of dangerous chemicals as low • junior engineers should never be tasked to perform
as possible. potentially dangerous activities when more experienced
engineers are available.
3.8. Chernobyl explosion and radioactivity release
(April 1986) 3.9. Herald of Free Enterprise capsize (March 1987)

One of the world’s worst nuclear disasters was not caused A set of poor regulations that was rarely enforced was the root
by any mechanical or equipment failure but instead occurred cause for the capsize of the passenger and vehicle ferry Her-
because the engineers on site deliberately disabled a series of ald of Free Enterprise outside the Belgium port of Zeebrugge.
safety systems in order to conduct a safety experiment on one Before the advent of the rail link under the English Channel,
of the operating reactors (Mannan, 2005g). ferries such as the Herald of Free Enterprise and its two sister
The Chernobyl power station comprised four water-cooled ships operated across the waterway. The ferry carried cars,
but graphite-moderated reactors each of which powered two trucks and walk-on passenger usually between Dover and
turbines. A feature of this type of reactor is that they are very Calais with occasional runs between Dover and Zeebrugge.
unstable at low power outputs and they are required to be The ship had eight main decks, two of which were the two
always operated above 20% of rated output. The reactor system main vehicle decks with doors at either end of the ship. These
was designed with a number of different safety systems in through decks, completely open and without bulkheads along
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e19

their length, permitted cars and trucks to drive on and off culture of safety and lack of appropriate and fit-for-purpose
quickly. Ramps between the dock and the ship allowed vehicle procedures that allowed the Herald of Free Enterprise to cap-
access to the ship. size.
On the night of March 6, 1987 the ship was loading vehicles
in the port of Zeebrugge for the crossing to Dover. Because of 3.10. Fire at BP Grangemouth Refinery (March 1987)
the high spring tide the ship was riding higher relative to the
dock than normal and so the captain was forced to take on Two separate accidents occurred at the BP Oil Refinery at
ballast water so as to trim the ship forward, i.e., the ship was Grangemouth in Scotland in March 1987. The first of these
in a bow down configuration. occurred on March 13 when a valve on a 760 mm diameter
At the conclusion of the loading process and immediately flare line was being removed for servicing. The line was still
prior to sailing it was the duty of the assistant bosun of the under pressure when the last bolts were removed allowing an
ship to ensure that the watertight doors on the bow of the estimated 20,000 L of hydrocarbon liquid to escape. The liq-
ship were closed before the ship sailed. On this occasion the uid vapourised and the hydrocarbon cloud was quickly ignited
bosun had fallen asleep in his quarters and was not on deck to by a nearby generator. Two contractors working on the valve
perform this and his other duties. No one noticed his absence. replacement job were killed while another two were seriously
The ship’s Standing Orders stated that at the time of sailing it injured (HSE, 1988).
was the responsibility of each section manager to notify the The refinery had three separate flares that could be used
captain in the event of any matter which might delay sailing on to safely flare gases from throughout the refinery. One of the
time. If the captain did not receive any reports then he was to valves in the flare system was found to not be closing prop-
assume that the ship was ready to sail. With the bosun absent erly and it decided that it should be removed, serviced and
from his post he was unable to report that the bow doors were then refitted at the earliest opportunity. Action was taken to
not closed. It was not part of the ship’s regular procedure to isolate the pipework on either side of the valve to be serviced.
confirm that the doors were closed. The Chief Officer was the It was important that the valve was completely isolated as
last to leave the main deck and left assuming the bosun would the refinery was to continue to operate during the mainte-
shortly arrive to close the doors. nance procedure. Workers closing one of the isolation valves
On the ship’s bridge the captain was under pressure from believed that it was completely closed when they were unable
the company to depart on time. As there were no indicators to turn the valve wheel any further even with the application
on the ship’s bridge that the bow and stern doors were closed of valve wheel keys. The maintenance workers ignored the
and sealed, the captain assumed that with no reports to the fact that between 75 and 100 mm of valve spindle protruded
contrary, the ship was ready to sail. The ship cleared the dock from the valve body, possibly indicating that the valve was
and then sailed across the shallow inner harbour. Once clear not completely closed. In fact, scale in the line had jammed
of the breakwater the ship rapidly accelerated. As it did so the in the valve body preventing the valve gate from completely
bow wave swept into the open doors flooding the lower car closing. Consequently the flare line remained pressurised. The
deck. The ship rolled to port and capsized less than a minute supervisor checked the pressure gauge on a nearby knock-out
later. The ship sank with the loss of 193 passengers and crew. drum and took its low reading to indicate that the line was
The incident and its causes were investigated by a British unpressurised. He could have checked the pressure at a further
enquiry in late-1987 (Marine Accident Investigation Board, location but did not.
1987). The enquiry found that there was a lack of an adequate Because it was accepted that the line would contain some
safety culture throughout the company that owned and oper- residual hydrocarbon gas the maintenance workers remov-
ated the ships. Requests for indicators that would display on ing the valve were required to wear breathing apparatus. It
the bridge the condition of the doors (i.e., whether opened was assumed however that the amount of residual hydrocar-
or closed) were denied by the owners as being wholly un- bon in the line would not be sufficient to pose a threat to the
necessary. Other concerns including the frequent overloading workers.
of the ships went unacknowledged by management. As the valve was elevated a scaffolding platform was built
On a ship such as the Herald of Free Enterprise, the Ship’s to allow the maintenance team to access the valve. Access to
Standing Orders, the set of procedures and divisions of respon- the platform was via a single ladder and workers had to climb
sibilities for the operation of the ship when at sea or in port around the valve to reach it from the far side of the platform.
made no mention of the requirement to close the bow and As the bolts were removed work was stopped by the team
stern doors prior to departure. when gas and liquid began to escape from the gap between
Key lessons that may be learned from the loss of the ship the valve flanges. It was only resumed when the workers were
include: reassured that the amount of hydrocarbon that could escape
was trivial.
• the need for clear instructions for all procedures and a clear When the final bolt was removed liquid flooded out of the
understanding of the division of responsibilities; open pipe generating a hazardous vapour cloud. Two contrac-
• the need for a reporting process that does not assume that tors managed to escape down the ladder but the other two
if no report is received that everything is ready to proceed; were unable to reach the ladder. Their bodies were recovered
• management must take seriously all safety concerns raised from the platform and the foot of the ladder (HSE, 1988).
by staff and must respond appropriately; Key lessons that may be learned from this maintenance-
• an appropriate safety culture must reach to all levels related incident include:
throughout an organization including the company direc-
tors.
• the need for a clear procedure for isolating the pipe sec-
While the loss of the ship was precipitated by the autho- tion and a series of tests that could and should have been
rised absence of the assistant bosun it was the ship’s poor conducted to ensure that the line was free of hydrocarbons;
e20 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

• the need for some form of indication on valves to show • pressure relief systems able to deal with the maximum
operators whether the valve is open or closed; anticipated gas flow rates should be installed on all pressure
• the need for all workers to have unobstructed emergency vessels;
evacuation routes even from temporary structures such as • data should be presented to control room staff in clear and
scaffolding platforms; unambiguous ways;
• all potential sources of ignition should be carefully consid- • the operation of control units should be consistent within a
ered and located appropriately when hydrocarbons might control room.
be exposed to the atmosphere.
3.12. Storage tank fire at Dalmeny Oil Storage Terminal
(June 1987)
3.11. Hydrocracker explosion at BP Grangemouth
Refinery (March 1987) The Dalmeny Oil Storage Terminal in Scotland consisted of 10
large tanks, three for the storage of ballast water and seven
This was the second of two fatal accidents that occurred at the identically size, floating roof tanks used for the storage of
BP Oil (Grangemouth) refinery in the space of 10 days in March crude oil. The seven tanks were all 78 m in diameter, 18 m in
1987. The hydrocracker unit had been shutdown for 8 days for height with a capacity of 81,000 m3 . In early 1987 it was found
repair work. Only a few hours after it had been re-started the that the bottom of one of the tanks contained approximately
unit tripped out, triggered by a reading of an excessively high 1000 tonnes of a thick sludge, unevenly distributed across the
temperature in the unit. The operators quickly established base of the tank. The decision was made to take the tank off-
that the single temperature reading that shutdown the plant line and then to clean the sludge out. This would be done by
was erroneous and that the plant had been operating nor- sending workers into the tank (HSE, 1988).
mally. The hydrocracker unit re-start procedure required that A contracting company with experience in cleaning sludge
the operators wait for the arrival of the hydrocracker supervi- from oil tanks was engaged. The tank was emptied of crude
sor before re-starting the unit. As it was very early on Sunday oil and then the tank covers were opened allowing air to enter
morning the operators had to wait for several hours for the the tank. The workers were provided with breathing apparatus
supervisor to arrive (HSE, 1988). for use whenever they were in the tank. The face masks were
Without warning at 7 am there was a violent explosion on supplied with air via air lines from an air source outside the
the site centred on a low pressure separator. The unit blew tank. The workers used hand tools to push the sludge towards
apart with the fractures triggered by severe over-pressuring of the open end of a 100 mm diameter pipeline that carried the
the unit. The force of the explosion threw a 3 tonnes fragment sludge out of the tank. The contractors worked in teams of
of the separator a kilometre away. The explosion and following four with three working inside the tank and one man standing
fires left one contractor dead. outside.
The separator became over-pressured when the liquid level Just after noon on June 11, 1987 the man outside the tank
in the adjacent high pressure separator dropped to such a level saw a pale blue flame surrounding the three workers inside
that the high pressure gases were able to leak to the low pres- the tank and called for them to evacuate immediately. Two of
sure separator. Liquid low level alarms on the high pressure the workers escaped but one did not, possibly tripping on his
separator had been disconnected some time before the inci- air hose. He died in the subsequent fire that engulfed the tank.
dent and it is possible that the operators were unaware how During the fire the tank did not fail and the conflagration was
low the liquid level in the high pressure separator had fallen. safely contained.
Some of the level indicators frequent gave wrong values and After the fire one of the men who had been working inside
so were not always trusted by the operators. On one of the the tank admitted to having been smoking inside the tank
chart traces used to show the liquid level the trace had been and to throwing his cigarette butt onto the floor of the tank.
offset by 10%. This meant that the trace showed a value of He did not appreciate the seriousness of this action at the
12% when the liquid level had actually fallen to just 2%. At time as he and others had previously been smoking within the
least one operator was unaware of this critical issue and so tank during the work. The workers also admitted to frequently
completely misjudged the height of liquid within the separa- removing their breathing masks as they claimed to have got-
tor. ten used to the smell within the tank and found it easier to see.
The set points on the controllers used in the plant were The workers made sure that they always wore their breathing
manipulated by turning thumbwheels. The controller used to masks when entering and leaving the tanks so as not to get
control the liquid level in the separator had a thumbwheel into trouble for breaking safety rules. It was impossible for
that turned in the opposite direction to many of the other anyone outside the tank to see any transgressions occurring
controllers in the control room. Investigators considered that within the tank.
an operator may inadvertently turned the thumbwheel in the While it appears that the workers did not undertake for-
wrong direction causing a valve connecting the high pressure mal safety training on site they admitted to being well aware
separator to the low pressure separator to open inappropri- of the rules relating to the banning of smoking, the banning
ately. The sudden over-pressuring caused the low pressure of carrying cigarettes, matches and lighters onto the site and
separator to fail catastrophically. the wearing of safety masks at all times within the site. How-
Important lessons that can be drawn from this incident ever within the contractor’s workers these rules were regularly
include (HSE, 1988): flouted.
Investigators concluded that there was a poor safety cul-
ture on the site at the time of the accident. The safety training
• alarm system should never be disconnected without a full was not enforced and the workers were not fully informed of
and comprehensive review of the safety of potential conse- the reasons for the safety rules being in place. Management
quences; could also have reduced the risks of an incident by using a
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e21

mechanical extraction system to help ventilate the tank prior • the need for adequate safety management systems.
to the maintenance operation.
Key lessons that may be learned from this fire include: 3.14. Crash of Air Ontario Flight 1363 at Dryden
Airport (March 1989)
• the importance of safety training including drills in evacu-
ating from the tank in an emergency; On March 10, 1989 Air Ontario Flight 1363 failed to gain suf-
• the need to reinforce safety every day amongst the work- ficient height to clear a group of trees beyond the end of the
force; runway at Dryden Airport in Canada and crashed killing 24
of the 69 passengers and crew on board. The Fokker F-28
regional jet aircraft with two tail-mounted engines was piloted
3.13. Loss of Piper Alpha platform (July 1988)
by an experienced captain. The plane failed to gain height
because the wings were covered with snow which severally
Piper Alpha was an offshore oil platform in the North Sea off
disrupted the ability of wings to generate sufficient lift. The
the Scottish Coast. As well as producing oil and gas from its
pilot had decided to takeoff without de-icing the plane’s wings
own wells it served as a transfer station for at least two other
(Moshansky, 1992).
oil platforms further out to sea. On July 6, 1988 one of two
On the day of the accident the auxiliary power unit on
hydrocarbon condensate pumps, pump A, was taken out of
board the aircraft was inoperable. This unit provided com-
service for routine maintenance. Pump B was started to take
pressed air and electrical power to different systems on the
over the duty of pump A. As the maintenance work would take
aircraft while the aircraft was on the ground. The unit was also
several days the decision was taken to use the opportunity
needed to start the engines when other power was unavail-
to test and calibrate a pressure relief valve on the discharge
able at an airfield. The auxiliary power unit on this particular
side of the pump. The valve was removed from the pump and
unit had a recent history of operational problems which the
replaced with a blind flange that was not tightened down. At
maintenance department had tried to rectify during the rel-
the end of the shift the recertification task on the pressure
atively short periods between scheduled flights. The decision
relief valve was incomplete and the decision was taken to
was taken to defer the correction of the persistent problems
complete the task the next day. At shift change the fact that
with the unit until the aircraft reached the maintenance base
the task was incomplete and that the blind flange was not
at Toronto after it had completed several more flights.
properly secured was not communicated to the supervisors
The airline released the pilot to fly the aircraft from Thun-
(Atheron and Gill, 2008b; Paté-Cornell, 1993).
der Bay to Winnipeg via Dryden with the auxiliary power unit
At 9:50 pm pump B tripped out and could not be re-started.
inoperable on the condition that the pilot would not shutdown
The decision was then taken to put pump A back into service.
both engines at Dryden. Keeping one engine running while on
All that had been done towards the maintenance task was
the ground would allow the other engine to be re-started for
to electrically isolate the pump. The pump was re-connected
takeoff.
and started up. Operators were unaware due to a failure of the
On arrival at Dryden several passengers disembarked while
permit-to-work system that the pressure relief valve was not
other passengers joined the flight to Winnipeg. While on the
in place and that the blind flange was not properly secured.
ground the plane was re-fuelled with one engine kept run-
Immediately the pump was started condensate leaked from
ning at all times. The flight had arrived late into Dryden and
the loose flange and ignited. The room in which the pumps
there was pressure on the pilot to takeoff from Dryden as
were located was designed to be fire proof but not explosion
soon as practicable. At the time the plane landed at Dryden
proof. The resulting explosion generated shrapnel and severed
a light snow shower set in covering the runway and aircraft
oil lines resulting in further fires and explosions.
with snow.
The Tartan and Claymore platforms continued to send oil
It is well known that accumulated snow on the wings of
and gas to the platform after the explosions on board Piper
an aircraft can significantly adversely affect the ability of the
Alpha. They were unaware of any problems. Twenty minutes
wings to generate lift. The snow disrupts the flow of air over
after the first explosion the riser carrying natural gas from the
the wing. De-icing is a normal procedure at airports subject
Tartan platform failed resulting in a massive explosion. This
to snow. The snow and ice on the wings and fuselage may be
was followed later by the failure of a second riser giving rise
removed either by mechanical methods such as scraping or by
to the third massive explosion within 30 min.
the use of chemicals such as glycols which lower the freezing
The emergency fire water system failed. Staff on board the
point of water.
platform were directed to wait within the accommodation
The operating manual for the Fokker jet aircraft expressly
block for helicopter rescue however due to the fires, explo-
prohibited any de-icing of the aircraft while an engine was
sions and heavy black smoke it was impossible for helicopters
running. The pilot in command of the aircraft was therefore
to safely reach the platform. Sixty-two escaped from the plat-
faced with a dilemma – shutdown the running engine to allow
form but 167 died. By morning the entire platform was lost.
the plane to be de-iced but stranding the aircraft at the airport
While the root cause of the disaster was traced to a faulty
as the engines could not then be re-started for takeoff.
permit-to-work system further issues relating to safety train-
The pilot elected to takeoff without de-icing the aircraft. An
ing and safety management were identified by an enquiry
experienced pilot travelling on board the aircraft observed the
established after the event. The event is summarized by Cullen
amount of ice on the wing and made the judgment that the
(1990) and Mannan (2005h).
wings needed to be de-iced. When the pilot positioned the air-
Key lessons learned from the Pipe Alpha disaster include:
craft at the threshold of the runway for takeoff the passenger
pilot did not express his concern to anyone as he did not wish
• the importance of an adequate permit-to-work system that to interfere the command decisions of the pilot in command.
cross-references related tasks; The subsequent investigation established that there was
• the need for safety training of all staff including contractors; too much snow on the wings to allow the aircraft to gain
e22 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

altitude and that the pilot erred in not having the plane indicators on the air lines to signify which air line connected
de-iced. Neither the pilot nor co-pilot were able to participate to which connection port.
in the investigation as both had been killed in the crash. Key lessons learned from the Phillips 66 disaster include:
Lessons that may be learned from this aircraft crash
include (Moshansky, 1992): • valves should always have external indicators on them clear
show whether they are open or closed;
• never dispatch an aircraft with an inoperable auxiliary • valve connectors should be designed so that they cannot
power unit; be inadvertently mis-connected particularly where such an
• the importance of training pilots (and operators) that safety error would result in a catastrophic situation;
always comes first in any situation; • if a simple mistake can be made by any person in a process
• the need for professional to speak up when they see a poten- then eventually that mistake will be made.
tial dangerous situation arise.
3.16. Shell Stanslow Refinery explosion (March 1990)
3.15. Explosion at Phillips 66 complex at Pasadena
(October 1989) A chemical reactor at the Shell Stanlow fluoroaromatics
plant exploded in March 1990 just after it had been charged
The Phillips 66 Company manufactured high-density (Mannan, 2005j). Operators in the control room watched as the
polyethylene in its Pasadena, Texas plant. In the plant contents of the reactor were heated to 165 ◦ C as normal. How-
ethylene gas was dissolved in isobutane inside long tubular ever instead of stabilising the temperature continued to rise
reactors. Under elevated temperatures and pressures the eth- beyond 170 ◦ C. The reaction vessel began to vent gas and the
ylene polymerized to produce polyethylene. Other chemicals operators began to cool the reactor in an effort to control the
were added to the process to modify the exact composition situation. At the time they were unaware that the pressure had
of the polymer to ensure that the final product had the reached in excess of 6 MPa compared to the normal operating
desired characteristics. The polyethylene was formed as pressure of 500 kPa. The reaction vessel finally failed cata-
particles within the reactor, collecting in settling legs located strophically generating a large fireball which in turn sparked
along the length of the pipe reactor. In normal operation the of other fired around the facility. One person was killed as a
polyethylene granules would be collected by closing a large result of the event with five others injured.
ball valve at the top of the settling leg where it joined the Investigators later determined that water had entered the
reactor loop. Another valve at the base of the settling leg reactor earlier in the process initiating a series of reactions
would then be opened and the granules would be dumped for that resulted in the generation of acetic acid. The acid reacted
collection. With the lower valve closed again the upper ball vigorously with the initial contents of the reactor leading to
valve would be opened and the settling leg would begin to the runaway reaction.
fill with particles. At no time should both the upper or lower At the time of the incident the operators were unaware of
valves in a settling leg be open together as the contents of the the real extent of the problem. Their instrumentation only told
reactor under high temperature and pressure would vent to them that the reactor contents were above the desired tem-
the atmosphere (Bethea, 2003). perature. The data display units in the control room did not
In October 1989 one the settling legs became blocked and display the reaction vessel pressure and so they were unaware
the granules would not dump to the collection point. Nor- of the rapid over-pressuring of the vessel. They were only
mal maintenance procedures for the plant were followed and alerted to the possibility of a runaway reaction when an oper-
work started clearing the blocked settling leg while the tubu- ator outside the control room actually observed the venting
lar reactor continued to operate. Because there was no way on and entered the control room to advise the staff there of the
the ball valve itself to identify whether the valve was open or situation. The pressure that built up within the reaction vessel
closed operators queried the control room staff who advised significantly exceeded the pressure relief valve setting indicat-
them that the indicator showed the valve as closed. The air ing that the relief system was overwhelmed by the amount of
lines controlling the valve were disconnected and work com- gas generated within the reaction vessel.
menced to release the blocked settling leg through the open Key lessons learned from this incident include (Mannan,
lower valve. At some point the air lines were re-connected to 2005j):
the control valve while the maintenance job continued. This
was clearly against company maintenance policy. However, • vital process information must always be available to oper-
in re-connecting the air lines they were connected the wrong ators;
way around so that the valve position indicator in the control • the pressure relief system should have been sized to cope
room showed that the valve was open when it was in real- with such an emergency.
ity closed. At some point the upper control valve was opened
while the lower valve was still open and over 38½ tonnes 3.17. Allied Colloids fire (July 1992)
of ethylene, isobutene, hexane and hydrogen escaped to the
atmosphere. The released gas was ignited less than 2 min after A fire broke out in a chemical store at the Allied Colloids chem-
the leak started and the resulting explosion devastated the ical plant just outside Bradford in the United Kingdom. Two
area. Two further massive explosions occurred in the next chemicals which should never have been stored together in
hour as nearby tanks and process units ruptured. The total the same location came into contact with one another and
death toll was 23 with estimates of the number of injuries ignited causing a blaze that left several people affected from
ranging from 130 to 300 (Mannan, 2005i). inhaling the chemical plume (HSE, 1993a).
A simple design change in the connectors for the control The Allied Colloids chemical plant outside Bradford pro-
valve air lines could have made it impossible to inadvertently duced a range of speciality chemicals including polymers and
cross-connect the air lines as happened. There were no stored a range of hazardous chemicals. Much of the feedstock
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e23

for the plant was stored in the raw materials warehouse which While the sludge was being raked out the sludge material
had been built in 1989. The warehouse included two fire- ignited and a jet flame almost 5 m in diameter erupted from
resistant store rooms. Known as the oxystores these rooms the end of the process unit and struck the plant control build-
contained floor to ceiling shelving into which bags and kegs ing as well as a larger office building standing behind it and
of material could be stored. over 50 m away from the process unit. Five people were killed
The genesis of the situation occurred when several kegs and many others were affected by exposure to the chemicals
of azodiisobutyronitrile (AZDN) were stored on the top shelf over the coming days. While the exact source of ignition was
in one of the oxystores directly above sacks of sodium per- never confirmed it appears the most likely explanation is that
chlorate. These two chemical should never have been stored the heating by the steam caused the thermally unstable sludge
in the same location, and certainly not in a situation in which residues to exothermically decompose. The heat generated
the contents of one container might actually leak onto another was sufficient to ignite the chemical mixture in the vessel.
container. The jury at the Coroner’s Court identified a list of factors
In the morning of July 21, 1992 rain fell in the district and that contributed to the incident (HSE, 1993b):
forklift trucks operating on the site brought water onto the
floor of the raw materials warehouse, making the floor slip- • the decision to clean out a process unit for the first time
pery. A decision was taken to apply some heating to room to in 30 years in the absence of a proper understanding of the
evaporate the water from the floor. It is believed that one of contents of the sludge in the vessel;
the workers may have accidently turned on the steam heating • the decision to apply heat to the process unit;
system in to one of the oxystores. The steam heating system • the inadequacy and inaccuracy of the temperature measur-
had been originally installed in the store room when it was ing and recording system within the process unit;
intended for other chemicals to be stored in that room. The • the use of a metal rake to clean out the sludge; and, the
heating system was not required and a request had been made decision to allow the vessel to be raked out while heat was
to have the system removed. Instead a worker simply turned still be applied to the vessel.
the control off rather than disconnecting the system. In any
case, on this day the steam was switched on. The condensate Key lessons learned from this sudden fire include:
return line passed just under the ceiling near to the kegs of
AZDN. Because AZDN is thermally unstable it is believed that • the need to develop well thought out procedures for all tasks
the kegs became overheated and ruptured spilling onto the including those that are only rarely undertaken;
sodium perchlorate and then the floor below. The rupture of • where any work is to be conducted in a confined space
the AZDN kegs was unobserved as the store room doors were which contains process material, then the nature of that
closed. material must be fully understood and appropriate safety
Several hours after heating of the store room commenced precautions put in place;
smoke was seen to be coming from the air vents leading into • the design and locating of office and control buildings
the store room. The alarm was sounded and the store room around a process facility must be carefully assessed consid-
door opened to allow the managers to assess the situation. ering the possibilities of fires, explosions or toxic releases.
The chemicals then ignited and the fire then spread to the sec-
ond oxystore and then the entire warehouse. Although no one 3.19. Fire and explosions at Texaco Refinery, Milford
was killed several people suffered from the inhalation of the Haven (July 1994)
chemicals and the water used to fight the fires escaped to the
environment causing considerable damage to the waterways Just before 9 am on a Sunday morning a fierce electrical storm
downstream of the site. swept through the Pembroke region of south Wales. The storm
Key lessons learned from this incident include (HSE, 1993a): caused a number of plant upsets and disturbances at the Tex-
aco Refinery located near the town of Milford Haven. Operators
• chemicals should be stored properly and the different trying to restore the refinery to normal operation allowed a
classes of chemicals should be kept segregated; vessel to overfill resulting in the failure of piping. This led to
• work orders, particularly those relating to safety issues, the release of some 20 tonnes of hydrocarbons which formed a
should always been completed with the highest priority. vapour cloud that drifted with the wind. When the cloud found
a point of ignition the resulting explosion had the destructive
3.18. Hickson and Welch fire (September 1992) power equivalent to at least 4 tonnes of high explosives. No
one was killed in the explosion, primarily because it was a
On 21 July 1992 workers began cleaning out the sludge from Sunday morning when few staff were around the facility, and
the base of a process unit. The process unit had never been because of the safe and sound construction used in the plant
cleaned out in its more than 30 years of operation. Only a very buildings (HSE, 1995).
simple test was made to determine the nature of the sludge During an intense period of time following the electrical
and on the basis of this test it was assumed that the sludge storm the operators in the refinery were busy restoring the
was thermally stable tar. In fact the sludge was not simple tar operation of the plant. Once the level in the de-ethaniser was
but a mixture of accumulated sludge containing pockets of restored to its correct setting, flow to the de-butaniser was
flammable material (HSE, 1993b). re-started. At this time the outlet valve on the de-butaniser
It was decided to apply some heat to the unit in order to to the naphtha should have opened but did not. In the con-
soften up the sludge which was thought to be tar. Instructions trol room an incorrect signal from the valve indicated that it
were given not to exceed a temperature of 90 ◦ C during the had opened when in fact it remained closed. Because the way
heating process. However because of poor placement of the the information was displayed on the computer screens in the
temperature sensor the sludge was actually heated to about control room the operators were unable to identify from the
180 ◦ C. information available that the control valve was stuck closed.
e24 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

Reacting to indications that the de-butaniser was over- speed trains were originally formed as monoblocs, cast as a
pressured the operators opened another valve which allowed single piece of steel. However after several months of use the
the hydrocarbon to move out of the de-butaniser to the wet wheels were seen to be wearing an unacceptably high rate.
gas compressor system. Eventually the mixture of liquid and Metal fatigue and uneven wear on the wheels caused the
gas overwhelmed the knock-out drum system and liquid at too wheels to go out of round which in turn caused vibrations.
high a flow rate entered the gas line to the flare. This line failed The rail engineers decided to solve the wheel problem by
releasing around 20 tonnes of hydrocarbon to the atmosphere. fitting a steel tire to the main section of the wheel. The steel
The explosion followed shortly after, sparking fires throughout tire was separated from the main part of the wheel by using
the facility. The line that failed was found to be partly corroded a rubber ring. Steel tires had long been successfully used on
yet investigators concluded that it would have failed under the trams and streetcars throughout Germany. What the rail engi-
fast flow of liquid whether it had been corroded or not. neers did not appreciate was that the trams and streetcars that
During the almost 5 h between the electrical storm sweep- used wheel sets of an inner steel wheel with a steel tire usu-
ing across the refinery and the explosion the operators had ally travelled up to 60 km/h only over short distances. The high
been acting to restore operation of the plant. In the control speed trains were deigned to operate at speeds up to 250 km/h
room the alarm system kept sounding hundreds of alarms, for extended periods of several hours. The engineers decided
with at one stage operators being faced with a new alarm every that there was no need to conduct any tests on the new two-
2–3 s. They were overwhelmed by the information that they steel piece wheel sets at high speed.
were receiving and found it difficult to distinguish between In operation the rail engineers observed that the steel tires
the critical alarms and those that were merely advisory (HSE, were failing more often than they should have. Every time the
1995). wheels turned they were subjects to repetitive dynamic forces
Key lessons learned from this refinery fire include: which had not been accounted for in the design modelling of
the steel sets. And the wheels turned up to 500,000 times a day.
• the need to provide operators with information that allows The fatigue cracks that formed were on the inside of the tires
them to make appropriate decisions; where they could not be observed. As the tires became thinner
• the need to permit operators to shutdown a plant when due to the continuous wear the rate of crack growth increased.
they are overwhelmed with responding to alarms and non- The regular maintenance checks were unable to detect the
standard situations; fatigue cracks. Staff on the train logged issues relating to noise
• the fact that with properly designed buildings personnel can and vibrations from the wheel set containing the failed tire as
survive extreme explosions and fires. many as eight times in the 2 months immediately preceding
the failure however no action was taken. The engineers had
3.20. Eschede Train Disaster (June 1998) designed a wheel set that was not fit for purpose. They had not
adequately designed the wheels to meet the severe demands
On June 3, 1998 a high speed German express train travel- placed on them by the continuous high speed operation of
ling between Munich and Hamburg at over 200 km/h derailed the trains. They took technology that worked for one applica-
just before passing under a bridge. The fourth passenger car tion and assumed that it would work in a completely different
crashed into the bridge causing the bridge to collapse onto the environment.
following passenger cars. Over 100 people died and 88 people Key lessons learned from the this rail disaster include
were injured (Esslinger et al., 2004; Brumsen, 2011). (Esslinger et al., 2004):
During the train trip passengers in the first passenger car
sitting above one of the wheel sets felt severe and unusual • the design engineers assumed that technology that worked
vibrations. Moments later the steel tire around one of the successful in one application could be transplanted to a
wheels peeled away from the wheel and punctured the floor more aggressive operating environment without the need
of the car. The passengers were rightly alarmed to witness the proper design tests;
the steel tire spear through the floor and an armrest narrowly • the railway management responsible for maintenance of
missing two passengers sitting close by. Rather than pull the the trains did not have in place an adequate testing regime
emergency stop handle located in every passenger car, one of that should have identified the metal fatigue on the tires;
the passengers went looking for the conductor to report the • the bridge support should not have been placed so close to
incident. What no one realized was that the steel tire had not the running track.
only speared the floor upwards but was hanging down below
the car running just centimetres away from the one of the rails. 3.21. Longford explosion (September 1998)
It took time to find the conductor and they did not want to stop
the train until they had assessed the damage. As the conduc- The Longford Gas Plant located near the Australian coast pro-
tor entered the first passenger car the train passed over a set cesses the gas that comes ashore from the many offshore
of diverging points. The embedded steel tire hanging below platforms in Bass Strait. Following a process upset on February
the passenger car hit the switch work causing the trailing car- 25, 1998 a pump supplying warm lean oil to a heat exchanger
riages to skew off onto the parallel set of tracks. The passenger stopped operating (Kletz, 2003). The heat exchanger used the
cars then jack-knifed as the train passed under a road bridge warm lean oil flowing through the shell-side to heat rich
at the town of Eschede. The fourth passenger car hit one of the oil flowing on the tube-side. With the supply of lean oil to
bridge supports standing beside the track causing the bridge the heat exchanger suddenly stopped the temperature of the
to collapse onto the trailing passenger cars. The leading power exchanger temperature rapidly fell to the temperature of the
car separated from the trapped carriages and came to a safe cold rich oil, around −48 ◦ C. Operators noted that ice formed
stop further down the track. on the outside of the exchanger but did not fully understand
The cause of the separation of the steel tire from the wheel its significance. When the lean oil pump re-started sometime
lay in the design of the wheel. The train wheels on the high later the oil entered the exchanger at 230 ◦ C. The thermal
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e25

shock caused by this sudden and very large change in tem- consumed what little oxygen was left in the rear engineering
perature induced a brittle fracture in the exchanger releasing spaces.
about 10 tonnes of hydrocarbon vapour. The vapour cloud that The first explosion was caused by the two reactants com-
formed drifted downwind and ignited when it encountered a ing into contact with one another outside the combustion
set of heaters 170 m away. The resulting explosion and subse- chamber in an uncontrolled manner. This occurred because of
quent fires killed two operators on the site and injured eight severe corrosion of one of the two fuel chambers. The practice
others. torpedo that was used that day had been manufactured in
Some years before almost all the engineers on site had been 1990, 10 years before it was prepared to be fired and in that
relocated to Melbourne, some 180 km away from the plant. decade it had never been fired nor had any maintenance ever
There was therefore little day-to-day face-to-face discussions been performed on it. It had just sat for 10 years in a warehouse
between the engineers and the site operators. Subsequent on the navy base. Other torpedos from the same manufactur-
investigations identified that the plant operators did not ing batch were found to have suffered similar corrosion. If an
understand the risks of brittle fracture nor of thermal damage. inspection had have been carried out before the torpedo was
It was suggested that operator training focussed on what the loaded onto the submarine the corrosion would most likely
operators needed to know to complete their jobs rather than have been identified and the torpedo not used.
on giving them a deeper understanding of the process allow- The key lesson learned from the loss of the Kursk is that
ing them to cope with unforeseen circumstances (Mannan, regular maintenance is vital for safe operation. An adequate
2005k). Obviously the decision to re-start the lean oil pump safety management system would have ensured that the tor-
injecting hot oil into the freezing heat exchanger was incor- pedos were subject to routine maintenance and would have
rect, however the operator was unaware of the dangers of been inspected prior to the fuel being loaded into them.
thermal shock.
Key lessons learned from this disaster include: 3.23. Thermal decomposition incident at BP Amoco,
Augusta (March 2001)

• the need for train staff to understand more about the pro-
Three workers were fatally injured when the cover they were
cess than just required to complete their tasks;
unbolting from a process unit blew off the vessel releasing
• the importance of regular face-to-face contact between
hot molten plastic. The incident occurred at the BP Amoco
operators and engineers;
Polymers plant in Augusta, Georgia where a nylon thermoplas-
• the need to have engineers on site on a day-to-day basis.
tic polymer was manufactured (USCSHIB, 2002U.S. Chemical
Safety and Hazard Investigation Board, 2002).
3.22. Loss of nuclear submarine Kursk (August 2000) The manufacture of the thermoplastic polymer occurred in
a number of stages. The raw materials were first fed to a pres-
The K-141 Kursk was a nuclear-powered missile submarine, surised and heated reaction vessel in which the prepolymer
the most advanced submarine of its kind possessed by the was formed. A high pressure pump then sent the prepoly-
Russian Navy. In August 2000 it was participating in a series mer to a tubular reactor before passing the material on to the
of war games with other submarines and surface ships of the extruder and finally the pelletizer. During start-up and shut-
Russian Navy. As part of the activities it was required to make down the effluent from the tubular reactor was sent to the
a stealthy approach on one of the surface ships before firing a polymer catch tank, a 2.8 cubic meter horizontal cylindrical
torpedo at the ship. The torpedo was a practice one in which vessel.
the explosive-filled war-shot had been replaced by a pod of On March 10, 2001 the entire unit was shutdown for main-
instruments and data loggers which would monitor and record tenance on the extruder. The next day the polymer catch tank
the progress of the torpedo towards the target. The torpedo was opened and thoroughly cleaned of waste material. The
was designed to move through the water at the speed of a unit was then sealed ready for the unit to be started up the next
regular torpedo but at a depth that would allow it to pass under day. The normal start-up procedure called for the extruder to
the keel of the target ship (Moore, 2004). be test run ahead of the system being charged with material.
In 2000 the Russian submarine force used torpedos pro- Unaccountably this task was not done and the unit was started
pelled by reacting hydrogen peroxide with kerosene. With a up with the raw materials flowing into the reactors. Following
length of around 11 m and a mass of approximately 5 tonnes normal procedures the effluent from the reactors was diverted
the reaction was powerful enough to propel the torpedos to the polymer catch tank for the first 50 min of operation.
through the water at 56 km/h over a distance of 80 km. The When the operators attempted to start the extruder the screws
exothermic reaction that occurred within the torpedo was par- would not turn. After almost 20 min the operators abandoned
ticular violent and it was essential that the two reactants were the attempt to start the extruder and decided to shutdown the
kept separated until needed. entire process. During this period the effluent from the tubular
As a practice torpedo was being loaded into the torpedo reactors continued to fill the catch tank. As the reactors were
tube the corroded tank containing one of the reactants failed being flushed with solvent as part of the shutdown procedure
allowing the hydrogen peroxide to prematurely react with the the catch tank continued to collect the effluent which was a
kerosene. The resulting detonation of the fuel, equivalent to hot, partially polymerized material. Finally the catch tank was
the energy released by 100 kg of TNT, caused the submerged closed off and no additional material entered the tank.
submarine to sink bow first. As the bow of the stricken Over its years of operation the polymer catch tank had
submarine hit the seabed at a depth of 115 m the live torpedos never been filled to such an extent. The polymer near the
filled with explosives in the forward torpedo room detonated outside of the tank solidified into a hard crust. Solid polymer
with such a force that the forward two-thirds of the boat also solidified around the drainage points and at the pressure
were destroyed. Several sailors survived for some days in the tapping. The hot polymer within the centre of the tank
stern sections of the boat but they died later when a flash fire began to thermally decompose generating gases. These gases
e26 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

pressurised the closed off tank. Because the pressure port and underlying safety culture on the site. Training staff numbers
drainage points were blocked by solid polymers there was no had been reduced significantly in the years leading up to the
way for the operators to know that the tank was at an elevated incident and the company had not responded sufficiently to
pressure. Three workers were sent to open the polymer catch safety concerns raised in the past.
tank to clean it and remove the accumulated material. As Key lessons learned from this disaster include:
normal they began unbolting the flat end plate that was held
in place by 44 bolts. When 22 had been removed the plate • the need for appropriately trained staff;
blew off venting the hot molten plastic over the three workers • the need for an appropriate staff management system that
who died from their injuries. The force of the release of the does not permit staff to become tired working on 12-h long
polymer severed an oil line that led to an explosion and fire. shifts for weeks at a time;
Key lessons that can be learned from this incident include • staff should not be accommodated on site or near operating
(USCSHIB, 2002U.S. Chemical Safety and Hazard Investigation facilities unless there is a real need for them to do so, and
Board, 2002): any staff accommodation must be built to an appropriate
standard and should not be simple trailer accommodation;
• the need for a more rigorous assessment of the hazards and • and appropriate safety culture must be in place.
risks associated with filling the tank to near capacity with
molten plastic; 3.25. Buncefield explosion and fire (December 2005)
• the need for pressure sensors appropriate for the type of
material stored in the tank; The Buncefield oil storage and transfer facility is located to the
• the importance of learning from past experiences when north of London. Refined stocks such as petrol and aviation
the pressure tapping and pressure relief device had become jet fuel are pumped remotely into the facility from refiner-
blocked with plastic; ies across England and out to sites across south-east England
• the operators were unaware that the polymer could thermal including Heathrow and Gatwick airports. On the morning of
decompose within the tank leading to overpressurization; December 11, 2006 the liquid level indicator on one of the
• operators had no direct measure of the level of the polymer large tanks failed while it was receiving unleaded petrol from
in the polymer catch tank. a remote site. Even though the petrol was being pumped in
at a rate of 550 m3 /h into Tank 912 from 3:00 am onwards the
3.24. Texas City BP refinery explosion (March 2005) liquid level indicator did not show a change in the height of
liquid in the tank. Just over 2 h later the tank was completely
In 2005 the Texas City refinery of BP was the third largest oil full and flow should have stopped automatically. It did not
refinery operating in the US. After maintenance had been per- and unleaded petrol began to cascade down the outside of the
formed on one of the units the raffinate splitter tower was tank.
re-started. As part of the start-up procedure flammable liquid Operators at the pumping station seeing that the tank was
hydrocarbons were pumped into the base of the tower. Due apparently not yet full increased the flow rate of the petrol
to an operator error an outlet valve was not opened and the flowing into the tank to 890 m3 /h. The operators did not stop
tower began to fill with the hydrocarbon. The tower level indi- to consider that they had been pumping petrol into a tank for
cator malfunctioned and indicated that the liquid level in the several hours but the height as displayed had not increased.
tower was actually decreasing when in fact it was overfilling. At 5:46 am nearby security cameras showed a 2 m thick vapour
The high level alarm did not function. The operators who were cloud on the ground and spreading out in all directions from
fatigued from repeated long shifts did not realize the true sit- the storage facility. At 6:01 am the cloud detonated, ignited
uation in the tower (USCSHIB, 2007U.S. Chemical Safety and by a source in a car park. The resulting explosion did a huge
Hazard Investigation Board, 2007). amount of damage but because it was early on a Saturday
The liquid overflowed the top of the tower and ran down morning no one was injured.
an overhead pipe to pressure relief valves located near the The incident occurred because a single piece of equipment
ground 45 m below. These valves open discharging the liquid failed (the level indicator) and because there were no other
to a blowdown drum. The liquid under pressure then vented checks in place to safeguard against this. Operator response to
out the top of a stack connected to the drum forming a geyser. what appeared to be a tank that was not filling quickly enough
The liquid droplets vapourised as their rained back down to was to increase the flow rate of petrol to the tank rather than
the ground, forming a dense vapour cloud. The flammable understanding why the tank was apparently slow to fill.
cloud found an ignition source and detonated devastating the Key lessons to be learnt from the Buncefield incident:
unit. All the 15 people killed were working in temporary office
accommodation which had been located just 37 m away from • the importance of having a system that can withstand the
the blowdown drum. inevitable failure of a single piece of equipment;
While the direct cause of the incident was the failure • the need for appropriately trained staff.
to open a valve and the subsequent failure of the instru-
mentation to correctly indicate that the raffinate tower was The BMIIB (2008)Buncefield Major Incident Investigation
overfilling the deaths were a direct result of the temporary Board (2008) published their final reports in 2008.
office accommodation being located too close to an operating
process facility. The offices were not associated with the oper- 3.26. Imperial Sugar refinery explosion in Port
ation of the unit and there was no need to locate them where Wentworth, Georgia (February 2008)
they did. The U.S. Chemical Safety and Hazard Investigation
Board found that cost-cutting and a failure to invest impaired A series of sugar dust explosions at the Imperial Sugar refinery
the safety management at Texas City. Managers relied on low in Port Wentworth, Georgia, US, killed 13 people and injured
personal injury rates as a safety measure rather than the another 36. The company received raw sugar and refined it into
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e27

granulated sugar which was then either shipped as a product isolating the pressure control valve from the heat exchanger.
or further processed on site to a range of other sugar-based The operator was aware that the shell-side was full of pres-
products. The refined sugar was stored in three silos, each 12 m surised ammonia but was unaware that the isolation valve
in diameter and 32 m in height. The sugar was moved around remained closed form the operations from the day before. The
the site and between the silos on conveyor belts, screw convey- operator assumed that any over-pressuring that might occur
ors and by buckets. Beneath the three silos two belt conveyors would be able to vent through the valve to the pressure relief
ran in a tunnel 40 m long, 2.3 m high and 3.7 m wide. The valve (USCSHIB, 2011U.S. Chemical Safety and Hazard Investi-
refined, granulated sugar formed fine dust particles within the gation Board, 2011).
process and these dust particles accumulated over the many The operator connected a steam line to the tube-side of
years of operation (USCSHIB, 2009bU.S. Chemical Safety and the exchanger in order to clean the exchanger. The steam
Hazard Investigation Board, 2009b). quickly heated up the ammonia, and with the shell-side effec-
A 0.8 m wide steel conveyor belt in the tunnel transported tively isolated the pressure began to build up as the liquid
sugar from two of the silos into an elevator system that ammonia began to evaporate. Less than an hour later the
conveyed the sugar to the packaging area. Concerned the con- heat exchanger shell violently ruptured spraying the area with
taminants might fall onto the refined sugar on its way for metal shrapnel and releasing dangerous levels of ammonia to
packaging the engineers decided to fully enclose the conveyor the atmosphere. Five nearby workers were exposed to the gas
belt and its assembly. By enclosing the conveyor belt the engi- and had to be treated.
neers prevented the fine sugar dust from dispersing into a Later that morning the plant management declared the
wider volume of air. Investigators later concluded that the con- incident over and work began to clean up the area. It was at
centration of sugar dust in the enclosed conveyor belt system this point that the body of a company employee was discov-
belt up to such a level that it exceeded the minimum explosible ered amongst the debris. She had been felled by the flying
concentration. shrapnel and died on the scene. Since she was a member
While the exact ignition source was never identified but of the plant’s emergency response team no one considered
may have been an overheated roller bearing on the conveyor, her absence during the incident unusual. The company’s sys-
what is known is that a large dust explosion occurred within tem of accounting for staff had failed as no one identified
the enclosed conveyor belt system in the evening of February that the employee was missing after the incident. Indeed
7, 2008. The explosion triggered a series of secondary explo- several people who had the responsibility for accounting
sions that rippled through the facility devastating the entire for staff were unaware that this was their role in an emer-
facility. It is surmised that each successive explosion dislodged gency. Although internal company safety policies required
accumulated dust into the air which then ignited. that plant-wide emergency drills be conducted at least once
The investigators found that the conveying equipment every three months, no such drill had been conducted in the
used on site was neither designed or maintained to mini- facility for the 4 years prior to the incident.
mize the production of sugar dust. They found that inadequate Key lessons learned from this incident at Goodyear include
housekeeping activities resulted in sugar dust accumulating (USCSHIB, 2011U.S. Chemical Safety and Hazard Investigation
throughout the facility to unacceptably high levels. Further Board, 2011):
they found that the recently installed enclosure around the
conveyor belt increased the likelihood of a dust explosion by
• maintenance procedures were not followed;
allowing the concentration of dust particles to exceed the min-
• the operator did not visually check that the isolation valve
imum explosible concentration (USCSHIB, 2009bU.S. Chemical
to the pressure relief valve was open before steaming the
Safety and Hazard Investigation Board, 2009b).
tubes of the exchanger;
Key lessons learned from the sugar refinery explosions
• the head count was not correctly performed and a missing
include:
worker was not identified as being missing;
• established safety drills were not held in the facility on a
• the enclosure as designed and installed was not fit for pur-
regular basis so that the workers and management were not
pose;
properly prepared to adequately respond to the incident.
• the need for appropriate levels of housekeep to ensure that
dust did not accumulate within the process;
• the need for adequate evacuation plans and the practice of 4. Student feedback
those plans.
Three months after completing the oral presentations stu-
3.27. Goodyear heat exchanger rupture (June 2008) dents were asked for their feedback on the effectiveness of
the oral presentations as a vehicle for instruction on pro-
Goodyear used pressurised anhydrous ammonia as a cooling cess safety. Participation in the survey was voluntary and the
fluid in a shell and tube heat exchanger at their synthetic responses were anonymous. Using a paper-based survey form
rubber plant in Houston, Texas. The process chemicals to be students were asked to state the extent to which they agreed
cooled were pumped through the tubes inside the exchanger or disagreed with a series of statements. On a 5-point Likert
while the ammonia was circulated shell-side. On June 10, 2008 scale in which 1 is assigned to the response “Strongly disagree”
operators closed an isolation valve on the shell-side so that and 5 is assigned to “Strongly agree”, the responses and the
they could replace a burst rupture disk. Closing the isolation average scores for the students for the questions are presented
valve also closed off a pressure relief valve that was located in Table 2.
there to prevent pressure build up of the ammonia on the Of the students surveyed 92% either agreed or strongly
shell-side. At the conclusion of the rupture disk replacement, agreed with the statement that chemical engineers need com-
the isolation valve was not re-opened. The next day another munication skills of a high standard. A similar percentage also
operator closed a block valve on the ammonia shell-side loop agreed that the oral presentations helped them develop their
e28
Table 2 – Summary of survey responses. Students asked to indicate the extent to which they either agreed or disagreed with eight statements using a 5-point Likert scale.
Statement Number of Strongly Disagree (2) Neither agree Agree (4) Strongly Average % Agree % Disagree
respondents disagree (1) nor disagree (3) agree (5) score

education for chemical engineers 8 ( 2 0 1 3 ) e12–e30


Chemical engineers need communication 38 0 0 3 17 18 4.4 92.1 0.0
skills of a high standard
The oral presentations helped me develop 37 0 2 1 25 9 4.1 91.9 5.4
my presentation skills
The oral presentations were an effective 38 0 3 6 24 5 3.8 76.3 7.9
way to learn about my particular topic
The oral presentations were an effective 38 0 5 7 22 4 3.7 68.4 13.2
way to learn about a range of safety
case studies
I found that preparing the critique for 37 1 3 11 16 6 3.6 59.5 10.8
another student helped me to think
about what is important in improving
my own presentations
My team should have been allowed to 38 1 7 16 6 8 3.3 36.8 21.1
choose its own topic from a list of topics
I recommend that the next time the 38 2 2 10 16 8 3.7 63.2 10.5
subject is taught that the presentations
are again recorded for later review by
the students
I recommend that the next time the 38 0 0 3 14 21 4.5 92.1 0.0
subject is taught all students receive
written feedback from the
lecturer-in-charge
education for chemical engineers 8 ( 2 0 1 3 ) e12–e30 e29

presentation skills. Over three-quarters of the class agreed Atheron, J., Gill, F., 2008b. Incidents That Define Process Safety.
that the oral presentations were an effective way for them to Center for Chemical Process Safety/AIChE, New York, pp.
learn about the particular topic for which they had to present 277–281.
Bethea, R.M., 2003. Explosion and fire at the Phillips Company
on. The majority of students also agreed that the oral pre-
Houston Chemical Complex, Pasadena, TX. In: Proc. SACHE
sentations whether they were a presenter or a member of the Faculty Workshop on Designing for Safe and Reliable Process
audience were an effective way to learn about a range of safety Operations, Baton Rouge, USA, September 2003.
case studies. Brumsen, M., 2011. Case description: the ICE train accident near
The requirement for each student to prepare a written cri- Eschede. Euro. Bus. Ethics Cases Context 28, 157–168.
tique for a class mate’s presentation was set with the intention Bryan, L.A., 1999. Educating engineers on safety. J. Manage. Eng.
that not only would each student receive detailed written feed- 15, 30–33.
Buncefield Major Incident Investigation Board, 2008. Buncefield
back from a class mate but that the preparation of the critique
Investigation.
would allow them to reflect on their own performance. In http://www.buncefieldinvestigation.gov.uk/index.htm
response to a yes/no question, “Was the written critique that (accessed 25 August, 2012).
you received from your class mate helpful?” over 90% of the Cortés, J.M., Pellicer, E., Catalá, J., 2012. Integration of
cohort responded positively. However only 59.5% of the class occupational risk prevention courses in engineering degrees:
either agreed or strongly agreed with the statement that “I Delphi study. J. Prof. Issues Engin. Educ. Prac. 138, 31–36.
Cullen, W.D., 1990. The Public Inquiry into the Piper Alpha
found that preparing the critique for another student helped
Disaster. HM Stationery Office, London.
me to think about what is important in improving my own
Engineers Australia, 2008. G02 Accreditation Guidelines.
presentations.” This suggests that while the activity was pos- Engineers Australia Accreditation Board. http://www.
itively viewed by the students as worthwhile the students engineersaustralia.org.au/sites/default/files/shado/Education/
might have benefited from more preparation in self-reflection. Program%20Accreditation/AMS%20Professional%20Engineer/
The cohort was generally ambivalent about being able to G02%20Accreditation%20Criteria%20Guidelines.pdf (accessed
choose their own topics with a small margin favouring that 25 August, 2012).
Esslinger, V., Kieselbach, R., Koller, R., Weisse, B., 2004. The
outcome.
railway accident of Eschede–technical background. Eng.
The students strongly agreed with the proposition that Failure Anal. 11, 515–535.
the next class completing the subject should receive written European Federation of Chemical Engineering, 2010. EFCE
feedback from the lecturer-in-charge. While they did view the Bologna Recommendations – EFCE recommendations for
critique written by their class mates favourably they appeared chemical engineering education in a Bologna three cycle
to have greater confidence in the teaching staff to provide degree system, EFCE. http://www.efce.org/
useful feedback. Bologna Recommendation.html (accessed 25 August, 2012).
Ferjencik, M., 2007. Best starting point to comprehensive process
The students found the video recording of their presen-
safety education. Process Saf. Prog. 26, 195–202.
tations less useful, with just over a quarter of the class Gillett, J.E., 2001. Chemical engineering education in the next
downloading their presentations from the subject web site. century. Chem. Eng. Technol. 24, 561–570.
Comments from the class suggest that the main reason for Hendershot, D.C., Smades, W., 2007. Safety culture begins in the
this was the relatively large size of the video file being a bar- classroom. Process Saf. Prog. 26, 83–84.
rier to downloading. In future the video files will be saved in HSE, 1988. The Fires and Explosion at BP Oil (Grangemouth)
Refinery Ltd. HSE Books, London.
a format with a significantly smaller file size. Of those that
HSE, 1993. The Fire at Allied Colloids Limited: A Report of HSE’s
did download the video recordings of their presentations 80%
Investigation Into the Fire at Allied Colloids Ltd., Low Moor,
found reviewing their presentations very helpful. Bradford on 21 July 1992. HSE Books, London.
HSE, 1993. The Fire at Hickson & Welch Ltd: A Report of the
Investigation by the Health and Safety Executive into the Fatal
5. Concluding remarks Fire at Hickson & Welch Ltd, Castleford on 21 September 1992.
HSE Books, London.
HSE, 1995. The Explosion and Fires at the Texaco Refinery, Milford
The 27 case studies presented have been successfully used
Haven, 24 July 1994. HSE Books, London.
in the an undergraduate chemical engineering subject to not HSE, 2010. Refinery Fire at Feyzin, 4th January 1966.
only introduce students to the importance of safety, but also http://www.hse.gov.uk/comah/sragtech/casefeyzin66.htm
to develop their presentation and general communication (accessed 25 August, 2012).
skills. The activity described has also been designed to try to Institution of Chemical Engineers, 2012. Accreditation of
develop the students’ willingness and ability to reflect on their chemical engineering degrees: a guide for university
performance. The survey conducted with a random group departments and assessors, IChemE, Rugby. http://www.
icheme.org/membership/∼/media/Documents/icheme/
of students who participated in the activity 3 months later
Membership/Accreditation/accreditationguide0212.pdf
showed that they responded very well to the activity and found (accessed 25 August, 2012).
it a useful learning experience on a number of levels. International Engineering Alliance, 2009. Graduate attributes and
professional competencies, IEA.
http://www.washingtonaccord.org/IEA-Grad-Attr-Prof-
References Competencies-v2.pdf (accessed 25 August, 2012).
Khan, F.I., Abbasi, S.A., 1999. Major accidents in process
industries and an analysis of causes and consequences. J.
ABET, 2011. Criteria for accreditation engineering programs.
Loss Prev. Process Ind. 12, 361–378.
ABET, Engineering Accreditation Commission, Baltimore.
Kletz, T., 1999. What Went Wrong? Case Histories of Process Plant
http://www.abet.org/uploadedFiles/Accreditation/
Disasters, 4th ed. Gulf Professional Publishing, Burlington.
Accreditation Process/Accreditation Documents/Current/
Kletz, T., 2003. Still Going Wrong. Elsevier, London.
eac-criteria-2012-2013.pdf (accessed 25 August, 2012).
Kletz, T., 2009. What Went Wrong? Case Histories of Process Plant
Atheron, J., Gill, F., 2008a. Incidents That Define Process Safety.
Disasters and How They Could Have Been Avoided, 5th ed.
Center for Chemical Process Safety/AIChE, New York,
Elsevier, London, pp. 345–346.
pp.125–127.
e30 education for chemical engineers 8 ( 2 0 1 3 ) e12–e30

Marine Accident Investigation Board, 1987. Herald of Free Parker, R.J., 1975. Flixborough disaster: Report of the Court of
Enterprise report. http://www.maib.gov.uk/ Inquiry. UK Department of Employment. HMSO, London.
publications/investigation reports/herald of free enterprise/ Paté-Cornell, M.E., 1993. Learning for the Pipe Alpha accident a
herald of free enterprise report.cfm (accessed 25 August, postmortem analysis of technical and organizational factors.
2012). Risk Anal. 13, 215–235.
Mannan, S., 2005a. A38 Feyzin, France, 1966. In: Lees’ Loss Petroski, H., 1992. To Engineer is Human: The Role of Failure is
Prevention in the Process Industries, third ed. Elsevier, Structural Design. Vintage.
London, p. A1/33. Saleh, J.H., Pendley, C.C., 2012. From learning from accidents to
Mannan, S., 2005b. Flixborough. In: Lees’ Loss Prevention in the teaching about accident causation and prevention:
Process Industries, third ed. Elsevier, pp. A2/1–A2/18. multidisciplinary education and safety literacy for all
Mannan, S., 2005c. Seveso. In: Lees’ Loss Prevention in the engineering students. Reliab. Eng. Syst. Saf. 99, 105–113.
Process Industries, third ed. Elsevier, pp. A5/1–A5/13. U.S. Chemical Safety and Hazard Investigation Board, 2002.
Mannan, S., 2005d. San Carlos de la Rapita. In: Lees’ Loss Investigation Report Thermal Decomposition Incident. U.S.
Prevention in the Process Industries, third ed. Elsevier, pp. Chemical Safety Board Report No. 2001-03-1-GA.
A16/1–A16/4. U.S. Chemical Safety and Hazard Investigation Board, 2007.
Mannan, S., 2005e. Three Mile Island. In: Lees’ Loss Prevention in Investigation Report Refinery Explosion and Fire BP. U.S.
the Process Industries, third ed. Elsevier, pp. A21/1–A21/13. Chemical Safety Board Report No. 2005-04-1-TX.
Mannan, S., 2005f. Bhopal. In: Lees’ Loss Prevention in the U.S. Chemical Safety and Hazard Investigation Board, 2009.
Process Industries, third ed. Elsevier, pp. A5/1–A5/11. Investigation Report T2 Laboratories Inc Runaway Reaction.
Mannan, S., 2005g. Chernobyl. In: Lees’ Loss Prevention in the U.S. Chemical Safety Board Report No. 2008-3-1-FL.
Process Industries, third ed. Elsevier, pp. A22/1–A22/10. U.S. Chemical Safety and Hazard Investigation Board, 2009.
Mannan, S., 2005h. Piper Alpha. In: Lees’ Loss Prevention in the Investigation Report Sugar Dust Explosion and Fire Imperial
Process Industries, third ed. Elsevier, pp. A19/1–A19/14. Sugar Company. U.S. Chemical Safety Board Report No.
Mannan, S., 2005i. Pasadena. In: Lees’ Loss Prevention in the 2008-05-1-GA.
Process Industries, third ed. Elsevier, pp: A6/1–A6/5. U.S. Chemical Safety and Hazard Investigation Board, 2011. Case
Mannan, S., 2005j. A131 Stanlow, Cheshire, 1990. In: Lees’ Loss study – heat exchanger rupture and ammonia release in
Prevention in the Process Industries, third ed. Elsevier, Houston, Texas. U.S. Chemical Safety Board Report No.
London, p. A1/62. 2008-064-1-TX.
Mannan, S., 2005k. Longford. In: Lees’ Loss Prevention in the Venart, J.E.S., 2007. Flixborough: a final footnote. J. Loss Prev.
Process Industries, third ed. Elsevier, London, pp. A1/66–A1/67. Process Ind. 20, 621–643.
Moore, R., 2004. A Time to Die: the Untold Story of the Kursk Willey, R.J., Fogler, H.S., Cutlip, M.B., 2011. The investigation of
Tragedy. Three River Press. process safety into a chemical reaction engineering course:
Moshansky, V.P., 1992. Commission of inquiry into the Air Ontario kinetic modelling of the T2 incident. Process Saf. Prog. 30,
crash at Dryden. Ontario Final Report. Government of Canada, 39–44.
Ottawa.

Вам также может понравиться