BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Thursday, September 03, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
PILE CAP STATUS

Lower DECk PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 13 nos.
total Number OF Pile Caps@ Lower Deck 27 nos. 48.15%
Upper DECk PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 28 nos.
total Number OF Pile Caps 30 nos. 93.33%
Structural work

MSCP PILES 100.00%


CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 66.45%
1ST STOREY WALL- COLUMN STUMP CAST TO DATE 42.10%
DETENTION DRAIN CAST TO DATE 62.66%
INTERNAL DRAINAGE :32 18.75%

SITE VIEW
Architectural
work
M & E Work

cast 2 Pile Caps today PILE CAP P31and P30 at Upper Pile Cap Construction AT LOWER DECK PILE CAPS remains at
Deck Level. STATUS: at Lower Deck Level is at 48.15% COMPLETE, At Upper Deck is at 93.33% Complete LCT
48.15% Complete, Upper Deck Level PILE CAP STARTED INSTALLING reinforcing bars BELOW ELECTRICAL
SUBSTATION TRANSFORMER ROOM AREA SUCH AS DEEP BEAM
IS AT 93.33% Complete , 13 Pile caps more to
for UPSTAND BEAM & BEAM Wall rebar Preparation AT
complete at lower Deck Level
Electrical Substation TO FORM UP THE UPPER DECK SLAB
LEVEL BEHIND ELECTRICAL SUBSTATION Area ( YELLOW
CLOUD )

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor 1 Generator 2
Site Supervisor Safety Supervisor 1 Excavator CL
1 1
DETENTION DRAIN:
Safety officer REBAR
WORK/FRMWRK ddrain
UPDATED AT 63%
1
top slab 3 COMPLETE, nowDRAIN
08:30 17:30
DETENTION
installing Top slab
Site engineer FORMWORK D DRAIN BAR BENDER MACHINE
1 WALL/CAST 3 1 Formworks to cast on
RTO BIG BREAKER
Saturday Morning
1 PILE CAP 3 1 and Detention Drain Wall to
REBAR WORK D DRAIN 1 TONNE ROLLER- Cast on Friday After Lunch
REMARKS Administrator 1 TOP SLAB 5 COMPACTOR 1

Coordinator 1 ESS DEEP BEAM 3 AIR RECEIVER 1


PILE CAP P23 TC INSTALLED
ECO 1 3 1

Weather G Worker 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 5
IC WORKS IC#4
DRIZZLE
EXCAV SUPVSR 1
Manpower
2:00 14:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 DETENTION DRAIN @63% COMPLETEDETENTION AT DETENTION DRAIN TOP SLAB FORMWORK Installation TO CAST
DRAIN: UPDATED AT 63% COMPLETE, now installing SATURDAY AFTER Lunch
Top slab Formworks to cast on Saturday Morning
and Detention Drain Wall to Cast on Friday After Lunch
Housekeeping work inprogress,

Pile Cap Construction AT LOWER DECK PILE CAPS remains at 48.15% COMPLETE, At Upper Deck is at
93.33% Complete LCT STARTED INSTALLING reinforcing bars BELOW ELECTRICAL SUBSTATION
TRANSFORMER ROOM AREA SUCH AS DEEP BEAM for UPSTAND BEAM & BEAM Wall rebar RC SUMPS AND PIPE
Preparation AT Electrical Substation TO FORM UP THE UPPER DECK SLAB LEVEL BEHIND ELECTRICAL HAUNCHING PROGRESS
SUBSTATION Area ( YELLOW CLOUD ) CAST LEANCONCRETE @18.75%
AT THE BASE OF M&E
DETENTION DRAIN @63% COMPLETEDETENTION DRAIN: UPDATED AT 63% COMPLETE, now PIPES
installing Top slab Formworks to cast on Saturday Morning
and Detention Drain Wall to Cast on Friday After Lunch

INTERNAL DRAINAGE

AT DETENTION DRAIN TOP SLAB FORMWORK Installation TO CAST SATURDAY AFTER Lunch CAST LEAN CONCRETE AT BASE OF M&E PIPES FROM RC SUMPS AND PIPE HAUNCHING REMAINS @ 18.75% COMPLETE
IC#4 TO IC#3

INSTALLING DEEP BEAM REINFORCING BARS BELOW ELECTRICAL-SUBSTATION TRANSFORMER


ROOM AREA

INSTALLING PILE CAP REINFORCING BARS AT PILE CAP P 21 TO CAST ON FRIDAY AFTERNOON INSTALLING DEEP BEAM REINFORCING BARS BELOW INSTALLING PILE CAP REINFORCING BARS AT PILE CAP P 21 TO
ELECTRICAL-SUBSTATION TRANSFORMER ROOM AREA CAST ON FRIDAY AFTERNOON

22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @DETENTION 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS:
DRAIN CONSTRUCTION: 6 REBAR workers &SLAB FORMWORKS INSTALLATION pILE CAPS:4 workers
BEAKDOWN OF MANPOWER @DETENTION DRAIN
REBAR+ FORMWORK INSTALLATION, INTERNAL DRAINAGE: 6REBAR+FORMWORKS, BELOW ESS: 4
REBAWORKERS DEEP BEAMS INSTALLING, 2 workers Upper Deck Slab Preparation 2 WORKERS CONSTRUCTION: 6 REBAR workers &SLAB FORMWORKS
SAFETY & HOUSEKEEPING, SHIFTING HOISTING MARTERIALS FROM LC&T Laydown Area, 3 LBD INSTALLATION pILE CAPS:4 workers REBAR+ FORMWORK
HACKING OF MSCP PILES+ 4 WORKERS IC WORKS @HDB BLOCK 231
INSTALLATION, INTERNAL DRAINAGE:
6REBAR+FORMWORKS, BELOW ESS: 4 REBAWORKERS
DEEP BEAMS INSTALLING, 2 workers Upper Deck Slab
Preparation 2 WORKERS SAFETY & HOUSEKEEPING,
SHIFTING HOISTING MARTERIALS FROM LC&T Laydown
Area, 3 LBD HACKING OF MSCP PILES+ 4 WORKERS IC
WORKS @HDB BLOCK 231

yellow shades compaction of soil and


levelling started at Grid Line 12 to 10 cast
Leanconcrete towards Grid Line 7 in
preparation for Upper Deck Slab Casting

Today Noise Meter does not exceed