Академический Документы
Профессиональный Документы
Культура Документы
DAILY SITE RECORD Thursday, September 03, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
PILE CAP STATUS
SITE VIEW
Architectural
work
M & E Work
cast 2 Pile Caps today PILE CAP P31and P30 at Upper Pile Cap Construction AT LOWER DECK PILE CAPS remains at
Deck Level. STATUS: at Lower Deck Level is at 48.15% COMPLETE, At Upper Deck is at 93.33% Complete LCT
48.15% Complete, Upper Deck Level PILE CAP STARTED INSTALLING reinforcing bars BELOW ELECTRICAL
SUBSTATION TRANSFORMER ROOM AREA SUCH AS DEEP BEAM
IS AT 93.33% Complete , 13 Pile caps more to
for UPSTAND BEAM & BEAM Wall rebar Preparation AT
complete at lower Deck Level
Electrical Substation TO FORM UP THE UPPER DECK SLAB
LEVEL BEHIND ELECTRICAL SUBSTATION Area ( YELLOW
CLOUD )
Weather G Worker 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 5
IC WORKS IC#4
DRIZZLE
EXCAV SUPVSR 1
Manpower
2:00 14:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 DETENTION DRAIN @63% COMPLETEDETENTION AT DETENTION DRAIN TOP SLAB FORMWORK Installation TO CAST
DRAIN: UPDATED AT 63% COMPLETE, now installing SATURDAY AFTER Lunch
Top slab Formworks to cast on Saturday Morning
and Detention Drain Wall to Cast on Friday After Lunch
Housekeeping work inprogress,
Pile Cap Construction AT LOWER DECK PILE CAPS remains at 48.15% COMPLETE, At Upper Deck is at
93.33% Complete LCT STARTED INSTALLING reinforcing bars BELOW ELECTRICAL SUBSTATION
TRANSFORMER ROOM AREA SUCH AS DEEP BEAM for UPSTAND BEAM & BEAM Wall rebar RC SUMPS AND PIPE
Preparation AT Electrical Substation TO FORM UP THE UPPER DECK SLAB LEVEL BEHIND ELECTRICAL HAUNCHING PROGRESS
SUBSTATION Area ( YELLOW CLOUD ) CAST LEANCONCRETE @18.75%
AT THE BASE OF M&E
DETENTION DRAIN @63% COMPLETEDETENTION DRAIN: UPDATED AT 63% COMPLETE, now PIPES
installing Top slab Formworks to cast on Saturday Morning
and Detention Drain Wall to Cast on Friday After Lunch
INTERNAL DRAINAGE
AT DETENTION DRAIN TOP SLAB FORMWORK Installation TO CAST SATURDAY AFTER Lunch CAST LEAN CONCRETE AT BASE OF M&E PIPES FROM RC SUMPS AND PIPE HAUNCHING REMAINS @ 18.75% COMPLETE
IC#4 TO IC#3
INSTALLING PILE CAP REINFORCING BARS AT PILE CAP P 21 TO CAST ON FRIDAY AFTERNOON INSTALLING DEEP BEAM REINFORCING BARS BELOW INSTALLING PILE CAP REINFORCING BARS AT PILE CAP P 21 TO
ELECTRICAL-SUBSTATION TRANSFORMER ROOM AREA CAST ON FRIDAY AFTERNOON
22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @DETENTION 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS:
DRAIN CONSTRUCTION: 6 REBAR workers &SLAB FORMWORKS INSTALLATION pILE CAPS:4 workers
BEAKDOWN OF MANPOWER @DETENTION DRAIN
REBAR+ FORMWORK INSTALLATION, INTERNAL DRAINAGE: 6REBAR+FORMWORKS, BELOW ESS: 4
REBAWORKERS DEEP BEAMS INSTALLING, 2 workers Upper Deck Slab Preparation 2 WORKERS CONSTRUCTION: 6 REBAR workers &SLAB FORMWORKS
SAFETY & HOUSEKEEPING, SHIFTING HOISTING MARTERIALS FROM LC&T Laydown Area, 3 LBD INSTALLATION pILE CAPS:4 workers REBAR+ FORMWORK
HACKING OF MSCP PILES+ 4 WORKERS IC WORKS @HDB BLOCK 231
INSTALLATION, INTERNAL DRAINAGE:
6REBAR+FORMWORKS, BELOW ESS: 4 REBAWORKERS
DEEP BEAMS INSTALLING, 2 workers Upper Deck Slab
Preparation 2 WORKERS SAFETY & HOUSEKEEPING,
SHIFTING HOISTING MARTERIALS FROM LC&T Laydown
Area, 3 LBD HACKING OF MSCP PILES+ 4 WORKERS IC
WORKS @HDB BLOCK 231