BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Monday, September 21, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural wo PILE CAP STATUS

LOWER DECK: PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 17 nos.
total Number OF Pile Caps@ Lower Deck 28 nos. 60.71%
UPPER DECK: PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 29 nos.
total Number OF Pile Caps 29 nos. 100.00%
Structural work

MSCP PILES 100.00%

CONTIGUOUS Bored Pile ( CBP ) 100.00%

GROUT PILES 100.00%

TOWER CRANE PILE CAP CAST 100.00%

CAPPING BEAMS CAST TO DATE 82.00%

1ST STOREY WALL- COLUMN STUMP CAST TO DATE 45.00%


DETENTION DRAIN CAST TO DATE 88.00%
INTERNAL DRAINAGE UPDATE 42.86%

SITE VIEW
Architectural
work

@ LIFT CORE WALL SURFACE PREPARATION


TO RECEIVE DAVCO WATERPROOFING
MEMBRANE
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 60.71% LIFT COREWALL GRINDING TOUCH UP DO CHAMFER TO RECEIVE
WATERPROOFING MEMBRANE
11 Pile caps more to complete at lower Deck Level , GREEN
SHADES @ Upper Deck Level PILE CAP @ 100% Completed , AT
ELECTRICAL SUBSTATION AREA, AT LIFT PIT PREPARATION TO
RECEIVE DAVCO WATERPROOFING MEMBRANE

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE @ IC WORKS #4 TO SPLIT LEVEL BEAM AND WALL WB4 WB5 GH11b and
P Manager Supervisor Generator
1 1 2 @ DETENTION 2 WORKERS INSTALLED DAVCO WATERPROOF
Site Supervisor 1
Safety Supervisor
1
Excavator CL 1
DRAIN: UPDATED MEMBRANE MATERIALS, WALL BESIDES INSTALLED
AT 88% COMPLETE
DETENTION IC#3: INSTALL
DRAIN SUBSOIL PERFORATED PIPES
Safety officer LOWER DECK DEEP BEAM
DISMANTLE - FORMWORK 150MM DIAMETER
1 2
DUCTILE IRON PIPE
08:30 17:30

Site engineer LIFT PIT REBAR BAR BENDER MACHINE


1 FORMWORKS / CAST 4 1

RTO BIG BREAKER


@ REMAINING
AREA OF
1 ESS FORMWORKS 4 1
DETENTION DRAIN
TO COMPLETE
PREPARATION FOR WATER
PROOFING GRINDING
1 TONNE ROLLER-
COMPACTOR
@12%
REMARKS Administrator 1 TOUCH UP 2 1

UPPER /LOWER AIR RECEIVER


DECKSLAB/DROP PANEL/
Coordinator 1 INSTALLATION 8 22 1

TC INSTALLED
ECO 1 1

G Worker
Weather 10

TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
5
FAIR
EXCAV SUPVSR 1
Manpower
8:30AM 5:30PM TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @88% COMPLETE, DETENTION SPLIT LEVEL BEAM AND WALL WB4 WB5 GH11b and 2 WORKERS INSTALL
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF DAVCO WATERPROOF MEMBRANE MATERIALS
WORKS
Housekeeping work inprogress,
RC SUMPS AND PIPE
AT Lower Deck Level REMAINS @ 60.71% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE CAP @ HAUNCHING REMAINS
96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND FORMWORKS
INSTALLATION IN PROGRESS @42.86% COMPLETE

DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER
STAGE

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING 11 MORE PILE CAPS TO CAST AT LOWER DECK KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
LEVEL, STAIRCASE #1 PILE CAP TO BE CAST THIS WEEK 42.86% COMPLETE

GROUND BEAM AND DROP PANEL,SLAB


SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS AND TOP BOTTOM BARS INSTALLATION IN PROGRESS
REINFORCING BARS DONEUNTIL GRIDLINE 12-9F-G 70% COMPLETED, AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G

ESS

RWDP INSTALLED
AWAITING
INSPECTION

REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS
REINFORCING BARS AND TOP REINFORCING BARS DONEUNTIL GRIDLINE 12- WEEK.
9F-G 70% COMPLETED,

RC COREWALL: SURFACE PREPARATION TO RECEIVE DAVCO WATERPROOF MEMBRANE


REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE RC COREWALL: SURFACE PREPARATION TO RECEIVE DAVCO WATERPROOF
SPLIT LEVEL WALLS WB4a WB4 WB5 CAST MEMBRANE

INSTALLED 10 DROP PANELS SLAB SPLIT LEVEL BEAM APPLIED


22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP BOTTOM REINFORCING BARS AND 3 DAVCO WATERPROOF
22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
BEAM FORMWORK INSTALL / 6 WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4 ROWS OF GROUND BEAMS MEMBRANE
INSTALLED MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / 6
WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL
REBAR INSTALL=6 REBAR WORKERS 8 DEPLOYED TO WORKERS , WATERPROOFING PREPARATION GRINDING WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4
TOUCH UP, ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER
SITE WORKS /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8
@ELECTRICAL SUBSTATION
BELOW TRANSFORMER DEPLOYED TO WORKERS , WATERPROOFING PREPARATION GRINDING
ROOM : INSTALLING TOUCH UP, ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/
REBARS FOR UPSTAND HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS
BEAMS TO CAST WITHIN
THIS WEEK

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed


OTHER PERTINENT ACTIVITIES

INSTALLING HARD POLYFOAM PROTECTION TO NEWLY


APPLIED DAVCO WATERPROOFING MEMBRANE PRIOR TO
BACKFILLING

SPLIT LEVEL BEAMS AND RC WALL INSTALLING DAVCO


WATERPROFING MATERIALS COVERED WITH HARD
POLYFOAM PROTECTION PRIOR TO BACKFILLING WORKS

LIFT COREWALL GRINDING TOUCH UP DO CHAMFER AT


BASE TO RECEIVE DAVCO WATERPROOFING MEMBRANE

DETENTION DRAIN TOP SLAB CAST AT 88% COMPLETE

ESS -ELECTRICAL SUBSTATION BELOW TRANSFORMER ROOM


UPSTAND BEAMREBAR IN PROGRESS TO CAST WITHIN THIS
WEEK