Академический Документы
Профессиональный Документы
Культура Документы
DAILY SITE RECORD Monday, September 21, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural wo PILE CAP STATUS
SITE VIEW
Architectural
work
STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 60.71% LIFT COREWALL GRINDING TOUCH UP DO CHAMFER TO RECEIVE
WATERPROOFING MEMBRANE
11 Pile caps more to complete at lower Deck Level , GREEN
SHADES @ Upper Deck Level PILE CAP @ 100% Completed , AT
ELECTRICAL SUBSTATION AREA, AT LIFT PIT PREPARATION TO
RECEIVE DAVCO WATERPROOFING MEMBRANE
TC INSTALLED
ECO 1 1
G Worker
Weather 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
5
FAIR
EXCAV SUPVSR 1
Manpower
8:30AM 5:30PM TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @88% COMPLETE, DETENTION SPLIT LEVEL BEAM AND WALL WB4 WB5 GH11b and 2 WORKERS INSTALL
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF DAVCO WATERPROOF MEMBRANE MATERIALS
WORKS
Housekeeping work inprogress,
RC SUMPS AND PIPE
AT Lower Deck Level REMAINS @ 60.71% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE CAP @ HAUNCHING REMAINS
96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND FORMWORKS
INSTALLATION IN PROGRESS @42.86% COMPLETE
DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER
STAGE
INTERNAL DRAINAGE
RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING 11 MORE PILE CAPS TO CAST AT LOWER DECK KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
LEVEL, STAIRCASE #1 PILE CAP TO BE CAST THIS WEEK 42.86% COMPLETE
ESS
RWDP INSTALLED
AWAITING
INSPECTION
REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS
REINFORCING BARS AND TOP REINFORCING BARS DONEUNTIL GRIDLINE 12- WEEK.
9F-G 70% COMPLETED,
INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE RC COREWALL: SURFACE PREPARATION TO RECEIVE DAVCO WATERPROOF
SPLIT LEVEL WALLS WB4a WB4 WB5 CAST MEMBRANE