Вы находитесь на странице: 1из 1

BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Thursday, September 17, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS

LOWER DECK: PILE CAP STATUS


Pil e CAP works in progress.

total completed to date: 17 nos.


total Number OF Pile Caps@ Lower Deck 27 nos. 62.96%
UPPER DECK: PILE CAP STATUS
Pil e CAP works in progress.

total completed to date: 29 nos.

total Number OF Pile Caps 30 nos. 96.67%


Structural work

MSCP PILES 100.00%


CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 82.00%
1ST STOREY WALL- COLUMN STUMP CAST TO DATE 45.00%
DETENTION DRAIN CAST TO DATE 70.00%
INTERNAL DRAINAGE UPDATE 42.86%

SITE VIEW

INSTALL ING REINFORCING


Architectural

BARS, AND CLOSING


FORMWORKS @ LIFT PIT AREA
work
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 62.96% INSTALL ING REINFORCING BARS, AND CLOSING FORMWORKS @ LIFT PIT AREA
TO CAST FRIDAY WITH WATERPROOF CONCRETE
10 Pile caps more to complete at lower Deck Level , GREEN SHADES
@Upper Deck Level PILE CAP @ 96.67% Complete YELLOW CLOUDS
AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT
REINFORCING BARS AND FORMWORKS INSTALLATION IN PROGRESS

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE SPLIT LEVEL BEAM
P Manager 1 Supervisor 1 Generator 2 GH11b and GH11c
CAST
Site Supervisor 1 Safety Supervisor 1 Excavator CL 1
@ DETENTION
@ IC WORKS #4 TO
Safety officer LOWER DECK DEEP BEAM
FORMWORK INSTALL / DRAIN: UPDATED IC#3: INSTALL 150MM
08:30 17:30 1
CAST
6
DIAMETER
DETENTION
AT 70% COMPLETE DRAINDUCTILE
IRON PIPE
Site engineer LIFT PIT REBAR BAR BENDER MACHINE
1 4 1
FORMWORKS @ REMAINING
RTO BIG BREAKER
AREA OF
1 ESS FORMWORKS 2 1
DETENTION DRAIN
TO COMPLETE
DISMANTLE DEEP BEAM 1 TONNE ROLLER- COMPACTOR

Administrator
FORMWORKS @30%
REMARKS 1 2 1

UPPER /LOWER AIR RECEIVER


DECKSLADROP PANEL/
Coordinator 1 6 1
WALL BEAM REBAR
INSTALL
TC INSTALLED
ECO 1 1

Weather G Worker 10

TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR IC WORKS IC#4
1 5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 CAST
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 62.96% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND RC SUMPS AND PIPE
FORMWORKS INSTALLATION IN PROGRESS
HAUNCHING @42.86%
COMPLETE

DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE

GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS
STARTED TO INSTALL AT GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G

ESS

LIFT PIT REINFORCING BARS INSTALLATION AND FORMWORKS IN PROGRESS GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION

BARS, SLAB BOTTOM REINFORCING BARS STARTED TO INSTALL AT GRIDLINE IN PROGRESS.

12 TO 7 / G TO D

REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE

REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT REINFORCING BARS INSTALLATION AND FORMWORKS IN PROGRESS
WALLS WB4a WB4 WB5 CAST

22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP BEAM FORMWORK 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
INSTALL / CAST= 6 WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS DISMANTLE DEEP INSTALLED 10 DROP PANELS SLAB BEAM GH11b GH11c CAST
BOTTOM REINFORCING BARS AND 3 MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / CAST= 6
BEAM FORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8 DEPLOYED TO
ROWS OF GROUND BEAMS INSTALLED
WORKERS ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4

WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER

/LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8


@ELECTRICAL DEPLOYED TO WORKERS ASSIST TOWER CRANE/ SHIFTING OF
SUBSTATION BELOW
MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS
TRANSFORMER ROOM :
FABRICATE FORMWORKS
FOR DEEP BEAMS,

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed

Вам также может понравиться