DAILY SITE RECORD Thursday, September 17, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS
SITE VIEW
STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 62.96% INSTALL ING REINFORCING BARS, AND CLOSING FORMWORKS @ LIFT PIT AREA
TO CAST FRIDAY WITH WATERPROOF CONCRETE
10 Pile caps more to complete at lower Deck Level , GREEN SHADES
@Upper Deck Level PILE CAP @ 96.67% Complete YELLOW CLOUDS
AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT
REINFORCING BARS AND FORMWORKS INSTALLATION IN PROGRESS
Administrator
FORMWORKS @30%
REMARKS 1 2 1
Weather G Worker 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR IC WORKS IC#4
1 5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 CAST
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
AT Lower Deck Level REMAINS @ 62.96% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND RC SUMPS AND PIPE
FORMWORKS INSTALLATION IN PROGRESS
HAUNCHING @42.86%
COMPLETE
DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
INTERNAL DRAINAGE
RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE
GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS
STARTED TO INSTALL AT GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G
ESS
LIFT PIT REINFORCING BARS INSTALLATION AND FORMWORKS IN PROGRESS GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION
12 TO 7 / G TO D
REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE
INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT REINFORCING BARS INSTALLATION AND FORMWORKS IN PROGRESS
WALLS WB4a WB4 WB5 CAST
22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP BEAM FORMWORK 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
INSTALL / CAST= 6 WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS DISMANTLE DEEP INSTALLED 10 DROP PANELS SLAB BEAM GH11b GH11c CAST
BOTTOM REINFORCING BARS AND 3 MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / CAST= 6
BEAM FORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8 DEPLOYED TO
ROWS OF GROUND BEAMS INSTALLED
WORKERS ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4