Table of Contents
Page No.
1 PURPOSE....................................................................................................................................... 1
2 SCOPE ............................................................................................................................................ 1
3 BRIEF DESCRIPTION OF CHANGE ....................................................................................... 1
4 SAFETY.......................................................................................................................................... 3
5 APPROVED MATERIALS:......................................................................................................... 3
6 STORAGE AND MIXING............................................................................................................ 3
7 CADWELD PROCEDURE .......................................................................................................... 4
8 SURFACE PREPARATION ........................................................................................................ 4
9 COATING APPLICATION ......................................................................................................... 5
9.1 Cutting Sealant and Top Coat ............................................................................................. 5
9.2 Application of Primer ......................................................................................................... 5
9.3 Application of Sealant ........................................................................................................ 6
9.4 Application of Top Coat ..................................................................................................... 7
10 INSPECTION................................................................................................................................. 7
4 SAFETY
a) The Contractor shall maintain copies of Material Safety Data Sheets (MSDS) for all
controlled products and shall ensure their employees are familiar with the precautions of the
MSDS regarding hazards, necessary personal protective equipment, first-aid measures and be
trained in the handling and use of these products.
b) Work gloves or rubber gloves and safety glasses shall be worn when handling the primer.
c) Protection from inhalation is required. The primer should only be used in well ventilated
areas. Personnel should wear appropriate respiratory protection in areas where vapors may
accumulate.
d) During coating application, no open flames, smoking or welding shall be allowed in the
immediate vicinity during the application of the primer.
e) To prevent contamination of the contents, primer coating containers shall not be left open,
and only authorized persons shall handle the product.
5 APPROVED MATERIALS:
Approved Manufacturers Coating Component Approved Product
Polyguard Primer Polyguard 600 Series Primer
Kemacoat Sealant Kema 250 Mastic
Kemacoat Top Coat Kema 250-12 Tape
Note: liquid epoxy coating systems shall NOT be used for thermite weld connections since they
do not adhere to the cable insulation and create the potential for a water channel to be created.
6 STORAGE AND MIXING
Primer should be stored at a temperature between 5°C and 30°C (40°F and 85°F). Maintain
primer and coating products at temperatures between 15°C to 30°C (60°F and 85°F) for at least
twenty-four (24) hours immediately prior to use. Keep primer and coating products within these
temperature ranges during application. Ensure the primer has not expired prior to use. Mix
primer prior to application.
8 SURFACE PREPARATION
Remove dirt, dust, moisture and other contaminants from the bare metal area and adjoining
coating. Remove rust, scale and thermite weld splatter with a hand wire brush or file.
9 COATING APPLICATION