BACHE A EAU CAPACITE 16 M3

MATERIAUX
ITEM DESIGNATION DES ARTICLES QUANTITE U RATIO PU MONTANT
A BETON 10.52 M3

CIMENT CPA 50 KG 73.64 U 7.00 SAC/M3 340.00 25,037.60


HYDROFUGE SIKA LIQUIDE 47.87 L 0.65 L/SAC 120.00 5,743.92
GRAVIER 8.42 M3 0.80 L/M3 1400.00 11,782.40
SABLE 4.21 M3 0.40 L/M3 1800.00 7,574.40
ACIER 841.60 KG 80.00 KG/M3 26.00 21,881.60

B GICLAGE 49.60 M2

CIMENT CPA 50 KG 1.70 U 7.00 L/SAC 340.00 578.19


SIKA CHAPE 11.90 L 0.24 L/M2 450.00 5,356.80
SABLE ( BROUETTE) 1.70 U 1.00 B/SAC 110.00 187.06
EAU 23.81 L 14.00 L/SAC -

C FINITION 49.60 M2

CIMENT CPA 50 KG 9.92 U 1.00 KG/SAC 340.00 3,372.80


SUPERSIKALITE 9.92 KG 0.2 KG/M2 250.00 2,480.00
SABLE ( BROUETTE) 19.84 U 2.00 B/SAC 110.00 2,182.40
EAU 208.32 L 21.00 L/SAC -

TOTAL VENTE 112,030.33

MAIN D'OEUVRE
ITEM DESIGNATION DES ARTICLES QUANTITE U RATIO PU MONTANT
A TERRASSEMENT

TERRASSEMENT 45.00 M3 500.00 22,500.00


EVACUATION 24.60 M3 500.00 12,300.00
CHARGEMENT 24.60 U 2.50 M3/C 400.00 9,840.00
REMBLAIS 20.40 M3 250.00 5,100.00

B BETONNAGE

MISE EN OEUVRE Y COMPRIS


COFFRAGE FERRAILLAGE 47.10 M2 1200.00 56,520.00

C CREPISSAGE

INTERIEUR 41.60 M2 1.00 120.00 4,992.00


EXTERIEUR 8.00 M2 0.2 120.00 960.00

TOTAL VENTE 112,212.00

RECAPITULATION
TOTAL MATERIAUX 112,030.33
TOTAL MAIN D'OEUVRE 112,212.00
TOTAL GENERAL 224,242.33

ARRETE LE PRESENT DEVIS A LA SOMME DE :

DEUX CENT VINGT QUATRE MILLE , DEUX CENT QUARANTE DEUX DINARS
TRENTE TROIS CENTIMES EN HORS TAXES .
OBSERVATION

POUR UNE EP DE 2 MM

POUR UNE EP DE 2 CM

OBSERVATION
BACHE A EAU

MATERIAUX
ITEM DESIGNATION DES ARTICLES QUANTITE U RATIO

A BETON 1.00 M3

CIMENT CPA 50 KG 7.00 U 7.00 SAC/M3


HYDROFUGE SIKA LIQUIDE 4.55 L 0.65 L/SAC

GRAVIER 0.80 M3 0.80 L/M3


SABLE 0.40 M3 0.40 L/M3
ACIER 80.00 KG 80.00 KG/M3

B GICLAGE 1.00 M2

CIMENT CPA 50 KG 0.03 U 7.00 L/SAC


SIKA CHAPE 0.24 L 0.24 L/M2
SABLE ( BROUETTE) 0.03 U 1.00 B/SAC
EAU 0.48 L 14.00 L/SAC

C FINITION 1.00 M2

CIMENT CPA 50 KG 0.20 U 1.00 KG/SAC


SUPERSIKALITE 0.20 KG 0.2 KG/M2
SABLE ( BROUETTE) 0.40 U 2.00 B/SAC
EAU 4.20 L 21.00 L/SAC

TOTAL TOTAL ACHAT


TOTAL VENTE
MAIN D'OEUVRE
ITEM DESIGNATION DES ARTICLES QUANTITE U RATIO

A TERRASSEMENT

TERRASSEMENT 1.00 M3
EVACUATION 1.00 M3
CHARGEMENT 0.40 U 2.50 M3/C
REMBLAIS 1.00 M3

B BETONNAGE

MISE EN OEUVRE Y COMPRIS


COFFRAGE FERRAILLAGE 1.00 M2

C CREPISSAGE 1.00 M2

INTERIEUR 1.00 M2 1.00


EXTERIEUR 1.00 M2 0.2

TOTAL TOTAL ACHAT


TOTAL VENTE
PU MONTANT OBSERVATION

340.00 2380.00
120.00 546.00

1400.00 1120.00
1800.00 720.00
25.00 2000.00

340.00 11.66 POUR UNE EP DE 2 MM


450.00 108.00
110.00 3.77
0.00

340.00 68.00 POUR UNE EP DE 2 CM


250.00 50.00
110.00 44.00
0.00

7051.43
9166.86
PU MONTANT OBSERVATION

500.00 500.00
500.00 500.00
400.00 160.00
250.00 250.00

1200.00 1200.00

120.00 120.00
120.00 120.00

2850.00
2850.00