Add: CN2-2, Que Vo IP3, Viet Hung Commune, Que Vo District, Bac Ninh Province
Tel : +84 222 3855 988 ; Fax : +84 222 3856 989 ; Emai : admin@wec.com.vn; Website : http://wec.com.vn
Rev.: 0
ISSUED DATE
REV. WRITTEN BY REVIEWED BY APPROVED BY
DD/MM/YYYY
TABLE OF CONTENT
A. GENERAL..................................................................................................................... 3
1. Introduction................................................................................................................. 3
2. Document reference....................................................................................................3
3. Scope of work.............................................................................................................3
4. Definitions abbreviation..............................................................................................3
5. Responsibility..............................................................................................................4
B. ORGANIZATION CHART...........................................................................................4
1. Site Manager:..............................................................................................................4
2. Construction Manager.................................................................................................5
3. QA/QC Manager.........................................................................................................5
4. HSSE Manager............................................................................................................5
C. MANPOWER & EQUIPMENT MOBILIZATION.......................................................5
1. Manpower mobilization..............................................................................................5
2. Equipment mobilization..............................................................................................6
D. CONSTRUCTION SCHEDULE....................................................................................6
E. ERECTION PROCEDURE............................................................................................6
1. Work flow...................................................................................................................6
2. Mobilization and Unloading........................................................................................7
3. Survey of Location and Alignment.............................................................................8
4. Construction tower crane foundation:.........................................................................8
5. .Assembly of Tower Crane..........................................................................................9
F. RISK ASSEESMENT (FOR METHOD STATEMENT).............................................14
1. Method ensures safety...............................................................................................14
2. Method ensures health & environment......................................................................14
3. Method ensures fire prevention and protection.........................................................15
4. Project HSE document for reference.........................................................................16
G. ATTACHMENTS........................................................................................................17
A. GENERAL
1. Introduction.
2. Document reference.
4. Definitions abbreviation.
CLIENT .
PROJECT
…..
…..
CONTRACTOR or
…….
Consortium Members
SUBCONTRACTOR …….
….. …….
HSE Health, Safety and Environment
RA Risk Assessment
5. Responsibility.
Project specifications/
procedure X
Method Statement,
construction procedures X
Installation &
Alignment X
B. ORGANIZATION CHART
ATTACHMENT
1. Site Manager:
Site Manager shall be responsible for the entire activities on site including
preparation, maintaining and monitoring of execution progress. Site manager shall also
Doc. No.: WEC-GEN/DCC-001
Rev.: 0
WE CONSTRUCTION JSC
Add: CN2-2, Que Vo IP3, Viet Hung Commune, Que Vo District, Bac Ninh Province
Tel : +84 222 3855 988 ; Fax : +84 222 3856 989 ; Emai : admin@wec.com.vn; Website : http://wec.com.vn
2. Construction Manager
3. QA/QC Manager
QA/QC Manager will report directly to Site Manager. His responsibilities include
organize, supervise and control QA/QC Team and all aspect of construction’s quality.
4. HSSE Manager
HSSE Manager will report directly to Site Manager. His responsibilities include
organize, supervise and control HSSE Team and all aspect of HSSE during performing
construction works. HSSE Manager and his staffs shall coordinate with Construction
Team to ensure that all Subcontractor’s activities are complied with Contractor’s HSSE
regulations.
ATTACHMENT
D. CONSTRUCTION SCHEDULE
ATTACHMENT
E. ERECTION PROCEDURE
1. Work flow
a) Mobilization
Make sure there is space and firmed pathway for trailer delivery. The trailer and
listed in the equipment register).
WEC will use 8 trailers going to near the Site after register by WEC. Make sure
there is a safe method to unload the working area.
b) Unloading
Four (4) Trailer is going to position for unloading Tower Crane.
Using mobile crane to lifting as: Tower section, Tower head section, Jib, Slewing
platform…all load bearing equipment.
They are unloaded by crane of worker manually up to the material properties.
The average load of trucks carried materials is about 30 ton. Therefore, the
temporary road in the job site must be prepared properly for crane and trucks
working.
Before unloading materials out of trucks, it is required to take pictures of real
materials status to job site.
When after unloading 4 trailers. We continue delivery 4 trailer remain.
c) Material Arrangement
To avoid materials being moved so much on jobsite that might cause unexpected
damages of paint, shapes, when materials delved to jobsite, they must have unloaded
and arranged closed to the designed erection point. Up to the materials shall be stacked
in locations according to the building/areas, should be near to the lifting position
adjacent to the area to be erected. This is to facilitate the sorting and delivery during the
erection.
To provide reference as to the start, survey team will conduct the survey and making
the points. Each point will be marked by driving a stake with a coloured flag on top in
order to distinguish them easily
g) Telescoping installation:
Use Mobile Crane Tadano TG1000M: 100 Ton, boom length 44 m
Checking cylinder’s operation
Checking the condition of hydraulic pump
Use ballast weight to keep balance
Fire prevention and protection should be provided (Mobile gas detector, fire
extinguisher…)
Provide firefighting training for all employees.
Many jobs will involve flammable or combustible materials or tools and equipment,
which require careful handling for fire prevention. There are safe procedures and
practice for every job, materials and piece of equipment, and each employee working
with these will receive appropriate instruction and training.
All workers are responsible for learning and following safe practice and for
reporting unsafe practices to their supervisors. Careless disregard for the roles of fire
safety and prevention jeopardizes everyone’s safety and is grounds for disciplinary
action.
Portable fire extinguishing equipment, appropriate to the job and materials at hand,
will be provided and clearly visible. The number and type of equipment will be in
accordance with local and industry standards. Access to this equipment must be clear at
all times.
Smoking is permitted only in designated areas. This greatest care should be taken at
all times with smoking materials and all combustibles.
Fire hazardous areas requiring to be defined as hot work permit area are designated
by the HSE&S Manager after consulting the OWNER responsible personnel, and the
work is carried out in accordance with the hot work permit procedure.
All inflammable materials and debris near and/or under any hot work, such as
welding, gas cutting, etc., shall be removed or covered with non-combustible materials.
Fire extinguishers shall be supplied near and/or under the hot work locations.
An experienced person shall be assigned responsibility for the hot work and his/her
name shall be displayed in a prominent location at the workplace. The person
responsible shall always inspect and validate the workplace and conditions. Such
inspection includes checks on whether there are any fire hazards during the work and
that no sources of fire remain after the work as well as the proper containment of sparks
during cutting, grinding and welding activities
(….)
G. ATTACHMENTS
and storage areas. Inadequate access to They should have communication facilities;
He must also elevated areas resulting in They must be maintained in satisfactory condition
2. Lifting over Check floor level evenness /enough space for out-
equipment's and riggers.
piping. Use of proper outriggers plates.
Out riggers fully extended.
Crane boom length radius to be barricaded.
Restrict traffic movement.
No lifting shall be done without proper rigging study
and approval of rigging plan. Avoid lifting over major
equipment wherever possible Tie required taglines on
Doc. No.: WEC-GEN/DCC-001
Rev.: 0
the Equipment to control swing.
Check the condition of the lifting tools and tackles
before each use.
Lifting over live lines, double up the slings and
tackles.
Work must be stopped when wind speed exceeding 32
km/h.
Do not leave any suspended load unattended.
V Equipment O O O O Rigging Supervisor/
Installation Foreman, Erector
1. Preparation for Trap in between Competent person (supervisor), certified crane Equipment Safety,
Installation of Fall of part's operator and rigger will thoroughly study and review Officer
Equipment Strike against the lifting plan.
Falling of any loose part's operation shall be discussed with the safety officer t
resulting to serious physical assure proper planning and achieve smooth operation
Fall of loose materials If required, prior to lifting, guy wire (steel rope)
attached to anchor bolts or column will be secured c all
corners of erected Equipment.
Tag Lines will be attached to Structures and sub
members to control load movements.
Doc. No.: WEC-GEN/DCC-001
Rev.: 0
Rigging / Crane Lifting will be stopped if wind velocil
(speed) reached 32 kph.
Nylon Slings, Lifting Devices & Steel ropes will not
be removed until erected Item is fully bolted and
secure.
Full body harness to be used while working in 1,8m
height and anchored on a rigid structure.
Proper scaffolding must be used.
Certified man basket may be used, if necessary.
Static Life lines to be installed at Overhead Structure
to which erectors can hook-up.
Loose Materials at Height to be placed in container
w/lanyards or in pouches.
Ladder Access not be used by Erectors carrying to or
materials in one hand.
Use certified Nylon Slings, Lifting Tackles & Crane.
Barricade the entire swing radius area & warning s
boards to be installed.
VI Cutting, Welding All workers shall be done confined space training.
2.Construct access site Segregate stored materials away from work areas
scaffold Manual handling Place bunting around sharp corners of flashings Supervisor/
3.Working at Falling from height Scaffolding components to remain in storage cradles, Foreman, Erector
height Falling objects cradles to be stacked pn level ground Equipment
Sharp edges Hard hats, gloves and safety glasses to be worn during Safety,
Structure collap 0 0 0 0 all work Officer
Falling from the structure Prestart stretching and flexing by scaffolders Buddy