Академический Документы
Профессиональный Документы
Культура Документы
AND
R. AUDY
Piette, Arrdy, Lipitray, Bertratrcl, atld Letnierrx, It!yPt~ieru.sCotrseils, Qrribec, Qrribec.
Received June 17, 1971
It has often been shown by previous investigators that the existing pile driving formulas yield
bearing capacities which usually d o not stand in good correlation to the actual bearing capacities of
piles in sand. These poor correlations have always been attributed to the formulation of the equations.
Based on the observations made on a very large foundation built in an homogeneous sand deposit
it is shown in the present paper, that the poor quality of the usual pile driving formulas originates
essentially in the estimate of the driving energy; while it is assumed that each blow delivers a constant
energy equal to W X H for drop hammers, it appears actually that the energy delivered by a given
equipment varies systematically from blow to blow. This conclusion, drawn from a statistical analysis
of 478 driving records, is confirmed by the driving tests made on four instrumented piles.
The results of 45 load tests also confirm this conclusion in showing no correlation between the
actual bearing capacities and the estimated driving energy or the bearing capacities computed from
five different formulas. The observations also show a possible time effect on the bearing capacities
For personal use only.
Introduction Q, = cw x H)IS
The most usual method of construction of where W is the weight of the ram in tons,
piled foundations being by dynamic driving, H the drop height in inches, and S the set
the idea of measuring the energy necessary per blow in inches. Although the simplest
to bring the pile to its final depth in the soil possible, this formula is no more mentioned
and of using this energy to predict the bearing or used, so that Wellington's formula, also
capacity of the pile has been logically put called the Engineering News Formula (Well-
forward very earlv in the history of piling. ington 1893) is the oldest one to be well
The first mathematical formulation of a known and used. It is still simple but a
correlation between the static bearing capacity constant C has already been added to take
and the dynamic driving resistance of a pile in account the energy losses occuring at the
is due to Sanders (1851) and was of the most impact :
simple form i.e.,
Qf = (H X H)/(S + C)
lPaper presented at the 24th Canadian Geotechnical In the search for a greater "accuracy"
Conference, Halifax, Nova Scotia, September, 1971. or for more mathematically looking formulas,
Canadian Geotcchnical Journal, 9, 47 (19i2)
a large number of sophisticated expressions of 93 piles as computed by these formulas,
have been proposed since that time. As a vary from 0 . 2 9 to 0 . 8 1 while it should be
matter of fact, Dean (1935) listed 27 different equal to one for a perfect correlation; by
formulas, while Chellis (1951) referred to a statistical adjustment of the Gates formula
36 expressions; actually the real number of they establish a new formula which seems
existing formulas may be somewhat from to be slightly better as the coefficient of cor-
50 t o 100, a n d possibly more. However it is relation is equal to 0.85.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
of great interest to note that the only differ- Surprisingly enough, while the empirical
ences between the various formulas lie in the coefficients involved in the various formulas
introduction of a variable quantity of empir- have been the object of numerous investiga-
ical constants, while the basic parameters tions. only o.le good study has been carried
remain exactly the same for all expressions, out on the basic parameter involved in all
i.e. the weight of the hammer, the height of formulas, namely the energy delivered t o the
the d r o p and the penetration of the pile, also pile during usual driving operations. T h e
called the set under the effect of one blow. Michigan study on pile driving hammers
This has already been noted by Cummings reported by Housel (1965) was concerned
(1942) who stated: "there are only five basic essentially with the efficiency of a number of
types of dynamic pile driving formulas, diesel a n d steam hammers but succeeded in
. . ., a n d all of them can be represented by giving valuable information on the general
the formula: behaviour of pile driving systems a n d o n the
variability of the energy delivered t o a pile
For personal use only.
Over a length of about 9000 ft (2700 m) FIG. 2. Grain size distribution of St. Charles River
on both sides of the river the soils conditions sand.
are very uniform. A typical soi! profile is
shown on fig. 1. The sand layer has been
investigated by means of more than 300 split
spoon samples and standard penetration
tests, and 78 undisturbed piston samples.
One hundred and thirty-seven grain size
distributions have been determined on samples
originating from locations distributed all
over the site; the results, presented in fig. 2,
show that the sand is a uniform medium sand
(note that particles larger than g4 were found
only on 5y0 of the samples in a limited super-
ficial zone). The statistical distribution of the
FIG. 1. Typical soil profile at St. Charles River site. FIG. 3. Statistical distribution of N and rd.
50 CANADIAN GEOTECHNICAL JOURNAL. VOL. 9. 19i2
may be considered as very homogeneous. and taking advantage of the uniformity of
This is confirmed by the results obtained on the sand deposit, the design of the foundation
the undisturbed samples: the in situ dry was based on the results of an extensive full-
unit weight varies from 93.5 to 102 1b/ft3 scale pile driving and testing program.
(1380 to 1571 kg/m3) around an average of The testing program was planned in such
97.5 1b/ft3 (150 1 . 5 kglm3) and the relative a way as, first to reproduce as exactly as pos-
density measured according to ASTM D- sible the working conditions of the piles in
the foundation; second to allow a comparison
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
any of the existing bearing capacity formulas, sand (fig. 5), which was used to determine
ALE DRIVING R W
to control the quality of the individual piles, quencies of 15% and 85Gi/,, thus indicatins
and that an analysis of the observed driving that 709; of the observations are randomly
energies would be of great interest. distributed between the different intervals.
A statistical analysis of the observations As shown in Table 1, the standard deviation
on the driving energy has been made for 478 increases with an increasing energy and a
piles from the south shore. The energies decreasing number of observations from
86 kips ft/ft (38.7 t m/m) at a depth of 1 ft
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
vidual observations are very largely scattered for an absolutely non-reproducible or ran-
around this average. The cumulated frequency domly scattered phenomenon. The actual
curves shown on fig. 9 for each depth level are values indicate a phenomenon of low re-
more or less linear between cumulated fre- producibility or large scattering.
TAVENAS AND AUDY: LI1\IIITATIONS O F DRIVING FORMULAS 53
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
If we now consider that the soil deposit is over-simplification of the phenomenon; the
fairly homogeneous and that the piles are fact that the energies so computed are widely
For personal use only.
identical and driven in rows (see fig. 4), thus scattered, as shown in fig. 8 and 9, is no at
eliminating any possible group effect, so that all surprising.
the driving energies should actually be quite
uniform and statistically distributed according Driving Tests on Instrumented Piles
to a Gaussian law with a very low coefficient
of dispersion, the observed random distri- In order to further investigate the driving
bution has to be attributed to the procedure behaviour of the piles and to confirm the
for evaluating the energy, and more precisely previous observations, four driving tests have
to the assumption that the energy generated been carried out on instrumented piles of
by each blow is equal to the product of the various lengths. The piles were equipped
weight of the hammer by a constant height with a central vertical pipe on which electric
of drop, and therefore is a constant. On the strain gauges were glued at five different
contrary, it becomes evident that the energy levels, in particular at 1 ft ( . 3 m) above the
delivered to the pile varies widely from blow pile tip and at 8 ft (2.4 m) below the pile head.
to blow due to the many variable parameters The strain gauges were glued on the outside
involved: the actual height of drop which is of a 2 in. extra strong steel pipe, in groups of
determined by hand of the operator of the four, with two active and two reference
rig and is essentially variable, the drag gauges connected in full bridge. The gauges
exerted by the cable during clutch release, were protected with a waterproof coating and
the friction of the hammer along the lead two layers of electric tape.
during the drop, the relative position of the The instrumented pipes, equipped with
hammer, the driving cap and the pile at im- dowels spaced at 12 in. (30.5 cm) symetrical-
pact, the state of the wood cushion on top ly to the gauge levels, were attached in the
of the driving cap, which certainly varies axis of the reinforcement cages made up of
from blow to blow, the state of the fiber six #5 with f 3 spiral styrup, spaced at 6 in.
cushion between the cap and the pile head, (15.2 cm) (fig. 10). After correct positioning
the rythm of blows application, the elastic of the cages, the piles were cast in the standard
behaviour of the pile, etc. . . Therefore, the hexagonal molds with a concrete having a
assumption that the energy delivered to the 7500 p.s.i. (52 700 kg/m') minimum strength.
pile is identical from blow to blow and equal In the same mold a reference piece of pile was
to W X H must be considered as a large casted with the same concrete; the reference
54 C:\NADI.\N GEOTECHNICAL JOURNAI,. VOL. 9, 1 9 i 2
piece had a length of 36 in. (91.44 cm) and were measured at ground level. Fig. 11
was equiped with an instrument pipe bearing reproduce examples of the results obtained.
a single strain gauges group glued at mid A total of 20 series of measurements have
height; this reference piece was used to meas- been made.
ure in the laboratory the modulus of elast- From the peak driving force Fl, observed
icity of the finished pile on the same day at pile head, and the maximum displacement
as the tests were made and to checlc the read- S,, at the same level under the impact of a given
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
ings given by the strain gauges. blow, the actual energy at pile head El, =
For the tests, after balancing the different F,, x S,, has been computed. From the peak
bridges with the pile in horizontal position, driving force Ft at pile tip and malting the
the standard bridge measuring unit was con- assumption that the final set S at ground level
nected to an oscillograpl~and the sensitivity represented to tip displacement under the
of the oscillograph set so as to give 250 ~1 impact of a given blow, the actual energy a t
in. per $ in. (. 63 cm) division on the cathodic pile tip Et = Ft x S was also computed.
screen. At different states of driving, dynamic The computed energies El, and Et have
stress measurements were made for series been compared to the energy theoretically
of three consecutive blows, photos being delivered by the blow, i.e. E = W x H. The
taken of the traces on the oscillograph. For
the same blows the deformation of the piles
/- reinforcing : 6 -5
/- styrrup : 5 n 6"
instrumented pipe : 0 I"
2
/'-
strain gouges
VERTICAL SECTION
statistical distribution of the computed The loading tests have been performed on
ratios E,,/E and E,/E is given in fig. 12. piles, driven at various locations on both shores
If the product W x H would accurately of the river; and which were usually selected
represent the energy delivered to the pile on the basis of a final driving resistance below
and if each blow would be nearly identical, average. The final sets observed on these
the E,JE curve should be nearly a vertical piles varied from 0.22 in. to 0.66 in. per
line passing by the abcissa 1; as shown in blow. The test load was applied by means
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
fig. 9, this is by far not the case, the observed of the same jack for all piles, the necessary
values of E,,/E being scattered between 0 . 6 reaction being provided either by a loaded
and 2 . 2 around an average of 1.1. This result platform or by pull-out reaction on four
therefore confirms the previous conclusions: neighbouring piles. The loads were applied
the actual energy delivered by a free fall in 12.5 tons (1 1 . 3 t) increments sustained
hammer during normal driving operations for 60 min. up to a maximum load equal to
differs greatly from blow to blow and is four times the design bearing capacity of the
generally not equal to the product W x H. piles. A typical load-settlement curve is given
in fig. 13, which shows a clear definition of the
Validity of the Driving Formulas failure load; however, on 25% of the piles
The analysis of the observations on the no failure was reached, the ultimate bearing
assumed driving energy has led to the con- capacity being then extrapolated from the
clusion that the usual energy estimate was not form of the load-settlement curve. Table 3
satisfactory, and when used in pile driving gives the complete basic information on the
45 tested piles.
For personal use only.
In all these formulas, the constants were ell = efficiency of the hammer = 0 . 8 ac-
selected as follows : cording to Whitaker (197 1)
C = constant of the hammer = 1 ac-
cording to Chellis (1951)
C, = 0.15, C, = 0.50, C, = 0 . 1 0 Accord-
ing to Chellis (1951)
rz = 0.25 according to Chellis (1951)
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
pp
el, X W X H
Engineering News Qfcl = s+
(Wellington 1893)
el, X W X H
Danish Qfc3 = etlX W X H B
(Sorensen & Hansen 1957)
S + ( 2 X A X E )
Modified Gates
(Olson & Flaate 1967)
-
N m r : None of the presented formulas contains a factor of safety.
T \\'EN \S .\ND .\UDY: LIMIT.\TIONS O F DRIVING FORlIUL.\S
TABLE
3. Characteristics of tested piles
- ----
Test Pile C?jm L WII H Blows/foo t
No. No. Tons Foot Kips Foot Last foot
--
1
2
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
For personal use only.
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
J1
J2
J3
54
J5
J6
estimated.
'@j,/,,
The computed values of Qf,and the energy program. The sole observation of fig. 14
delivered to drive the last foot of pile have shows that no valuable correlation exists
been compared to the measured ultimate between any of the computed bearing capac-
bearing capcaity Of,. The results obtained ities and Or,,,.By means of a least square
are given in fig. 14, where the light symbols adjustment method the regression lines Qf,=
refer to the piles tested during the construction +
a Qf,, b and Qf,,= a' Qf, b' have +
of the foundation and the dark symbols to been defined as shown on fig. 14; the values
the piles tested during the design testing of the coefficients a, b, a', and b' as well as
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
For personal use only.
The Effect of Time on the Bearing Capacity Yang also considers the effect of the soil
The influence of time on the behaviour of structure and suggests that for piles driven
piles driving in cohesionless soils has often in dense sand a low driving resistance has to
been recognized as a potential difficulty be expected at redriving while for loose sand
related to the use of pile driving formulas the driving resistance will increase with time;
for predicting the static bearing capacity of however, he failed to show an evidence of this
such piles. last statement on case histories.
Parsons (1966) has presented case histories During the initial testing program, as re-
from the New York City area which show ported by Tavenas (1971) the piles were driven
that the penetration resistance of piles in in 10 ft (3.0 m) increments and load tested
granular soils may vary with time. As re- after each driving sequence. Delays of at
ported the observed penetration resistances least 12 h between the end of driving and the
at the beginning of redriving of steel piles in beginning of the test, and about 24 h between
submerged sand were much lower than at the end of the test and the start of the next
the end of the initial driving which had been driving sequence were provided. No signif-
performed weeks or months before; also, icant differences were observed in the driving
resistances at the end of driving and at the
beginning of redriving despite a delay of at
TABLE 4. Characteristics of correlation between QM least 48 h between these operations. Thus,
and QC as shown on fig. 14, the correlation between
Q , and the driving energy is the same which-
Coefficient Regression lines
Pile driving of - ever energy is considered.
formula correlation a b a' b' If we now consider the results of the test-
piles in the actual foundation, fig. 14 shows
ENR 0.181 0.052 44.0 0.810 60.8 clearly that their behaviour was sensibly
Hiley 0.131 0.030 46.5 0.284 86.6
Danish 0.272 0.234 100.5 0.387 52.7
different, their static bearing capacity being
Gates 0.225 0.081 59.0 1.169 22.2 usually much larger for the same fina! driving
Gates modified energy. As these piles were perfectly identical
by Olson and to the reference test piles with respect to
Flaate 0.253 0.130 67.9 0.727 41.8 material, geometry, driving equipment, spac-
60 CANADIAN GEOTECHNICAL JOURNAL. VOL. 9.1972
ing, and surrounding soil, the systematic vestigated and questioned. However, these
increase of the ultimate bearing capacity analysis were usually based on observations
has to be explained by the influence of the made on various types of piles driven at differ-
only variable parameters, i.e. the time lag ent sites so that not real uniformity of the
between driving and testing of each pile. basic information was ensured. Thus, the
Fig. 15 shows the relationship between thc conclusions of these investigations could
time lag and the ratio of the ultimate bearing always be related, no only to the basic
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
capacity of each pile to the ultimate bearing phenomenon under investigation. but also
capacity of the corresponding test pile for to variations in the site conditions, in the type
which the time lag was 12 h. Despite an of pi!es as well as in the testing techniques, and
important scattering of the results, a definite were therefore not definite.
tendency can be observed, the ultimate On the contrary, the investigation presented
bearing capacity increasing during the first in this paper has been carried out on a very
15 to 20 days to reach a constant value 70% large pile foundation where a good uniformity
higher than that observed a t 12 h. As observed in all the parameters was ensured: a unique
by Tavenas (1970) in an analysis of the first type of piles, hexagonal precast concrete
15 tests performed at the St. Charles River piles with an equivalent diameter of 12 in.
Site. this phenomenon cannot be explained (30.5 cm), was driven by the same equip-
by the influence of pore pressure, as the sand ment (drop hammer) in a sand deposit which
is so pervious (K = 10-2 cm/sec) that com- was proven to be uniform in its physical and
plete pore pressure dissipation can be expected mechanical properties. Therefore ideal con-
to occur within a few hours; the increase in ditions were provided for an extensive in-
For personal use only.
bearing capacity has therefore to be related to vestigation of the validity of the usual con-
changes occuring in the sand structure around trols of quality based on the driving energy.
the pile. The statistical analysis of 478 complete
driving record shows that the driving energy,
as evaluated by multiplying the weight of the
Very often in the past the validity of the hammer by the drop height, is very widely
existing pile driving formulas has been in- scattered. The limits of the range of variation
driving behaviour of the pile soil system, but weeks after driving, the long term behaviour
to the erroneous evaluation of the driving of these piles being therefore not related to the
energy delivered to the pile, and mainly driving resistance.
on the assumption that each blow generates
an identical energy equal to W x H. Acknowledgments
Driving tests carried out on instrumented The project analyzed in this paper is owned
piles show that the actual energy delivered by by the Federal Government of Canada,
different blows varies much and is usually the government of the Province of QuCbec,
not equal to W x H. and the City of QuCbec. The Technical
The usual energy estimate being proved Committee for the St. Charles River project
erroneous, it is possible to conclude, first which represents the owners gave the per-
that any pile driving formulas in which this mission for the publication of the data.
estimate will be used will also be erroneous, The presentation of this paper was sponsored
second that the control of the driving energy by grant No. A-7724, parts of the instrumenta-
cannot even be used to verify the uniformity tion being supported by grant No. A-1503
For personal use only.
in the bearing capacities of the piles and to of the National Research Council of Canada.
extrapolate to them the observations made on
a few tests piles. Actually the driving energy
control was absolutely useless on the reported AGERSCHOU, H . A. 1962. Analysis of the Engineering
pile job. news pile formula. J. Soil Mech. Found. Div.,
A.S.C.E., 88 (SM5).
The analysis of the results of 45 load tests A.S.C.E. 1941. Pile driving formulas, progress report of
confirms this conclusion: it is shown that the committee on the bearing value of pile founda-
the bearing capacity computed by any of the tions. Proc. A.S.C.E., 97, pp. 853-866.
five following formulas, Wellington, Hiley, CHELLIS,R. D. 1951. Pile foundations-theory-design
-practice. McGraw Hill, New York.
Danish, Gates, Gates modified by Olson, CUMMINGS, A. E. 1940. "Dynamic Pile Driving For-
and Flaate, had no useful correlation to the mulas". J. Boston Soc. Civil Eng., 27 (I).
actual bearing capacity, the highest coefficient CUMMINGS, A. E. 1942. Discussion to "pile driving
of correlation being 0.27. formulas. Progress Report of the Committee o n
the Bearing Value of Pile Found." Proc. A.S.C.E.,
As this poor quality of the results, obtained 68, p. 172.
by pile driving formulas, is at least partly, DEAN,A. C. 1935. Piles and pile driving. Crosby Lock-
related to the erroneous estimate of the wood, London.
driving energy, efforts should be made now GATES,M. 1957. Empirical formula for predicting pile
develop a technique for measuring as accurate- bearing capacity. Civil Eng. 27 (3), pp. 65-66.
HILEY,A. 1925. A rational pile driving formula and its
ly as possible the actual energy delivered to application in piling practice explained. Engineering,
the pile by each blow; this could probably 119, pp. 657-721.
be achieved by developing an instrumented HOUSEL,W. S. 1965. Michigan study of pile driving
driving cap. In the meantime the validity hammers. J. Soil Mech. Found. Div., A.S.C.E.,
of the usual pile driving formulas is best 91 (SM5.)
1966. Pile load capacity: estimates and test
defined by a statement made by Peck (1942): results. J. Soil Mech. Found. Div., A.S.C.E.,
"It can be demonstrated by a purely statistical 92. (SM4).
approach that the chances of guessing the MOHR,H. A. 1942. Discussion to "pile driving formulas:
bearing capacity of a pile are better than of progress report of the committee on the bearing value
computing it by a pile driving formula". of pile foundation." Proc. A.S.C.E., 68, pp. 170-172.
OLSON,R. E., and FLAATE,K. S. 1967. Pile driving
Finally, it is shown that, even if a method formulas for friction piles in sand. J. Soil Mech.
of measurine the drivingu energv
.
2 -, would be Found. Div., A.s.c.E., 93. (SM6).
62 CANADIAN GEOTECHNICAL JOURNAL. VOL. 9.19i2
PARSONS, J. D. 1966. Piling difficulties in the New York lonnage non remanit. Can. Geotech. J. 7, (1) pp.
area. J. Soil Mech. Found. Div., A.S.C.E., 90 (SMI) 37-53.
PECK,R. B. 1942. Discussion to "pile driving formulas: TAVENAS, F. 1970. Discussion to "tests on instrumented
progress report of the committee on the bearing piles, Ogeechee River site" by A. S. Vesic, J. Soil
value of pile foundations". Proc. A.S.C.E., 68, pp. Mech. Found. Div., A.S.C.E. 96 (SM6).
323-324. 1971. Load tests results on friction piles in
SANDERS, J. 1851. Rule for calculating the weight that sand. Can. Geotech. J. 8 (1).
can be safely trusted upon a pile which is driven for TEAZAGHI, K., 1942. Discussion to "pile driving formulas:
the foundation of a heavy structure. J. Franklin progress report of the committee on the bearing
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14