Вы находитесь на странице: 1из 16

Limitations of the Driving Formulas for Predicting the

Bearing Capacities of Piles in Sand'


F. TAVENAS
Dipartetnetlt de Ginie Civil, Fac~rlthcles Sciexces, Utliversitt Lava], Qrribec, Quibec.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

AND
R. AUDY
Piette, Arrdy, Lipitray, Bertratrcl, atld Letnierrx, It!yPt~ieru.sCotrseils, Qrribec, Qrribec.
Received June 17, 1971

It has often been shown by previous investigators that the existing pile driving formulas yield
bearing capacities which usually d o not stand in good correlation to the actual bearing capacities of
piles in sand. These poor correlations have always been attributed to the formulation of the equations.
Based on the observations made on a very large foundation built in an homogeneous sand deposit
it is shown in the present paper, that the poor quality of the usual pile driving formulas originates
essentially in the estimate of the driving energy; while it is assumed that each blow delivers a constant
energy equal to W X H for drop hammers, it appears actually that the energy delivered by a given
equipment varies systematically from blow to blow. This conclusion, drawn from a statistical analysis
of 478 driving records, is confirmed by the driving tests made on four instrumented piles.
The results of 45 load tests also confirm this conclusion in showing no correlation between the
actual bearing capacities and the estimated driving energy or the bearing capacities computed from
five different formulas. The observations also show a possible time effect on the bearing capacities
For personal use only.

of concrete piles in sand.


I1 a CtC dCmontre antkrieurement par divers chercheurs que les formules actuelles de battage de
pieux conduisent i la prediction de capacitCs portantes qui ne concordent pas avec les capacitCs por-
tantes rtelles des pieux dans le sable. Ce manque de concordance a toujours CtC attribue B un dtfaut
dans la forme des Cquations.
Le prCsent article fait Ctat des observations faites lors de I'Ctude d'une fondation importante cons-
truite sur un dCpBt hornogine de sable. Ces observations dernontrent que le dCfaut des formules usuel-
lcs de battage origine dans l'estimation de I'energie de battage; alors que l'on admet gCnCralement
que chaque coup d'un martea11 pilon fournit m e Cnergie constante Cgale 2 W X H, il appert cn fait
que l'energie fournie par un Cquipenlent donne varie systematiquement d'un coup i l'autre. Cette
conclusion tiree d'une analyse statistique de 478 rapports de battage, est confirnlCe par des essais de
battage exCcutCs sur quatre pieux instrumentCs.
Lcs rCsultats de 45 essais de chargement confirment egalement cette conclusion en dCnlontrant le
nlanque de correlation entre les capacitCs portantes rCelles et celles estimCes en partant de l'energie
de battage au nloyen de cinq fornlules diffkrentes. Les observations dirnontrent aussi qu'il existe
possiblement un effet de temps sur les capacitCs portantes des pieux de bCton dans le sable.

Introduction Q, = cw x H)IS
The most usual method of construction of where W is the weight of the ram in tons,
piled foundations being by dynamic driving, H the drop height in inches, and S the set
the idea of measuring the energy necessary per blow in inches. Although the simplest
to bring the pile to its final depth in the soil possible, this formula is no more mentioned
and of using this energy to predict the bearing or used, so that Wellington's formula, also
capacity of the pile has been logically put called the Engineering News Formula (Well-
forward very earlv in the history of piling. ington 1893) is the oldest one to be well
The first mathematical formulation of a known and used. It is still simple but a
correlation between the static bearing capacity constant C has already been added to take
and the dynamic driving resistance of a pile in account the energy losses occuring at the
is due to Sanders (1851) and was of the most impact :
simple form i.e.,
Qf = (H X H)/(S + C)
lPaper presented at the 24th Canadian Geotechnical In the search for a greater "accuracy"
Conference, Halifax, Nova Scotia, September, 1971. or for more mathematically looking formulas,
Canadian Geotcchnical Journal, 9, 47 (19i2)
a large number of sophisticated expressions of 93 piles as computed by these formulas,
have been proposed since that time. As a vary from 0 . 2 9 to 0 . 8 1 while it should be
matter of fact, Dean (1935) listed 27 different equal to one for a perfect correlation; by
formulas, while Chellis (1951) referred to a statistical adjustment of the Gates formula
36 expressions; actually the real number of they establish a new formula which seems
existing formulas may be somewhat from to be slightly better as the coefficient of cor-
50 t o 100, a n d possibly more. However it is relation is equal to 0.85.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

of great interest to note that the only differ- Surprisingly enough, while the empirical
ences between the various formulas lie in the coefficients involved in the various formulas
introduction of a variable quantity of empir- have been the object of numerous investiga-
ical constants, while the basic parameters tions. only o.le good study has been carried
remain exactly the same for all expressions, out on the basic parameter involved in all
i.e. the weight of the hammer, the height of formulas, namely the energy delivered t o the
the d r o p and the penetration of the pile, also pile during usual driving operations. T h e
called the set under the effect of one blow. Michigan study on pile driving hammers
This has already been noted by Cummings reported by Housel (1965) was concerned
(1942) who stated: "there are only five basic essentially with the efficiency of a number of
types of dynamic pile driving formulas, diesel a n d steam hammers but succeeded in
. . ., a n d all of them can be represented by giving valuable information on the general
the formula: behaviour of pile driving systems a n d o n the
variability of the energy delivered t o a pile
For personal use only.

from blow t o blow. I n particular, for the piles


where Rd is the dynamic resistance of the pile driven in col~esionlesssoils at the Muskegon
a n d Q the energy losses that occur during s'te, Housel showed that the energy per blow,
impact". described by the R-value (ratio of the number
With the great development of pile driving of blows of a given hammer to drive a pile
operations, the various formulas have been on a given distance to the average number of
increasingly used and a t the same time their blows of all hammers t o drive this type of
validity has been investigated a n d merely pile o n that distance), is widely scattered
questioned. Many references in the literature between limits of 0 . 2 a n d 1 . 5 for example.
a r e dealing with the validity of one o r the H e concluded that energy losses occurring a t
other formula o r with the fundamental impact were the cause of the h r g e scattering.
aspects of pile driving formulas; important While this study showed that the actual
papers have been presented by Cummings energy delivered by a diesel or steam hammer
(1940), ASCE (1941) with related discussions was systematically different from its "rated
by M o h r (1942), Terzaghi (1942), Peck energy" a n d was much variable, therefore
(1942) a n d Cummings (1942), Sorensen a n d m a k ~ n gthe use of that rated energy in driving
Hansen (1957), Agerschou (1962), Housel formulas very questionn~ble, the problem
(1966), a n d recently, Oslon and Flaate (1967). of the evaluation of the energy delivered by
Typically, many of these papers are concerned a free fall hammer is still t o be solved. It could
with the validity of the different coefficients be formulated as follows: what is the accuracy
involved in the analyzed formulas a n d are of the driving energy's estimate obtained by
based o n actual field loading tests performed multiplying the weight of the hammer W
o n various sites. They show the evidence of a by the height of drop H ? Also, does each
very large scattering in the results given by any blow of a given driving system deliver exactly
formula a n d eventually try to reduce it by the same energy, equal t o W x H , t o t h e
some kind of statistical adjustment of the pile, and if this is not the case. what is the
coefficient o r by introducing new empirical variation from blow to blow? T o evaluate
parameters. F o r example, Olson a n d Flaate these phenomena, one should analyze a
(1967) analyze seven formulas and show that large quantity of driving records of identical
the coefficient of correlation, between the piles driven by the same equipment in an
observed failure loads a n d the ultimate loads llomogeneous soil deposit.
T.AVEN:\S AND XUDY: LIMITATIONS OF DRIVING FORMUL:\S 49
Such conditions have been encountered at N values is shown in fig. 3. The standard
the St. Charles River site in Quebec City, penetration index N increases slightly with
Canada, where a large pile foundation con- depth with a mean value of 23 for the entire
sisting of three parallel rows of precast con- deposit. As this average value applies to any
crete piles was built in a fairly homogeneous zone of the site this medium dense sand deposit
deposit of fine sand. In this paper the prop-
erties of the deposit, the characteristics of
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

the foundation and the analysis of the pile


-
driving observations are presented.
-

Geotechnical Properties of the


St. Charles Ever Site -
The foundation under consideration is part -
of two 12 500 ft (3800 m) long retaining walls
-
in construction on both sides of the St. Charles
River in downtown Quebec City. The soil -

investigation consisted of 32 standard borings -


with split spoon sampling and standard
penetration tests and of 10 special borings
with undisturbed sampling of the sand. The -
1.

technique used and the results obtained have Sllt


fins I medium I awse I hns I
been published by Tavenas et a1 (1970). sond I
For personal use only.

Over a length of about 9000 ft (2700 m) FIG. 2. Grain size distribution of St. Charles River
on both sides of the river the soils conditions sand.
are very uniform. A typical soi! profile is
shown on fig. 1. The sand layer has been
investigated by means of more than 300 split
spoon samples and standard penetration
tests, and 78 undisturbed piston samples.
One hundred and thirty-seven grain size
distributions have been determined on samples
originating from locations distributed all
over the site; the results, presented in fig. 2,
show that the sand is a uniform medium sand
(note that particles larger than g4 were found
only on 5y0 of the samples in a limited super-
ficial zone). The statistical distribution of the

FIG. 1. Typical soil profile at St. Charles River site. FIG. 3. Statistical distribution of N and rd.
50 CANADIAN GEOTECHNICAL JOURNAL. VOL. 9. 19i2
may be considered as very homogeneous. and taking advantage of the uniformity of
This is confirmed by the results obtained on the sand deposit, the design of the foundation
the undisturbed samples: the in situ dry was based on the results of an extensive full-
unit weight varies from 93.5 to 102 1b/ft3 scale pile driving and testing program.
(1380 to 1571 kg/m3) around an average of The testing program was planned in such
97.5 1b/ft3 (150 1 . 5 kglm3) and the relative a way as, first to reproduce as exactly as pos-
density measured according to ASTM D- sible the working conditions of the piles in
the foundation; second to allow a comparison
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

2043-64T is equal to 587, k 15%.


Due to this homogeneity this site is per- between different pile materials, i.e., steel,
fectly suited for any large scale investigation precast concrete, and timber; third to give
on the behaviour of foundations, in particular information not only on the variations of the
of piles. ultimate bearing capacities with the length
of the piles in the sand and with the driving
Design and Characteristics of the resistances but also on the variations of the
Pile Foundation unit skin friction and point resistance with
Due to structural and architectural con- the depth in sand. The technique and the
siderations, it was proposed to rest the walls results have been reported by Tavenas (1969,
on two or three rows of piles driven in the 1971).
sand; typical plans and sections are shown in For design purposes the three following
fig. 4. As the bearing capacity of friction relationships were developed:
piles in sand is practically impossible to 1) The relationship between the ultimate
evaluate with a satisfactory accuracy from bearing capacity Q, and the length of pile in
For personal use only.

any of the existing bearing capacity formulas, sand (fig. 5), which was used to determine

lWCk (ROSS SECTION

ALE DRIVING R W

FIG.4. Typical implantations of the piles in the foundation.


TAVENAS A N D AUDY: LIMITATIONS O F DRIVING FORMULAS 51

a, tLms 2) The relationship between Q, and the


o energy necessary to drive the last foot of each
pile (fig. 6), which was intended to be used
10 as a control of the quality of each pile driven
in the actual foundation, and of the uniformity
=- 20 of the piling work.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

31 3) The relationship between Qf and the


f 50 total energy necessary to drive the piles in
0
= the sand (fig. 7), which could possibly be
% 40 used as a complement to the second correla-
tion.
50 According to the results obtained, five
categories of precast concrete piles were
60 designed with working capacities of 20, 22,
FIG.5. Ultimate bearing capacity vs. length of pile 25, 27.5. and 32.5 tons (18.0, 19.8, 22.5,
in sand. 24.8, and 29.3 t) and corresponding lengths
of 15, 18, 22, 25, and 32ft (4.6, 5.5, 6.7,
O f , tDnl
7.6, and 9 . 7 m) in the sand. The specifications
- 0 called for the piles being driven by means of a
-8
% free fall hammer weighing about 7000 1b
;- m (3.2 t) operated by clutch release at a drop
For personal use only.

3 height of no more than 30 in. (76.2 cm)


2 800 the driving energy had to be controlled for
6
r 6
the last 2 ft (.6 m) of each pile and for the
entire length of one every 20 piles, and the
energy necessary to drive the last foot of each
1600
pile was specified in order to comply with
the values given in fig. 6. Finally load bearing
2000 tests to failure were specified on one of
FIG.6. Ultimate bearing capacity vs. driving energy every 150 piles of each
i n the last foot. A total of 4160 piles on the north shore
and 4520 piles on the south shore had to be
driven. Approximately 707, of the work
is now completed; 478 full driving records
have been compiled on the south shore,
and 45 driving and load bearing tests have
been made on both shores. These results
obtained on identical piles driven with the
same equipment in an homogeneous sand
deposit will be further analyzed.

Analysis of the Observed Driving Energies


Very early in the control of the driving
operations it appeared that the observed
energies varied much from pile to pile. At
the same time, load bearing tests carried out
FIG. 7. Ultimate bearing capacity vs. total driving on piles, for which the energy in the last foot
energy. was much below the required limit, showed
that the ultimate bearing capacity was in
the characteristics of the piles necessary to excess of the required value. It appeared
ensure a factor of safety of 3 against failure therefore, that the relationship shown in
in the actual foundation. fig. 6 was not unique and could not be used
52 CANADIAN GEOTECHNICAL JOURNAL. VOL. 9, 1 9 i 2

to control the quality of the individual piles, quencies of 15% and 85Gi/,, thus indicatins
and that an analysis of the observed driving that 709; of the observations are randomly
energies would be of great interest. distributed between the different intervals.
A statistical analysis of the observations As shown in Table 1, the standard deviation
on the driving energy has been made for 478 increases with an increasing energy and a
piles from the south shore. The energies decreasing number of observations from
86 kips ft/ft (38.7 t m/m) at a depth of 1 ft
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

necessary to drive the lst, 5th, loth, 20th,


25th, and 30th ft of pile in the sand have been (. 3 m) to 173 kips ft/ft (77.9 t m!m) depth
analyzed and the following parameters de- of 30 ft (9.1 m). On fig. 8, the curves repre-
termined: the minimum, maximum and aver- senting the variation with the depth of the
age of all observations; the statistical distri- average energy plus or minus the standard
bution of the observed values in form of deviation are shown. Their form confirms
cumulated frequency curves; the standard that the observed variability of the energy is
deviation and the coefficient of dispersion, not related to the behavionr of the soil in
equal to the ratio of the standard deviation which the pile is driven but is due to a phenom-
to the average. enon independant of the tota! energy. The
computed coefficients of dispersion vary
Fig. 8 gives the variations of the minimum, from 0.450 to 0.225, a value of 0.25 being
maximum and average energy per linear foot possibly typical. Such values have to be com-
as a function of the depth of pile in sand. pared to the possible limits of the coefficient
While the average energy increases linearly of dispersion, equal to 0 for a perfectly re-
with depth, this figure shows that the indi- producible phenomenon and to about 0.5
For personal use only.

vidual observations are very largely scattered for an absolutely non-reproducible or ran-
around this average. The cumulated frequency domly scattered phenomenon. The actual
curves shown on fig. 9 for each depth level are values indicate a phenomenon of low re-
more or less linear between cumulated fre- producibility or large scattering.
TAVENAS AND AUDY: LI1\IIITATIONS O F DRIVING FORMULAS 53
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

FIG.9. Statistical distribution of the observation per foot.

If we now consider that the soil deposit is over-simplification of the phenomenon; the
fairly homogeneous and that the piles are fact that the energies so computed are widely
For personal use only.

identical and driven in rows (see fig. 4), thus scattered, as shown in fig. 8 and 9, is no at
eliminating any possible group effect, so that all surprising.
the driving energies should actually be quite
uniform and statistically distributed according Driving Tests on Instrumented Piles
to a Gaussian law with a very low coefficient
of dispersion, the observed random distri- In order to further investigate the driving
bution has to be attributed to the procedure behaviour of the piles and to confirm the
for evaluating the energy, and more precisely previous observations, four driving tests have
to the assumption that the energy generated been carried out on instrumented piles of
by each blow is equal to the product of the various lengths. The piles were equipped
weight of the hammer by a constant height with a central vertical pipe on which electric
of drop, and therefore is a constant. On the strain gauges were glued at five different
contrary, it becomes evident that the energy levels, in particular at 1 ft ( . 3 m) above the
delivered to the pile varies widely from blow pile tip and at 8 ft (2.4 m) below the pile head.
to blow due to the many variable parameters The strain gauges were glued on the outside
involved: the actual height of drop which is of a 2 in. extra strong steel pipe, in groups of
determined by hand of the operator of the four, with two active and two reference
rig and is essentially variable, the drag gauges connected in full bridge. The gauges
exerted by the cable during clutch release, were protected with a waterproof coating and
the friction of the hammer along the lead two layers of electric tape.
during the drop, the relative position of the The instrumented pipes, equipped with
hammer, the driving cap and the pile at im- dowels spaced at 12 in. (30.5 cm) symetrical-
pact, the state of the wood cushion on top ly to the gauge levels, were attached in the
of the driving cap, which certainly varies axis of the reinforcement cages made up of
from blow to blow, the state of the fiber six #5 with f 3 spiral styrup, spaced at 6 in.
cushion between the cap and the pile head, (15.2 cm) (fig. 10). After correct positioning
the rythm of blows application, the elastic of the cages, the piles were cast in the standard
behaviour of the pile, etc. . . Therefore, the hexagonal molds with a concrete having a
assumption that the energy delivered to the 7500 p.s.i. (52 700 kg/m') minimum strength.
pile is identical from blow to blow and equal In the same mold a reference piece of pile was
to W X H must be considered as a large casted with the same concrete; the reference
54 C:\NADI.\N GEOTECHNICAL JOURNAI,. VOL. 9, 1 9 i 2

piece had a length of 36 in. (91.44 cm) and were measured at ground level. Fig. 11
was equiped with an instrument pipe bearing reproduce examples of the results obtained.
a single strain gauges group glued at mid A total of 20 series of measurements have
height; this reference piece was used to meas- been made.
ure in the laboratory the modulus of elast- From the peak driving force Fl, observed
icity of the finished pile on the same day at pile head, and the maximum displacement
as the tests were made and to checlc the read- S,, at the same level under the impact of a given
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

ings given by the strain gauges. blow, the actual energy at pile head El, =
For the tests, after balancing the different F,, x S,, has been computed. From the peak
bridges with the pile in horizontal position, driving force Ft at pile tip and malting the
the standard bridge measuring unit was con- assumption that the final set S at ground level
nected to an oscillograpl~and the sensitivity represented to tip displacement under the
of the oscillograph set so as to give 250 ~1 impact of a given blow, the actual energy a t
in. per $ in. (. 63 cm) division on the cathodic pile tip Et = Ft x S was also computed.
screen. At different states of driving, dynamic The computed energies El, and Et have
stress measurements were made for series been compared to the energy theoretically
of three consecutive blows, photos being delivered by the blow, i.e. E = W x H. The
taken of the traces on the oscillograph. For
the same blows the deformation of the piles

/- steel plote : 3/4''


For personal use only.

P.V.C. pipe : @ I "


ekctric coble

/- reinforcing : 6 -5

/- styrrup : 5 n 6"
instrumented pipe : 0 I"

2
/'-
strain gouges

VERTICAL SECTION

FIG.11. Driving forces at pile (a) head and (b) tip.


Scale of photographs. Onc square has a length of 250
pin./in. = 30 tons. Pile number = A2-138, pile length =
42 ft 4 in., lcngth in soil at testing = 36 ft 6 in., weight
SECTION A-A
of hammer = 67801b, drop height = 24 in., average set
under observed blows = ; :in., and average displacement
FIG.10. Details of the instr~lmented pile. of pile head under observed blows = ;t in.
TAVENAS A N D RUDY: LIMITATIONS O F DRIVING FORMULAS 55

statistical distribution of the computed The loading tests have been performed on
ratios E,,/E and E,/E is given in fig. 12. piles, driven at various locations on both shores
If the product W x H would accurately of the river; and which were usually selected
represent the energy delivered to the pile on the basis of a final driving resistance below
and if each blow would be nearly identical, average. The final sets observed on these
the E,JE curve should be nearly a vertical piles varied from 0.22 in. to 0.66 in. per
line passing by the abcissa 1; as shown in blow. The test load was applied by means
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

fig. 9, this is by far not the case, the observed of the same jack for all piles, the necessary
values of E,,/E being scattered between 0 . 6 reaction being provided either by a loaded
and 2 . 2 around an average of 1.1. This result platform or by pull-out reaction on four
therefore confirms the previous conclusions: neighbouring piles. The loads were applied
the actual energy delivered by a free fall in 12.5 tons (1 1 . 3 t) increments sustained
hammer during normal driving operations for 60 min. up to a maximum load equal to
differs greatly from blow to blow and is four times the design bearing capacity of the
generally not equal to the product W x H. piles. A typical load-settlement curve is given
in fig. 13, which shows a clear definition of the
Validity of the Driving Formulas failure load; however, on 25% of the piles
The analysis of the observations on the no failure was reached, the ultimate bearing
assumed driving energy has led to the con- capacity being then extrapolated from the
clusion that the usual energy estimate was not form of the load-settlement curve. Table 3
satisfactory, and when used in pile driving gives the complete basic information on the
45 tested piles.
For personal use only.

formulas, would have a detrimental effect


in inducing an important scattering of the Beside the energy necessary to drive the
results. This conclusion can be verified on the last foot of each pile, five pile driving formulas
observations made on 45 piles which were have been considered for comparison with
submitted to driving and loading tests. the observed failure loads (Table 2).

octwl energy in the pile =force x displacement


theoriticd energy delivered = weight of hammer x drop height
FIG.12. Statistical distribution of EIJEand Et/E.
56 C.\NADIhN GEOTECHNICAL JOURNAI,. I'OL. 9, 19i2

In all these formulas, the constants were ell = efficiency of the hammer = 0 . 8 ac-
selected as follows : cording to Whitaker (197 1)
C = constant of the hammer = 1 ac-
cording to Chellis (1951)
C, = 0.15, C, = 0.50, C, = 0 . 1 0 Accord-
ing to Chellis (1951)
rz = 0.25 according to Chellis (1951)
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

A = Cross sectional area of the pile =


125 in.' (806.3 cm')
E = Young's modulus of the pile = 6 x
1061b/in2. (4218.6 x 106 kg/m?)
The parameters are defined as follows:
W = weight of the hammer in tons
H = height of drop in inches
S = set of the pile per blow in inches
W,, = weight of the pile in tons
Qfc = ultimate bearing capacity in tons
I I I I
The values of these parameters for each pile
FIG. 13. Load settlement curve for pile No. A2-789. are given in Table 3.

TABLE1. Average, standard deviation and coefficient of dispersion of the energy.


-- - -
For personal use only.

pp

Number Standard Coefficient


of Erninimunl Ernasimum Eaverase deviation of
Depth ft observations k-ft/ft k-ft/ft k-ft/ft k-ft/ft dispersion

TABLE2. Pile driving formulas considered in this investigation

el, X W X H
Engineering News Qfcl = s+
(Wellington 1893)

el, X W X H
Danish Qfc3 = etlX W X H B
(Sorensen & Hansen 1957)
S + ( 2 X A X E )

Gates (1957) Qfc4 = 5 . 6 X


(
ei,X W X H
)" Xlog-
10
s

Modified Gates
(Olson & Flaate 1967)
-
N m r : None of the presented formulas contains a factor of safety.
T \\'EN \S .\ND .\UDY: LIMIT.\TIONS O F DRIVING FORlIUL.\S

TABLE
3. Characteristics of tested piles
- ----
Test Pile C?jm L WII H Blows/foo t
No. No. Tons Foot Kips Foot Last foot
--
1
2
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
For personal use only.

21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
J1
J2
J3
54
J5
J6
estimated.
'@j,/,,

The computed values of Qf,and the energy program. The sole observation of fig. 14
delivered to drive the last foot of pile have shows that no valuable correlation exists
been compared to the measured ultimate between any of the computed bearing capac-
bearing capcaity Of,. The results obtained ities and Or,,,.By means of a least square
are given in fig. 14, where the light symbols adjustment method the regression lines Qf,=
refer to the piles tested during the construction +
a Qf,, b and Qf,,= a' Qf, b' have +
of the foundation and the dark symbols to been defined as shown on fig. 14; the values
the piles tested during the design testing of the coefficients a, b, a', and b' as well as
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14
For personal use only.

CANADIAN GEOTECHNICAL JOURNAL. VOL. 9, 1972


TXVENXS AND AUDY: LIMITATIONS O F DRIVING FORMULIZS 59
of the coefficients of correlation which the measured static bearing capacities de-
have been c t m p ~ t e dare given in Table 4. termined by load testing were on some oc-
All these results confirm that no correlation casions much smaller than expected as com-
can be found between Qr, and Qf, for the puted from driving formulas. Parsons called
piles tested, and that all five formulas are this phenomenon of the reduction of the soil
practically similar in their inefficiency as resistance around the pile, "relaxation",
the coefficient of correlation vary from 0.13 but failed to propose valuable explanations
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

for the Hiley formula to 0.27 for the for it.


Danish formula. Yang (1970) has recently analyzed very
These results are in concordance with the extensively this relaxation phenomenon of
observed scattering of the driving energy on piles in sand and showed that pore-water
which the formulas are based. Therefore, it pressures as well as changes in the soil
can be concluded that for the type of piles structure after driving could lead to variations
tested the usual driving formulas are of no of the driving resistance. Investigating the
practical value, not because of an erroneous influences of these two parameters, he showed
formulation but at least partly because the that, for piles in fine sand, the permeability
basic parameters which are used, i.e. the driv- is low enough to allow the build up of pore
ing energy and the set per blow are not ac- pressures during driving and therefore the
curately controlled and are therefore affected dissipation of some energy in the pore water;
by a very large scattering which directly consequently, a high driving resistance is
reflects on the results yielded by the formulas. measured which however is not significant
for the long term behaviour of these piles.
For personal use only.

The Effect of Time on the Bearing Capacity Yang also considers the effect of the soil
The influence of time on the behaviour of structure and suggests that for piles driven
piles driving in cohesionless soils has often in dense sand a low driving resistance has to
been recognized as a potential difficulty be expected at redriving while for loose sand
related to the use of pile driving formulas the driving resistance will increase with time;
for predicting the static bearing capacity of however, he failed to show an evidence of this
such piles. last statement on case histories.
Parsons (1966) has presented case histories During the initial testing program, as re-
from the New York City area which show ported by Tavenas (1971) the piles were driven
that the penetration resistance of piles in in 10 ft (3.0 m) increments and load tested
granular soils may vary with time. As re- after each driving sequence. Delays of at
ported the observed penetration resistances least 12 h between the end of driving and the
at the beginning of redriving of steel piles in beginning of the test, and about 24 h between
submerged sand were much lower than at the end of the test and the start of the next
the end of the initial driving which had been driving sequence were provided. No signif-
performed weeks or months before; also, icant differences were observed in the driving
resistances at the end of driving and at the
beginning of redriving despite a delay of at
TABLE 4. Characteristics of correlation between QM least 48 h between these operations. Thus,
and QC as shown on fig. 14, the correlation between
Q , and the driving energy is the same which-
Coefficient Regression lines
Pile driving of - ever energy is considered.
formula correlation a b a' b' If we now consider the results of the test-
piles in the actual foundation, fig. 14 shows
ENR 0.181 0.052 44.0 0.810 60.8 clearly that their behaviour was sensibly
Hiley 0.131 0.030 46.5 0.284 86.6
Danish 0.272 0.234 100.5 0.387 52.7
different, their static bearing capacity being
Gates 0.225 0.081 59.0 1.169 22.2 usually much larger for the same fina! driving
Gates modified energy. As these piles were perfectly identical
by Olson and to the reference test piles with respect to
Flaate 0.253 0.130 67.9 0.727 41.8 material, geometry, driving equipment, spac-
60 CANADIAN GEOTECHNICAL JOURNAL. VOL. 9.1972

ing, and surrounding soil, the systematic vestigated and questioned. However, these
increase of the ultimate bearing capacity analysis were usually based on observations
has to be explained by the influence of the made on various types of piles driven at differ-
only variable parameters, i.e. the time lag ent sites so that not real uniformity of the
between driving and testing of each pile. basic information was ensured. Thus, the
Fig. 15 shows the relationship between thc conclusions of these investigations could
time lag and the ratio of the ultimate bearing always be related, no only to the basic
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

capacity of each pile to the ultimate bearing phenomenon under investigation. but also
capacity of the corresponding test pile for to variations in the site conditions, in the type
which the time lag was 12 h. Despite an of pi!es as well as in the testing techniques, and
important scattering of the results, a definite were therefore not definite.
tendency can be observed, the ultimate On the contrary, the investigation presented
bearing capacity increasing during the first in this paper has been carried out on a very
15 to 20 days to reach a constant value 70% large pile foundation where a good uniformity
higher than that observed a t 12 h. As observed in all the parameters was ensured: a unique
by Tavenas (1970) in an analysis of the first type of piles, hexagonal precast concrete
15 tests performed at the St. Charles River piles with an equivalent diameter of 12 in.
Site. this phenomenon cannot be explained (30.5 cm), was driven by the same equip-
by the influence of pore pressure, as the sand ment (drop hammer) in a sand deposit which
is so pervious (K = 10-2 cm/sec) that com- was proven to be uniform in its physical and
plete pore pressure dissipation can be expected mechanical properties. Therefore ideal con-
to occur within a few hours; the increase in ditions were provided for an extensive in-
For personal use only.

bearing capacity has therefore to be related to vestigation of the validity of the usual con-
changes occuring in the sand structure around trols of quality based on the driving energy.
the pile. The statistical analysis of 478 complete
driving record shows that the driving energy,
as evaluated by multiplying the weight of the
Very often in the past the validity of the hammer by the drop height, is very widely
existing pile driving formulas has been in- scattered. The limits of the range of variation

FIG.15. Variation of Qfwith time.


T.\VENAS A N D AUDY: L I M I T X T I O S S O F DRIVING FORMUL.\S 61
are related to the average value En,, by E,,, developed, the use of good pile formulas
f 70C;, and the coefficient of variation, would not necessarily lead to a valuable
defined as the ratio of the standard deviation estimate of the static bearing capacities of
to E,,,, varies from 0.225 to 0.450 despite piles, due to possible time effects. For the
the very large number of observations. As sand and the concrete piles under considera-
the soils conditions are uniform this scattering tion, the bearing capcity shows a trend to
must be attributed, not to variations in the increase by about 70% in the first two to three
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

driving behaviour of the pile soil system, but weeks after driving, the long term behaviour
to the erroneous evaluation of the driving of these piles being therefore not related to the
energy delivered to the pile, and mainly driving resistance.
on the assumption that each blow generates
an identical energy equal to W x H. Acknowledgments
Driving tests carried out on instrumented The project analyzed in this paper is owned
piles show that the actual energy delivered by by the Federal Government of Canada,
different blows varies much and is usually the government of the Province of QuCbec,
not equal to W x H. and the City of QuCbec. The Technical
The usual energy estimate being proved Committee for the St. Charles River project
erroneous, it is possible to conclude, first which represents the owners gave the per-
that any pile driving formulas in which this mission for the publication of the data.
estimate will be used will also be erroneous, The presentation of this paper was sponsored
second that the control of the driving energy by grant No. A-7724, parts of the instrumenta-
cannot even be used to verify the uniformity tion being supported by grant No. A-1503
For personal use only.

in the bearing capacities of the piles and to of the National Research Council of Canada.
extrapolate to them the observations made on
a few tests piles. Actually the driving energy
control was absolutely useless on the reported AGERSCHOU, H . A. 1962. Analysis of the Engineering
pile job. news pile formula. J. Soil Mech. Found. Div.,
A.S.C.E., 88 (SM5).
The analysis of the results of 45 load tests A.S.C.E. 1941. Pile driving formulas, progress report of
confirms this conclusion: it is shown that the committee on the bearing value of pile founda-
the bearing capacity computed by any of the tions. Proc. A.S.C.E., 97, pp. 853-866.
five following formulas, Wellington, Hiley, CHELLIS,R. D. 1951. Pile foundations-theory-design
-practice. McGraw Hill, New York.
Danish, Gates, Gates modified by Olson, CUMMINGS, A. E. 1940. "Dynamic Pile Driving For-
and Flaate, had no useful correlation to the mulas". J. Boston Soc. Civil Eng., 27 (I).
actual bearing capacity, the highest coefficient CUMMINGS, A. E. 1942. Discussion to "pile driving
of correlation being 0.27. formulas. Progress Report of the Committee o n
the Bearing Value of Pile Found." Proc. A.S.C.E.,
As this poor quality of the results, obtained 68, p. 172.
by pile driving formulas, is at least partly, DEAN,A. C. 1935. Piles and pile driving. Crosby Lock-
related to the erroneous estimate of the wood, London.
driving energy, efforts should be made now GATES,M. 1957. Empirical formula for predicting pile
develop a technique for measuring as accurate- bearing capacity. Civil Eng. 27 (3), pp. 65-66.
HILEY,A. 1925. A rational pile driving formula and its
ly as possible the actual energy delivered to application in piling practice explained. Engineering,
the pile by each blow; this could probably 119, pp. 657-721.
be achieved by developing an instrumented HOUSEL,W. S. 1965. Michigan study of pile driving
driving cap. In the meantime the validity hammers. J. Soil Mech. Found. Div., A.S.C.E.,
of the usual pile driving formulas is best 91 (SM5.)
1966. Pile load capacity: estimates and test
defined by a statement made by Peck (1942): results. J. Soil Mech. Found. Div., A.S.C.E.,
"It can be demonstrated by a purely statistical 92. (SM4).
approach that the chances of guessing the MOHR,H. A. 1942. Discussion to "pile driving formulas:
bearing capacity of a pile are better than of progress report of the committee on the bearing value
computing it by a pile driving formula". of pile foundation." Proc. A.S.C.E., 68, pp. 170-172.
OLSON,R. E., and FLAATE,K. S. 1967. Pile driving
Finally, it is shown that, even if a method formulas for friction piles in sand. J. Soil Mech.
of measurine the drivingu energv
.
2 -, would be Found. Div., A.s.c.E., 93. (SM6).
62 CANADIAN GEOTECHNICAL JOURNAL. VOL. 9.19i2

PARSONS, J. D. 1966. Piling difficulties in the New York lonnage non remanit. Can. Geotech. J. 7, (1) pp.
area. J. Soil Mech. Found. Div., A.S.C.E., 90 (SMI) 37-53.
PECK,R. B. 1942. Discussion to "pile driving formulas: TAVENAS, F. 1970. Discussion to "tests on instrumented
progress report of the committee on the bearing piles, Ogeechee River site" by A. S. Vesic, J. Soil
value of pile foundations". Proc. A.S.C.E., 68, pp. Mech. Found. Div., A.S.C.E. 96 (SM6).
323-324. 1971. Load tests results on friction piles in
SANDERS, J. 1851. Rule for calculating the weight that sand. Can. Geotech. J. 8 (1).
can be safely trusted upon a pile which is driven for TEAZAGHI, K., 1942. Discussion to "pile driving formulas:
the foundation of a heavy structure. J. Franklin progress report of the committee on the bearing
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by San Francisco (UCSF) on 09/12/14

Inst. XXII, p. 304. value of pile foundations". Proc. A.S.C.E., 68 pp.


SORENSEN, T., and HANSEN. B. 1957. Pile driving formula: 31 1-323.
an investigation based on dimensionnal considerat- WELLINGTON, A. M. 1893. Piles and pile driving. Engi-
ion and a statistical analysis. Proc. 4th I.C.S.M.F.E. neering News Publication. New York.
2, pp. 61-65. WHITAKER, T. 1970. The design of piled foundations".
TAVENAS, F., 1969. The bearing capacity of friction piles Pergamon Press, London.
in sand-results of loading tests. 7th I.C.S.M.F.E., YANG,N. C. 1970. Relaxation of piles in sand and
Specialty Session, No. 8, Mexico. inorganic silt., J. Soil Mech. Found. Div., A.S.C.E.,
TAVENAS, F., CAPELLE,J. F., and LA ROCHELLE, P. 96 (SM2).
1970. Etude des sables subrnergts par Cchantil-
For personal use only.

Вам также может понравиться