WORK SCHEDULE

PROJECT TITTLE : SEWAGE TREATMENT PLANT FOR PROPOSED DEVELOPMENT ON LOT 1720, 4355 & 4356, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM FOR MESSRS NUSA UTAMA SDN BHD (4,600 PE).

CONSTRUCTION PERIOD: 6 MONTHS


Stage 2: Construction , Completion with Surat Sokongan & 12 Months of Defect Liability Period

YEAR 2006 2007


MONTH AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL
NO
WEEK 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

Design, Submission & Approval for PDC3


1.0
Civil, Structure Works
2.0 Preliminaries & site Preparation

a.
Excavation

b.
Piling Works

c.
Aeration Tank

d.
Secondary Clarifier

e.
Gravity Sludge Thickener

f.
Sludge Holding Tank

g.
Disinfection Chamber

h.
Incoming, Primary Chamber, Pump Sump

i.
Secondary, Grit & Grease Chamber

j.
Sludge Drying Bed

k.
Control Room & Blower Room

l.
Internal Drainage, Premix Road and Fencing

m.
Landscaping

n.
Installation of M&E Works
3.0 Delivery of Equipment

Installation of Equipment and Piping


4.0 Pretreatment Equipment

a.
Secondary Treatment Equipment

b.
Biological Treatment Equipment

c.
Sludge Treatment Equipment

d.
Electrical Works
5.0 Major Wiring Installation

a.
Control Panel Installation

b.
Testing & Inspection
6.0 Testing Commisioning

a.
C & S Inspection with IWK

b.
M & E Inpection with IWK
c.
Final Inspection

d.
WORK SCHEDULE
PROJECT TITTLE :HOUSING PROJECT AT PERUMAHAN KAMPUNG TERSUSUN Kg. TUANSEH DI ATAS PTD 3280- 3327 DAN PTD 3347 MUKIM SEDELI BESAR DAERAH KOTA TINGGI JOHOR.

SEWAGE TREATMENT PLANT 500 PE


CONSTRUCTION PERIOD: 18 WEEKS

YEAR 2017 2018


NO MONTH October November December January February Mach
WEEK 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Particulars
1.0 Civil, Structure Works
a. Preliminaries & site Preparation including submission
approval to IWK ( PDC 2 approval )
b. Fabrication of Equalization tank, anoxic tank, aeration
tank, clarifier tank & sludge holding tank
Excavation
c.

Piling Works - Bakau pile with rough foundation


d.

Installation of Equalization Tank, Anoxic Tank ,Aeration


e.
Tank, Clarifier Tank & Sludge Holding Tank
Construction of incoming chamber, Primary screen
g.
& Pump sump
Construction of control panel & blower room
h.

Disinfection Chamber
i.
Secondary, Grit & Grease Chamber
k.
Internal Drainage, Premix Road and Fencing
n.

2.0 Installation of M&E Works


a. Delivery of Equipment

Control Panel Installation


b.

5.0 Testing & Inspection


a. Testing Commisioning

b. C & S Inspection with IWK( PDC 7 )

c. M & E Inpection with IWK( PDC 7 )

d. Final Inspection( PDC 8 inspection )


WORK SCHEDULE
PROJECT TITTLE : SEWAGE TREATMENT PLANT FOR PROPOSED DEVELOPMENT ON LOT 1720, 4355 & 4356, MUKIM PULAI,
DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM FOR MESSRS NUSA UTAMA SDN BHD (4,600 PE).

CONSTRUCTION PERIOD: 9 MONTHS


Stage 1: Design, Submission & Obtaining Approval

YEAR 2006
MONTH SEPTEMBER OCTOBER NOVEMBER
NO
WEEK 1 2 3 4 1 2 3 4 1 2 3 4
Particulars
1.0 Preparation of Detail Design Criteria
a. Design calculation & M&E drawing

2.0 Submission & Approval From JPP/IWK


a. SSA/PDC 3 submission

b. Target 1st Comment From IWK/JPP

Design Amendment & Discussion with IWK/JPP


c.
2 nd Submission to IWK/JPP
d.
Target Approval SSA/PDC 4
e.

f. C&S Drawing Preparation

3.0 Soil Investigation Test


a. Borehole Test

b. Soil Investigation Test Report Analysis