ZXSDR BC8911B

Hardware Installation

Version: V1.0

ZTE CORPORATION
No. 55, Hi-tech Road South, ShenZhen, P.R.China
Postcode: 518057
Tel: +86-755-26771900
URL: http://support.zte.com.cn
E-mail: support@zte.com.cn
LEGAL INFORMATION
Copyright 2020 ZTE CORPORATION.

The contents of this document are protected by copyright laws and international treaties. Any reproduction
or distribution of this document or any portion of this document, in any form by any means, without the

prior written consent of ZTE CORPORATION is prohibited. Additionally, the contents of this document

are protected by contractual confidentiality obligations.

All company, brand and product names are trade or service marks, or registered trade or service marks,

of ZTE CORPORATION or of their respective owners.

This document is provided as is, and all express, implied, or statutory warranties, representationsor

conditions are disclaimed, including without limitation any implied warranty of merchantability, fitness for

a particular purpose, title or non-infringement. ZTE CORPORATION and its licensors shall not be liable

for damages resulting from the use of or reliance on the information contained herein.

ZTE CORPORATION or its licensors may have current or pending intellectual property rights or

applications covering the subject matter of this document. Except as expressly provided in any written
license between ZTE CORPORATION and its licensee, the user of this document shall not acquire any

license to the subject matter herein.

ZTE CORPORATION reserves the right to upgrade or make technical change to this product without

further notice.

Users may visit the ZTE technical support website http://support.zte.com.cn to inquire for related

information.

The ultimate right to interpret this product resides in ZTE CORPORATION.

Revision History

Revision No. Revision Date Revision Reason


R1.0 2019–12–12 First edition

Serial Number: SJ-20150203110107-016

Publishing Date: 2019-12-12 (R1.0)


Contents
1 Cabinet Overview...................................................................................... 1-1
2 Installation Flow........................................................................................ 2-1
3 Installation Preparation............................................................................ 3-1
3.1 Cabinet Transportation Precautions......................................................................3-3
3.2 Installation Precautions......................................................................................... 3-3
4 Unpacking and Inspection....................................................................... 4-1
5 Cabinet Installation................................................................................... 5-1
5.1 Space Requirements.............................................................................................5-1
5.2 Installing the BC8911B Cabinet............................................................................ 5-2
6 Cabinet Component Installation.............................................................. 6-1
6.1 Installing Storage Battery Pack.............................................................................6-1
6.2 Installing the GPS Antenna (Optional)..................................................................6-2
7 Cable Installation.......................................................................................7-1
7.1 Connecting Grounding Cable................................................................................7-3
7.2 Connecting Uplink Optical Fiber (Optional).......................................................... 7-4
7.3 Connecting Ethernet Cable (Optional).................................................................. 7-5
7.4 Connecting RF Optical Fiber................................................................................ 7-6
7.5 Connecting GPS Cable.........................................................................................7-6
7.6 Connecting AC Input Power Cable.......................................................................7-7
8 Post-Installation Check.............................................................................8-1
8.1 Cabinet Installation Check.................................................................................... 8-1
8.2 Module Installation Check.....................................................................................8-2
8.3 Cable Installation Check....................................................................................... 8-2
8.4 Other Checks........................................................................................................ 8-3
9 Powering On the Equipment....................................................................9-1
10 Closure................................................................................................... 10-1
Glossary............................................................................................................. I

I
About This Manual
Purpose

This manual describes how to install the cabinets and cables of the ZXSDR BC8911B.

Intended Audience

Hardware installation engineers


Maintenance engineers

What Is in This Manual

This manual contains the following chapters.

Chapter 1, Cabinet Describes the brief Information of the ZXSDR BC8911B.


Overview

Chapter 2, Installation Describes the basic installation flow of the ZXSDR BC8911B.
Flow

Chapter 3, Installation Describes the environment acceptance requirements and tool


Preparation preparations before equipment internationa.

Chapter 4, Unpacking Describes precautions about equipment unpacking and inspection.


and Inspection

Chapter 5, Cabinet Describes how to install cabinets.


Installation

Chapter 6, Cabinet Describes how to install a storage battery pack and the GPS antenna.
Component Installation

Chapter 7, Cable Describes how to connect cables.


Installation

Chapter 8, Post- Describes how to inspect hardware installation.


Installation Check

Chapter 9, Powering On Describes how to power on the equipment.


the Equipment

Chapter 10, Closure Describes how to clean the site.


Conventions

This manual uses the following conventions.

Italics Variables in commands. It may also refer to other related manuals and documents.

Danger: indicates an imminently hazardous situation. Failure to comply will result in


death or serious personal injury.

Warning: indicates a potentially hazardous situation. Failure to comply can result in


death or serious personal injury.

Caution: indicates a potentially hazardous situation. Failure to comply can result in


moderate or minor personal injury.

Notice: indicates equipment or environment safety information. Failure to comply


can result in equipment damage, data loss, equipment performance degradation,
environmental contamination, or other unpredictable results.

Note: provides additional information about a topic.

III
IV
Chapter 1
Cabinet Overview
The ZXSDR BC8911B is the baseband cabinet of the BS8900B cabinet family. The
ZXSDR BC8911B contains one set of storage batteries and 11U space reserved for
other devices. Figure1-1 shows the layout of the ZXSDR BC8911B cabinet.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 1-1


ZXSDR BC8911B Hardware Installation

Figure1-1 ZXSDR BC8911B Cabinet Layout

Position Hardware Unit Description

1 BCIF2 fan unit Fan unit in the ZXSDR BC8911B cabinet.

2 AC/DC power system The B201 subrack is used as the AC/DC power system
in the ZXSDR BC8911B cabinet. It monitors the power
supply in the cabinet and converts the external AC/DC
power.

3 DC power distribution unit The DCPD7A subrack is used for powering each part in
the cabinet.

1-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


1 Cabinet Overview

Position Hardware Unit Description

4 BBU subrack Baseband unit in the ZXSDR BC8911B cabinet.

5 DC power distribution unit The DCPD6 subrack is used to power RRUs.

6 Cable trough Used for binding and routing internal and external
cables.

7 Reserved space Reserved for installing other devices such as the


microwave IDU device, cable trough, and LPU.

8 Storage batteries Storage batteries can be installed in the ZXSDR


BC8911B.

9 Door Used for keeping the cabinet from water ingress.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 1-3


ZXSDR BC8911B Hardware Installation

1-4 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 2
Installation Flow
Figure2-1 shows the installation flow of the ZXSDR BC8911B.

Figure2-1 Installation Flow

SJ-20150203110107-016 | 2019-12-12 (R1.0) 2-1


ZXSDR BC8911B Hardware Installation

2-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 3
Installation Preparation
Table of Contents
Cabinet Transportation Precautions.............................................................................. 3-3
Installation Precautions.................................................................................................. 3-3

Table3-1 shows tools and meters required during installation.

Table3-1 Tools and Meters


Category Name Example

Punching Hammer drill


tools

Auxiliary percussion drill bits

Vacuum cleaner

Power strip (providing at least three two-


phase sockets and three three-phase
sockets, with the current capacity larger
than 15 A)

General- Phillips screwdrivers (4",6" and 8" each)


purpose
tools Flat head screwdrivers (4", 6" and 8" each)

Adjustable wrenches (6", 8", 10" and 12"


each)

SJ-20150203110107-016 | 2019-12-12 (R1.0) 3-1


ZXSDR BC8911B Hardware Installation

Category Name Example

Dual-purpose wrenches (17" and 19" each)

5 kg claw hammer

Inner-hexagon wrench

Angle instrument
Measurement
tools

Level bar

Antistatic wrist strap


Protection
tools

slip-proof gloves

Safety helmet

3-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


3 Installation Preparation

3.1 Cabinet Transportation Precautions


The cabinet must be transported with an outer packing container to protect the
cabinet from scratches.
After the packing container is removed on site, the cabinet must be protected
before you move or store it. For example, If a cabinet is stored temporarily,
cushioning materials must be put under the bottom of the cabinet to avoid direct
contact with the ground.
When you transport a cabinet, use machines. When you lift a cabinet, take care
to pull the cabinet to avoid collision with other objects.
If a cabinet has to be transported without packing due to environment restrictions,
cushioning materials such as foamed plastic and paperboard must be used to
protect the cabinet from scratches.

3.2 Installation Precautions


The following precautions should be abided by during the installation:
The hardware installation personnel must participate in the training related to
communication equipment installation to master installation skills.
During the installation, ensure the personal safety and avoid accidents such as
electric shock or bruise.
The installation personnel should wear an antistatic wrist strap when inserting
and pulling out boards. Ensure that the other end of the antistatic wrist strap is
grounded well.
When taking a board, take hold of the edge of the board and do not touch the
circuit, components, and wires.
Install the board along the slot to avoid short circuits caused by the contact
between parallel boards. Use proper force to install the boards to avoid pin
distortion.
When installing or maintaining an optical fiber, do not directly stare at the section
of optical fiber or an optical socket in case that laser beams hurt your eyes.
To protect the internal units from local climate conditions, the equipment must
be powered on within 24 hours after the package is opened. Power-off cannot
exceed 24 hours in maintenance.
The ZXSDR BC8911B should be installed 1,000 m away from the sea.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 3-3


ZXSDR BC8911B Hardware Installation

3-4 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 4
Unpacking and
Inspection
Goods Counting

During unpacking and inspection, the representative of the customer and ZTE
project supervisor must be present.
Verify that the packaging boxes are intact. If any goods shortage or damage, or
wrong delivery is found, contact the transport company immediately.
Unpack the boxes and verify that the goods are consistent with the inspection
packing list.
Verify that the chassis is in good condition without scratches, peeling paint,
blisters, or stains.
Verify that the accessories required for the installation are correct and complete.

Equipment Handover

After the examination of goods, the engineering supervisor from ZTE and the customer'
s representative should sign the Unpacking Acceptance Report. The Unpacking
Acceptance Report is made in duplicate, and kept by both parties. The engineering
supervisor must send the Unpacking Acceptance Report back to the representative
office and the logistics department within seven days.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 4-1


ZXSDR BC8911B Hardware Installation

4-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 5
Cabinet Installation
Table of Contents
Space Requirements......................................................................................................5-1
Installing the BC8911B Cabinet..................................................................................... 5-2

5.1 Space Requirements


Dimensions of the Cement Platform

The ZXSDR BC8911B, as an outdoor device, requires a reliable foundation.


The cement platform should be horizontal, with an flatness of not greater than 1.5
mm/m.
The compressive strength of the cement platform must be greater than 25 N/
2
mm . The hole depth is at least 110 mm.
If only one cabinet is to be installed, the minimum dimensions of the cement
platform are 800 × 800 mm, and its height must be greater than 200 mm.

Space Requirements for the Device

Figure5-1 show the space that should be reserved around the ZXSDR BC8911B for
operation and maintenance.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 5-1


ZXSDR BC8911B Hardware Installation

Figure5-1 Space Requirements of the BC8911B and other Cabinet

Note

The cabinet of the ZXSDR BC8911B uses the left-hand doors. If the left side of the
cabinet is close to the wall, the distance between the cabinet and wall must be greater
than 400 mm, so that the cabinet door can be opened completely.

5.2 Installing the BC8911B Cabinet


This procedure describes how to install the BC8911B cabinet.

Steps

1.Determine the installation position of the cabinet in accordance with the design
drawing.
2.Mark the hole positions on the cement platform in accordance with the drilling
template or the dimensions shown in Figure5-2.

5-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


5 Cabinet Installation

Figure5-2 Positions for Drilling Holes

3.Drill four 110 mm-deep holes in the marked positions with a φ16 drill bit and
install M12×90 nut and lead sleeve assembly of the expansion bolt.
4.Loosen the screws on the left and right sides at the bottom of the cabinet, see
Figure5-3.

Figure5-3 Loosen the screws

5.Push the cable inlet plates along the rail in the direction indicated by the arrow,
see Figure5-4.

Figure5-4 Push the cable plate to fix the cabinet

6.Fasten the cabinet by using the four M12 expansion bolts, see Figure5-5.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 5-3


ZXSDR BC8911B Hardware Installation

Figure5-5 Fasten the cabinet

7.Route the cable through the cable inlet.


8.Push the cable inlet plates along the rail in the direction indicated by the arrow,
and then fasten the screws, see Figure5-6.

Figure5-6 Fasten the cable inlet plates

5-4 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 6
Cabinet Component
Installation
Table of Contents
Installing Storage Battery Pack..................................................................................... 6-1
Installing the GPS Antenna (Optional).......................................................................... 6-2

6.1 Installing Storage Battery Pack


This section describes installation of a storage battery pack.

Battery Packs Available

One pack of 90 AH Gel lead-acid batteries can be installed in the BC8911B cabinet.

Battery Pack Placement

The storage batteries should be placed neatly in a cabinet. The electrode side of
each battery faces outside.
The cables (such as power cables and monitoring cables) must be routed
properly before you place storage batteries. Otherwise, cable routing may be
difficult.

Note

If only one pack of storage batteries is installed, it is recommended that the storage
battery pack is installed on the lower layer of the the battery subrack. The terminals of
the spare battery connecting lines must be insulated.

Power Cable Connection

Connect a group of four batteries in series, and then lead out the positive and negative
power cables and connect them to the terminals of the power supply unit.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 6-1


ZXSDR BC8911B Hardware Installation

Note

For how to install and connect storage batteries in series, refer to the installation guide
provided by the storage battery manufacturer.

6.2 Installing the GPS Antenna (Optional)


A GPS antenna can be installed on any corner of the top of the ZXSDR BC8911B
cabinet. This cabinet-top installation method can shorten the distance between the
GPS antenna and the cabinet, reduce the complexity of installing the GPS antenna and
cables, and save installation space and time.

Context

To install the GPS antenna on the top of the cabinet, you need to install GPS installation
assembly on the hanger on the top of the cabinet. For GPS installation assembly, see
Figure6-1.

Figure6-1 GPS Installation Assembly

1. GPS antenna
2. GPS clamp
3. GPS cable trough
4. GPS installation accessory

Steps

1.Place the GPS installation accessory on the hanger hole, which is on the top of
the cabinet , and fasten it with the hanger, see Figure6-2.

6-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


6 Cabinet Component Installation

Note

The GPS cable trough is fixed to the GPS installation accessory to bind the GPS
cable.

Figure6-2 Fixing the GPS Accessory on the Top of the Cabinet

2.Use a GPS clamp to fix the GPS antenna, and use two bolts to fix the GPS clamp
on the GPS installation accessory, see Figure6-3.

Figure6-3 Fixing the GPS Antenna

Result

For the installed GPS antenna on the top of the cabinet, see Figure6-4.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 6-3


ZXSDR BC8911B Hardware Installation

Figure6-4 GPS Antenna Installed on the Top of the Cabinet

6-4 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 7
Cable Installation
Table of Contents
Connecting Grounding Cable........................................................................................ 7-3
Connecting Uplink Optical Fiber (Optional)................................................................... 7-4
Connecting Ethernet Cable (Optional)...........................................................................7-5
Connecting RF Optical Fiber......................................................................................... 7-6
Connecting GPS Cable..................................................................................................7-6
Connecting AC Input Power Cable................................................................................7-7

Cables to Be Connected

For the cables of the ZXSDR BC8911B that are needed to be connected, refer to
Table7-1.

Table7-1 Cables to Be Connected


No. Cable Name Connection Point Remarks

Cabinet side Far end

1 Grounding Grounding busbar in a Outdoor grounding -


cables cabinet of the ZXSDR busbar
BC8911B

2 Uplink optical Uplink interface TX/RX Optical distribution The Ethernet cable
fiber between a on a CC board frame/optical fiber box and the optical fiber
BBU and CN on transmission device cable cannot be used
at the same time.
you can use one of
them according to the
3 Ethernet cable ETH0 of the CC board Transmission device
onsite transmission
conditions.

4 RF optical fiber Optical interface on a OPT of the RRU -


between a BBU BP board or FS board
and an RRU

SJ-20150203110107-016 | 2019-12-12 (R1.0) 7-1


ZXSDR BC8911B Hardware Installation

No. Cable Name Connection Point Remarks

Cabinet side Far end

5 GPS Cable REF interface on a CC GPS lightning arrester GPS jumper


board

GPS lightning arrester GPS antenna GPS feeder

6 AC input power AC INPUT interface AC output end of the -


cable of the B201 power power supply device
distribution unit of the
ZXSDR BC8911B

Note

When you connect cables, you should install grounding cables for the chassis, and then
install power cables. When you remove cables, you should remove them in reverse
order.

The Waterproof Modules

During cabling, you need to thread a cable through the corresponding cable hole in the
waterproof module at the bottom of the cabinet. The waterproof modules of the BC8911
B cabinet are described as follows:
1.Left waterproof module

7-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


7 Cable Installation

Figure7-1 Left Waterproof Module

1. W: leads in an AC input power cable


2. T: leads out a GPS cable
3. P: leads out a grounding cable
4. D: used for an optical fiber that connects to the core network or an RF optical
fiber remotely connects to an RRU
5. F: used for an Ethernet cable

2.Right waterproof module

Figure7-2 Right Waterproof Module

1. F: leads out a door control line to the PC8910B cabinet, power cable to a fan
in the PC8910B cabinet, or power cable to the LED lamp in the PC8910B
cabinet
2. P: leads out a DC power cable to the PC8910B cabinet, or a power cable to
the storage battery subrack
3. T: leads out a power cable to feed an RRU

7.1 Connecting Grounding Cable


This procedure describes how to connect an outdoor grounding cable.

Context

The grounding cable connects the cabinet ground to an outdoor grounding busbar to
provide grounding protection for the equipment. Figure7-3 shows the connection point
on the ZXSDR BC8911B.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 7-3


ZXSDR BC8911B Hardware Installation

Figure7-3 Connection Point

1. Grounding connection point

Steps

1.Connect one end of the grounding cable to the connection point shown in
Figure7-3.
2.Pull the grounding cable through the left cabling module of the cabinet, and
connect it to an outdoor grounding busbar.

7.2 Connecting Uplink Optical Fiber (Optional)


This procedure describes how to connect the uplink optical fiber between BBU and CN.

7-4 SJ-20150203110107-016 | 2019-12-12 (R1.0)


7 Cable Installation

Context

The uplink optical fiber transmits S1/X2/A/Gb/Iub signals between the BBU and the CN.

Steps

1.Connect one end of the optical fiber to the TX/RX optical interface on the CC
board of the BBU.
2.Route the optical fiber along the left side of the cabinet to the cabling module,
and then lead it out of the optical fiber box or optical distribution frame on
transmission device.

7.3 Connecting Ethernet Cable (Optional)


A transmission cable can be an Ethernet cable, optical fiber, or E1/T1 cable. A straight-
through cable is used when the cable is connected from the ETH0 optical interface of
the CC board to the transmission equipment. If the length of the cable is greater than 10
meters, an LPU should be configured.
When the LPU is configured, two cables are required for connecting to the
corresponding interfaces on the transmission equipment.
Cable 1: One end of the cable is connected to the ETH0 interface on the BBU
and the other end to the BBU_A0 interface on the LPU.
Cable 2: One end of the cable is connected to the ETH0 interface on the LPU and
the other end to the corresponding interface on the transmission equipment.
This procedure describes how to install an Ethernet cable.

Steps

1.Pass an Ethernet cable through the hole in the top left corner of the cabinet, and
then lay it along the tray on the left side of the cabinet, and finally put it on the
LPU.
2.Insert the RJ45 connector of the Ethernet cable into the ETH_0 or ETH_1
interface of the LPU.
3.Bundle the cables.

Wire Color

Table7-2 Wire Color of a Straight-Through Cable


End A Cable Color End B

1 White, Orange 1

2 Orange 2

SJ-20150203110107-016 | 2019-12-12 (R1.0) 7-5


ZXSDR BC8911B Hardware Installation

End A Cable Color End B

3 White, Green 3

4 Green 4

5 White, Blue 5

6 Blue 6

7 White, Brown 7

8 Brown 8

7.4 Connecting RF Optical Fiber


This procedure describes how to connect the RF optical fiber between a BBU and an
RRU.

Context

The RF optical fiber transmits RF signals between the BBU and the RRU.

Steps

1.Connect one end of the optical fiber to the TX/RX optical interface on the FS
board or the baseband processing board for LTE board of the BBU.
2.Route the optical fiber along the left side of the cabinet to the cabling module, and
then lead it out of the cabling module to the optical fiber box or optical distribution
frame.

7.5 Connecting GPS Cable


This procedure describes how to connect a GPS cables.
The GPS cables including the GPS jumper and the GPS feeder.
The GPS feeder is to connect the GPS antenna and the GPS lightning arrester,
and to transmit the signal received by the GPS antenna to the CC board for
processing. At the same time, it transmits the DC power supply supplied by the
clock module to the GPS antenna as the working voltage.
The GPS jumper connects a GPS lightning arrester to the CC board. The GPS
jumper is used to transfer the clock signals from the CC board to whole ZXSDR
BC8911B system.

Context

Figure7-4 shows a GPS lightning arrester.

7-6 SJ-20150203110107-016 | 2019-12-12 (R1.0)


7 Cable Installation

Figure7-4 Interfaces of the GPS Lightning Arrester

1. CH1 interface: Connecting to an REF interface of the CC board


2. CH2 interface: Connecting to an REF interface of the CC board
3. Feeder interface: Connecting to a GPS antenna feeder

Note
When the BBU is configured with only one CC board, the GPS jumper must be
connected to CH1 interface of the GPS lightning arrester.
When the BBU is configured with two CC boards, the GPS jumpers of CH1 and
CH2 interfaces are respectively connected to the REF antenna interfaces of the
two CC boards.

Steps

1.Plug one SMA terminal of the GPS jumper into the REF interface on the CC
board, and the other SMA terminal into interface 1 or 2 on the lightning arrester
shown in Figure7-4.
2.Connect the feeder of the external GPS antenna to the feeder interface of the
GPS lightning arrester shown in Figure7-4.

7.6 Connecting AC Input Power Cable


This procedure describes how to connect an external AC input power cable.

Context

The external AC input power cable leads AC power to the B201 subrack. The equipment
supports the single-phase three-wire power cable and the three-phase five-wire power
cable.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 7-7


ZXSDR BC8911B Hardware Installation

Note

If the equipment is connected to an external circuit breaker for maintenance, the


recommended capacity of the circuit breaker is 80 A for the single-phase three-wire
power cable, and 50 A for the three-phase five-wire power cable.

Steps

1.Lead an external AC input power cable out of the power distribution box, pull the
cable from the base through the left cabling module at the bottom of the cabinet,
and route the cable along the left side of the cabinet and finally to the AC input
terminal of the B201 subrack.
2.Strip off 10 mm of the cable jacket, and then crimp a tubular terminal at the end of
each core wire of the cable.
3.Connect the AC input power cable to the AC INPUT terminal of the power
module. For connection relationships, refer to Table7-3.

Table7-3 Cable Connection Relationship


Cable Type B201 Terminal Cable Description Core Wire Color

Single-phase L 220 V AC phase line (live wire) Brown


three-wire
N 220 V AC center line (neutral Blue
power cable
wire)

PE AC input protective earth Yellow-green

Three-phase L1 220 V AC phase line (live wire) Brown


five-wire
L2 220 V AC phase line (live wire) Brown
power cable
L3 220 V AC phase line (live wire) Brown

N 220 V AC center line (neutral Blue


wire)

PE AC input protective earth Yellow-green

7-8 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 8
Post-Installation Check
Table of Contents
Cabinet Installation Check............................................................................................. 8-1
Module Installation Check..............................................................................................8-2
Cable Installation Check................................................................................................ 8-2
Other Checks................................................................................................................. 8-3

8.1 Cabinet Installation Check


Item Check

Cabinet overview Verify that the surface of the cabinet is intact, for example, the bottom of the
cabinet, the gap between stacked cabinets, and the gap between the cabinet
and the base. If the cabinet has damage, scratches, or paint stripping, the
cabinet must be repaired to avoid corrosion.

Cabinet installation All bolts and screws in the cabinets, including the baseband cabinet, and other
auxiliary cabinet, are tightened.

All cabinets are horizontally laid and vertical to the concrete base. The
horizontal and vertical errors are within the allowed range.

The spacing between cabinets and the space reserved for cabinet
maintenance meet the space requirements.

All cabinets, including the baseband cabinet, and other auxiliary cabinet, are
properly secured without shake.

The top cover of the cabinet is secured.

All seams between two stacked cabinets, including the seams around fastening
screws, are sealed with glue seals.

The red cap of the smoke sensor is removed.

The inside and outside of the cabinet are clean.

The sliding covers for the cable outlets on the top and bottom of the cabinet are
installed in proper positions.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 8-1


ZXSDR BC8911B Hardware Installation

Item Check

Insulation between the cabinet The cabinets, including the baseband cabinet, and other auxiliary cabinet are
and the earth insulated from the earth (< 3.5 mA). A multimeter can be used to verify the
insulation.

8.2 Module Installation Check


Module Check

Power distribution subrack All power distribution subracks are properly installed.

BBU The BBU is installed in a 2U slot with ventilation vents above or under the
slot.

The BBU is secured with all bolts fastened.

The green-yellow grounding wire is firmly connected to the ground terminal.

The special power cable is firmly connected to the BBU.

LPU The LPU is secured with all bolts fastened.

The green-yellow grounding wire is firmly connected to the ground terminal.

8.3 Cable Installation Check


Item Check

Power wires and grounding wires The power cables and grounding cables are properly laid and bound at the
required spacing.

The external AC input power cable, which are used in the case of AC power
supply, are properly connected to corresponding power terminals, and secured
with fastened screws.

The power cables are fixed and bound through the cable trough inside the
cabinets.

The -48 V power cable and -48 V GND cable, which are used in the case of
DC power supply, are firmly connected to the PM2 terminal and the PM2 GND
terminal.

The grounding cables are firmly connected to the grounding strap.

SA cable The SA cable is firmly connected to the SA interface of the BBU.

The grounding wire of the SA cable is firmly connected to the ground terminal
of the BBU.

The other end of the SA cable is firmly connected to the BBU interface on the
LPU module.

8-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


8 Post-Installation Check

Item Check

RF jumpers The RF jumpers are firmly connected to corresponding ANT interfaces.

Optical fiber cables All optical fiber cables are properly routed and laid.

RS232 monitoring cable One end of the RS232 cable is firmly connected to the RS232/485 interface on
the LPU, and the other end is firmly connected to the X22 interface.

Transmission cables The Ethernet cables, which are used in the case of IP transmission, are
properly and firmly connected.

Cable routing specification No cable is suspended in the air.

The cables are routed properly and bundled with proper intervals. The excess
tail of each cable tie is cut off with a smooth cutting surface.

The surface of each cable is clean and free of the engineering marks. The
sheath insulation layer of the cable is not damaged or scratched.

8.4 Other Checks


Item Check

ESD wrist strap The ESD wrist strap is connected to the jack on the right of the cabinet.

Labels Dedicated ZTE labels are used.

Labels should face the same direction; that is, the outbound side of a label
faces upwards or faces the operation maintenance side for easy reading.

The contents about cabinet row and column on the labels meet the
requirements of the engineering design documents. ZTE devices in the
equipment room are installed in a proper order.

In battery and power distribution cabinets, the labels on the circuit breakers for
ZTE devices are properly pasted.

In battery and power distribution cabinets, the circuit breakers for ZTE devices
are marked with the directions using normative labels.

Both ends of all the cables such as the power cable, grounding cable,
transmission cable, and jumpers are pasted with labels. No labels are pasted
on the grounding cables of the cabinet door and side panel. The labels are
written neatly, and are pasted in the same positions. The labels are pasted 200
mm away from the connectors.

The labels (if required) on modules must be written neatly and pasted properly.

On-Site environment No waste material, such as scrap of cable ties or cables, is left in the cabinets.
The front, back, and side doors are clean. The inside and outside of the
cabinets are clean.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 8-3


ZXSDR BC8911B Hardware Installation

Item Check

No useless material is placed in the equipment room. The materials in the


equipment room are placed properly. The operating floor and raised floor are
clean.

The ground under the raised floor near the cable trough and cabinet bottom
is clean. No excessive engineering material such as cable tie, thread, and
desiccant is left. All the cables are properly routed.

8-4 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 9
Powering On the
Equipment
Check the power-on status of all subracks and modules.

Prerequisite

Hardware units of the ZXSDR BC8911B are installed, and cables are connected.

Steps

Detecting AC Power Input

1.Set the external power switch in the AC distribution box to the OFF position.
2.Set the AC input air circuit breakers in the equipment to the OFF position.
3.Switch the multimeter to the buzzer mode.
4.At the AC input air circuit breaker, detect the short circuit on the AC input circuit.
For detection criteria, refer to Table9-1.

Table9-1 Detection Criteria


AC Input Mode Detection Contact Criteria

Input form the power grid L-N  If the buzzer does not
sound, there is no
L-PE
short circuit fault. The
electric connection is
qualified.
 If the buzzer sounds,
there is a short circuit
fault. Find out the fault
and re-connect cables.

Detecting AC Input Voltage

5.Keep the AC input air circuit breakers in the equipment to the OFF position.
6.Set the external power switch in the AC distribution box to the ON position.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 9-1


ZXSDR BC8911B Hardware Installation

7.Switch the multimeter to the AC voltage mode. Measure the AC input voltage
at the AC input circuit breaker in the equipment. For detection criteria, refer to
Table9-2.

Table9-2 Detection Criteria


AC Input Detection Criteria
Mode Contact

Input form the N-PE  The neutral-to-ground voltage must be lower than
power grid 5 V. If the criterion is not satisfied, it is necessary
L-N
to upgrade the power grid to reduce the neutral-
to-ground voltage difference.
 The phase-to-neutral voltage is in the range of
80 V to 300 V. If the criterion is not satisfied, it is
recommended that you start an oil engine.

8.After detection, set the power switch of the external power supply to the OFF
position.

Detecting DC Output Circuits

9.Switch the multimeter to the buzzer mode.


10.Detect the short circuit on each DC output circuit. For detection criteria, refer to
Table9-3.

Table9-3 Detection Criteria


Detection Contact Criteria

Black probe: input of the load circuit breaker  If the buzzer does not sound, there
is no short circuit fault. The electric
Red probe: GND grounding bar
connection is qualified.
 If the buzzer sounds, there is a short
circuit fault. The redundant cables
that cause the short circuit should be
removed.

Turning on the Power Switch of Each Power Distribution Unit

11.Set the external power switch (in the AC distribution box) that is externally
connected to the B201 to the ON position.
12.Set the AC input air circuit breaker of the B201 to the ON position.
13.Set the DC output switch of the B201 to the ON switch.
14.Set the output power switch of the DC Power Distribution (DCPD) unit to the ON
position.

9-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


9 Powering On the Equipment

CAUTION

If an error occurs during power-on, cut off the power supply immediately to avoid
equipment damage.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 9-3


ZXSDR BC8911B Hardware Installation

9-4 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Chapter 10
Closure
After installation, perform the following operations:
Put tools in order.
Put the tools used during the installation back in right positions.
Collect remaining materials.
Collect remaining engineering materials and hand them over to the customer.
Remove waste and scraps.
Remove wastes and scraps and clean the environment.
Complete the installation report.
Complete the installation report and submit the installation report to the person in
charge.
If the site is operating properly, notify the operation and maintenance engineers
that the installation is completed.

SJ-20150203110107-016 | 2019-12-12 (R1.0) 10-1


ZXSDR BC8911B Hardware Installation

10-2 SJ-20150203110107-016 | 2019-12-12 (R1.0)


Glossary

BBU

- Base Band Unit

CC

- Control and Clock Module

CN

- Core Network

DCPD

- DC Power Distribution

ESD

- Electrostatic Discharge

FS

- Fabric Switch Module

GND

- Ground

GPS

- Global Positioning System

IDU

- Indoor Unit

Iub

- Interface between an RNC and a Node B

LPU

- Line Lightning Protection Unit

LTE

- Long Term Evolution

I
PE

- Protective Earth

RRU

- Remote Radio Unit

SMA

- SubMiniature version A

II