DAYS LOST DUE TO WORK HOLD BY DIPL

Time
S.No Item Description Hold Date Released Date Impact to Other Activities Remarks
loss

1-Due to change in elevation new Rebar cut lengths has


Release of Foundation is delayed
to be ordered which will add further slippage in progress
1 Pipe Rack 13-Jan-11 20-Jan-11 -7 which will also impact the erection of
2-Foundation's will ready for the steel structure within
the steel structure
next 20 working days

1-Anchor Bolts elevation not yet finalized by engineering


which will delay the final pouring
Release of Foundation is delayed
2-Due to change in elevation new Rebar cut lengths has
2 Truck Loading Rack 13-Jan-11 22-Jan-11 -9 which will also impact the erection of
to be ordered which will add further slippage in progress
the steel structure
3-Foundation's will be ready for the steel structure within
next 20 working days

1-it will impact the concrete pouring 1-Due to change in elevation new Rebar cut lengths has
3 Day Tank 13-Jan-11
13 Jan 11 20-Jan-11
20 Jan 11 -7
7
off the
th ring
i wallll off ttanks
k t be
to b ordered
d d which
hi h will
ill add
dd ffurther
th slippage
li iin progress

1-Foundation work can't be started untill the elevations


Release of Foundation is delayed
Drum Filling & Oil are finalized by DIPL
4 13-Jan-11 20-Jan-11 -7 which will also impact the erection of
Blending Area 2-Anchor Bolts required at the mid of Feb. with
the steel structure
completed fixing detaits
1-Anchor Bolts required at the Mid of Feb. with
Release of Foundation is delayed
completed fixing detaits
5 Hose Exchange Area 13-Jan-11 23-Jan-11 -10 which will also impact the erection of
2-Foundation's will ready for the steel structure within
the steel structure
next 20 working days

Release of Foundation is delayed


Still not released Foundation work can't be started untill the elevations
6 IA & Nitrogen Building 13-Jan-11 which will also impact the erection of
for further work are finalized by DIPL
the steel structure
Release of Foundation is delayed
MCC & Sub station Still not released Foundation work can't be started untill the elevations
7 13-Jan-11 which will also impact the erection of
building for further work are finalized by DIPL
the steel structure
Release of Foundation is delayed
Still not released Foundation work can't be started untill the elevations
8 Office Building 13-Jan-11 which will also impact the erection of
for further work are finalized by DIPL
the steel structure
PW line material is at site however can't be started
Still not released
9 Rerouting of PW line 25-Jan-11 because of the elevation not yet released by
for further work
engineering

1-Laying of fire water line can't be started because


10 Fire water line 25-Jan-11 elevation of the pipe and the coat wrap material is not
yet finalized