DOCUMENT NO.
XXXX-00X
Index Page
1.0 General 02
2.0 Policy 02
3.0 Quality Objectives and Strategies 03
4.0 Applicability 03
5.0 Scope 04
6.0 References 04
7.0 Definitions 05
8.0 Quality Planning & Execution 05
9.0 Quality Management Reports 15
10.0 Attachments 15
11.0 Approval Authority 15
GENERAL:
1.1 This Master Project Quality Plan (XXXX) describes the structure, procedures, elements and
processes to implement quality management system for the ABC Project. It also defines the
roles and responsibilities of Saudi Aramco Project Management Team (SAPMT) and Inspection
Department (ID) for the Quality of the facilities being provided to the Company under the ABC
Project.
1.2 This XXXX documents the agreement on, and commitment to, the project scope of work
requirements, all Saudi Aramco standards and specifications, mandatory standard drawings,
COMPANY adopted national or international codes and standards and project specifications by
the Saudi Aramco Project Management Team (SAPMT) and Inspection Department (ID). This
is accomplished through careful evaluation of the project objectives during Project Proposal
preparation to ensure the optimum results.
1.3 This XXXX outlines the project organization related to quality and the relationship between
Project Management Team and Inspection Department during the various project phases. It will
also insure that all quality requirements are contained in the contracts and cover any exceptional
quality requirement of the project.
1.4 This XXXX complies, as applicable, with the requirements of ISO 9001:1994 “Quality System
-Model for Quality Assurance in Design, Development, Production, Installation and Servicing”
and GI 400.001 “Quality Management Roles and Responsibilities”.
1.5 This XXXX establishes the basis for the Project Quality Performance Indices and is the
benchmark from which all subsequently considered Quality changes are measured.
1.6 This XXXX shall be completed and approved during the Project Proposal phase to support the
Expenditure Request Approval (ERA) as per SAEP-14.
1.7 This XXXX is a controlled document, and revisions shall be approved by Project Quality
Manager (PQM) and the most senior Project Management Representative assigned to the ABC
Project.
1.8 This XXXX will be revised and updated as a minimum at thirty percent (30%) of completion
stage for the Procurement and forty percent (40%) Construction WORK Phases, and will be re-
signed when any major changes are approved.
1.9 PQM will update, control and distribute all revisions of this XXXX to the Department
Managers, Projects Inspection Division (PID) / Vendors Inspection Division (VID)
Superintendents, Project Managers, Sr. Proponent Representatives, and ID Representatives.
2. POLICY
“The Project Team (PMT, ID, Proponent and Contractors) is committed to provide
facilities that fully meet or exceed the Company requirements. The Project Team
shall insure that Quality Objectives are fully achieved, and the attained degree of
excellence "Quality" as established within the Company Standards, Procedures, and
Specifications shall achieve the full satisfaction of all stakeholders, specifically the
end user (Proponent).”
Implement an Integrated Quality System that Recognizes and Eliminates the Causes of Potential
Non-conformities to Prevent their Occurrence by implementing the following strategies:
3.2.1. QA/QC Personnel: Approved & Mobilized 10 Working Days prior to Construction
Activities Start
3.2.3. 100% Inspection of the first three (3) occurrences of an inspection process
3.2.4. Share XXX and XXX Projects Lessons Learned with vendors and Contractors
3.2.5. Interview and/or test all Contractors QA/QC Personnel to ensure their
competency
3.2.7. Total Quality Performance through monthly scheduled PQI evaluation and review
with SAPMT and Contactor.
4. APPLICABILITY
This Master Project Quality Plan applies to all facilities and personnel directly responsible for the
quality of the ABC Project.
5. SCOPE
The scope of ABC Projects is to design, procure and construct facilities to handle:
6. REFERENCES
Saudi Aramco Standard Contracts (LSTK & LSPB)
International Standards
ISO-9001: 1994 “Quality System -Model for Quality Assurance in Design, Development,
Production, Installation and Servicing”
ISO-8402: 1994 “Quality Management and Quality Assurance – Vocabulary”
7. DEFINITIONS
Definitions relevant to this procedure are listed in the above-mentioned references and ISO
8402:1994, Quality Management and Quality Assurance – Vocabulary.
vendor Inspection Division to cover the design and procurement inspection activities.
Assign Inspection representative(s) to attend the Job-Explanation meeting as well as
the kick-off meeting to present Schedule “Q” to the potential & successful bidders.
Ensure preparation of NCRs for issuance by Project Management.
Issue worksheets to Project Management if valid NCRs are not issued to the
contractor within two working days from delivery of the NCRs.
Resolve ID/Project Management conflicts or refer them to the respective Department
Manager for resolution.
Promote and build awareness of the project quality requirements.
Establish effective methods of communication (meeting …etc.)
Initiate focused assessments of specific work elements (Construction Phase) to
ensure that the project quality activities and processes are effective.
Maintain Project Performance Index (PQI) per established system.
Discuss PQI with the Contractor and the Project Manager.
8.1.8 The Vendor Inspection Representative (SAIR) responsibilities during design and
procurement phases are prescribed in SAEP-1150 and VID-M-016.
8.1.9 The Project Inspection Representative(s) responsibilities during construction and pre-
commissioning phases are prescribed in SAEP-1150.
8.1.10 The Project Manager roles and responsibilities are prescribed in GI-400.001.
8.1.11 Sr. Project Engineer responsibilities will include but not limited to:
Implementation of the XXXX.
Ensure with and through the Inspection Representative(s) that the contractor(s), sub-
contractors and vendors implement project quality requirements in accordance with
the Contract.
Ensure the review and approval of the QA/QC personnel by the Inspection
Representative(s)
Ensure that a Project Management member acknowledges all logbook entries with
initials and dates.
Resolve all deviations identified by Inspection Representatives with the contractor and
address all open issues in regular Project Management/Contractor meetings.
Control of design review and changes.
Control of all technical information received from, and issued to, other departments,
contractor(s), sub-contractors or vendors.
Monitor progress in accordance with performance/progress measurement report and
project milestones completion schedule.
Ensure projects materials procured and delivered on time.
Track status of all issued Non-conformance Reports/Worksheets.
Obtain Inspection Representative’s concurrence prior to the closeout.
8.1.12 Project Engineer responsibilities will include but not limited to:
Implementation of the XXXX.
Control of design review and changes.
Control of all technical information received from, and issued to, other departments,
contractors or vendors.
Inspect construction work and initial with dates all logbook entries (Response time
shall be 24 hours).
Ensure technical compliance of the Contractor in his assigned area(s).
Maintain contact with other organizations within the Company for technical issues.
Review material specifications, purchase requisitions and purchase orders.
Provide alternatives/ suggestion to improve project quality, schedule and cost.
8.1.13 The SAPMT and Project Inspection Team will hold weekly QA/QC meeting with the
Contractors and sub-contractors’ Quality Department to review the projects QA/QC status,
outstanding issues (e.g.; NCRs, WS’s, Logbook Entries), upcoming activities, etc. SAPMT
Project Manager or Sr. Project Engineer shall chair this QA/QC meeting.
The frequency of this Project Phase meeting will be dependent on the availability
of all Contactors at one location. As a minimum, the following items shall be
covered:
Reports on internal and external quality assessment with any outstanding CAR
and their dispositions.
Weekly Inspection/fabrication Status report as per Schedule “Q” requirements.
Non-conformance reports issued to vendors: number issued, number closed out,
status and pending NCRs.
Worksheet issued to date: number issued, number closed out, status and
pending WS.
8.1.14.3 The meeting will be chaired by ABCPD Manager. The PQM will arrange and
coordinate the agenda of such meeting. The attendees of such meeting shall be:
ABC Department Manager
Inspection Department Manager
Proponent Manager
VID/PID Supt.
SAPMT Project Manager
SAPMT Sr. Project Engineer
PQM
QPIS Supervisors (As required)
SAIR’s (As required)
Contractor’s & major sub-contractor’s Project Managers
Contractor’s & major sub-contractor’s QA/QC Managers
8.1.14.4 For OOK (Design and Procurement Phase), the department manger can
delegate his representative(s) to attend these meetings.
8.1.15 The Contractor’s and Sub-Contractor’s Management Responsibilities for the Project shall
be described in their Quality Plan and in accordance with Schedule “Q” requirements.
PQM will communicate all findings, in writing, to Project Manager of that Contract.
8.3.2 Project Manager shall have the contract language reviewed by all required Saudi Aramco
departments in accordance with Saudi Aramco internal procedures. Also, he shall ensure
that all comments are documented, addressed and resolved prior to contract award. The
result of the Contract Reviews shall be documented by SAPMT in accordance with Saudi
Aramco established procedures.
8.3.3 SAPMT shall review proponent requirements and ensure that all their inputs are actioned.
SAPMT shall document the proponent inputs and the action taken to address such inputs as
per SAEP-14.
8.3.4 For all equipment to be re-used from the existing facilities, Project Manager shall ensure
that the Contract Language for the demolishing Package includes the procedure and
method of equipment preservation as recommended by Saudi Aramco Mothball Manual
for pressure vessels and pumps.
8.6. PURCHASING
8.6.1 During the project proposal and in addition to Project management review, PQM or his
representative(s) shall review COMPANY novated Purchase Requisitions, Novated
Purchase Orders and Technical Bids.
8.6.2 In addition to Project Management review of purchase documents, Vendor Inspection
representative(s) shall review all purchasing documents as per VID-M-016.
8.6.3 Project Manager shall ensure the resolution of review comments prior to PO’s placement.
8.6.4 With the assistance of Inspection Department, SAPMT shall prepare quality and inspection
requirements for any new equipment which does not have Saudi Aramco specification.
8.6.5 Project Manager and SAIR shall ensure that the Contractor controls purchasing and
verification of materials as per the requirements listed in Attachment III of Schedule “Q”.
is complete. PQM or his representative shall ensure that the Contractor maintains records
of receiving inspection findings.
8.13.5 Project Inspection Team shall issue EDR for any equipment received with deficiencies. ID
will act on the issued EDR as per Saudi Aramco Inspection Procedure 00-SAIP-12.
8.13.6 PQM or his representative(s) shall ensure that the Contractor’s quality plan procedure and
implementation for the control of non-conformance are in accordance with Schedule “Q”.
8.14.1 PQM or his designated SAIR shall promote and disseminate the preventive measures
through the Project Team to recognize and consequently eliminate potential non-
conformities.
8.14.2 Project Manager or his representative(s) shall address and resolve all issued NCRs and
Worksheets on timely matter and ensure that corrective actions are carried out by the
responsible contractor.
8.14.3 Project Manager or his representative(s) shall track status of all Contractor and Company
issued NCRs and obtain the Inspection Representative’s concurrence prior to closeout of
any NCR.
8.14.4 SAPMT shall prepare and provide project information addressing all Project Phases in
accordance with SAEP-329 to help others teams in planning and executing future projects.
8.14.5 PQM or his designated SAIR shall ensure that the Contractor’s quality plan procedures for
corrective and preventive action of non-confirming product or activity are in accordance
with Schedule “Q”.
8.14.6 PQM or his designated SAIR shall identify projects that are similar among those already
undertaken by PMT in order to make the best use of feedback from previous projects.
preventive actions.
8.18. TRAINING
8.18.1 Project Manager shall deliver a complete copy of the Project Proposal Package to PQM.
This Package will be used to train and familiarize the Project Inspection Team members in
the facilities that they are going to inspect.
8.18.2 PQM or his designated SAIR shall ensure that the Contractor’s, sub-contractor’s and third
party agency’s QA/QC personnel assigned to the WORK meet the minimum qualification
requirements of Attachment I of Schedule “Q”, and must be technically trained to perform
their duties.
8.18.3 PQM or designated SAIR shall be responsible to promote and build awareness of the
project QA/QC requirements and system within all Saudi Aramco personnel assigned to
the projects. The PQM or his representative(s) shall prepare and present various quality
topics that cover the project quality requirements.
CONTRACT
Project Proposal
GI 400.001
GI 2.710
This Master Project Quality Plan
8.18.5 PQM shall maintain training records.
8.19. SERVICING
8.19.1 Project Manager shall ensure that the Contractor identifies and plans for any required
vendor representative(s) services during the preparation of the Purchase Orders.
8.19.2 Project manager shall ensure that all required Spare Parts are available prior to project
Start-up Phase.
10. ATTACHMENTS
Attachment I “Project Organization Chart”
Attachment II “Minimum ID manning level and Mobilization Plan”
Attachment III “Preliminary COMPANY quality assessments schedule”
Attachment IV “Project Performance Index (PQI) Form”
Approved By:
Revision Summary:
Date Changes