YEMGAS – Marine flare was utilized 12 months prior to first shipment of LNG
Etileno XXI – Demineralized water quantities for steam blows were reflected in
design, estimates and schedule
QChem – Chemical cleaning solutions and hydrotest water disposal
requirements were addressed, i.e., neutralization tanks and aeration ponds
designed (sized)
CPChem – Energization of utility substation, F&G requirements, required
stand alone F&G panel for buildings prior to F&G panel connection to CCR
SINCOR – Plant main piperack battery limit modules fabricated in Singapore
and priority systems defined
East Area Offshore Project – Molecular sieves loaded onshore rather than
offshore, realized 8 week shorter schedule off critical path
“ The Devil is in the Details” – Do the Homework!
Technip’s AWP process, developed from start-up packs, ensures always having the
right materials and resources at the right place at the right time.
START-UP AND CONSTRUCTION PROJECT REQUIREMENTS DEFINE THE WORK PACKAGES
Diesel Safety
Supply Barriers
Temp. Small Aggreko Substation 5 EPC Scope ITR-3 Marine Flare Nitrogen Master Blind
Power Generators Building Complete PCS Piping Trucks List
On-Line
Substation 3 HVAC - Split EPC Lines ITR-3 Spare Flare Nitrogen Personnel GTG Fuel
Building Unit Clean PSS KO Drum Imported CSU Train Gas Skid
HVAC Air EDG -B SS-5 EPC Purge ITR-3 Flare Nitrogen Lock and Fire and Gas
Handling Generator UPS Nitrogen SSS Jumpover Storage Tag Out Ready
SS-3 UPS Diesel ITR-5 Line Dew ITR-3 Flare C3 Nitrogen CSU Permit Turbine
Supply ICSS Point <-40C FGS (Final) Igniter Vaporizer to Work Wash water
IN SERVICE TO SUBSTATION # 3
GAS TURBINE GENERATOR
Substation 8 Temporary Temp F&G EDG -A ITR-5 SS-3 In Nitrogen Emergency
On Line Power Monitor Generator FGS (Final) Service Supply Resp Team
ITR-3 SAT
Ready
SS-3 SS-5
Marine Flare GTG - 01
Backfeed In Service In Service EPC Pipeline CSU/HSE YLNG Gas at Gas Recep-
Camp Power Ready Ready for
ITR-3 ITR-5 RFC NS & EW Prepared 35 Bar YGS 24 B
Operation Operation
Pending Complete Piperack
Gas In Hdr
Chiller Unit Boiler C Temporary
On-Line RFC SW RFO
Building Chiller Load Temp F&G Wet Flare Plant Air C5+
Lines Share PLC Monitor Header Supply In Service
Substation 7 Firefighting -
Building Equipment
Note:
Utilities must be tracked to ensure readiness to support the Process
System commissioning and start-up
Note: Assign main piperack to one subcontractor with milestone for completion
• Measurement of the progress achieved from the most detailed level – progress
by Item (Tag) – by Discipline, per Project WBS, per PC&C System, etc.
• At all levels, comparison between physical progress vs certified progress
• The gap between the curves is continually monitored so as to avoid negative
impact on the plant completion date
Planned
vs. GAP to be monitored
Physical
vs.
Certified
Onshore Subsea
Offshore
The EasyPlant™ architecture is web-based, modularized, scalable and integrated with Technip tools
http://easyplant.apps.technip.com/login.asp
19 Technip's EPC Back to Front Strategy - Rice E and C Roundtable 01/13/2017
EasyPlant™ Platform - Modules Overview
Collection of item tags Execution recording and status reporting System Subdivision linked to
information from Engineering from fabrication yards, sites, vendors, Construction Area –
Registers: from Engineering, subcontractors, i.e., equipment, spares, Quality Progress Monitoring
SCs, Vendors, Licensors, etc. motors, all preservation activities prior to by System, Reports and Charts
handover
Quality Control Forms Management of the entire life cycle of Selected Site Activities
(Certificates) follow-up, collection piping construction activities, including Readiness status – to match
and status reporting for fabrication and QC activity in sequence the SC/Vendor Work process
Construction, PC&C and Start-up
Progress recording and status Structural database, Laydown Areas, Punch list management,
reporting for Construction and Material Follow-Up and Tracking, project reporting, formal
PC&C, by Area and System Status Reports and Charts Turnover certificates – digital
verification
Collection and reporting of Work Packages and Job Cards creation, Centralization of information
information and data relevant to validation and follow-up. To facilitate, and reporting available in other
HSE/BBS (Behavior Based Safety module hook-up, vendor punch lists, modules for the plant handover
Program) on site completion of carryover work, etc. to Client
Material Preservation
Module is designed to
track, schedule and notify
the required preservation
activities required/when
Preservation
follow-up is
realized by tag,
system, area,
location and
handover
33 2345
Projects Users
Online Profiled
EasyPlant™ was derived from input and requirements of site personnel, Lessons
Learned and Best Practices