A set of related and scheduled task which has a specific goal is known as
(A) Process
(B) Management
(C) Project
(D) None of above
2. A process that involves continuously improving and detailing a plan as more detail become
available is termed as
(A) project analysis
(B) project enhancing
(C) progressive deliberation
(D) progressive elaboration
3. ----------- is “the application of knowledge, skills, tools and techniques to project activities to
meet project requirements.”
(A) Human resource management
(B) Marketing management
(C) Strategic management
(D) Project management
4. Which of the following is not a potential advantage of using good project management?
(A) shorter development times
(B) higher worker morale
(C) lower cost of capital
(D) higher profit margins
6. If any one factor of a project changes, _____ other factor(s) is/are likely to be affected.
(A) one
(A) HRM
(B) CSO
(C) PMO
10. The statistical tool that depicts a project’s tasks and the relationships between those tasks is known as
(A) milestone
(B) goal
(C) Gantt chart
(D) PERT chart
12. What approach to developing a WBS involves writing down or drawing ideas in a nonlinear format?
(A) top-down
(B) bottom-up
(C) analogy
(D) mind mapping
13. The method of calculating and expected net monetary gain or loss from a project is called
(A) NPV
(B) NBV
(C) NCD
(D) All of above
14. Who has the MOST power in a projectized organization?
(A) The project manager
(B) The project sponsor
(C) The project analyst’s
(D) The project Stakeholder
15. Which framework tells about roles, responsibilities, coordination and control?
(A) Human resource
(B) Structural
(C) Political
(D) All
16. What is the name of one of the popular certifications provided by the Project Management Institute?
(A) Certified Project Manager (CPM)
(B) Project Management Professional (PMP)
(C) Project Management Expert (PME)
(D) Project Management Mentor (PMM)
18. Which of the following is NOT an input to the initiating process group?
(A) Company processes
(B) Company culture
(C) Historical WBSs
(D) Project scope statement
19. Some projects have a senior manager called a------------- who acts as a key supporter for a
project.
(A) Liaison
(B) Champion
(C) Leader
(D) All of the above
20. Buyers often prepare a _____________ list when selecting a seller to make the process more
manageable.
(A) Preferred
(B) Short
(C) Qualified suppliers
(D) BAFO
23. ------------- governance addresses the authority and control for key IT activities in
organizations, including IT infrastructure, IT use, and project management.
(A) Political
(B) Corporate
(C) Information technology
(D) All of above
24. ____________is a term used to describe various procurement functions that are now done
electronically.
(A) E-procurement
(B) eBay
(C) E-commerce
(D) EMV
26. If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days,
what is the standard deviation of this activity?
(A) 1
(B) 1.3
(C) 6
(D) 3
30. If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost
variance (CV)?
(A) 350
(B) -75
(C) 400
(D) -50