Академический Документы
Профессиональный Документы
Культура Документы
Research Article
Application of a Viscoelastic Model to Creep Settlement of
High-Fill Embankments
Received 30 January 2019; Revised 2 June 2019; Accepted 25 June 2019; Published 28 July 2019
Copyright © 2019 Liang Jia and Guangli Huang. This is an open access article distributed under the Creative Commons
Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is
properly cited.
In order to predict the creep settlement of high-fill embankments, the time-dependent viscoelastic model of Poynting–Thomson
(the standard linear solid) has been chosen to represent the creep behavior of soils. In the present study, the hereditary integral was
applied to calculate the strain while the load increase is varied with time. Calculation expressions of the creep settlement of an
embankment during and after construction were obtained under one-dimensional compression conditions. Using this approach,
the three parameters of every layer can be determined and adjusted to accommodate in situ monitoring data. The calculated results
agreed well with those from the field, which imply that the method proposed in this paper can give a precise prediction of creep
settlement of high-fill embankments.
_ � ε_ .
εM (6) R is called the creep factor.
EM EH
Substituting equations (5) and (6) into equation (4) Tr � . (15)
EM + EH η
yields
η T � t/Tr is called the time factor.
_ σ_H + σ M � ηεM
σ− _. (7) And equation (13) can also be written as
EM
ε(t) � σ 0 J(T), (16)
The calculation expression of σ M is obtained from
equation (7): where
η 1 −T
_ −
σ M � ηεM σ_ − σ_H , (8) J(T) � 1 − Re . (17)
EM EH
and substituting the expressions of σ M and equation (3) into The mechanical meaning of J(T) is the strain under unit
equation (1) yields force, which can easily be measured in practical tests. J(T) is
η η called the creep compliance. After applying the stress σ 0
σ − EH ε � η_ε − σ_ − σ_H � η_ε − σ_ − EH ε_ . (9)
EM EM when T � 0, the strain of the model is σ 0 J(T). Then, when
Advances in Civil Engineering 3
T′ T′ + dT′ T′
If Δσ ″ is applied when T T″ , then ε(T) should increase
Δσ ″ J(T − T″ ). The effect of each Δσ on ε(T) can be su- Figure 2: Sketch of the loading curve.
perposed in this way, which is called the Boltzmann su-
perposition principle [27]. If σ changes when T 0, the
relationship between applied stress and the time factor T will
be replaced by a stepped polyline, as shown in Figure 2. σ
When dT′ ⟶ 0, the sum becomes integral: N
T
ε(T) J T − T′ dσ T′ . (19)
0
σi σc
If the applied load varies with time, according to Fig-
ure 3, because σ 0 0, the strain at time factor T will be given
by the hereditary integral:
0 T Tc Tc + DT T = t/Tr
1
T
ε(T) 1 − Re (
− T−T′ ) dσ
dT′ . (20) Figure 3: Variation of loading with time.
0 EH dT′
The solution of the hereditary integral is
Z
1
σ − Re I1 ,
−T
ε(T) (21)
EH DT
N
where
ZI ZII n
T
I1 (σ, T) e
dσT′
dT′ . (22) Z ΔZ
0 dT′
The strain from T to Tc (Figure 3) can be described as Z∗ H
ZII
Δε T, Tc ε Tc − ε(T) T ≤ Tc . (23) ZI
Z
Δε(T, Tc ) is obtained from equation (21):
1
Δε T, Tc σ c − σ − Re c I1 σ, Tc − e I1 (σ, T).
−T −T T TI TII T∗ Tc T′
EH
Figure 4: Variation of fill height with time.
(24)
And when T ≥ Tc , the strain from Tc to T is (Figure 3) 3.1. Settlement of the Embankment during Construction
Δε Tc , T ε Tc − ε(T). (25)
3.1.1. Degree of Settlement of the Embankment at Height zI
From equation (21), it is supposed that the stress during Construction. The degree of settlement of the em-
maintains a constant value when T ≥ Tc (Figure 3): bankment at height zI during construction can be described
as follows:
Δε Tc , T ε Tc + DT − ε Tc e I1 σ, Tc 1 − e−DT .
R −Tc
zI
S zI Δε TI − T, Tc − Tdz.
EH
(27)
(26) 0
TI I TII i�II
dz dz
I2 z, TI � zeT dT � zi eTi Δzi , I1 TI , TII � eT dT � eTi Δzi , (46)
0 dT i�1 (35) TI dT i�I
zI+1 � zN . zi+1 − zi−1
Δzi � ,
If it is assumed that the height of the embankment 2
increases linearly with time, and in order to simplify the zII+1 � zII , (47)
deduction process, we assumed that the slope of the zII+1 � zII .
loading curve is 1, and then equations (33) and (35) will
become
Tc dz Tc
3.2. Settlement of the Embankment after Construction
I1 TI , Tc � eT dT � eT dT � eTc − eTI , (36)
TI dT TI
3.2.1. Settlement of an Embankment at Height zI after
TI dz TI Construction. The settlement of an embankment at height zI
I2 z, TI � zeT dT � TeT dT � TI eTI − eTI + 1. after construction can be described as follows:
0 dT 0
zI
(37)
ΔS zI � Δε Tc , Tc + DTdz. (48)
0
Substituting equations (36) and (37) into equation (31)
gives Substituting equation (26) into equation (48) gives
S zI EH ΔS zI EH
� ZI zI − R1 + e−H − e−ZI − e−zI . (38) � a1 − e−DT , (49)
c cR
Advances in Civil Engineering 5
If the height of the embankment varies linearly with where the value of b is equal to equation (44).
time, with a slope of 1, then equations (49) and (51) will
become
3.3. Parameter Determination. The three parameters of the
ΔS zI EH model are the elastic modulus EH , the creep ratio R, and the
� zI − e−zI + e−H 1 − e−DT , (52)
cR time factor Tr .
If settlement is measured from different heights of the
ΔS(H)EH embankment, from equation (55), the time factor Tr is
� H + e−H − 11 − e−DT . (53) obtained from
cR
ΔS Tc , T2 1 − e−DT2 1 − e−Δt2 /Tr
� � , (57)
3.2.2. Settlement of a Finite Layer (zI , zII ) after Construction. ΔS Tc , T1 1 − e−DT1 1 − e−Δt1 /Tr
The strain of a finite layer (zI , zII ) after construction is
where Δt is the time increment after construction.
ΔS zI , zII ΔS zII − ΔS zI The solution of equation (57) with different time in-
Δε � � , (54)
Δz Δz crements will permit an adjustment for Tr .
Substituting equation (55) into equation (42), the values
The settlement of a finite layer (zI , zII ) after construction
of R from different layers are obtained:
is
ZII
R� . (58)
e−Tc I 1 TII , Tc + b S zI , zII / ΔS zI , zII (1 − e−DT ) + 1 − be−TII
Substituting the value of Tr and R into equation (41) 15 m, and 18.3 m. And the embedment depth is reflected in
gives Figure 5(b). Almost two-year settlement data are obtained
c −T −T −T from the embankment after construction. And the field-
EH � Z − Re c I1 TII , Tc + be c − e II . measurement settlement data during construction is ob-
S zI , zII II
tained from [28], which monitored the settlement of each
(59)
layer of the filling during the construction, and the re-
lationship between filling height and settlement of the
4. Practical Verification filling during construction is represented in Figure 6. And
from the monitored data during construction in Figure 6,
For the Lanzhou–Yongjing highway, a section from firstly, the value of Tr is obtained from equation (57),
24 + 160 km to 25 + 838 km was completed with a high-fill secondly, substituting the value of Tr and all the monitored
subgrade. The settlement meters were set up from 24 + 400 km parameters into equation (58) to calculate the value of R,
to 24 + 405 km, which was semifilling and semiexcavating thirdly, the values of Tr and R are substituted into equation
subgrades (Figure 5(a)). On the right side of the subgrade, a (59) to get the value of EH , and finally, the creep settlement
steep slope was there. However, flood drainage was on the left of every layer of the embankment is calculated from
side of the subgrade. The materials excavated from the slope equations (42) and (55), respectively, which are presented
were used to fill the subgrade. The maximum fill height of this in Figures 7 and 8. From the field-measured data, the Tr , R,
section was 18.3 m. From 0 to 15 m height, the subgrade was and EH parameters for every layer were established as
filled with loess. From 15–16.1 m height, it was filled with a indicated in Table 2.
sandy pebble. From 16.1–18.3 m height, it was filled with gravel. Settlement values during construction from field mea-
The physical and mechanical properties of the subsoils are surement and settlement values calculated from equation (31)
shown in Table 1. Single-point settlement meters were adopted are presented in Figure 6, which is basically consistent with the
to monitor the long-term settlement of the subgrade [29]. It can experimental finding [30].
be seen that for both the road shoulder and driveway, 6 layers of The measured and calculated settlements after con-
settlement meters were embedded. The layout of settlement struction obtained with equation (49) are presented in
meters is shown in Figure 5, which were 3 m, 6 m, 9 m, 12 m, Figure 7.
6 Advances in Civil Engineering
I II
(a) (b)
Figure 5: Single-point settlement meters. (a) Layout profile. (b) Planar graph (reproduced from Jia et al. [28] (under the Creative Commons
Attribution License/public domain)).
Table 1: Physical and mechanical parameters of subsoil (reproduced from Jia et al. [28] (under the Creative Commons Attribution License/
public domain)).
Moisture Gravity Compression Compression Bearing capacity
Soil type Thickness (m) Void ratio
content (%) (kN·m3) coefficient (MPa−1) modulus (MPa) eigenvalues (kPa)
Loess 10.4 8.5 14.1 0.96 0.21 6.2 150
Loess 4.8 16.5 14.9 0.89 0.23 7.6 180
Pebble 3.3 21 24.8 1.15 — — 400
Mudstone — — 25.3 — — — 600
20 16
350 18
300 16 14
250 14
Filling height (m)
12
Settlement (mm)
12
200
10
Height (m)
10
150 8
100 6 8
4
50
2 6
0 0
–50 –2 4
0 20 40 60 80 100 120
Date (day) 2
160 180 200 220 240 260 280 300 320 340
Settlement Settlement (mm)
Filling height
Obs.
Figure 6: Relationship between filling height and settlement of the Cal.
filling during construction.
Figure 7: Comparison between observed and calculated settle-
ments during construction.
The agreement between the measured and calculated
settlements is excellent, although the measured settlement history is reflected by the hereditary integral. One-dimensional
values are more irregular because this area is in a soil region compression was assumed in this investigation. The settlement
that is seasonally frozen, and during the winter, soil freezing values at a point and of a finite layer during construction and
leads to the ground heave [31, 32]. after construction are obtained. The three parameters of this
model, Tr , R, and EH , can be adjusted for the in situ monitoring
5. Conclusions data from every layer. By comparison of calculated results
obtained by the proposed method with the field monitoring
To describe the time-dependent behavior of clay inside a high- data, it was concluded that the proposed method can give a
filled embankment, the viscoelastic model of Poynting– precise prediction of the creep settlement of high-filled em-
Thomson was applied in this study in order to calculate the bankments. In the future work, the other viscoelastic models
creep settlement of high-filled embankments. And the stress which can better reflect the time-dependent creep behavior of
Advances in Civil Engineering 7
Rotating Advances in
Machinery Multimedia
The Scientific
Engineering
Journal of
Journal of
Hindawi
World Journal
Hindawi Publishing Corporation Hindawi
Sensors
Hindawi Hindawi
www.hindawi.com Volume 2018 http://www.hindawi.com
www.hindawi.com Volume 2018
2013 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018
Journal of
Control Science
and Engineering
Advances in
Civil Engineering
Hindawi Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018
Journal of
Journal of Electrical and Computer
Robotics
Hindawi
Engineering
Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018
VLSI Design
Advances in
OptoElectronics
International Journal of
International Journal of
Modelling &
Simulation
Aerospace
Hindawi Volume 2018
Navigation and
Observation
Hindawi
www.hindawi.com Volume 2018
in Engineering
Hindawi
www.hindawi.com Volume 2018
Engineering
Hindawi
www.hindawi.com Volume 2018
Hindawi
www.hindawi.com www.hindawi.com Volume 2018
International Journal of
International Journal of Antennas and Active and Passive Advances in
Chemical Engineering Propagation Electronic Components Shock and Vibration Acoustics and Vibration
Hindawi Hindawi Hindawi Hindawi Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018