Академический Документы
Профессиональный Документы
Культура Документы
6.0 Channel NA
6.1 Min Thick 6.8599mm (Appendix 1-1-a-1) 7.9 (Table R-3.13) 7.531mm Regl. 366
6.2 Pass Partition thick NA since single pass (Table RCB-9.131)
6.3 Dividing Plate Thick NA since single pass (Table RCB-9.131)
7.0 Shell
7.1 Min Thick 13.3mm (Appendix 1-1-a-1) 12.7mm (Table R-3.13) NA NA NA 11.47mm Regl. 366
10.0 Baffles NA NA
10.1 Min Thick 9.5mm (Table R-4.41) Twice the corrosion allowance of shell I.e 6.4mm (7.6.3.1) 6.4mm (3.5.5)
Min Spacing- 0.2 Times of Shell ID or 51mm which ever is
greater I.e 229mm (RCB-4.51) Max Spacing - Table
10.2 Spacing RCB-4.52 I.e 1880mm NA
10.3 Notches NA Min 10mm Height (7.6.3.2)
Clearance between BaffleOD &
10.4 Shell ID 6.4mm (Table RCB-4.3) As per the TEMA Std. Table RCB 4.3 (9.1.3)
OD + 0.4mm I.e Dia 25.8mm & Over Tolerance of 0.3mm
10.5 Tube Holes (RCB-4.2)
12.0 Spacers NA
12.1 No Of. 8 NA
12.2 OD & BWG 19.05mm & 14 BWG (Table D7-M) NA
18.0 Gaskets
Gasket width is of Min 25mm for Flange ID upto 900mm &
Min 32mm from 900mm to 1500mm & Min 38mm over 9.5mm for Shell Nom. Dia of < 584mm & 12.7mm for Shell
18.1 Gaskets width 1500mm Nom. Dia of > 584mm (RC-6.31) NA
6.4mm for Shell Nom. Dia of < 584mm & 9.5mm for Shell
18.2 Pass partition gasket width NA Nom. Dia of > 584mm (RCB-6.4) NA
18.3 Gasket Joint NA Confined type Should be of One Piece Design (7.10.3)
18.4 Asbestos fill NA NA Should not used (8.2.1)
Such that Base & Filler material should with stand Max. Design temp
18.5 Material Selection As Per Appendix - 2 Table 2-5.1 NA (8.2.5)
21.0 Tubes
21.1 Tube Dia NA (Table RCB-2.21) Min 19.05mm
21.2 Tube Wall Thick NA 1.65mm (Average) (alloy material) (7.6.1.2) 2.3mm Min Regl. 631
21.3 Tube Length NA
To be Carried out for the welded tubes in finished Condition over full
21.4 Eddy Current test NA Length (8.3.2)
Extansion of tube beyond the May be Flush with tubesheet or Should not more than 0.5
21.5 tube sheet times of tube OD (RB-7.513) NA 4 mm Extansion & 15° Flering to be done on the edge
21.6 Tube Pitch NA 1.25 times the tube OD (R-2.5) NA
50.8mm or tubesheet thick minus 3.2mm which ever is
21.7 Length of expansion of tubes smaller (RB-7.511)
22.0 General
Castings Shall not be used un less approved by the Purchaser
22.1 Casting materials NA NA (8.1.2)
MOC of parts Connecting to Heat
22.2 Exchanger NA NA Same material of Connecting Parts (8.1.3)
Weld Overlay, integrally-Clad Or Explosion bond are Permitted. But
Loose Liners or Sleeves Shall not be used with out Approval of
22.3 Alloy Lining NA Purchaser (8.1.4)
23.0 Welding
23.1 Welding Process NA Oxyacetylene gas welding. Should not used (9.5.1)
(A.) Category A & B and shall be comply with pressure design code
23.2 Full Penetration weld NA (9.5.2); (B.) All attaching connections to the Vessels (9.5.3)
When the nozzle is Fab. From plate shall be Examined By means of
23.3 Examine for lamination Magnetic particle or liquid penetrent method. (9.5.4)
23.4 Continuous Weld for the no pressure parts such as (such as lugs or supports) (9.5.8)
Repair-associated Welding
23.5 Procedure To be submitted to the purchaser (9.5.9)
29.0 Assembly
29.1 Match marks or dowels NA To be provided for Channel cover to Channel (9.11.1.c)
(A.) As per the Pressure Design code (10.2.1) (B.) At least one
radiograph to be made for of each category A & B welded joints,
nozzle welds are Exempted. (10.2.1.a). (C.) shall include each start
& stop of welds made by the automatic sub merged arc welding.
30.1 Radiography Full Radiography (100%) As per UW-11-a-3 & UW-11-a-4 As Per Code (10.2.1.b). (D.) Shall be carried at lest 250mm long (10.2.1.c)
(A.) Weld metal and heat affected zone of pressure retaing welds to
be tested (10.2.5.a) (B.) Examination Shall be made after any
required PWHT (10.2.5.b) (C.) Brinell hardness For CS-225
HBW(10.2.5.c), Hardness to be termained by using 10mm Dia ball
(10.2.5.d) (D.) One longitudinal weld, one cicumferetial weld, &
connection-to-component weld if the connection is Greater than 2"
shall be tested (10.2.5.e). (E.) If more thn one welding procedure is
used , hardness readings shall be made of weld deposited by each
30.2 Weld Hardness Test NA procedure (10.2.5.f)
(A.)Striped section of base material & the weld shall be examined by
magnetic particle method prior to applying weld overlay. (10.2.6) (B.)
Prior to the Fab. Integrally clad material to be subjected to ultrosonic
Examination from clad side as per the Pressure design Code.
30.3 Alloy clad construction NA (10.2.10).
31 Pressure Testing
Tube weld integrity to be verified before expanding the tubes by a
pneumatic test from shell side at a gauge Pr. Between 50 Kpa to
31.1 Tube to tube sheet joint NA 100Kpa. Using soap water (10.3.1)
(A.) Independent hydrostatic test of shell side & tube side shall be
(A.) Test Pr. to be held for at least 30 Minutes (B.) Shell performed. Min Temp. for testing is as per the pressure design code.
side 7 Tube Side are to be tested seperatly (C.) Min (10.3.2) (B.) Hydrostatic test pressure shall be maintained for at
31.2 Hydrostatic test UG99-B Hydrotest Pr. Is As per code (RCB-1.31). least 1Hr. After the completion of test. (10.3.3)
(A.) Nozzle reinforcement pad to be tested for 170Kpa.(10.3.6). (B.)
If any supplementary pneumatic test shall be carried at a nominal Pr.
31.3 Pneumatic test NA Of 170 Kpa.(10.3.7)
31.4 Paint & other Coating NA Shall be applied over welds before the final hydrostatic test. (10.3.9)
Drawing
33.0 Outline Drawing for Review to the purchaser see the Attachments (6.1)
34.0 Information to be sent after drawing reviewed see the Attachments (6.2)
35.0 Documents to be submitted for review to purchaser see the Attachments (6.2.4)