PROJECT NAME: DELIVERY DRONE

REVISION NUMBER: 01
DATE: 6/6/2020

KEY # All in Weeks


Early Duration Early
Start Finish
Activity name and number
Critical Path
Late Total Late
Start Slack Finish

0 4 4
1.1.2 – Engage 6 3 9 9 2 11 11 3 14
stakeholders 1.2.1 – Schedule 1.2.6 – Risk 1.2.2 – Budget
2 2 6 Development Management Plan Estimate
13 7 16 16 7 18 18 7 21

0 0 0 0 6 6
6 0 6
1.1.1 – Develop 6 5 11 11 3 14 14 4 18
Start Milestone—
Scope and Plan 1.3.1 – Drone
0 0 0 End Initiating 1.5.1 – Flight Path 1.5.2 – Flight Path
0 0 6 Changes Design
6 0 6 Engineering Testing
6 0 11 14 3 17 17 3 21

11 3 14
0 3 3 6 3 9 14 8 22
1.3.2 – Purchase
1.1.3 – 1.2.5 – Process 1.3.3 – Custom
Design Materials
Communication Drones Structure
11 0 14
Management Plan 19 13 22 14 0 22
3 3 6

6 4 10 10 4 14
14 3.5 17.5
1.4.1 – System 1.4.2 – Specialized
Changes Design Customer Order 1.4.3 – Custom
Interface Management
11.5 5.5 15.5
Reporting Interface
# Equations 15.5 5.5 19.5
19.5 5.5 23

Total Slack = TS = LF – EF = LS – ES EF = ES + Dur LS = LF – Dur

14 4 15` 18 0 18
1.2.3 – Legal Contract Milestone – Contract
Negotiations Assigned
21 7 25 25 7 25

18 2 20 22 2 24 24 0 24
25 2 27 27 1 28
1.5.3 – Pharmacy 1.5.4 – Customization Milestone –
Manager Drone of Flight Processing 1.6.1 – Final 1.6.2 – Closing
End Flight
Implementation Out the Project
Operations Procedures 23 1 25 Operations
21 3 23 25 0 27 27 0 28
25 1 25

22 3 25 25 0 25
1.3.4 – Drone Milestone – End
Maintenance Procedures Adapted Drones 28 0 28
22 0 25 25 0 25
Finish

28 0 28
17.5 0 17.5
Milestone -- End IT
and App Interfaces
23 5.5 23