PROJECT: E-0018 Amman Strategic Reserve Terminal for Petroleum Products 3 SPHERES
TITLE: DATE:
20-10-2019
PROCESS PIPING & EQUIPMENT
CONSTRUCTION SPECIFICATION REVISION: 2
o The equipment that will be part of this unit are: Air Compressor (2 No.); Air Cooler (2
No.); Receiver (2 No.); Dryers (2 No.) this last one will be supplied in a common
skid.
o Every equipment will be supplied 100% fabricated, tested and painted. For the
Separator will be supplied with the heater already installed.
o It shall be considered that the the steel structure platforms, ladders and handrails
will be 100% fabricated and painted to be bolted at site.
o The equipment that will be part of this unit are: AERATION TANK, NITRIFICATION
TANK & SETTLING TANK (2 No.); CHEMICAL DOSING SYSTEM (1 No.);
TERTIARY TREATMENT SYSTEM (1 No.) including 1 pump; SLUDGE HANDLING
SYSTEM (1 No.)
o It shall be considered that the steel structure platforms, ladders and handrails will be
100% fabricated and painted to be bolted at site.
o It will be supplied 100% fabricated, painted, tested, in skid and the equipment that
will be part of this unit are such a: UNLOADING PUMP FOR JET FUEL, FLAME
ARRESTERS, AIR ELIMINATOR FOR TRUCK LOADING, AIR ELIMINATOR FOR
TRUCK UNLOADING, FILTER WATER SEPARATORS FOR JET FUEL, TRUCK
UNLOADING HOSES, piping, instrumentation, etc.
Página 44 de 81